GC __

Contract Award

M1000

Handover from Sales

Contract;
CAP form
ORDER ACQUISITION PROCESS

10.1.1. - develop Project Charter

10.1.1. - develop Project Charter

Project Charte

10.1.1. - develop Project Charter

Project
Charter

10.1.2. - acquire Project Management


Team

PMT org chart

Workload information resources


CV
Performing Organization
(Functional Managers)
10.1.2. - acquire Project Management Team

ORDER ACQUISITION PROCESS

10.1.1. - develop Project Charter

10.1.3. - identify Stakeholders

Customer
Contact Information

Project
Charter

Stakeholder R
10.1.3. - identify Stakeholders

M1010

Project Kick-off

Project M
10.1.1. - develop Project Charter

Project Charter

Project Baseline
(scope, time & cost)
10.2.7. - approve Project Baseline

10.2.1. - develop Project management Plan

10.2.1. - develop Project Management


Plan

Requireme

10.2.1. - develop Project Management


Plan

10.4.5. - perform Integrated Change


Control

ORDER ACQUISITION PROCESS

10.2.2. - collect Requirements and define Scope

Requirements Management
Plan

Approved
Change Requests

Customer
Contact Information

10.2.2. - collect Requirements and


define Scope

Project

Proposal WBS
ORDER ACQUISTION PROCESS

Requirements Matrix;
Project Scope Statement
10.2.2. - collect Requirements and
define Scope

10.2.3. - develop WBS

10.2.3. - develop WBS

WBS
WBS dictionary

Project Execution proposal


(Proposal Master Schedule);
Contract (Customer milestones)
ORDER ACQUISTION PROCESS

10.2.3. - develop WBS

10.2.6. - identify, analyse and plan


response to Risks

WBS
WBS dictionary

Risk Register
(Schedule Contingency Reserve)

project target set by Project Sponsor


(Time)
10.1.1. -develop Project Charter

10.2.4. - develop Schedule

10.2.4. - develop Schedule

Project Schedul
Schedule Basel

ORDER ACQUISTION PROCESS

10.2.3. - develop WBS

10.2.4. - develop Schedule

10.2.6. - identify, analyse and plan


response to Risks

10.2.1. - Develop Project


Management Plan

Cost Estimates

WBS
WBS dictionary

Project Schedule
Schedule Baseline

Risk Register
(Cost Contingency Reserve)

- Procurement Management Plan


(Make or Buy Strategy)
- Human Resource Plan
(Resource Staffing Plan)
project target set by Project Sponsor
(Cost)

10.1.1. -develop Project Charter

10.2.5. - estimate Costs and determine Budget

10.2.5. - estimate Costs and


determine Budget

Cost Baseline

10.2.1. - develop Project Management


Plan

Risk
Management Plan

10.2.6. - identify, analyse and plan


response to Risks

Requirements Matrix
Project Scope Statement
10.2.2. - collect Requirements and
define Scope

10.1.3. - identify Stakeholders

Lessons Learned

Stakeholders Register
Performing Organization

(Schedule Co

10.2.6. - identify, analyse and plan response to Risks

M1040

M1020
Project Scope Statement
10.2.2. - collect Requirements and
define Scope

10.2.3. - develop WBS

10.2.4. - develop Schedule

10.2.5. - estimate Costs and


determine Budget
10.2.7. - definee Project Baseline

10.2.7. - define Project Baseline

WBS
WBS dictionary

Schedule Baseline

Cost Baseline

Project Ba
(during M1
Meeting)

Initial Proje

Project Baseline

M1030

PMT meeting

Project M

Project Management Plan


10.2.1. - develop Project Management
Plan

10.2.7. - define Project Baseline

10.2.6. - perform Integrated Change


Control

10.3.1. - direct and manage Project


Execution

Project Baseline

approved
Change Requests

10.3.1. - direct and manage Project Execution

10.2.1. - develop Project Management


Plan

Quality
Management Plan

work performance data


10.3.1. -direct and manage Project
Execution

10.4.8. - perform Quality Control

10.3.2. - perform Quality Assurance

quality checklist completed;


NCs

10.3.2. -perform Quality Assurance

Lessons Learned;
Quality audit report;
KPI

Performing Organization

Human Re
10.2.1. - develop Project Management
Plan

Human Resource
Management Plan

work performance data


10.3.1. -direct and manage Project
Execution
10.3.3. - develop and manage Project Team

10.3.3. - develop and manage Project


Team

M1040

M1050

M1060

10.2.1. - develop Project Management


Plan

10.3.1.- direct and manage Project


Execution

Communications
Management Plan

work performance data


issue log

10.4.5. - monitor and control Project


Performance

Stakeholders Register
10.1.3. - identify Stakeholders

10.3.4. - distribute Information and Manage Stakeholder Expectations

Project Status Report to Cust

Customer Satisfaction Survey

10.3.4.- distribute Information and


manage Stakeholder Expectations

Project Performance Report


Project Status Report to Customer

Project Sponsor
work performance
reports

Project Performance Review

Project Stakeholders

10.2.1. - develop Project Management


Plan

Procurement
Management Plan

10.3.5. - conduct Procurements

work performance data


10.3.1. -direct and manage Project
Execution

Procureme

10.3.5. - conduct Procurements

work perf
10.2.1. - develop Project Management
Plan

10.3.1. -direct and manage Project


Execution

10.4.1. - control Scope

Procurement
Management Plan

work performance
data
(status of deliverable)

10.4.1. - control Scope

10.2.1. - develop Project Management


Plan

10.3.1. -direct and manage Project


Execution

10.4.2. - control Schedule

Procurement
Management Plan

work performance
data
(schedule progress)

work perf
10.4.2. - control Schedule

work perf
10.2.1. - develop Project Management
Plan

10.3.1. -direct and manage Project


Execution

10.4.3. - control Costs

Procurement
Management Plan

work performance
data
(cost incurred)

10.4.3. - control Costs

10.2.6. - develop Project Management


Plan

Procurement
Management Plan

work performance
data
10.3.1. -direct and manage Project
Execution
10.4.4. - monitor and control Risks

10.4.4. - monitor and control Risks

10.4.1. - control Scope

work performance
data

work performance information


(schedule forecasts)
10.4.2. - control Schedule

work performance information


(cost forecasts)
10.4.3. - control Costs

Risk Register
10.4.4. - monitor and control Risks

10.4.5. - monitor and control Project Performance

10.4.5. - monitor and control Project


Performance

change request
10.4.6. - perform Integrated Change
Control

10.4.1. - control Scope

proposed changes;
NCs

change request
10.4.2. - control Schedule

10.4.8. - perform Quality Control

change request
10.4.3. - control Costs

change request
10.4.4. - monitor and control Risks

change request
10.3.4. - distribute information and
manage stakeholder information

10.4.6. - perform Integrated Change Control

10.3.1. - direct and manage Project


Execution

completed
deliverables

M1070

10.2.1. - develop Project Management


Plan

10.4.8. - perform Quality Control

10.4.7. - verify Scope

Scope Baseline
(incl acceptance
criteria)

validated
deliverables

10.4.7. - verify Scope

Request fo

10.2.1. - develop Project Management


Plan

Quality
Management Plan

work performance data


10.3.1. -direct and manage Project
Execution

10.4.8. - perform Quality Control

quality c
10.4.8. -perform Quality Control

Procuremen
10.2.1. - develop Project Management
Plan

10.3.1. -direct and manage Project


Execution

10.4.9. - administer Procurements

Procurement
Management Plan

Work performance
data
Completed deliverable

10.4.9. - administer Procurements

Inspec
exped

10.4.9. - administer Procurements

Inspection and
expediting report

Acceptance documents
10.4.9. - verify Scope

10.5.1. - close Procurements

10.5.1. - close Procurements

M1080

Handover

Final Acceptance
Customer

GC __
Final Acceptance

10.4.6. - verify Scope

M1090

10.5.2. - close Project

Close-out Report
10.5.1. - close Procurements

closed
Procurements

Performing Organization

10.5.2. - close Project

Project C

Project Charter

10.1.2. - acquire Project Management


Team

10.1.3. - identify Stakeholders

10.2.1. - develop Project Management


Plan

PMT org chart

Workload information resources


CV

10.2.1. - develop Project Management


Plan

Stakeholder Register
10.2.1. - develop Project Management
Plan

10.2.6. - identify, analyse and plan


response to Risks

Project Management Plan


10.3.1. - direct and manage Project
Execution

Requirements Management
Plan

Quality
Management Plan

Quality
Management Plan

Human Resource
Management Plan

Communications
Management Plan

Risk
Management Plan

10.2.2. - collect Requirements and


Define Scope

10.3.2. - perform Quality Assurance

10.4.8. - perform Quality Control

10.3.3. - develop and manage Project


Team

10.3.4. - distribute Information and


manage Stakeholders Expectations

10.2.6. - identify, analyse and plan


response to Risks

Procurement
Management Plan
10.3.5. - conduct Procurements

Requirements Matrix;
Project Scope Statement

10.2.3. - develop WBS

Project Scope Statement


10.2.7. - approve Project Baseline

WBS
WBS dictionary

10.2.4. - develop Schedule

10.2.5. - estimate Costs and


determine Budget

10.2.7. - approve Project Baseline

Project Schedule
Schedule Baseline

10.2.5. - estimate Costs and


determine Budget

10.2.7. - approve Project Baseline

Cost Baseline

10.2.7. - approve Project Baseline

Risk Register
(Schedule Contingency Reserve)

10.2.4. - develop Schedule

Risk Register
(Cost Contingency Reserve)
10.2.5. - estimate Costs and
determine Budget

Risk Register

10.4.4. - monitor and control Risks

Project Baseline Update I


(during M1040 Project Performance Review
Meeting)
Initial Project Baseline Approval

Project Baseline

10.3.1. - direct and manage Project


Execution

Project Management Plan


(updates)
10.2.1. - develop Project Management
Plan

work performance data


(status of deliverables)

work performance data


(schedule progress)

10.4.1. - control Scope

10.4.2. - control Schedule

work performance data


(costs incurred)
10.4.3. - control Costs

work performance data


10.3.2. - perform Quality Assurance

work performance data


10.4.8. - perform Quality Control

work performance data


issue log

10.3.4. - distribute Information and


manage Stakeholders Expectations

work performance data


10.4.4. - monitor and control Risks

work performance data


10.4.9. - administer Procurements

work performance data


Change Requests

10.4.6. - perform Integrated Change


Control

10.4.6. - perform Integrated Change


Control

work performance data


10.3.5. - conduct Procurements

work performance data

10.3.3. - develop and manage Project


Team

Quality Management Plan


(updates)

10.2.1. - develop Project Management


Plan

Human Resource Management


Plan (updates)
10.2.1. - develop Project Management
Plan

Project Performance Review Meeting

Project Status Report to Customer

Customer Satisfaction Survey

Change
Requests

Project Performance Report


Project Status Report to Customer

10.4.6. - perform Integrated Change


Control

Customer Satisfaction Survey

Performing Organization

Purchase Orders
10.4.9. - administer Procurements

Sourcing Plan (updates)


10.4.5. - monitor and control Project
Performance
Procurement Management Plan
(updates)
10.2.1. - develop Project Management
Plan

work performance information


10.4.5. - monitor and control Project
Performance

Change
Requests

NCs

10.4.6. - perform Integrated Change


Control

10.4.8. - perform Quality Control

work performance information


(schedule forecast)
10.4.5. - monitor and control Project
Performance

Change
Requests

NCs

10.4.6. - perform Integrated Change


Control

10.4.8. - perform Quality Control

work performance information


(cost forecast)
10.4.5. - monitor and control Project
Performance

Change
Requests

NCs

10.4.6. - perform Integrated Change


Control

10.4.8. - perform Quality Control

Risk Register updates


10.4.5. - monitor and control Project
Performance

work performance reports


10.3.4. - distribute Information and
manage Stakeholder Expectations

Project Management
plan updates

10.2.1. - develop Project Management


Plan

approved changes
10.2.2. - collect requirements and
define scope
proposed changes;
NCs

approved changes
10.3.1. - direct and manage project
execution

Request for Final Acceptance

accepted deliverables
10.5.2. - close Project

quality checklist completed;


NCs
10.3.2. - perform Quality Assurance

proposed changes;
NCs
10.4.6. - perform Integrated Change
Control

Procurement Management Plan


(updates)
10.2.1. - develop Project Management
Plan

Inspection and
expediting report

10.1.5. - close Procurements

Sourcing Plan (updates)


10.4.5. - monitor and control Project
Performance

closed
Procurements

10.5.2. - close Project

Handover to After-Sales

Project Close-out Report

AFTER-SALES
PROCESS

INITIATING

PROCESS GROUPS

KNOWLEDGE AREAS

GC __
Contract Award

M.1000

Handover from
Sales

Contract

INTEGRATION MANAGEMENT

CAP form

10.1.1. - develop
Project Charter
Project Charter

SCOPE MANAGEMENT

TIME MANAGEMENT

COST MANAGEMENT

QUALITY MANAGEMENT

HUMAN RESOURCE MANAGEMENT

COMMUNICATIONS MANAGEMENT

RISK MANAGEMENT

PROCUREMENT MANAGEMENT

___

documents/deliverables from
external processes
___

documents/deliverables
produced as outputs from

10.1.2 - acqu
Manageme

10.1.3 - id
Stakeho

___

P10 processes

ter

PLANNING

M.1010

Project Kick-off
Meeting

10.2.1. - develop
Project Management
Plan
Project Management
Plan

10.2.1.a. - develop
Requirements
Management Plan
Requirements
Management
Plan

10.2.1.b. - develop
Quality Management

10.2.2. - collec
Requirements a
define Scope

10.2.1.b. - develop
Quality Management
Plan
Quality
Management
Plan

2 - acquire Project
nagement Team
PMT org chart

0.1.3 - identify
Stakeholders
Stakeholders
Register

10.2.1.c. - develop
Human Resource
Management Plan
Human Resource
Management
Plan

10.2.1.d. - develop
Communications
Management Plan
Communications
Management
Plan

