Communications 5 Design:

MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DESIGN OBJECTIVES
Statement of the Problem
Seven BTS sites, with one considered as the Hub station are to be connected in a ring
topology considering a fiber in the loop system. The hub station is located Masambong, Quezon
City and the six base transceiver stations are located within Del Monte Avenue, Roosevelt
Avenue and West Avenue, Quezon City. The team is to connect the hub and the base
transceiver stations and provide within this Fiber in the loop system an FOC service facility.

The Objectives of the Outside Plant design are as follows:


 To design an outside plant using fiber optic cables that will provide the seven stations in
a synchronous digital hierarchy ring employing underground, aerial connection or
combination of the two.
 To propose an outside plant design using fiber optic cables via a ring topology to provide
connection on six base transceiver stations with one acting as the hub. The hub is
located at Masambong Quezon City and the others are distributed within the areas of
Del Monte Avenue, Roosevelt Avenue and West Avenue, Quezon City
 To design a fiber optic transmission system that will meet the required loading of the
topology mentioned earlier.
 And most importantly, to be able to apply what we have learned in our lecture class and
be able to utilize what we have learned in order to design an outside plant employing
fiber in the loop system as prescribed by the instructor.

Page 99
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DESIGN PROCEDURES
PLANNING

o Plotting the location of the base transceiver station on a street map.


o Visiting the location for site surveying.
o Identifying the shortest cable route linking the stations creating a ring topology with no
common pole used and intersection within the connections.
FIELD WORK

o Locating the hub to start the field survey.


o Familiarizing the assigned area – hub station and base transceiver stations.
o Verifying the field if aerial cable installation is allowed.
o Measuring distances of each post to be installed in the area of route.
o Identifying the following information for each post.
o type of post
o type of extension arm
o type of guy
o exact location and distances for each post
o if new pole is needed
DOCUMENTATION

o Gathering all the data from the field survey.


o Drawing the detailed engineering plan.
o Choosing properly the equipment to be used based from the design requirements (e.g.
STM, fiber optic cable, etc.).
o Computing for the fiber optic transmission power budget.
o Identifying the bill of material.
o Compiling and finalizing the documentation parts.

Page 99
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DESIGN ASSUMPTIONS
The following are the restrictions and guidelines for this design:

 Any pole can be used.


 Any commercially available materials may be used.
 Consider “green fields and blue skies”.
 Provide different cable routes in employing the ring topology.
 Use Single Mode Fiber Optic Cable.
 Fiber optic cable cutting length is 2km/reel.
 Utilize short haul or long SDH design or EPON.
 The telephone, switch or PBX, router if there is any, and multiplexer equipment may
freely be chosen by the designer provided they work together seamlessly.
 E1/TDM, SDH, PDH or Ethernet may be used as transmission carrier.

Page 99
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design

BTS6

BTS5

BTS3
BTS2
BTS1-HUB

BTS4

BTS7
MAPÚA INSTITUTE OF TECHNOLOGY Communications 5 Design:
Outside Plant Design

TRANSMISSION NETWORK

BTS2
(Tolentino)

BTS1-HUB BTS3
(Masambong) (Paltok)

STM-4
BTS7 BTS6
(Roosevelt) (Baler, QC)

BTS4
(One BTS5
Executive (Examiner)
Office)
TRANSMISSION NETWORK COMPUTATION
Group 1 E1 Loading

GSM 900 GSM 1800 3G HSPA Broadband BTS Address


BTS Sites
Corumi St. cor. Wayan St.,
Masambong (Hub) 2 3 4 4 40Mbps Bo. Masambong, Quezon
City
Del Monte Avenue corner
Tolentino QC 2 3 4 4 40Mbps
Tolentino, Quezon City
NFA Bldg. Del Monte Ave.
Paltok 2 3 4 4 40Mbps
cor. Aragon St. Paltok
West Avenue cor Col.
One Executive Office 2 3 4 4 40Mbps Martinez St., Quezon City,
Metro Manila
#67 West Ave. cor. Examiner
Examiner 2 3 4 4 40Mbps
St., Paltok
Miller Avenue cor. Bayaya
Baler QC 2 3 4 4 40Mbps
St. Brgy. Bungad
PMI College Building,
Roosevelt 2 3 4 4 40Mbps
Roosevelt Ave., Quezon City

