SWITCHYARD

1. New 6 nos CTS are to be tested & shifted to 25 MVA Transformer bay, Existing 3 nos CTs
Shifted to GT-2 bay (Now CT,s are in 25 MVA transformer bay)
2. 33 KV panel to be tested & put in service. (12 MVA CT & control cables to be shifted from
110kv to 33kv panel)
3. In GT-1 bay B phase CT to be replaced due to oil leakage. (New CT kept in switch yard)
4. UNIT- 2 Drawing & Document s approval for CEIG electrical inspection work.
5. Bus coupler bay put in service for GT-1 ,GT-2 & LINE-1, LINE-2 Bays

ENMAS O & M SERVICES PRIVATE


LIMITED
TULSYAN NEC POWER LIMITED
GUMMIDIPOONDI
35 MW CAPTIVE POWER PLANT
TRIP /BREAK DOWN REPORT ON 03/10/2016
Name of the equipment Tripped/Break
down
Date of Trip /Break down

TG -1

TG-2

03.10.2016

03.10.2016

Time of Trip/ Break down

04:15 AM

04:15 AM

Date of Re-Synchronizing

03.10.2016

03.10.2016

Time of Re-Synchronizing

05:15 AM

Loss of time

01.00 Hrs

4.15 Hrs

Reason for Trip/Break down

At 04.15 PM TG-1 tripped due to Turbine gearbox high speed NDE shaft
vibration Y position high.
.

Analysis

Conclusion
.
REMARKS

At TG-1 6.15 AM synchronized with grid.


At TG-2 AM synchronized with grid.