10.2.1.e. - develop Risk


Management Plan
Risk
Management
Plan

10.2.1.f. - develop
Procurement
Management Plan
Procurement
Management
Plan

M.1040

M.1020

10.2.7. - Define Project


Baseline

Project Baseline (S
Schedule and Cost
to be approved

Proposal WBS
(egg NPS file)

. - collect
ments and
e Scope

10.2.3. - develop WBS

Requirements Matrix

WBS and
WBS dictionary

Project Scope
Statement
Project Execution
Proposal

10.2.4. - develop
Schedule
Project Schedule
Schedule baseline

Cost
Estimates

10.2.5. - estimate Costs


& determine Budget
Cost Estimates
Cost baseline

10.2.6. - identify
analyse and plan
Response to Risks
Risk
Register

1040

1020

EXECUTING

MONIT

Project Baseline
update (during
periodic "M1040
Project Review
Meeting")
Initial Project
Baseline Approval

seline (Scope,
and Cost baseline)
oved

M.1030

(periodic) Project
Management Team
(PMT) Meeting

10.3.1. - direct &


manage Project
Execution
Work performance data
- Engineering & Design
- Procurement
- Manufacturing
- Installation
- Commissioning &
Start-up

issue log /
action register
Completed
Deliverables

ne

10.3.2. - perform

10.3.2. - perform
Quality Assurance
Lessons Learned
Quality Audit Reports

10.3.3. - develop and


manage Project Team

Resource staffing plan


Updated employee
training records

M.1040

10.3.4. - distribute
Information and
manage Stakeholder
Expectations
Project Status Report
to Customer

M.1050

M.1060

Project Performance
Report
Change Request

10.3.5. - conduct
Procurements
Sourcing Plan

(periodic)
Project Review
Meeting
(periodic)
Project Status Report
to Customer

Customer Satisfaction
Survey

NITORING & CONTROLLING

10.4.5. - monitor and


control Project
Performance

10.4.6. - perform
Integrated Change
Control
Approved Changes

10.4.7. -

10.4.1. - control Scope


Change Requests
Non-Conformities
(NC System )

10.4.2. - control
Schedule
Change Requests
Non-Conformities
(NC System )

10.4.3. - control Costs


Change Requests
Non-Conformities
(NC System )

10.4.8. - perform

10.4.8. - perform
Quality Control
Non-Conformities
(NC System )

10.4.4. - monitor &


control Risks
Risk Register updates;
Contingency Reserve
updates

10.4.9. - administer
Procurements
Inspection &
Expediting Reports

CLOSING

GC80
Final Acceptance

M.1080

M.1090

10.5.2. - close Project


Project Closing Form

M.1070

Request for Final


Acceptance

10.4.7. - Verify Scope


Acceptance documents
(e.g. Buy-off Book) duly
completed

Handover to After
Sales
Project Close-out
Report

&
Reports

10.5.1. - close
Procurements
Closed
procurements
Claim settlement

P10 - PROJECT MANAGEMENT

ENT

P10 - PROJECT MANAGEMENT

GC __
Contract Award

M1000
Handover from
Sales

M1010
Project Kick-off
meeting

P10.1 INITIATING

M1020
M1030
Initial Project
(periodic)
Baseline Approval PMT Meeting

P10.2 PLANNING

335081696.xlsx - 10 - PROJECT MANAGEMENT

M1050
M1040
(periodic)
(periodic)
Project Status
Project Review
Report to Customer
Meeting

M1060
Customer
Satisfaction
Survey

P10.3 EXECUTING

P10.4 MONITORING AND CONTROLLING

page 78 of 247

P10.4 MONITORING AND CONTROLLING

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 79 of 247

P2 - SALES
GC __
Contract Award

M1000
M1000
Handover from
Sales

P10.1 INITIATING

10.1.1 develop Project Charter

10.1.2 acquire Project Management Team

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 80 of 247

10.1.3. identify Stakeholders

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 81 of 247

M1020
Initial Project
Baseline Approva

M1010
Project Kick-off
meeting

P10.2 PLANNING

10.2.1
Develop Project
Management
Plan
10.2.2
Collect
Requirements
and Define Scope

10.2.3
Develop WBS

10.2.4
Develop Schedule

10.2.5
Estimate Costs and
Determine Budget
335081696.xlsx - 10 - PROJECT MANAGEMENT

page 82 of 247

10.2.5
Estimate Costs and
Determine Budget

10.2.6
Identify, Analyse and Plan
Response to Risks

10.2.7
Define Project
Baseline

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 83 of 247

M1030
(periodic)
PMT
meeting

M1040
(periodic)
Project Review Meeting

M1050
(periodic)
Project Status
Report to Customer

M1060
Customer
Satisfaction Survey

P10.3 EXECUTING

10.3.1
Direct and manage Project Execution

10.3.2
Perform Quality Assurance

10.3.3
Develop and manage Project Team

10.3.4
Distribute Information and manage Stakeholders Expectations

10.3.5
Conduct Procurements
335081696.xlsx - 10 - PROJECT MANAGEMENT

page 84 of 247

10.3.5
Conduct Procurements

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 85 of 247

P10.4 MONITORING AND CONTROLLING

10.4.1
Control Scope

10.4.2
Control Schedule

10.4.3
Control Cost

10.4.4
Monitor and Control Risks
10.4.5
Monitor and control
Project Performance

335081696.xlsx - 10 - PROJECT MANAGEMENT

10.4.6
Perform Integrated
Change Control

page 86 of 247

10.4.8
Perform Quality Control

10.4.9
Administer Procurements

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 87 of 247

GC 80
Final
Acceptance

M1080
Handover to
After Sales

P10.5 CLOSING

10.5.1
Close Procurements

335081696.xlsx - 10 - PROJECT MANAGEMENT

10.5.2
Close Project

page 88 of 247

GC 80
Final Acceptance

M1060
M1070
Customer
SatisfactionRequest for Final
Acceptance
Survey

M1080
Handover to
After Sales

M1090
Project Close-out
Meeting

P10.5 CLOSING

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 89 of 247

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 90 of 247

M1010
Project Kick-off
meeting

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 91 of 247

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 92 of 247

M1020
M1040
Initial Project
(periodic) Project
Baseline Approval Performance Review Meeting

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 93 of 247

10.2.7
fine Project
Baseline

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 94 of 247

M1060
Customer
atisfaction Survey

xpectations

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 95 of 247

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 96 of 247

M1070
Request for
Final
Acceptance

ING

10.4.6
m Integrated
nge Control
10.4.7
335081696.xlsx - Verify
10 - PROJECT MANAGEMENT
Scope

page 97 of 247

10.4.7
Verify
Scope

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 98 of 247

M1090
Project Closeout Meeting

335081696.xlsx - 10 - PROJECT MANAGEMENT

page 99 of 247

glossary of terms and acronyms


acronym

term

ACU

Approved Current

BCU

Budget Current

CAP

contract approval package

COF / CPQ

cost of failure / cost of poor quality

MOD

Modification

NC

Non Conformity

335081696.xlsx - GLOSSARY

page 100 of 247

glossary of terms and acronyms


acronym

term

NCS

NC system

PM

project manager

PgM

program manager

PfM

project portfolio manager

PMD

project management director

PMT
PMP

project management team


Project Management Plan

PMIS

project management information system

335081696.xlsx - GLOSSARY

page 101 of 247

glossary of terms and acronyms


acronym
acronym

term
term

PMdb

Project Management database

PMO

Project Management Office

performing organization
project sponsor

functional manager
contract

project statement of work

QCU

Quotation Budget

Schedule Baseline
VAR

Variation

WBS

work breakdown structure

335081696.xlsx - GLOSSARY

page 102 of 247

glossary of terms and acronyms


acronym

term
work breakdown structure dictionary

work performance data

work performance information

work performance report

335081696.xlsx - GLOSSARY

page 103 of 247

definition

ref.

ACU is GPS/SAP term to indicate the rolling financial status of a project and contains the forecasted total cost of the project
GPS
(EAC - Estimate At Completion in PMI terms). ACU is equivalent to POR term referred in the COMAU Policy 16.
In practical terms ACU contains:
Actual costs (Purchasing Orders with good/services already delivered)
Committed costs (Purchasing Requisition and Purchasing Orders without delivery)
ETC (Estimate to Complete, the forecasted remaining work).
The ACU contains the EAC costs covering both Customers Scope of Supply and COMAU errors/reworks. ACU can be compared
with project Revenues to calculate project margin.

BCU is GPS/SAP term to indicate the initial project budget and represents the cost of the project referred to the Customers
GPS
Scope of Supply. During project life BCU is updated with costs coming from new Customer Change Orders or might be updated
(as per Project Sponsor decision) costs that are not depending upon the team responsibility (e.g.,. Make / Buy or Job Sharing
changes). BCU is equivalent to POI term referred in the COMAU Policy 16. BCU is the project performance baseline; B00 is the
initial project performance baseline formally approved by project sponsor

Tool to be filled by sales manager as per Policy 14

COMAU Policy 14

COF / CPQ is any variation from the Project Baseline (Quality, Time and Costs) not covered by Customer Revenues. In ERP
(e.g.,. SAP) (and project reporting terms) COF can be seen as equal to the difference between ACU (POR) and BCU (POI)
related to Team or difference between ACU (POR) and QCU (PV + changes) related to the company

Non Conformity
Management
Methodology

Comau Extra cost or Non Conformity define as a change of the Supply Volume (Materials & Activities) derived by a noncompliance between requisites & deliverables, generating impact on Cost, Resources and Timing.
this also includes: Work product not performed or delivered in expected condition or time

Non Conformity
Management
Methodology

Change of the Supply Volume (Materials & Activities) or non-compliance between requisites & deliverables, both generating
potential impact on Cost, Revenue, Resources and Timing.
this also includes: Work product not performed or delivered in expected condition or time

Non Conformity
Management
Methodology

335081696.xlsx - GLOSSARY

page 104 of 247

definition

ref.

It is a system that allows Non Conformities management as follows


Standardize and improve visibility of Projects, Product and Department issues in order to address proper (preventive)
recovery actions.
Perform timely application of (corrective) recovery actions.
Maintain a history of problems and solutions to create a lesson learned data base.
Measure:
Covering of Cost of Failure with NCs (Project Product and Standard Product) providing improved understanding to company
results impacts.
NC corrective action effectiveness.
Effectiveness of establishing Root Cause Analysis criteria (related to main problems).
NC closure timing and application (e.g. open and closure rates).
Effectiveness of addressing departmental systemic issues for improvement (e.g., error code analysis).
Effectiveness of Root Cause Analysis (related to correcting main problems).
COF by project and or functional departments for analysis.

Non Conformity
Management
Methodology

the person assigned by the performing organization to manage the project and achieve the project objectives

PMBOK

the person assigned by the performing organization to manage related projects in a coordinated way to obtain benefit and
PMBOK
control not available from managing them individually
the person responsible for the high-level governance of a collection of projects or programs, which are carried on at a certain PMBOK
moment in time by the performing organization
according to COMAU organizational announcements, the global or regional director of Project Management, with management COMAU Policy 16
authority over the PMs. He/she also acts as portfolio manager for the relevant project portfolio
the members of the project team who are directly involved in project management activities
a formal approved document that defines how the project will be executed, monitored and controlled

PMBOK
PMBOK

an information system used to gather, integrate and disseminate the outputs of project management processes. In its
simplest form it consists of a document repository, in more advanced use it may include collaboration work areas (e.g.,
SharePoint)

PMBOK

335081696.xlsx - GLOSSARY

page 105 of 247

definition
definition

ref.
ref.

an information system used to gather, integrate and disseminate data about project performance. It is maintained by PMO
with inputs from PfM and PM
the organizational body under the Contract & Project Management Vice President of COMAU assigned various responsibilities
related to the centralized and coordinated project governance for the entire COMAU portfolio. It is organized in global and
local entities supporting performing organizations in executing the projects

COMAU Policy 16

the COMAU entity executing the project; according to project size and characteristics it may be a local, regional, or global
organization
an executive manager of the performing organization at a level that is adequate for funding the project (i.e. normally the
responsible for the profit & loss or, upon his/her delegation, a manager directly reporting to him/her)

COMAU Policy 16

a person with management authority over an organizational unit (e.g., Engineering, Supply Chain, Manufacturing, ...) within
the performing organization or CIO
in legal terms a contract is a mutually binding agreement that obligates the seller to provide a specified service, product or
result, and obligates the buyer to pay for it.
For COMAU projects, which are done for an external customer, the contract includes documents either of technical nature
(e.g., specifications, standards,...) or commercial and/or contractual nature (e.g., terms & conditions, ...)

COMAU Policy 16

COMAU Policy 16

COMAU Policy 16

PMBOK

the statement of work (SOW) is a description of products or services to be delivered by the project. For COMAU projects, which PMBOK
are done for an external customer, the SOW is received as part of bid documents and/or as part of the contract and may
include COMAU technical proposal
QCU is GPS/SAP term to indicate the initial quotation budget and represents the cost of the project referred to the as sold
Customers Scope of Supply realized by Sales Proposal & Estimating. During project life QCU can be updated with costs
coming from new Customer Change Orders. Q00 (QCU as sold) is equivalent to PV term referred in the COMAU Policy 16.

GPS

A Schedule Baseline is the specific version of the schedule used to record the original version to which actual schedule che be
compared.
Customer Change Order / Request
Non Conformity
Management
Methodology
a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create
the required deliverable. It organizes the total scope of the project

335081696.xlsx - GLOSSARY

PMBOK

page 106 of 247

definition

ref.

a document that describes each component in the WBS. For each WBS component, the WBS dictionary includes a brief
definition of the scope or statement of work, defined deliverables(s), a list of associated activities and a list of milestones

PMBOK

the raw observations and measurements identified during activities being performed to carry out the project work. Examples
include reported percent of work physically completed, technical performance measures, start and finish dates of schedule
activities, number of change requests, number of defects, actual costs, actual durations etc.