Total 14 21 28 28 280Mbps

subtotalGSM 900 =14−2=12

subtotalGSM 1800 =21−3=18

subtotal3 G =28−4=24

subtotal HSPA =28−4=24

subtotal Broadband=280 Mbps−40 Mbps=240 Mbps

240 Mbps
E 1Broadband = =120
2 Mbps

TOTAL E 1=12+18+24 +24+ 120=198 E 1

 Choose STM-4 SDH ring since STM-4 has a capacity of 252 E1/622 Mbps.
Assumptions

Fade margin is 5dB

A splicing every 3km will be considered

Short-haul transmission

Equipment Specifications (based from manufacturer’s data sheet)

Single Mode Fiber Optic Cable Attenuation (at 1310 nm) 0.35 dB/km

Maximum Transmit Power -8 dBm

Minimum Receiver Sensitivity -28 dBm

Connector Loss 0.2 dB

Splicing Loss 0.15 dB/splice

Fade Margin 5 dB
Link 1 – Masambong (HUB) to Tolentino

Total Distance = 735.6 m

Power Budget

Power Budget = Max Transmit Power – Receive Threshold

Power Budget = -8 dBm – (-28 dBm)

Power Budget = 20 dB

Total Link Loss

Total Link Loss = FOC Loss + Connector Loss + Splicing Loss + Fade Margin

FOC Loss = Total Distance x FOC Attenuation

FOC Loss = 0.7356km x 0.35 dB/km

FOC Loss = 0.25746 dB

Connector Loss = Connector Loss x No. of Connectors

Connector Loss = 0.2 dB x 2

Connector Loss = 0.4 dB

Splicing Loss = Splicing Loss x No. of Splice

Splicing Loss = 0.15 dB x 0

Splicing Loss = 0 dB

Fade Margin = 5 dB

Total Link Loss = 0.25746 dB + 0.4 dB + 0dB + 5 dB

Total Link Loss =5.65746 dB

Power Margin
Power Margin = Power Budget – Total Link Loss

Power Margin = 20 dB – 5.65746 dB

Power Margin = 14.34254 dB

Link 2 – Tolentino to Paltok

Total Distance = 619.31 m


Power Budget

Power Budget = Max Transmit Power – Receive Threshold

Power Budget = -8 dBm – (-28 dBm)

Power Budget = 20 dB

Total Link Loss

Total Link Loss = FOC Loss + Connector Loss + Splicing Loss + Fade Margin

FOC Loss = Total Distance x FOC Attenuation

FOC Loss = 0.61931 km x 0.35 dB/km

FOC Loss = 0.2166 dB

Connector Loss = Connector Loss x No. of Connectors

Connector Loss = 0.2 dB x 2

Connector Loss = 0.4 dB

Splicing Loss = Splicing Loss x No. of Splice

Splicing Loss = 0.15 dB x 1

Splicing Loss = 0.15 dB

Fade Margin = 5 dB

Total Link Loss = 0.2166 dB + 0.4 dB + 0.15 dB + 5 dB

Total Link Loss = 5.7666 dB

Power Margin

Power Margin = Power Budget – Total Link Loss

Power Margin = 20 dB – 5.7666 dB


Power Margin = 14.2334 dB

Link 3 – Paltok to Baler, QC

Total Distance = 1242.6 m

Power Budget

Power Budget = Max Transmit Power – Receive Threshold


Power Budget = -8 dBm – (-28 dBm)

Power Budget = 20 dB

Total Link Loss

Total Link Loss = FOC Loss + Connector Loss + Splicing Loss + Fade Margin

FOC Loss = Total Distance x FOC Attenuation

FOC Loss = 1.2426 km x 0.35 dB/km

FOC Loss = 0.43491 dB

Connector Loss = Connector Loss x No. of Connectors

Connector Loss = 0.2 dB x 2

Connector Loss = 0.4 dB

Splicing Loss = Splicing Loss x No. of Splice

Splicing Loss = 0.15 dB x 0

Splicing Loss = 0 dB

Fade Margin = 5 dB

Total Link Loss = 0.4349 dB + 0.4 dB + 0 dB + 5 dB

Total Link Loss = 5.8349 dB

Power Margin

Power Margin = Power Budget – Total Link Loss

Power Margin = 20 dB – 5.8349 dB

Power Margin = 14.1651 dB


Link 4 – Baler to Examiner

Total Distance = 958.2 m

Power Budget

Power Budget = Max Transmit Power – Receive Threshold

Power Budget = -8 dBm – (-28 dBm)

