Professional Documents
Culture Documents
Final 50 Old River Road Proposal 2016
Final 50 Old River Road Proposal 2016
OF CANTON
Previous Studies
2007 - The engineering firm of Weston and Sampson performed the
following:
Facility Needs Assessment
Existing Site Assessment
Fuel Island Location Study
Weston and Sampson Findings:
DPW Facilities should be approximately 25,500 square feet
Estimated cost $7.8 million (2008 dollars)
Flood Mitigation Compensatory Storage may be possible if the Town is able to locate a
parcel with the same hydraulic reach and with a volume that was not
previously used for flood storage. Although feasible if such a property
exists, this would result in a substantial increase in construction costs
and as of now, no viable compensatory storage has been identified
Board of Selectmen
requested that the
current proposal be
reduced in scope and
cost. Fuss & ONeill draft
preliminary design and
site plan which is
presented to Selectmen
in August 2016.
Concerns:
Building was too tall
Required an elevator
Sight Lines for access road
Floor Plan
Office Area
2,640
Storage Area
11,500
Office Area
Mechanical
Room
Machine and
Repair Shop
Storage Area
Reserve
Area
Salt Shed
Capacity is 2.5 times the
Current Salt Shed
Proposal Attributes
Flood Mitigation
In order to compensate for the loss of floodplain, additional flood storage will
be created by deepening the existing floodplain. This will be accomplished by
lowering the softball field 9 to 15. The field will then be reconstructed and
utilized the same as it currently is.
Cost
BUILDING $2,577,135
Includes Salt Shed, Inspection and
escalation
SITE WORK
$ 673,618
PROFESSIONAL SERVICES
$ 378,637
EQUIPMENT $ 195,610
Includes Portable Lift and Crane
TOTAL $3,825,000
The amounts within each category are subject to change but the total cost
cannot be increased without additional public approval.
Cost Estimates Provided by Gibbons Estimating Group LLC. and Fuss & ONeill, Inc.
Payment Schedule
Transition Plan
Director and Admin Asst. Town Hall Basement
Parks Department 88 Simonds Avenue
Highway Foreman / Staff Transfer Station
Mechanics Horse Barn
Fuel Storage At time of relocation, fuel will be
purchased off site.
Construction will be sequenced so that critical phases are
done first.
Ballot Question
SHALL THE TOWN OF CANTON APPROPRIATE $3,825,000 FOR
DESIGN, CONSTRUCTION AND EQUIPPING OF A NEW CANTON
PUBLIC WORKS FACILITY TO BE LOCATED ON THE SITE OF THE
CURRENT FACILITY AT 50 OLD RIVER ROAD IN CANTON; AND
AUTHORIZE THE ISSUE OF BONDS AND NOTES IN THE SAME
AMOUNT TO FINANCE THE APPROPRIATION?
YES
NO