PMBOK

the performance data collected from various controlling processes, analysed in context and integrated based on relationship
across areas. Examples include status of deliverables, implementation status for change requests, forecasted estimates to
complete

PMBOK

the physical or electronic representation of work performance information complied in project documents, intended to
generate decisions, actions, or awareness. Examples include status reports, memos, justifications, information notes,
recommendations

PMBOK

335081696.xlsx - GLOSSARY

page 107 of 247

Comau Global P10


Document

Document Name

GOW-P10

Overview

Document Type

Level

GAC-P10.0

Activity Card

GEC-M1000
GEC-M1010

Event
Event
Event
Event

2
2
2
2

GCL-P7-M710
GCL-P7-M720
GCL-P7-M730
GCL-P7-M740

Process
Process
Process
Process

Card
Card
Card
Card
Check-List
Check-List
Check-List
Check-List

2
2
2
2

GCL-PMO-xxx

N.A.

Production Check-List

GFR-PMO-110
GFR-PMO-120
GFR-PMO-130
GFR-PMO-140
GFR-PMO-150
GFR-PMO-160
GFR-PMO-160A
GFR-PMO-160B
GFR-PMO-160C
GFR-PMO-160D
GFR-PMO-160E
GFR-PMO-160F
GFR-PMO-160G
GFR-PMO-160H
GFR-PMO-160I
GFR-PMO-170
GFR-PMO-180
GFR-PMO-190
GFR-PMO-200
GFR-PMO-210
GFR-PMO-220
GFR-PMO-230
GFR-PMO-240
GFR-PMO-241
GFR-PMO-242
GFR-PMO-243

Resource Staffing Plan example


WBS dictionary example
Stakeholder Register
Project Charter
Risk Register
Project Management Plan
Project Management Approach
Quality Management Plan
Human Resource Management Plan
Communications Management Plan
Risk Management Plan
Procurement Management Plan
Requirements Management Plan
Change Management Plan
Project Baseline
Project Status Report to Customer example
Project Status Report
Change Authorization Form
Change Request Log
Customer Satisfaction Survey
Internal Order
Project Close-out Report
Project Closing form

Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form
Form

Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template
Template

3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3

Form / Template

GOI-PMO-110
GOI-PMO-120
GOI-PMO-130
GOI-PMO-140
GOI-PMO-150
GOI-PMO-160
GOI-PMO-170
GOI-PMO-180
GOI-PMO-190

Risk Management
PMIS
Change Management

Operating
Operating
Operating
Operating
Operating
Operating
Operating
Operating
Operating

3
3
3
3
3
3
3
3
3

/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/

Instructions
Instructions
Instructions
Instructions
Instructions
Instructions
Instructions
Instructions
Instructions

Notes

Format

ACTIVITY CARD
P10.1.1. - Develop Project Charter
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

Customer;
Sales

Contract
or
formal document directing
COMAU to proceed with the
project (*);

P10.1.1.1 - Draft Project Charter


PfM
Upon Project Sponsor instruction, the Project Portfolio Manager (PfM)
shall prepare the Project Charter, clearly indicating project objectives
and applicable contractual documentation.

BY

A PM should be identified and assigned as early as possible by the


Contract Approval Package (CAP PfM, and in any case before the Project Kick-off Meeting
form) completed from P2 process (M1010). The PfM may delegate the preparation of the project
charter to the PM.
The PfM will collect necessary information to draft the Project
Charter from Sales, who shall make available the complete
documentation developed during proposal as well as the complete
all documents latest at the Handover from Sales (M1000).

PfM

Project Charter (GFR-PMO-140)


to be approved

335081696.xlsx - 10.1 - INITIATING

P10.1.1.2 - Define Project ID


The project _ID is defined by FA&C.

FA&C

page 109 of 247

PfM

Project Charter (GFR-PMO-140)


to be approved

P10.1.1.3 - Approve Project Charter


Project Sponsor; PfM
The Project Charter, when formally approved by the Project Sponsor
and signed for acknowledgment by Project Manager (PM), provides
him/her with the authority to apply organizational resources to
project activities.
Project Sponsor, at his/her option, may establish targets for project
objectives which are different from those identified during the Order
Acquisition process.
Project Sponsor shall also define PM level of authority with regard to:
value and %margin of quotations that are submitted for customer
change requests;
amount of changes that can be initiated before a fix price is
negotiated;
amount of COF and/or variance of overall project margin caused by
COF requiring prior Project Sponsor approval for funding.

Project Sponsor;

Project Charter (GFR-PMO-140)


approved by Project Sponsor

P10.1.1.4 - Initialize PMIS


PM; PMO
The PM, assisted by the PMO, shall initialize the Project Management
Information System (PMIS) to be used as project documentation
repository.

Project Sponsor;

Project Charter (GFR-PMO-140)


approved by Project Sponsor

P10.1.1.5 - Initialize PMdb


When applicable, the PfM shall also initialize the project into the
Portfolio Management Database (PMdb).

PfM

(*) Project Sponsor may decide to charter a project also without a formal customer instruction, and/or with an incomplete scope definition, when this is considered appropriate.
In such a case this shall be clearly stated in the Project Charter and the PfM is responsible to notify this to the respective PMO
aligns with PMBOK Fourth Edition: 4.1. "Develop Project Charter"
aligns with COMAU Policy #16: section 3.1.1. "Authorizing a new project"

335081696.xlsx - 10.1 - INITIATING

page 110 of 247

ACTIVITY CARD

P10.1.2. - Acquire Project Managem


FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

Although PMBOK places "Acquire Project Team" in the Executing


Processes Group, considering that involvement of PMT members in
the early phases of the project and particularly in the definition of
the initial baseline, this process has been included in the Initiating
Processes Group
The Project Management Team (PMT) include all individuals who are
directly involved in project management activities.
The PMT for COMAU projects will typically include:
project manager;
project controller;
technical leaders (mechanical and controls);
CIO leader;
site manager;
depending on the type, size and characteristics of the specific
project, the PMT may also include:
material planner;
project planner;
project estimator;
supply chain leader;
manufacturing leader;
The PM is required to reflect the impact of any unavailability of
required human resources in the project schedule, project budget,
project risks, project quality, training plans, and other project
management plans as required.
When feasible PMT members should be placed in the same physical
location to enhance their ability to perform as a team.

335081696.xlsx - 10.1 - INITIATING

page 111 of 247

functional managers workload information;


resources CV's

P10.1.2. - Acquire Project Management Team


PMT members are drawn from available sources considering
availability, ability, experience and interest. The selection of PMT
members is made by their respective functional managers, but the
PM, with the appropriate backup from PfM, should effectively
negotiate and influence the decision.

functional managers;
PM (PfM)

Ideally the PMT should be completely defined before Project kickoff meeting (M1010); when a specific role is not covered yet the
respective functional manager shall be involved.

aligns with PMBOK Fourth Edition: 9.2. "Acquire Project Team"


aligns with COMAU Policy #16: section 3.1.2. "Acquire and Manage Project Team"

335081696.xlsx - 10.1 - INITIATING

page 112 of 247

ACTIVITY CARD
P10.1.3. - Identify Stakeholders
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

Project Stakeholders are persons and organizations that are actively


involved in the project or whose interests may be positively or
negatively affected by the execution or completion of the project
For COMAU projects, Project Stakeholders (other than those internal)
are typically individuals in the customer organization, but there may
be also suppliers or third parties such as local authorities. It is
critical for project success to identify them early in the project, and
to analyse their levels of interest, expectations, importance and
influence.

Project Sponsor;
Customer;
Sales; Proposals

project charter (GFR-PMO-140);


customer contact information;
proposal documentation;
lessons learned

335081696.xlsx - 10.1 - INITIATING

P10.1.3.1 - Stakeholders Identification, Assessment &


PM
Classification
During the early stage of the project the PM, with the contribution of
the other PMT members, shall gather information from available
sources (e.g., Customer information, proposal documentation,
subject matter experts, such as, but not limited to, project managers
who have worked on projects on the same area) to identify all
project stakeholders.

page 113 of 247

PMT

Stakeholder Register (GFR-PMO- P10.1.3.2 - Stakeholders Assessment & Classification


130) (identification)
The PM, when deemed appropriate, may then identify the potential
impact each stakeholder could generate, and classify them so as to
define an approach strategy. Classification models include:
power/interest grid, grouping the stakeholders based on their
level of authority ("power") and their level of concern ("interest")
regarding the project outcome;
power/influence grid, grouping the stakeholders based on their
level of authority ("power") and their active involvement
("influence") in the project;
influence/impact grid, grouping the stakeholders based on their
active involvement ("influence") in the project and their ability to
effect changes to the project's planning or execution ("impact").

PM

PMT

Stakeholder Register (GFR-PMO- P10.1.3.3. - Stakeholder Risks Identification


130)
During this process the PMT may identify risks which shall be
captured in the risk register.

PMT

aligns with PMBOK Fourth Edition: 10.1. "Identify Stakeholders"


aligns with COMAU Policy #16: Policy does not spell out this specific process

335081696.xlsx - 10.1 - INITIATING

page 114 of 247

Develop Project Charter


TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Project Charter template

Project Charter (GFR-PMO-140)


to be approved

Project Sponsor
PM

ERP (SAP, Baan, )

ERP entry (project_ID)

PfM, PMT

335081696.xlsx - 10.1 - INITIATING

page 115 of 247

PMIS (GOI-PMO-120)

PMdb

Project Charter (GFR-PMO-140)


approved by Project Sponsor

Project Sponsor
PM

PMIS documentation repository

PMT, stakeholders

PMdb entry

PMO

when this is considered appropriate.

335081696.xlsx - 10.1 - INITIATING

page 116 of 247

Acquire Project Management Team


TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

335081696.xlsx - 10.1 - INITIATING

FOR

page 117 of 247

organization chart template


included in the Human Resource
Management Plan" document
(GFR-PMO-160C)

PMT organization chart included PMT;


in the Human Resource
functional
Management Plan document
managers
(GFR-PMO-160C)

335081696.xlsx - 10.1 - INITIATING

page 118 of 247

Identify Stakeholders
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

Stakeholder Analysis

Stakeholder Register (GFR-PMO- PMT


130) (identification)

335081696.xlsx - 10.1 - INITIATING

FOR

page 119 of 247

Stakeholder Analysis

Stakeholder Register (GFR-PMO- PMT


130) (assessment &
classification)

Stakeholder Analysis

identified risks in the risk


register (GFR-PMO-150)

335081696.xlsx - 10.1 - INITIATING

PMT

page 120 of 247

ACTIVITY CARD
P10.2.1. - Develop Project Management Plan
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

PM

Project Management Plan


template (GFR-PMO-160)

Project Management Plan (GFRPMO-160)

PMT

PM; PMT

Project Management Approach


template (GFR-PMO-160A)

Project Management Approach


(GFR-PMO-160A)

PMT

The Project Management Plan is a formal, approved document that


defines how the project is executed monitored and controlled. It
may be a summary or detailed document and may be composed of
one or more subsidiary management plans.

Project Sponsor;
Sales; Proposal

Project Charter (GFR-PMO-140); P10.2.1.1 - Draft Develop Project Management Plan


Contract;
The PM, with the contribution of the other PMT members, shall
outputs from planning processes develop a Project Management Plan which:
- selects the subsidiaries plans will be developed for the project;
- includes the selected subsidiaries plans.
The PM shall select the appropriated subsidiaries plans according to
the type and size of project.
The Project Management Plan (PMP) may include:

Sales

CAP form

P10.2.1.1.1 - Project Management Approach is the


document where the PMT select the project management
processes to be applied on the project. The selection
depends on the type and size of project.

Project Sponsor

Approved Project Baseline (GFRPMO-160I)

P10.2.1.1.2 - Project Baseline including Scope, Schedule PM


and Cost baseline (is an output of process 10.2.7.)

Customer

Contract Documents

P10.2.1.1.3 - Change Management Plan that documents PM; Sales Manager


how customer changes will be monitored and controlled;

Change Management Plan


template (GFR-PMO-160H)

Customer

Contract Documents

P10.2.1.1.4 - Requirements Management Plan,


describing how the project requirements will be fully
analysed and documented by the PMT

PM

Requirements Management Plan Requirements Management Plan PMT;


template (GFR-PMO-160G)
(GFR-PMO-160G)
functional managers

PMT

Project Schedule

P10.2.1.1.5 - Quality Management Plan, documenting


quality requirements and/or standards for the project and
how the PMT will demonstrate compliance

PM;
QA manager

Quality Management Plan


template (GFR-PMO-160B)

P10.2.1.1.6 - Human Resource Management Plan,


identifying and documenting project roles, responsibilities
and required skills and reporting relationships, as well as
staffing management plan

PM;
Human Resource Management
functional managers Plan template (GFR-PMO-160C)

functional managers Work loads;


Job descriptions

335081696.xlsx - 10.2 - PLANNING

Project Management Plan (GFRPMO-160) updated with


approved Project Baseline (GFRPMO-160I)
Change Management Plan (GFRPMO-160H)

Quality Management Plan (GFRPMO-160B)

PMT;
functional managers

Human Resource Management


Plan (GFR-PMO-160C)

PMT;
functional managers

page 121 of 247

ACTIVITY CARD
P10.2.1. - Develop Project Management Plan (continued)
FROM

INPUT DOCUMENTS

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Customer

Contract Documents

ACTIVITY DETAILS

P10.2.1.1.7 - Communications Management Plan,


PM
identifying and documenting project stakeholder information
needs and defining a proper communication approach

Communications Management
Plan template (GFR-PMO-160D)

Communications Management
Plan (GFR-PMO-160D)

project stakeholders

PMT

Risk Register (GFR-PMO-150)

P10.2.1.1.8 - Risk Management Plan, defining how to


conduct risk management activities for the project.