Power Budget = 20 dB
Total Link Loss

Total Link Loss = FOC Loss + Connector Loss + Splicing Loss + Fade Margin

FOC Loss = Total Distance x FOC Attenuation

FOC Loss = 0.9582 km x 0.35 dB/km

FOC Loss = 0.33537 dB

Connector Loss = Connector Loss x No. of Connectors

Connector Loss = 0.2 dB x 2

Connector Loss = 0.4 dB

Splicing Loss = Splicing Loss x No. of Splice

Splicing Loss = 0.15 dB x 1

Splicing Loss = 0.15 dB

Fade Margin = 5 dB

Total Link Loss = 0.33537 dB + 0.4 dB + 0.15 dB + 5 dB

Total Link Loss = 5.88537 dB

Power Margin

Power Margin = Power Budget – Total Link Loss

Power Margin = 20 dB – 5.88537 dB

Power Margin = 14.11463 dB


Link 5 – Examiner to One Executive Office

Total Distance = 890.7 m

Power Budget

Power Budget = Max Transmit Power – Receive Threshold

Power Budget = -8 dBm – (-28 dBm)

Power Budget = 20 dB

Total Link Loss

Total Link Loss = FOC Loss + Connector Loss + Splicing Loss + Fade Margin
FOC Loss = Total Distance x FOC Attenuation

FOC Loss = 0.8907 km x 0.35 dB/km

FOC Loss = 0.3117 dB

Connector Loss = Connector Loss x No. of Connectors

Connector Loss = 0.2 dB x 2

Connector Loss = 0.4 dB

Splicing Loss = Splicing Loss x No. of Splice

Splicing Loss = 0.15 dB x 0

Splicing Loss = 0 dB

Fade Margin = 5 dB

Total Link Loss = 0.3117 dB + 0.4 dB + 0 dB + 5 dB

Total Link Loss = 5.7117 dB

Power Margin

Power Margin = Power Budget – Total Link Loss

Power Margin = 20 dB – 5.7117 dB

Power Margin = 14.2883 dB


Link 6 – One Executive Office to Roosevelt

Total Distance = 1032 m

Power Budget

Power Budget = Max Transmit Power – Receive Threshold

Power Budget = -8 dBm – (-28 dBm)

Power Budget = 20 dB

Total Link Loss

Total Link Loss = FOC Loss + Connector Loss + Splicing Loss + Fade Margin

FOC Loss = Total Distance x FOC Attenuation

FOC Loss = 1.032 km x 0.35 dB/km

FOC Loss = 0.3612 dB

Connector Loss = Connector Loss x No. of Connectors

Connector Loss = 0.2 dB x 2

Connector Loss = 0.4 dB

Splicing Loss = Splicing Loss x No. of Splice

Splicing Loss = 0.15 dB x 1

Splicing Loss = 0.15 dB

Fade Margin = 5 dB

Total Link Loss = 0.3612 dB + 0.4 dB + 0.15 dB + 5 dB

Total Link Loss = 5.9112 dB

Power Margin
Power Margin = Power Budget – Total Link Loss

Power Margin = 20 dB – 5.9112 dB

Power Margin = 14.0888 dB

Link 7 – Roosevelt to Masambong (HUB)

Total Distance = 2692.2 m


Power Budget

Power Budget = Max Transmit Power – Receive Threshold

Power Budget = -8 dBm – (-28 dBm)

Power Budget = 20 dB

Total Link Loss

Total Link Loss = FOC Loss + Connector Loss + Splicing Loss + Fade Margin

FOC Loss = Total Distance x FOC Attenuation

FOC Loss = 2.6292 km x 0.35 dB/km

FOC Loss = 0.9202 dB

Connector Loss = Connector Loss x No. of Connectors

Connector Loss = 0.2 dB x 2

Connector Loss = 0.4 dB

Splicing Loss = Splicing Loss x No. of Splice

Splicing Loss = 0.15 dB x 2

Splicing Loss = 0.3 dB

Fade Margin = 5 dB

Total Link Loss = 0.9202 dB + 0.4 dB + 0.3 dB + 5 dB

Total Link Loss = 6.6202 dB

Power Margin

Power Margin = Power Budget – Total Link Loss

Power Margin = 20 dB – 6.6202 dB


Power Margin = 13.3798 dB

DETAILED OUTSIDE PLANT DESIGN


LEGEND

Proposed Pole

M Meralco Pole

P PLDT Pole

G Globe Pole

Not used Pole

Grounded Pole

Extension Arm (26")

Extension Arm (44")

10 Pin Alley Arm

Side walk guy

Side guy

BTS
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design

SINGLE- LINE DIAGRAM


Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design: Outside Plant
MAPÚA INSTITUTE OF TECHNOLOGY Design
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