PM;
Risk manager

Risk Management Plan template Risk Management Plan (GFR(GFR-PMO-160E)


PMO-160E)

Sales

make or buy / job sharing


(proposal);
vendor list;
contractual requirements

P10.2.1.1.9 - Procurement Management Plan,


describing how goods and services will be acquired from
external suppliers, including, but not limited to, make or
buy decisions, general contractual requirements (back-toback conditions), customer vendor list, ...
The Procurement Management Plan also include a Sourcing
Plan used to track procurement activities throughout the
project life cycle

PM; CIO leader

Procurement Management Plan


template (GFR-PMO-160F)

PMT

Project Management Plan (GFRPMO-160)

P10.2.1.2 - Approve Project Management Plan


The PMP shall be checked by the PfM and approved by the Project
Sponsor

BY

PfM, Project Sponsor

PMT; functional
managers

Procurement Management Plan PMT;


(incl. Sourcing Plan as defined in Supply Chain
the P6) (GFR-PMO-160F)

Approved Project Management


Plan (GFR-PMO-160)

PMT;
functional managers

aligns with PMBOK Fourth Edition: 4.2. "Develop Project Management Plan"
aligns with COMAU Policy #16: Policy does not spell out this specific process

335081696.xlsx - 10.2 - PLANNING

page 122 of 247

ACTIVITY CARD
P10.2.2. - Collect Requirements and Define Scope
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

The project's success is directly influenced by the care taken in


capturing and managing project and product requirements. The
development of requirements begins with an analysis of the
information contained in the project charter and the contractual
documents.
Sales;
Estimating;
Proposal:
PMT

Contract (particularly SOW,


P10.2.2.1 - Define Requirements Matrix
PM
Customer Specifications);
Particular emphasis shall be given to unusual requirements (differing
Project Charter;
from COMAU standards or previous applications) contained in
Requirements Management Plan customer specification. For this purpose the PM shall submit specific
(GFR-PMO-160G)
portions of the customer specification to PMT members and/or
subject matter experts in order to collect their evaluation.

expert judgment;
workshop

Requirements Matrix included in PMT;


the Requirements Management functional managers
Plan (GFR-PMO-160G)

Sales
Estimating
Proposal

Contract (particularly SOW,


Customer Specifications);

Project Scope Statement


template included in the Project
Baseline (GFR-PMO-160I)

Project Scope Statement


included in the Project Baseline
(GFR-PMO-160I)

P10.2.2.2 - Define Project Scope Statement


A detailed Project Scope Statement shall be prepared by the PM
(with the contribution of the other PMT members) including, either
directly or by reference to other documents, the following:

PM

PMT

Scope description - progressively elaborating the


characteristics of the product, service or result described in the
Project Charter and Requirements documentation;
Project Exclusions - generally identifying what is excluded
from the project, as explicitly stating what is out of scope for the
project helps to manage stakeholders' expectations;
Project constraints - listing and describing the specific project
constraints associated with the project scope that limits the team's
option (typically contractual provisions such as any imposed dates
or schedule milestones);
Project assumptions - listing and describing the specific
project assumptions associated with the project scope and the
potential impact of those assumptions if they prove to be false.

aligns with PMBOK Fourth Edition: 5.1. "Collect Requirements" and 5.2. "Define Scope"
aligns with COMAU Policy #16: Policy does not spell out this specific process

335081696.xlsx - 10.2 - PLANNING

page 123 of 247

ACTIVITY CARD
P.10.2.3. - Develop WBS
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

WBS dictionary example "GFRPMO-120-WBS dictionary


example"

WBS dictionary project specific;

PMT

Although each project is unique, a WBS from a previous project or a


WBS standard can often been used as a template for a new project.
When a standard WBS structure for the particular business is
available it shall be always used, already from the development of
the Proposal scope of supply during the Proposal phase
In the process of creating the project WBS, the PMT will aim at
achieving the level of detail necessary to define the project work but
considering the need of maintaining the number of work package at
a manageable size.
WBS dictionary shall include a responsibility assignment matrix
(RAM) clearly and uniquely allocating a responsible person to each
WP

Estimating;
Proposal

Contract (SOW);
P.10.2.3.1 - Develop WBS
PM
Requirements Matrix;
project controller
Proposal WBS (developed using a Develop Initial WBS
project estimator
standardized structure, e.g., NPS The PM, at very beginning of the project and with the contribution of
file)
the other PMT members, shall elaborate Proposal WBS to develop
the project specific WBS, assuring traceability of scope, time
and cost from Proposal to Project Execution phase.
WBS structure can be summarized as follows:
Q00 = elaborated "Proposal WBS structure"
B00 = Q00
A00 = Q00

WBS project specific :


1) ERP initial entry (Q00; B00
A00);
2) ERP rolling entry (QCU; BCU
ACU);
RAM (eg., included in the WBS
dictionary example (GFR-PMO120))

Develop Rolling WBS


As described in the Monitoring and Controlling process group
(ref."10.4."), in some cases, project changes can be so severe that a
complete new planning phase has to be undertaken.
In such case, the PM with the contribution of the PMT, shall
elaborate the project specific WBS to incorporate project changes.
WBS structure can be summarized as follows:
QCU -> Qn+1 = Qn + VAR
BCU -> Bn+1 = Bn + VAR + NC (appr.by Sponsor)
ACU -> An+1 = An + VAR + NC (appr.by Sponsor) + NC (team extra
costs)

335081696.xlsx - 10.2 - PLANNING

page 124 of 247

ACTIVITY CARD
P.10.2.3. - Develop WBS (continued)
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Estimating

cost estimates;
Proposal WBS;
WBS project specific

P.10.2.3.2 - Load Initial Budgets into ERP

project estimator,
project controller

ERP (SAP, Baan, ...)

ERP initial entry (Q00 - initial


Sales budget; A00)

PMT

The project estimator (usually coming from Proposal & Estimating)


assotiates costs to the restructured project specific WBS, assuring
traceability of scope, time and cost from Proposal to Project
Execution phase, mantaining proposal WBS total costs equal to
project specific WBS total cost:
Q00 = elaborated "Proposal WBS costs"
The project controller loads the above budgets into ERP system.
Load Rolling Budgets into ERP
As described in the Monitoring and Controlling process group
(ref."10.4."), in some cases, project changes can be so severe that a
complete new planning phase has to be undertaken.
In such case, the PM with the contribution of the PMT, shall
elaborate the project specific WBS to incorporate project changes.
The project estimator assotiates costs changes to the project
specific WBS,
Q00 = elaborated "Proposal WBS costs"
The project controller loads the above budgets into ERP system.

aligns with PMBOK Fourth Edition: 5.3. "Create WBS"


aligns with COMAU Policy #16: section 3.1.3. "Develop WBS and Responsibility Assignment Matrix (RAM)"

335081696.xlsx - 10.2 - PLANNING

page 125 of 247

ACTIVITY CARD
P.10.2.4. - Develop Schedule
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

Sales;
Proposal;
Project Sponsor
PM

Contract (customer milestones);


Project execution proposal;
Project Charter;
WBS;
Risk Register (GFR-PMO-150)

P.10.2.4.1 - Define Project Schedule


PM; project planner scheduling tool (e.g., MS
The PM (or the project planner, when such a resource is assigned to
Project, ...);
the project) with the contribution of the other PMT members shall
expert judgment
develop the project schedule aiming to achieve the target schedule
that may have been established by the Project Sponsor.
The appropriate scheduling tool to be used, and the relevant level of
implementation, is defined in accordance with project requirements.

OUTPUT DOCUMENTS

FOR

Project Schedule,
Risk Register (GFR-PMO-150)
updates

PMT

Developing an acceptable project schedule is an iterative process


which consists of the following steps:
define activities: each work package, identified at the lowest
level of the WBS, is decomposed into smaller components
(activities) that represent the work necessary to complete the work
package.
sequence activities: activities are sequenced using logical
relationships; every activity except the first and last shall be
connected to at least one predecessor AND one successor;
estimate activity resources: type and quantities of material,
people, equipment or supplies required to perform each activity are
estimated;
estimate activity durations: the number of work periods
needed to complete individual activities with estimated resources is
approximated using expert judgment;
As a part of the process, the risk register should be reviewed to
consider schedule Technical Contingency associated to specific risks

PMT

Project Schedule

P.10.2.4.2 - Define Schedule Baseline


PM; project planner scheduling tool (e.g., MS project, proposal schedule baseline
Once a Project Schedule has been defined, it is necessary to save it
)
as a proposal Schedule Baseline to be subsequently approved by the
Project Sponsor.

PMT; Project
Sponsor; functional
managers

Once defined the baseline schedule is saved into the scheduling


tool.
The Draft Schedule Baseline has to be formally approved by the
project sponsor ("M1020 - Initial Project Baseline Approval") to
become the Approved Schedule Baseline

PMT

Project Schedule

P.10.2.4.4. - Define Subsidiary Schedule Plans


PMT
The project schedule may be integrated by subsidiary, more
detailed, schedule plans typically developed by a specific function.

scheduling tool (e.g., MS project, subsidiary schedule plans (e.g.,


)
engineering schedule,
manufacturing schedule)

functional managers

aligns with PMBOK Fourth Edition: 6.1. "Define Activities", 6.2. "Sequence Activities", 6.3. "Estimate Activity Resources", 6.4. "Estimate Activity Durations" and 6.5. "Develop Schedule"
aligns with COMAU Policy #16: section 3.1.4. "Develop Project Master Schedule"

335081696.xlsx - 10.2 - PLANNING

page 126 of 247

ACTIVITY CARD
P.10.2.5. - Estimate Costs and Determine Budget
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

Project Sponsor

cost estimates;
project charter;
WBS;
project schedule;

P.10.2.5.2 - Estimate Costs and Determine Budget


PM, project
The PM and the project controller, with the contribution of the other controller, members
PMT members, shall then review and validate the budgets aiming to PMT
achieve the target costs that may have been established by the
Project Sponsor.

Proposal Resource Staffing Plan

Costs shall be verified for all resources that will be charged to the
project. This includes, but is not limited to labour, materials,
equipment, service and facilities, as well as special categories such
as an special allowance (e.g., rate exchange) or contingency costs.

risk register (GFR-PMO-150)


Procurement Management Plan
(GFR-PMO-160F) (Make or Buy
strategy);

During the process, the risk register should be reviewed to consider


risk mitigation costs.

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

expert judgment,
Resource Staffing Plan example
(GFR-PMO-110);
ERP (e.g., SAP, Baan)

work package validated cost


estimates;
Resource Staffing Plan (GFRPMO-110);
ERP entry (B00 - initial Cost
Baseline, or BCU - rolling Cost
Baseline)

PMT; Project
Sponsor; functional
managers

ERP entry (A00 - initial Cost


forecast);
ERP entry (ACU - current Cost
forecast)

Moreover the PMT will review "make or buy" and "job sharing"
strategy and resource staffing to assess their related costs impact

Develop Initial budget Cost Baseline


Once approved the Cost Baseline is loaded onto the ERP as follows:
B00 = Q00 + VAR (if any) + NC (appr.by Sponsor)
Once the very first baseline is approved project controller shall
upload the initial rolling forecast as follows:
A00 = B00

Develop rolling Cost Baseline and Actual budget


As described in the Monitoring and Controlling process group
(ref."10.4."), in some cases, project changes can be so severe that a
complete new planning phase has to be undertaken.
In such case, the PM with the contribution of the PMT, shall
elaborate the project specific WBS to incorporate project changes
(valid Change Order issued by the Customer or a baseline change
approved by the project sponsor).
WBS structure can be summarized as follows:
QCU -> Qn+1 = Qn + VAR
BCU -> Bn+1 = Bn + VAR + NC (appr.by Sponsor)
ACU -> An+1 = An + VAR + NC (appr.by Sponsor) + NC

aligns with PMBOK Fourth Edition: 7.1. "Estimate Costs" and 7.2. "Determine Budget"
aligns with COMAU Policy #16: section 3.1.5. "Cost Verification and Budgeting"

335081696.xlsx - 10.2 - PLANNING

page 127 of 247

ACTIVITY CARD
P.10.2.6. - Identify, Analyse and Plan Response to Risks
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

The PM shall call periodic planning meetings with PMT to perform


risk management activities; attendees at these meeting may also
include others as needed (e.g.,. Risk Manager).

PM

risk identification: the process of determining which risks may PMT


affect the project and document their characteristics.
As an input to this step the PMT will consider:
- the preliminary risk assessment done during the proposal phase
- the outcome of the contract and customer SOW carried out during
process 10.2.2. Collect Requirements and Define Scope and in
particular the project assumptions and constrains listed in the
Project Scope Statement
- any Lessons Learned from previous projects

expert judgment;

Risk Register entries

PMT

qualitative risk analysis: the process of prioritizing risks for


further analysis or action by assessing and combining their
probability of occurrence and impact (qualitative).

PMT

probability/impact matrix

Risk Register updates

PMT

quantitative risk analysis: the process of numerically


analysing the effect of identified risks on overall project objectives.

PMT

expert judgment;

Risk Register updates

PMT

current budget updates


current schedule updates

PMT

This process goes through the following steps:


Sales
Proposals

Project Scope Statement;


Requirements Matrix;
CAP (preliminary risk
assessment);
Lessons Learned

From previous step, top risks shall be selected for quantification;


remaining risks will be monitored on a regular basis (i.e. Watch List)

During this step the technical contingency of cost or schedule should PM; planner;
be modified in alignment with the current risk assessment.
project controller

Technical Contingency (TC) is an allowance used to cover


identified risks if they occur;
Management Contingency (MC) is a budget reserve used to
manage unidentified risks that are within project scope. It is not part
of the project cost baseline, but it is included in the total budget for
the project.

335081696.xlsx - 10.2 - PLANNING

page 128 of 247

ACTIVITY CARD
P.10.2.6. - Identify, Analyse and Plan Response to Risks (continued)
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

expert judgment;

Risk Register updates

PMT

All threats (i.e. "negative" risks) having medium or high probability


of occurrence shall be covered by a technical contingency of cost for
an amount equal to the total risk cost impact (quantitative).
It is not allowed to compensate threats with opportunities (i.e.
"positive" risks).

A suitable Management Contingency, based on a reasonable


evaluation of the project risk level, is defined at the beginning of the
project by the project sponsor, and it is maintained and reviewed
throughout project life cycle.

risk response planning: the process of developing options


PMT
and actions to enhance opportunities and to reduce threats to
project objectives. Actions must be appropriate to the significance of
risk, cost effective in meeting the challenge, timely, realistic within
the project context, agreed upon by all parties involved, and owned
by a responsible person.

aligns with PMBOK Fourth Edition: 11.2. "Identify Risks", 11.3. "Perform Qualitative Risk Analysis", 11.4. "Perform Quantitative Risk Analysis" and 11.5. "Plan Risk Responses"
aligns with COMAU Policy #16: section 3.1.6. "Risk Management"

335081696.xlsx - 10.2 - PLANNING

page 129 of 247

ACTIVITY CARD
P.10.2.7. - Define Project Baseline
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Project Baseline template (GFRPMO-160I)

M1020 planned
PMT;
Project Baseline (GFR-PMO-160I) functional manager;
to be approved
Project Sponsor

Although planning activities, and thus the Planning processes, will


extend throughout the entire duration of the project, it is in the first
phase of the project that these are particularly important and that
they are extensively executed.
This process is iterated only in case project changes are so severe
that a complete new planning phase has to be undertaken.
Normally, rolling Baseline modifications due to Change Request
(valid Change Order issued by the Customer or a change approved
by the project sponsor) approved as an output of process
P.10.4.6."perform integrated Change Control" are managed in the
Monitoring and Controlling process group (ref."10.4.").

Scope Statement (output of


Project Baseline is a document that includes:
PM
process 10.2.2);
Scope Baseline, which consists of:
WBS, and WBS dictionary (output
- Scope Statement (output of process 10.2.2)
of process 10.2.3); Schedule
- WBS, and WBS dictionary (output of process 10.2.3)
Baseline (output of process
Schedule Baseline (output of process 10.2.4)
10.2.4);
Cost Baseline (output of process 10.2.5)
Cost Baseline (output of process
10.2.5)
The initial Project Baseline is worked out by the PMT during the early
stages of the project. During this process, the PMT, led by the PM,
shall aim at achieving targets for project objectives set by Project
Sponsor.
PM shall call a meeting ("M1020 - Initial Project Baseline Approval")
with all internal key stakeholders (Project Sponsor, functional
managers ) and obtain formal "buy-in" of the Project Baseline.
This meeting should be scheduled within one (1) month from M1010
Project Kick-off
The Project Baseline:
shall only be changed upon contribution of a valid Change Order
(in the form foreseen by COMAU Policies) issued by the Customer or
a baseline change approved by the project sponsor (during the
periodic "M1040 - Project Performance Review Meeting")
it is used as a basis against which to measure, monitor and control
overall schedule performance on the project.

aligns with PMBOK Fourth Edition: PMBOK does not have a single process for definition of Project Baseline
aligns with COMAU Policy #16: section 3.1.7. "Formalizing of project baseline"

335081696.xlsx - 10.2 - PLANNING

page 130 of 247

ACTIVITY CARD

P10.3.1. - Direct and manage Projec


FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

The PM along with the PMT, directs the performance of the planned
project activities, and manages the various technical and
organizational interfaces that exist within the project.
The PM calls periodic meeting among PMT members to discuss
project status and issues, and decide corrective and/or preventive
actions ("M1030 - PMT meeting"); tracking of actions and
relevant responsible is kept in a issue log, which is maintained in the
PMIS

PMT

Team Functional area


Perfomance Data

P10.3.1. - Direct and manage Project Execution


PMT
Work performance data about the completion status of the
deliverables and what has been accomplished is collected by PMT as
part of project execution and is fed into the other Executing
processes. The work performance data will also be used as an input
to the Monitoring and Controlling Process Group.

This information can be related to various performance results,


including, but not limited to, deliverable status, schedule progress,
and cost incurred.
As an example:
TL(s) or project engineer shall collect and provide detailed work TL
performance data related to Engineering & Design;
CIO leader shall collect and provide detailed work performance CIO Leader
data related to Procurement, Manufacturing and in house Integration
;
Site Manager shall collect and provide detailed work data
information related to on site Installation and Commissioning &
Start-up.

335081696.xlsx - 10.3 - EXECUTING

site manager

page 131 of 247

aligns with PMBOK Fourth Edition: 4.3. "Direct and Manage Project Execution"
aligns with COMAU Policy #16: Policy does not spell out this specific process

335081696.xlsx - 10.3 - EXECUTING

page 132 of 247

ACTIVITY CARD

P10.3.2. - Perform Quality Assuranc


FROM

INPUT DOCUMENTS

PMT

Project Quality Management Plan P10.3.2.1. - Assess Quality Management


(GFR-PMO-160);
The PM, with the contribution of the other PMT members, shall
quality checklist compiled
ensure that project activities comply with the project Quality
Management Plan.

ACTIVITY DETAILS

BY
PMT

QA manager

COMAU Quality Management


System (QMS)

P10.3.2.2. - Perform Quality Audit


The Quality Assurance organization may also perform independent
quality audits to determine whether project activities comply with
organizational and project policies, processes and procedures.

QA engineer

PMT

Issue Log; NC System

P10.3.2.3. - Collect Lessons Learned


Throughout the project execution, PMT shall collect and document
lessons learned to update performing organization knowledge base
for the benefit of future projects.

PMT

PMT

NC
Cost Performance

P10.3.2.4. - Manage COF


The PM is responsible to assure that deviation from Project Cost
Baseline are documented and substantiated as COF through NC
System.

PM

aligns with PMBOK Fourth Edition: 4.3. "Perform Quality Assurance"


aligns with COMAU Policy #16: Policy does not spell out this specific process

335081696.xlsx - 10.3 - EXECUTING

page 133 of 247

ACTIVITY CARD

P10.3.3. - Develop and Manage Proj


FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

COMAU organizational structure is of matrix type, where individuals


report to their functional manager, who is responsible for assuring
the quality of the output, time and costs agreed in the PMT, and to
the project manager, who directs their activities when they are
working as project team members.

PMT

resource staffing plan (part of


Project HR Management Plan)

P10.3.3.1. - Manage Resourse Staffing


The PM, with the contribution of the other PMT members, shall
ensure that the necessary human resources to complete project
activities are assigned to the project.

PM

In case the project work load is requiring additional resources or a


change in the current allocation, PM shall address the issue with
functional managers.
In case any conflict arise about priorities for PMT members /
resources which are contemporarily allocated to several projects,
this shall be resolved by the PfM and relevant functional manager.

resource staffing plan

335081696.xlsx - 10.3 - EXECUTING

P10.3.3.2. - Manage Cost Charge Authorizations


PM;
A work authorization system shall be put in place to allow the PM to Project Controller
control the resources that will be charged to the project. For this
purpose the PM shall specifically authorize resources to charge on
specific WP, usually in the ERP system.

page 134 of 247

ACTIVITY CARD

P10.3.3. - Develop and Manage Proj


FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

Project HR Management Plan

P10.3.3.3. - Develop Project Team


Effective management of the project team throughout the project
life is a primary responsibility of the PM, which involves enhancing
cohesiveness among team members, assigning task and
responsibilities, tracking performance, providing feedback and
resolving issues.

PM; HR business
partner; functional
manager

In order to ensure effective project team management, the PM shall


foster team working and integrate the efforts of the human
resources assigned to the project through:
- improving knowledge and skills,
- improving feeling of trust to reduce conflict, raise morale, and
increase team work
- creating a flexible and cohesive team culture, spirit and
cooperation.
When possible, it is recommended to have the team working in colocation.
In case of multi-country projects a PM may lead a virtual team, being
able to cope with differences in the culture, local conditions, ...
In this case, for team members who are not accustomed to work in
global environment, it is recommended to plan multicultural
training.

P10.3.3.4. - Assess PMT Performance


The PM will cooperate with the functional managers in the
management of PMT members and will provide them with a report
about their performance at the end of their assignment in the
project (or earlier as the case may be).

PM

(*) because of confidentiality of information contained In this case, for team members who are not accustomed to work in global environment, it is recommended to plan multicul
aligns with PMBOK Fourth Edition: 9.2. "Acquire Project Team", 9.3. "Develop Project Team" and 9.4. "Manage Project Team"
aligns with COMAU Policy #16: section 3.1.2. "Acquire and manage Project Team"

335081696.xlsx - 10.3 - EXECUTING

page 135 of 247

ACTIVITY CARD

P10.3.4. - Distribute Information an


FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

The PM is responsible to make project information available to the


Project Stakeholders (internal and external) as planned, as well as
responding to additional requests of information.
Project information distributed to Project Stakeholders shall always
be as precise and current as possible.

PfM
PM; project
controller; planner

Projects Review Meeting agenda P10.3.4.1. - Prepare Project Report


PM
When convened to the periodic Projects Review Meeting by the PfM,
project performance information; the PM shall prepare and communicate project performance to the
risk register;
Project Sponsor and the internal Project Stakeholders ("M1040 change request log;
Project Review Meeting")
invoice and payment status

PM; project
controller; planner

project performance information;


risk register;
change request log;
invoice and payment status

PM
Customer

Project Communications
Management Plan

PM; project
controller; planner

P10.3.4.2. - Prepare Project Portfolio Information


On monthly basis the PM shall however provide summary
information of project performance to the PfM, who will collect and
integrate them into the overall portfolio performance information

P10.3.4.3. - Prepare Report to the Customer


As at regular intervals (as defined in the Communications
Management Plan) the PM shall prepare and distribute to the
project performance information; Customer a Project Status Report including all project pertinent
change request log;
information ("M1050 - Project Status Report to Customer")
invoice and payment status

335081696.xlsx - 10.3 - EXECUTING

PM

PM

page 136 of 247

ACTIVITY CARD

P10.3.4. - Distribute Information an


(continued)
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

PM
Customer

Project Communications
Management Plan

P10.3.4.4. - Manage Customer


PM
The PM shall also held regular meetings with Customer
representatives with the purpose of communicating and working
with them to meet their needs and addressing issues as they occur.
An issue log should be used to document and monitor the resolution
of issues, to facilitate communication and ensure a common
understanding of issues. The issues shall be clearly stated and
categorized based on urgency and potential impact. An owner shall
be assigned to each action item for resolution and a target date
established for closure. Alternatively minutes of meeting could be
used to record items discussed and decisions taken. It is highly
advisable that the minutes of meetings with Customer are written by
the PM (or by another COMAU person) who shall assure that all
items discussed are fully and correctly captured.

PM
Customer

Project Communications
Management Plan

P10.3.4.5. - Manage Conflicts with the Customer


PM
every reasonable effort will be made to resolve issues at project
level. However, there could be instances where the item in question
is outside the decision making authority of the project teams or an
agreement cannot be reached, in such a case PM shall follow the
escalation procedure defined in the communication plan.

Customer

Change Request

P10.3.4.6. - Manage Customer Change Requests


PMT
As a part of this process the PMT shall also collect Customer Change
Requests which are fed into the P10.4.6 Perform Integrated Change
Control process.

335081696.xlsx - 10.3 - EXECUTING

BY

page 137 of 247

Customer
PMT

Communications

P10.3.4.7. - Manage Customer Communications


Project records (including presentations, meeting minutes and any
other correspondence with the Customer) shall be, to the extent
possible and appropriate, be maintained in an organized manner.

PMT

Customer

Survey

P10.3.4.8. - Perform Customer Satisfaction Survey


The PM is also responsible to periodically contact the Customer to
measure their degree of satisfaction. ("M1060 - Customer
Satisfaction Survey")

PM

aligns with PMBOK Fourth Edition: 10.3. Distribute Information and 10.4. Manage Stakeholder Expectations
aligns with COMAU Policy #16: section 3.2.2. "Project Report to the Customer"

335081696.xlsx - 10.3 - EXECUTING

page 138 of 247

ACTIVITY CARD
P10.3.5. - Conduct Procurements
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

COMAU procurement process, under the overall responsibility


of CIO organization, is a cross-functional process with clear
responsibilities identified for each step with the aim to
achieve the highest level of competitiveness while
maintaining project objectives. The process is defined by
Process "P6 - Supply Chain Management" and therfore the
"P10.3.5. Conduct Procurements" process defines the
interactions between P6 and P10 processes
The PM shall be always directly involved by CIO leader and
Supply Chain function in the management of "critical"
suppliers (i.e. suppliers whose performance is critical for the
success of the project as they have been identified in the
Procurement Management Plan).
The CIO leader, with the contribution of the Supply Chain
function, will update the Sourcing Plan with relevant
information and make it available to the PMT focusing in
particular on the followings:

PMT

Procurement Management Plan


(Sourcing Plan);
Technical Specification

P10.3.5.1 - Bid Package preparation & revision


CIO Leader, supported by Supply Chain, is deemed to prepare the
Bid Packges based upon Technical Specifications from the PMT and
Sourcing Plan.

CIO leader
PMT

PMT shall review the Bid Packages to make sure they embody all
contractual and technical requirements.

335081696.xlsx - 10.3 - EXECUTING

page 139 of 247

Supply Chain

Vendor Bids

P10.3.5.2 - Supplier Technical Line-Up

CIO leader
PMT

CIO Leader, supported by Supply Chain, is deemed to collect Vendor


Bids and together with PMT and or Subject Matter Experts shall
evaluate Suppliers proposals regarding Technical Validity and
compliance of contractual obligations to project requirements.