BILL OF MATERIALS
ITEM NO. DESCRIPTION QUANTITY UNIT
Standard ADSS-Single Mode Fiber Optic Cable
1 5 reels
(2km/reel)
Cisco 7600 Series 1-Port Channelized OC-12/STM-4 to
2 7 pcs.
DS3/E3 OSM Multiplexer
SC Zirconia Ferrule 126um/3mm (cladding/jacket) Single
3 19 pcs.
Mode Connector
4 44” Extension Arm 138 pcs
5 26” Extension Arm 55 pcs.
6 Sidewalk Guy 168 pcs.
7 Side Guy 6 pcs.
8 Messenger Guy 5 pcs.
10-pin Alley Arm 36 Pcs.
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

POLE PICTURES
Link 1 – Masambong (HUB) to Tolentino
CR1 CR3

DM1

CR2
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM2 DM4

DM3 DM5
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM6 DM8

DM7 DM9
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM10 DM12

DM11 DM13
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM14

DM17

DM15

DM18

DM16
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM19

PROPOSED POLE

BTS1
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

Link 2 – Tolentino to Paltok


DM22
DM20

DM23
DM21
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM24

DM27

DM25

DM26 DM28
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM29 DM31

DM30 DM32
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

DM33 DM35

DM34 DM36
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

PROPOSED POLE

DM37

BTS2-PALTOK

AR1 Link 3 – Paltok to Baler, QC

AR2
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

AR3 AR5

AR4
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

AR6 AR8

AR7 PM1
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

PM2 JJL1

PM3 JJL2
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

JJL3 JJL5

JJL4 JJL6
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

JJL7 JJL9

JJL8 JJL10
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

JJL11 JJL13

JL12 JJL14
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

JL15 BY1

JJL16 BY2
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

BY3 BY5

BY4 BY6
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

BY7 ML1

PROPOSED POLE

BY8 ML2

BTS3-BALER QC
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

Link 4 – Baler QC to Examiner


ML5
ML3

ML6
ML4
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

ML9

ML7

ML10

ML8

ML11
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

ML12 ML14

ML13
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

ML17

ML15

ML18

ML16
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WA1

ML19

PROPOSED POLE

WA2

ML20
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WA3 WA5

WA4 WA6
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WA7 WA9

WA8 BTS4-EXAMINER
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

Link 5 – Examiner to One


Executive Office
WA12
WA10

WA13
WA11
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WA14

WA17

WA15

WA16
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WA20

WA18

WA21

WA19
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WA24

WA22

WA25

WA23
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WA28

WA26

WA29

WA27
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

BTS5-ONE EXECUTIVE OFFICE

WA30

WA31
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

Link 6 – One Executive Office to


Roosevelt

WA32
QA1

WA33
QA2
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA3 QA5

QA4 QA6
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA7 QA9

QA8 QA10
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA11 QA13

QA12 QA14
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA15 QA17

PROPOSED POLE

QA18
QA16
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA19 QA21

QA20 QA22
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA23 QA25

QA24 RV1
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

RV2 BTS6 – ROOSEVELT

PROPOSED POLE

GL1
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

Link 7 – Roosevelt to
Masambong (HUB)
GL4
GL2

GL5
GL3
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GL6 GL8

GL7 GL9
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GL10 GL12

PROPOSED POLE

QA26
GL11
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA27 QA29

QA28 QA30
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA31 QA33

QA32 QA34
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

QA35 GA1

QA36 GA2
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA3 GA5

GA4 GA6
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA7 GA9

PROPOESED POLE

GA8 GA10
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA13

GA11

PROPOSED POLE

GA14

GA12

Proposed Pole
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA15 GA17

GA16 GA18
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA19 GA21

PROPOSED POLE

GA22
GA20
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA23 GA25

GA24 GA26
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA27 GA29

GA28 GA30
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA31 GA33

PROPOSED POLE

GA32
GA34

PROPOSED POLE
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA35 GA37

PROPOSED POLE

GA36
GA38
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

GA39 WY1

PROPOSED POLE

WY2
GA40

PROPOSED POLE PROPOSED POLE


Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WY3 WY5

WY4 WY6
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

WY7

HUB-WAYAN

WY8
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

ATTTACHMENTS
(BROCHURES AND GROUP PICTURE)
Communications 5 Design:
MAPÚA INSTITUTE OF TECHNOLOGY Outside Plant Design

TABLE OF CONTENTS

1. Design Objectives 1

2. Design Procedures 2
3. Assumptions 3
4. Vicinity Map 4
5. Transmission Network ` 5
 Transmission Network Computation 6
6. Detailed OSP Design 22
7. Bill of Materials 38
8. Pole Pictures 39
9. Attachments 99
 Brochures
 Group Picture