Supply Chain

Selected Suppliers

P10.3.5.3 - Selected Supplier Notification

CIO leader

PMT shall be knowledgeable of the technical contents and the


contractual obligations of suppliers to properly manage supplier buyoff activities (both for materials and activities).
For this purpose the PMT shall have access to Purchase Orders and
attached documentation as needed.

aligns with PMBOK Fourth Edition: 12.2. "Conduct Procurements"


aligns with COMAU Policy #16: section 3.2.4. "Management of Critical Suppliers"

335081696.xlsx - 10.3 - EXECUTING

page 140 of 247

Y CARD
- Direct and manage Project Execution
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Executing Processes

Project Work Performance Data

PMT

Engineering & Design work


performance data

PMT; functional
managers

Procurement and Manufacturing PMT; functional


work performance data
managers
Installation and Commissioning
& Start-up work performance
data

335081696.xlsx - 10.3 - EXECUTING

PMT; functional
managers

page 141 of 247

335081696.xlsx - 10.3 - EXECUTING

page 142 of 247

Y CARD
- Perform Quality Assurance
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

quality audit

Quality Management Plan


updated (GFR-PMO-160)

Project Sponsor;
PMT; functional
managers; QA
manager

quality audit

quality audit report

Project Sponsor;
PMT; functional
managers; QA
manager

expert judgment; workshop

lessons learned

functional
managers; QA
manager

NC system

KPI (maximize ratio of COF value QA manager; project


documented in NC System vs.
sponsor; PMD
cost variance)

335081696.xlsx - 10.3 - EXECUTING

page 143 of 247

Y CARD
- Develop and Manage Project Team
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

resource staffing plan example


(GFR-PMO-110)

resource staffing plan updated

PMT; functional
managers

ERP; E-mail; etc.

work authorization

PMT; functional
managers

335081696.xlsx - 10.3 - EXECUTING

page 144 of 247

Y CARD
- Develop and Manage Project Team (continued)
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

team building activities;


co-location;
ground rules;
project team incentives;
recognition and rewards (ref.
Lead to Profit);
training;
multi-cultural project
management;
soft skills (e.g., leadership,
conflict management, effective
decision making,)

updated employee training


records

project team

COMAU leadership model

team performance assessment


(*)

employee skill assessment

functional managers

ment, it is recommended to plan multicultural training

335081696.xlsx - 10.3 - EXECUTING

page 145 of 247

Y CARD
- Distribute Information and Manage Stakeholder Expectations
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Project Review presentation


template (GFR-PMO-180)

Project Review presentation

Project Sponsor;
PfM; functional
managers

PMdb

PMdb updates

PfM

Project Status Report to


Customer example (GFR-PMO170)

Project Status Report to


Customer

Customer; PfM;
Project sponsor

335081696.xlsx - 10.3 - EXECUTING

page 146 of 247

Y CARD
- Distribute Information and Manage Stakeholder Expectations
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Issue log updated;


meeting minutes

Customer; PMT

Escalation plan included in the


Communications Management
Plan (GFR-PMO-160D)

Escalation process according to


the escalation plan

Project Sponsor

Change Request Log (GFR-PMO200);


Change Management form
template (GFR-PMO-190)

Change Request Log updated;


Change Management form

PMT

335081696.xlsx - 10.3 - EXECUTING

page 147 of 247

PMIS (GOI-PMO-120)

Communications with the


customer (eg., mail PST)

PMT

Customer Satisfaction Survey


template (GFR-PMO-210)

Customer Satisfaction Survey


completed
as requested by M1060 event

Project Sponsor;
PfM; functional
managers; Sales;
Marketing

335081696.xlsx - 10.3 - EXECUTING

page 148 of 247

Y CARD
- Conduct Procurements
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Sourcing Plan updates


Supply Chain; PMT
Bid Packages; (material
requisition available, RfQ issued
to vendors)

335081696.xlsx - 10.3 - EXECUTING

page 149 of 247

Sourcing Plan updates


(vendor bids received, vendor
bids evaluated);
Vendor Bids Technical Approval

Supply Chain; PMT

Sourcing Plan updates


(PO issued)

PMT

335081696.xlsx - 10.3 - EXECUTING

page 150 of 247

ACTIVITY CARD
P10.4.1. - Control Scope
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Customer
PMT

Scope Baseline;
work performance data (Change
Requests received, deliverable
completed,)

P10.4.1.1 - Change Identification


The PM, with the contribution of the other PMT members, shall
control project scope, managing changes to the scope baseline and
avoiding that uncontrolled changes are implemented in the project
scope (project scope creep)

PMT

variance analysis

Change Request

PMT

NC system

NC

PMT

Controlling the project scope ensures all requested changes are


processed through the Perform Integrated Change Control process
(process 10.4.6.)
In some cases, project changes can be so severe that a complete
new planning phase has to be undertaken (ref. "P10.2")

PMT

Change Request

P10.4.1.2 - Change Process initiation on NC system


PMT
Any anticipated deviation from the scope baseline, either coming
from a variation of the contracted scope or timing (customer change
request) or not, shall be documented and managed through the NC
system

aligns with PMBOK Fourth Edition: 5.5. "Control Scope"


aligns with COMAU Policy #16: sections 3.1.4. "Develop Project Master Schedule" and 3.2.5. "Authorizing deviations from project baseline"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 151 of 247

ACTIVITY CARD
P10.4.2. - Control Schedule
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

PMT

Schedule Baseline;
work performance data
(information about project
progress,)

P10.4.2.1 - Control Schedule


PM;
The PM (or the project planner when such a resource is assigned to project planner
the project) shall monitor the status of the project to update project
progress and manage changes to the schedule baseline. Schedule
control has to be performed at regular intervals as defined in the
Project Management Plan (ideally weekly), and it is concerned with:

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

scheduling tool (e.g., MS


Project);
trend analysis;
variance analysis (e.g., EVM)

work performance information


(e.g., SV, SPI);
schedule forecast;
Change Requests

PMT

NC system

NC

PMT

determining the current status of the project schedule (e.g.,


updating "percent complete");
influencing the factors that create schedule changes;
determining that the project schedule has changed;
managing the actual changes as they occur.
"An updated project schedule will be generated from the updated
schedule data to reflect the schedule changes and manage the
project.
In some cases, project changes can be so severe that a complete
new planning phase has to be undertaken (ref. "P10.2").

PMT

Change Request

P10.4.2.2 - Change Process initiation on NC system


PMT
Any anticipated deviation from the schedule baseline, either coming
from a variation of the contracted scope or timing (customer change
request) or not, shall be documented and managed through the NC
system.

aligns with PMBOK Fourth Edition: 6.6. "Control Schedule"


aligns with COMAU Policy #16: sections 3.1.4. "Develop Project Master Schedule" and 3.2.5. "Authorizing deviations from project baseline"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 152 of 247

ACTIVITY CARD
P10.4.3. - Control Cost
FROM

INPUT DOCUMENTS

PMT

Cost Baseline;
P10.4.3.1. - Control Cost
work performance data (actual & The PM and the project controller shall monitor the status of the
committed costs,)
project to update project budget and manage changes to the cost
baseline. Cost control has to be performed at regular intervals as
defined in the Project Management Plan (at least monthly), and it is
concerned with:

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

PM;
project controller

ERP (e.g., SAP, Baan, );


trend analysis;
variance analysis (e.g., EVM)

work performance information


(e.g., CV, CPI);
ETC/EAC;
Change Requests

PMT
project sponsor

NC system

NC

PMT

determining the actual and committed costs on the project;


estimating the cost to complete;
monitoring cost performance to isolate and understand variances
from the approved cost baseline;
acting to bring expected costs overruns within acceptable limits.
Much of the effort of cost control should be dedicated to analyse the
relationship between the consumption of the project funds to the
physical work being accomplished, rather than simply monitoring
the expenditure of funds.
In some cases, project changes can be so severe that a complete
new planning phase has to be undertaken (ref. "P10.2").

PMT

Change Request

P10.4.3.2 - Change Process initiation on NC system


PMT
Any anticipated deviation from the cost baseline, either coming from
a variation of the contracted scope or timing (customer change
request) or not, shall be documented and managed through the NC
system.

aligns with PMBOK Fourth Edition: 7.3. "Control Costs"


aligns with COMAU Policy #16: section 3.2.5. "Authorizing deviations from project baseline"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 153 of 247

ACTIVITY CARD
P10.4.4. - Monitor and Control Risks
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

PMT

Risk Register;
work performance information;
NC;
issue log

P10.4.4.1 - Monitor and Control Risks


PM; planner;
The PM shall organize periodic planning meetings of PMT with the
controller
purpose of implementing risk response plans, tracking identified
risks, monitoring residual risks, identifying new risks, and evaluating
risk management process effectiveness throughout the project ;
attendees at these meeting may also include others as needed
(e.g.,. Risk Manager)

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

expert judgment;
probability/impact matrix;
contingency analysis

Risk Register updates;


Technical Contingency updates;
ref. to Risk Management (GOIPMO-110)

PMT;
Project Sponsor

Throughout execution of the project some risks may occur, with


positive or negative impacts on budget or schedule Technical
Contingency. Contingency analysis shall be done to compare the
remaining amount of the Technical Contingency to the amount of
risk remaining at any time in the project in order to determine if the
remaining contingengy is adequate.
In some cases, project changes can be so severe that a complete
new planning phase has to be undertaken (ref."10.2.")

PMT

Risk Register updates;


Technical Contingency updates

P10.4.4.1 - Management Contingency Authorization


Project Sponsor;
Project sponsor may authorize the use of Management Contingecy
controller
to cover part, or the entire impact of an unidentified risk that has
occurred, or the portion exceeding the foreseen impact of an
identified risk that has occurred.
Operating Instructions to manage risks is described in the document
"GOI-PM-410 Risk Management".

Technical Contingency updates; PM


Management Contingency
updates;
ref. to Risk Management (GOIPMO-110)

aligns with PMBOK Fourth Edition: 11.6. "Monitor and Control Risks"
aligns with COMAU Policy #16: section 3.1.6. "Risk Management"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 154 of 247

ACTIVITY CARD
P10.4.5. - Monitor and control Project Performance
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

work performance reports

PMT

Issue log updates;


Project Management Plan
updates

PMT

The PM, with the contribution of the other PMT members, shall track,
review and regulate the progress to meet the performance
objectives defined in the Project Management Plan
Monitoring includes collecting, measuring and distributing
performance information, and assessing measurements and trends
to effect process improvements.
Control includes determining corrective or preventive actions or replanning and following up on action plans to determine if the actions
taken resolved the performance issue

PMT

work performance information


P10.4.5.1. - Monitor Project Performance
(from control schedule and cost); Monitoring includes collecting, measuring and distributing
risk register
performance information, and assessing measurements and trends
to effect process improvements.

PMT

issue log

PM; planner; project trend analysis;


controller
variance analysis;
expert judgment

P10.4.5.2. - Control Project Performance


PM
Control includes determining corrective or preventive actions or replanning and following up on action plans to determine if the actions
taken resolved the performance issue
As a result of comparing planned results to actual results, the Project
Management Plan may need to be updated in a typical "plan-docheck-act" cycle.

aligns with PMBOK Fourth Edition: 10.4 "monitor and control Project Work" and 10.5. "Report Performance"
aligns with COMAU Policy #16: section 3.2.1. "Project Performances Evaluation and Reporting"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 155 of 247

ACTIVITY CARD
P10.4.6. - Perform Integrated Change Control
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

PM; PMT; Project


Estimator

NC System

Scope of supply, change


implementation Schedule and
budget Cost estimate (SSC in
short) attached to NC

FOR

For the purpose of this process, a "change" is defined as any


anticipated deviation from the project baseline (scope, time, cost).

project stakeholder

NC initiated Control Scope,


Schedule anc Cost processes;
Change Request

P10.4.6.1. - Determine Change Scope, Schedule and Cost


(SSC)
Change requests are collected from various project stakeholders
(PMT, customer, ) as an output from Monitoring and Controlling
processes and fed into this "Perform Integrated Change Control"
process, with the purpose to coordinate them across the entire
process (as a proposed change on one project objective, will often
affect some others).
A "change" may entitle COMAU to raise a Change Request to the
customer (should the change involve a variation of the contracted
scope or timing, hereinafter referred to as "VAR"), or not (should the
modification become necessary to cope with contractual
requirements not previously taken into consideration, hereinafter
referred to as "MOD").
The PM, with the contribution of the other PMT members, is
responsible to assess the change, i.e. to correctly determine change
scope and estimate change cost and schedule impact.
In some cases, project changes can be so severe that a complete
new planning phase has to be undertaken (ref."10.2.")

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 156 of 247

ACTIVITY CARD
P10.4.6. - Perform Integrated Change Control (continued)
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Change Authorization Form


Template (GFR-PMO-190);
NC System

Change Authorization Form


PM
signed (GFR-PMO-190) attached Sales
to NC

NC System

Technical / Economical Offer;


Change Request Log updated
(GFR-PMO-200) attached to NC

customer
PMT
Sales

Change Order; LOI;


Change Request Log updated
(GFR-PMO-200);

Sales
PM

process to be followed in case of "VAR"


project sponsor

Project Charter
SCS

P10.4.6.2A.1. - Change Instruction and Authorization ("VAR") Project Sponsor;


The PMT shall initiate a NC in the system or manage NC already
PM
initiated (ref. Control Scope, Schedule anc Cost processes), to track
change.
The PM, with Sales, shall define margin to be added to the estimated
change cost and prepare the quotation package.
Before submitting the quotation to the customer, the PM is
responsible to verify the feasibility of the change with respect to and
to get prior authorization from the project sponsor in accordance
with the level of authority defined in the Project Charter.

PM
Sales

Change Instruction and


Authorization Form (GFR-PMO190)

P10.4.6.2A.2. - Submit Offer & Change Tracking ("VAR")


PM;
Contract provisions related to the procedure for change request shall Sales
be conscientiously complied with (e.g., a certain notification period
may be required, or a particular format shall be adopted); in
addition, as a minimum, changes shall be requested in written to the
proper customer representative, and a change log of all change
requests, with their relevant status shall be properly maintained.

PMT
Sales

Technical / Economical Offer

P10.4.6.2A.3. - Receive Customer Change Order / LOI ("VAR") Customer;


Through negotiation process, Customer and Comau rapresentatives PM; Sales
eventually got change price agreement.
Customer formal acceptance of the Change, with the issuance of a
Change Order, is a prerequisite for updating project scope, schedule
and cost.
PM/Sales shall duly inform PMT about customer change approvals
and instruct changes to the project baseline.

project sponsor

Project Charter

P10.4.6.2A.4. - Change requests without formal Customer


Project Sponsor
acceptance ("VAR")
Execution of Customer change requests without formal Customer
acceptance is subject to approval by the project sponsor in
accordance with the level of authority defined in the Project Charter
and according to Change Management (GOI-PMO-130) operative
instruction

Change Management (GOI-PMO- Change Authorization Form


130);
signed (GFR-PMO-190) and
NC System
attached to NC

PM/ Sales

Change Request Log (GFR-PMO200)

P10.4.6.2A.5. - Prepare Customer change request summary


("VAR")
A summary of the Customer change requests to date (with
indication of status and relevant margin) is to be maintained and it
shall be presented to the project sponsor during periodic PPR

Change Request Log template


(GFR-PMO-200)

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

PM

PM
Sales

customer change request


project sponsor
summary on PPR included in the
Change Request Log (GFR-PMO200) package

page 157 of 247

ACTIVITY CARD
P10.4.6. - Perform Integrated Change Control (continued)
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Project Sponsor
PM

NC system

Authorization Form signed (GFR- PMT


PMO-190) attached to NC

process to be followed in case of "MOD"


project sponsor

Project Charter;
NC

P10.4.6.2B.1. - Approve COF ("MOD")


The PMT shall initiate a NC in the system or manage NC already
initiated (ref. Control Scope, Schedule anc Cost processes), to track
change.
PM shall inform project sponsor who shall approve the COF before
funds are actually spent.
In order to reduce the number of authorizations to be given by the
project sponsor, it is acceptable that only COF above a certain
threshold previously defined by the Project Sponsor in the Project
Charter have to be approved separately.
However the PM is responsible to notify to the project sponsor when
the amount of COF over the last month exceeds the threshold value
defined in the Project Charter.
PM shall duly inform PMT about internal change approvals and
instruct updates to WBS, cost forecast and schedule.

PM

NC completed

P10.4.6.2B.2. - Prepare COF summary ("MOD")


A summary of the COF to date is to be maintained and it shall be
presented to the project sponsor during periodic PPR

PM

COF summary on PPR

project sponsor

aligns with PMBOK Fourth Edition: 4.5. "Perform Integrated Change Control"
aligns with COMAU Policy #16: section 3.2.3. "Change Control"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 158 of 247

ACTIVITY CARD
P10.4.6. - Perform Integrated Change Control (continued)
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

PM

Authorization Form (GFR-PMO190)

P10.4.6.3. - Update schedule baseline and forecast


Project Planner shall update schedule baseline and forecast
according to "VAR" or "MOD".

Project Planner

scheduling tool

Schedule Baseline update;


Project schedule update;

FOR

Project Controller

ERP system

EAC update (ERP entry, ACU);


PMT
Cost Baseline update (ERP entry,
QCU-BCU)

In very special circumstances (e.g., "MOD" for Make / Buy or Job


Sharing changes), where any of the assumptions under which the
PMT is executing the project is changing, even if this is not a
customer change, the Project Sponsor may authorize a change of
the schedule baseline which takes into account the new conditions
(ref. Change Management (GOI-PMO-130))

PM

NC promoted

P10.4.6.4. - Update cost baseline and forecast


Project Controller shall update baseline and forecast into the EAC
according to "VAR" e "MOD".
In very special circumstances (e.g., "MOD" for Make / Buy or Job
Sharing changes), where any of the assumptions under which the
PMT is executing the project is changing, even if this is not a
customer change, the project sponsor may authorize a change of
the cost baseline which takes into account the new conditions (ref.
Change Management (GOI-PMO-130)).

aligns with PMBOK Fourth Edition: 4.5. "Perform Integrated Change Control"
aligns with COMAU Policy #16: section 3.2.3. "Change Control"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 159 of 247

ACTIVITY CARD
P10.4.7. - Verify Scope
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

Customer

Contract (acceptance criteria);


Scope Baseline;
Validated Deliverables

P10.4.7.1 - Obtain formal acceptance


The PM, with the contribution of the other PMT members, is
responsible to get formal acceptance of the completed project
deliverable.

PM;
PMT;
Customer;
Suppliers;

inspection

acceptance documents (e.g.,


Buy-off Book) duly completed

Customer; Project
Sponsor; PMT

snag list

PMT

The PM shall check and record the fulfilment of the all the conditions
needed to request Customer final acceptance in a dedicated
meeting with the PMT ("M1070 - Request for Final Acceptance")
Verifying scope includes reviewing deliverables with the Customer to
ensure that they are completed satisfactorily and obtaining formal
acceptance of deliverable.
This may be a stepped process, involving subsequent phases of
progressive acceptance of the deliverables (e.g., design review,
manufacturing review, acceptance tests).

Customer;
PMT

open issues

P10.4.7.2 - Document open issues on snag list


PMT
During the verification process (e.g., as a result of the review of the
drawings, or the inspection of the installation) a list of the items still
to be completed and/or to be corrected may be produced.
The PM is therefore responsible that items listed in this list are
timely and correctly addressed for resolution

aligns with PMBOK Fourth Edition: 5.4. "Verify Scope"


aligns with COMAU Policy #16: Policy does not spell out this specific process

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 160 of 247

ACTIVITY CARD
P10.4.8. - Perform Quality Control
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

PMT

Control Plan included in the


Quality Management Plan (GFRPMO-160B)

P10.4.8. - Perform Quality Control


PMT
The PM, with the contribution of the other PMT members, shall
monitor and record the results of the quality activities that are
executed in order to assess performance and recommend necessary
changes

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

inspections

quality reports; NC; proposed


change

PMT
Quality

aligns with PMBOK Fourth Edition: 8.3. "perform Quality Control"


aligns with COMAU Policy #16: Policy does not spell out this specific process

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 161 of 247

ACTIVITY CARD
P10.4.9. - Administer Procurements
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

PMIS (GOI-PMO-120)

correspondence with suppliers


(eg., mail PST)

FOR

COMAU procurement process, under the overall responsibility


of CIO organization, is a cross-functional process with clear
responsibilities identified for each step with the aim to
achieve the highest level of competitiveness while
maintaining project objectives. The process is defined by
Process "P6 - Supply Chain Management" and therfore the
"P10.4.9. Administer Procurements" process defines the
interactions between P6 and P10 processes.
The PM shall be always directly involved by CIO leader and
Supply Chain function in the management of "critical"
suppliers (i.e. suppliers whose performance is critical for the
success of the project as they have been identified in the
Procurement Management Plan).

P10.4.9.1. - Supplier Reletionship Management


CIO leader; Supply
The legal nature of the contractual relationship makes it imperative Chain; PM; PMT
that the PMT is aware of the legal implications of actions taken when
controlling any procurement. In particular, any correspondence with
the suppliers shall be carefully written and reviewed in the
perspective of a "claim" (e.g. a situation when COMAU and the
supplier cannot reach an agreement on compensation for a change
requested by COMAU, or cannot agree that a change has occurred).

PMT

Procurement Management Plan

P10.4.9.2. - Supplier Monitoring and Controlling


PMT;
The PM with the support of the CIO leader and contribution of Supply CIO leader (Supply
Chain function (and the other PMT members), shall assure a
Chain function)
structured review of supplier's progress. This may include review of
supplier-prepared documentation and inspections (e.g., supplier
schedule of activities and result of their internal milestone check), as
well as quality audits conducted during supplier's execution of work.

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

Sourcing Plan updates


(suppliers process internal
milestones, shipped ExW,
delivered at site, final
documentation issued);
Expediting and Inspection
Reports;
supplier's work performance
data;

Supply Chain; PMT

page 162 of 247

ACTIVITY CARD
P10.4.9. - Administer Procurements (continued)
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

Supply Chain;

procurement documentation
(Purchase Order);

P10.4.9.3. - Procurements Buy Off


During the execution phase and when applicable(*), the PM (and/or
the responsible person in the PMT) will provide the supplier with
formal written notice that the contract has been completed (Buy
Off), after positive verification that all works and deliverables in
supplier' scope were acceptable.
Procurements Buy Off is a preliminary step before Close
Procurement process performed by Supply Chain in the P6 process.

PMT

PMT, Supplier

work performance data


(deliverable completed, ...)

TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

procurements buy off

Supplier;
Supply Chain;
FA&C

claim settlement

Supply Chain

(*) For example: supplies which can only be verified at customer


site, engineering activities, time and material activities outside CIO
perimeter, etc.

P10.4.9.4. - Claim Settlement


During the execution phase, the process of closing procurements
(performed in P6) may also involve finalization of open claims, which
should always include a formal settlement preventing each party to
claim additional amount later on. PM and PMT shall support Supply
Chain by providing all necessary information and evidences to settle
the claims.

PMT;
CIO Leader
Supply Chain;
Legal / Contract
Manager

negotiation

aligns with PMBOK Fourth Edition: 12.3. "Administer Procurements"


aligns with COMAU Policy #16: section 3.2.4. "Management of Critical Suppliers"

335081696.xlsx - 10.4 - MONITORING & CONTROLLING

page 163 of 247

ACTIVITY CARD
P10.5.1. - Close Procurements
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

COMAU sourcing process, under the overall responsibility of


CIO organization, is a cross-functional process with clear
responsibilities identified for each step with the aim to
achieve the highest level of competitiveness while
maintaining project objectives. The process is governed by
Process P6 - Supply Chain Management and therefore this
"P10.5.1. - Close Procurements" process defines the
interactions between P6 and the other P10 processes.

Supply Chain;

PMT, Supplier

procurement documentation
(Purchase Order);
work performance data
(deliverable completed, ...)

P10.5.1.1. - Procurements Buy Off


PMT
For any outstanding contracts and when applicable(*), the PM
(and/or the responsible person in the PMT) will provide the supplier
with formal written notice that the contract has been completed
(Buy Off), after positive verification that all works and deliverables in
supplier' scope were acceptable.
Procurements Buy Off is a preliminary step before Close
Procurement process performed by Supply Chain in the P6 process.
(*) For example: supplies which can only be verified at customer
site, engineering activities, time and material activities outside CIO
perimeter, etc.

P10.5.1.2. - Claim Settlement


The process of closing procurements (performed in P6) may also
involve finalization of open claims, which should always include a
formal settlement preventing each party to claim additional amount
later on. PM and PMT shall support Supply Chain by providing all
necessary information and evidences to settle the claims.

PM;
CIO Leader;Supply
Chain;
Legal / Contract
Manager

Before completing the Closing phase, PM shall verify that there are
not any outstanding claims with suppliers.

335081696.xlsx - 10.5 - CLOSING

page 164 of 247

aligns with PMBOK Fourth Edition: 12.4. "Close Procurements"


aligns with COMAU Policy #16: section 3.3.1. "Contract closure (external)"

335081696.xlsx - 10.5 - CLOSING

page 165 of 247

ACTIVITY CARD
P10.5.2. - Close Project
FROM

INPUT DOCUMENTS

ACTIVITY DETAILS

BY

Formal Customer acceptance (in the terms defined in the Contract)


issued by the Customer is a prerequisite for project closure.
The PM is responsible for all the activities necessary for
administrative closure of the project, including:

PMT

Open Issue List;


Open NCs

P10.5.2.1. - Close NCs


Ensure that all NC are closed out and corrective actions have been
implemented.

PM

P10.5.2.2. - Update PMIS


Ensure that all project files reside in the proper data repository.

PM

P10.5.2.3. - Transfer Warranty


Transfer of the warranty obligations under the contract to the
responsibility of the After-Sales service, which is formalized in a
dedicated meeting between PMT and After-Sales responsible
("M1080 - Handover to After-Sales");

PM; After-Sales

P10.5.2.4. - Prepare Project Closing Form


PM; Project
Inform project controller that project acceptance has been achieved, Controller
directing him/her to close job orders, transfer allocated budget to
After-Sales (e.g., budget for completing open issues left in addition
to warranty budget), and provide final cost report.

335081696.xlsx - 10.5 - CLOSING

page 166 of 247

P10.5.2.5. - Prepare Project Close Out Report


The PM, with the contribution of the other PMT members, shall also
prepare a Project Close-out report which shall serve as a repository
of information which can benefit future projects, by recording
events, data, lessons learned and Customers relationship.

PM, PMT

A foundamental requirement is the preparation of the


lessons learned document.
The Project Close-out Report shall be typically completed within one
month from project Final Acceptance and shall be presented by PM
and PMT to Project sponsor and internal stakeholders during a
dedicated meeting ("M1090 - Project Close-out Meeting")

aligns with PMBOK Fourth Edition: 4.6. "Close Project or Phase"


aligns with COMAU Policy #16: section 3.3.1. "Contract closure (external)", 3.3.2. "Administrative closure (internal)" and 3.3.3. "Project Close-out report"

335081696.xlsx - 10.5 - CLOSING

page 167 of 247

Y CARD
- Close Procurements
TOOLS & TECHNIQUES

negotiation

OUTPUT DOCUMENTS

FOR

procurements buy off

Supplier;
Supply Chain;
FA&C

claim settlement

Supply Chain

335081696.xlsx - 10.5 - CLOSING

page 168 of 247

335081696.xlsx - 10.5 - CLOSING

page 169 of 247

Y CARD
- Close Project
TOOLS & TECHNIQUES

OUTPUT DOCUMENTS

FOR

NC system

NCs closed

PMT; functional
managers

PMIS (GOI-PMO-120)

Documents stored

PMT; functional
managers

M1080 - Handover to After-Sales PfM; After-Sales


meeting planned

Project Closing form (GFR-PMO240)

Project Closing form duly filled

335081696.xlsx - 10.5 - CLOSING

Project Sponsor;
FA&C; PfM

page 170 of 247

Project Close-out Report


template (GFR-PMO-230)

Project Close-out Report;


M1090 - Project Close-out
Meeting planned

Project Sponsor;
PfM; PMT; functional
managers, Sales;

ose-out report"

335081696.xlsx - 10.5 - CLOSING

page 171 of 247

EVENT CARD
M1000 Handover from Sale
responsible: Sales
INPUT DOCUMENTS
Contract
CAP form (duly filled)
COMAU Proposal
Cost Estimates

FROM

EVENT DETAILS

Sales
Proposal
Estimating

when a new project is acquired, Sales shall call a meeting with the
purpose of presenting and handover to Project Execution functions
the complete contractual documentation and COMAU Proposal and
Cost Estimates.
during the meeting Sales shall present:
- Technical Proposal (highlighting the specific technical solution
adopted to cope with customer specifications);
- Project Execution Proposal (including proposal project schedule
and proposal make or buy strategy)
- Cost Estimates;
- Contract Approval Package (CAP form), with particular reference to
the Preliminary Risk Assessment;
- applicable Terms & Conditions;
- any other relevant information

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

closes P2 - ORDER ACQUISITION


starts P10.1 - (Project) INITIATING

Sales, Proposal & Estimating


Project Sponsor, PfM, PM (if already identified)
functional managers, PMT (if already identified)
QA engineer

EVENT PREPARATION

335081696.xlsx - EVENT CARDS

page 172 of 247

EVENT CARD
M1010 Project Kick-off Meet
responsible: Project Manager
INPUT DOCUMENTS

FROM

EVENT DETAILS

Project Charter

PfM
(Project Sponsor);

Contract, CAP form, Proposal and Cost Estimate

Sales
Proposal
Estimating

After the PM and the other PMT members have been identified and
assigned to the project, the PM shall call a meeting with the purpose
of :
- present the PMT org chart;
- verify the availability of all resources (other than PMT) needed for
project planning phase;
- align the PMT on the content of the Contract, Proposal and Cost
Estimate in preparation of the next planning activities;
- present the Stakeholders Register that has been prepared on the
basis of the information provided by Sales

this meeting should be tentatively scheduled one (1) week after PM


and PMT have been assigned to the project

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

closes P10.1. - (Project) INITIATING


starts P10.2. - (Project) PLANNING

PM and PMT
functional managers
QA engineer

EVENT PREPARATION
PM should make available input documents to attendees some days before the meeting

335081696.xlsx - EVENT CARDS

page 173 of 247

EVENT CARD
M1020 Initial Project Baseline Ap
responsible: Project Manager
INPUT DOCUMENTS
Project Charter

FROM

EVENT DETAILS

PfM
(Project Sponsor)

Once the Project Planning phase has been completed, the PM shall
call a meeting with Project Sponsor and internal stakeholders to
obtain formal "buy-in" of the Project Baseline and all other planning
documents

Project Management Plan;


PMT
Project Baseline proposal from PMT (including Project
Scope Statement, WBS, WBS dictionary, Schedule
Baseline and Cost Baseline)

The Project Baseline shall be formally approved by the Project


Sponsor. A signed copy of the Project Baseline document (including
Project Scope Statement, Project Master Schedule Baseline and
summary of Cost Baseline) shall be stored in the appropriate project
folder.

this meeting should be scheduled within one (1) month from M1010
Project Kick-off

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

closes P10.2. - (project) PLANNING


starts P10.3. - (project) EXECUTING

Project Sponsor
PM and PMT
PfM, functional managers
QA engineer

EVENT PREPARATION
PM and PMT should make available input documents to attendees some days before the meeting

335081696.xlsx - EVENT CARDS

page 174 of 247

EVENT CARD
M1030 Project Management Team
responsible: Project Manager
INPUT DOCUMENTS

FROM

EVENT DETAILS

Issue Log
Project Management Plan (incl. subsidiary plans)

PM

the PM shall call periodic meetings (ideally weekly) of PMT to review


Project Issue Log in order to ensure that all issues are addressed in
a timely fashion.

Change Request Log


Change Requests

PM
PMT

PMT will review change requests (MOD and VAR) to promote them
to the Integrated Change Control process P10.4.6

Schedule Baseline
Cost Baseline
work performance data

PM
PMT

PMT members will make available work performance data for their
respective area of responsibility, and identify deviations from Cost
and Schedule Baseline, assessing need for reaction and adjustment

Risk Register

PM

on regular basis, as defined in the Project Risk Management Plan,


PMT will also review the Risk Register

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

performed thru
P10.2. - (Project) PLANNING
P10.3. - (Project) EXECUTING
P10.4. - (Project) MONITORING AND CONTROLLING

PMT

EVENT PREPARATION
work performance data available and properly stored

335081696.xlsx - EVENT CARDS

page 175 of 247

EVENT CARD
M1040 Project Review Meet
responsible: Project Manager
INPUT DOCUMENTS

FROM

EVENT DETAILS

work performance reports


Change Request Log
Summary of invoice and payments

PMT
PM
project controller

the PM shall periodically report to the Project Sponsor and internal


stakeholders the status of the project.
this presentation take place during the monthly Projects Review
Meeting called by the PfM
the presentation shall typically include:
analysis of past performance;
significant accomplishment during the reporting period;
work to be completed during the next reporting period;
current status of risks and issues;
results of trend and variance analysis;
forecasted project completion (including time and cost);
summary of changes approved in the period;
summary of invoice and payments;
(any other relevant information to be reviewed and discussed)

Deviations from the Project Baseline, if any, shall be properly


addressed and must be attested by the Project Sponsor.
As a formal evidence of this, the project performance summary
sheet shall be signed by both the PM and the Project Sponsor

Project Baseline change request


Management Contingency utilization request

LINK WITH OTHER PROCESSES/EVENTS

PM

During the same meeting the Project Sponsor may authorize


changes to the Project Baseline and/or the use of the Management
Contingency to cope with unknown risks occurrence

PARTICIPANTS ROLES
Project Sponsor; PfM; functional managers; PMO
PM and PMT

335081696.xlsx - EVENT CARDS

page 176 of 247

EVENT PREPARATION
PM shall discuss and share with PMT the Project Performance Report presentation in advance
presentation will be made available to PfM in advance

335081696.xlsx - EVENT CARDS

page 177 of 247

EVENT CARD
M1050 Project Status Report to C
responsible: Project Manager
INPUT DOCUMENTS

FROM

EVENT DETAILS

project communications management plan

PM

the PM shall periodically distribute to the customer a report of the


status of the project, which shall typically include:

work performance reports

PMT

significant accomplishment during the reporting period;


work to be completed during the next reporting period;

issue log
change request log
invoice aging summary

LINK WITH OTHER PROCESSES/EVENTS

PM
PM
project controller

open issues;
summary of changes approved in the period;
summary of invoice and payments;
(any other relevant information to be reviewed and discussed)

PARTICIPANTS ROLES
(according to communications management plan)
customer
PM (with PMT)
sales

EVENT PREPARATION
PM shall share with Sales the content of the Report before submitting it to the customer

335081696.xlsx - EVENT CARDS

page 178 of 247

EVENT CARD
M1060 Customer Satisfaction S
responsible: Project Manager /Sales
INPUT DOCUMENTS

FROM

EVENT DETAILS

Project Communications Management Plan


Yearly plan for Customer Satisfaction Survey

PM
Marketing & Sales

The PM, with the assistance of Sales, shall periodically contact the
Customer to measure their degree of satisfaction
PM and Sales should review and discuss in a face-to-face meeting
the Survey once it has been completed in order to understand any
issue that may have been raised

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

(P1/P2 - to be developed)

Customer, PM, Sales

EVENT PREPARATION
accurate reporting to the Customer thru periodic Project Status Reports

335081696.xlsx - EVENT CARDS

page 179 of 247

EVENT CARD
M1070 Request for Final Accep
responsible: Project Manager
INPUT DOCUMENTS
completed scope verification
(checklists from other processes)

FROM

EVENT DETAILS

PMT

once verified that all project deliverables have been satisfactorily


completed and contractual requirements have been fulfilled, the PM
shall formally request customer final acceptance in accordance with
the specific procedure set forth in the contract

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

closes P10.3. - (project) PLANNING and


P10.4. - (project) MONITORING & CONTROLLING

PM, PMT
customer

starts P10.5. - (project) CLOSING

EVENT PREPARATION
PMT meeting to verify input documents

335081696.xlsx - EVENT CARDS

page 180 of 247

EVENT CARD
M1080 Hand-over to After Sa
responsible: Project Manager
INPUT DOCUMENTS

FROM

EVENT DETAILS

customer final acceptance

PM

when project has achieved customer final acceptance, the PM shall


transfer the remaining warranty obligations under the contract to
the responsibility of the After-Sales service
hand-over to After Sales may also take place when few minor items
are still to be completed, but project has been substantially
completed and it becomes more appropriate to follow up remaining
works
the PM shall call a meeting with PMT and After Sales manager to
brief him/her on project status and handover all pertinent
information

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

closes Project Execution activities apart from internal


and administrative project closure

PM; PMT
functional managers
Sales
After Sales

starts After Sales activities

EVENT PREPARATION
PM shall collect all pertinent documentation to be
handed-over to After-Sales

335081696.xlsx - EVENT CARDS

page 181 of 247

EVENT CARD
M1090 Project Close-out mee
responsible: Project Manager
INPUT DOCUMENTS

FROM

EVENT DETAILS

Project Close-out Report

PM

After having compiled the Project Close-out Report, the PM shall call
a meeting with PMT and Project Sponsor and all internal
stakeholders
during the meeting the PMT will discuss with the other attendees
the content of the Report, focusing on the problems encountered
during the project and the solutions applied
following the issues, concerns and proposals raised by the PMT, the
functional managers attending the meeting may define action plans
to:
create new/modify standards
review/change performing organization's processes and
procedures
review/change performing organization's knowledge base,
including, but not limited to:
- historical information (cost estimate database, vendor lists, )
- lessons learned
evaluate/implement new infrastructure and/or working tools
evaluate/develop human resources skills and behaviours
which will be captured in a dedicated action register/minute of
meeting

LINK WITH OTHER PROCESSES/EVENTS

PARTICIPANTS ROLES

Closes 10.5 - (Project) CLOSING

PM and PMT
Project Sponsor, PfM, functional managers
Quality, PMO

EVENT PREPARATION
PM shall make available to attendees the Project Close-out Report latest one (1) week
before the scheduled date of the meeting

335081696.xlsx - EVENT CARDS

page 182 of 247

EVENT CARD
M1000 Handover from Sales

M1000

OUTPUT DOCUMENTS
M1000 checklist completed
Contract, CAP form, Proposal and Cost Estimate made available

OUTPUT RECIPIENT
PfM, functional managers
PM and PMT (if already identified)
QA engineer

TOOLS

335081696.xlsx - EVENT CARDS

page 183 of 247

EVENT CARD
M1010 Project Kick-off Meeting

M1010

OUTPUT DOCUMENTS
M1010 checklist completed

OUTPUT RECIPIENT
PM and PMT
functional managers
QA engineer

TOOLS
PMIS (GOI-PMO-120)

335081696.xlsx - EVENT CARDS

page 184 of 247

EVENT CARD
0 Initial Project Baseline Approval

M1020

OUTPUT DOCUMENTS
M1020 checklist completed
approved Project Management Plan;
approved Project Baseline

OUTPUT RECIPIENT
Project Sponsor
PM and PMT
PfM, functional managers
QA engineer

TOOLS
PMIS (GOI-PMO-120)

335081696.xlsx - EVENT CARDS

page 185 of 247

EVENT CARD
Project Management Team Meeting

M1030

OUTPUT DOCUMENTS
Issue Log updated
Project Management Plan (incl. subsidiary plans) updated

proposed changes (COF and Customer)

work performance information


Project Schedule updated
Project Cost Performance updated
Risk Register updated

OUTPUT RECIPIENT
PMT

TOOLS
PMIS (GOI-PMO-120)
scheduling tool
ERP system

335081696.xlsx - EVENT CARDS

page 186 of 247

EVENT CARD
1040 Project Review Meeting

M1040

OUTPUT DOCUMENTS
Project Performance Report presentation

PPR sheet signed at least quarterly

Project Baseline update

OUTPUT RECIPIENT
Project Sponsor; PfM; functional managers; PMO
PMT (Project Baseline update)

335081696.xlsx - EVENT CARDS

page 187 of 247

TOOLS
PMIS (GOI-PMO-120)
Project Performance Review presentation template

335081696.xlsx - EVENT CARDS

page 188 of 247

EVENT CARD
M1050
Project Status Report to Customer
OUTPUT DOCUMENTS
Project Status Report

OUTPUT RECIPIENT
customer
project sponsor
sales
PMT

TOOLS

335081696.xlsx - EVENT CARDS

page 189 of 247

EVENT CARD
60 Customer Satisfaction Survey

M1060

OUTPUT DOCUMENTS
Customer Satisfaction Survey

OUTPUT RECIPIENT
Sales, Marketing, Quality, Project Sponsor, PfM

TOOLS
Customer Satisfaction Survey template

335081696.xlsx - EVENT CARDS

page 190 of 247

EVENT CARD
70 Request for Final Acceptance

M1070

OUTPUT DOCUMENTS
request for Final Acceptance
M1070 checklist completed

OUTPUT RECIPIENT
customer,
project sponsor (for information)

TOOLS

335081696.xlsx - EVENT CARDS

page 191 of 247

EVENT CARD
1080 Hand-over to After Sales

M1080

OUTPUT DOCUMENTS
M1080 checklist completed

OUTPUT RECIPIENT
After Sales

TOOLS
PMIS (GOI-PMO-120)

335081696.xlsx - EVENT CARDS

page 192 of 247

EVENT CARD
1090 Project Close-out meeting

M1090

OUTPUT DOCUMENTS
action register/minute of meeting

OUTPUT RECIPIENT
Project Sponsor, PfM, functional managers
Quality, PMO

TOOLS
PMIS (GOI-PMO-120)

335081696.xlsx - EVENT CARDS

page 193 of 247

M1000 Handover from Sales check


< project_name >
#

item

does a valid contract exist?

is the applicable contractual documentation defined and available?


(contractual documentation also includes engineering documentation such as product data, CAD libraries, "as built" drawings, ...)

have the Customer contact information been presented and made available?

has the COMAU Technical Proposal been presented during the meeting and is it available?

has the COMAU Project Execution Proposal (Proposal Schedule, Proposal Make or Buy / Job Sharing strategy) been presented during the meeting
and is it available?

are both the Technical and Project Execution Proposals compliant with Customer Statement of Work (standard and specifications) or have been the
discrepancies been agreed in written with the Customer (final contracted SOW)?

has the Cost Estimate been presented during the meeting and is it available?

has the Cost Estimate been developed on the basis of the final contracted SOW (see item 7 above)?

10

Has the CAP Form been presented during the meeting and is it available?

11

has the Preliminary Risk Assessment included in the CAP form been duly filled?

11.1

has a suitable response strategy been foreseen for the risk identified therein?

11.2

have the risk mitigation costs, if any, been considered in the Cost Estimate?

11.3

has a suitable Technical Contingency been considered in the Cost Estimate for "known" risks?

11.4

has a Management Contingency been allocated for "unknown" risks?

12

is the Project Sponsor defined?

attendees
signatures

name

SALES
PROPOSAL
ESTIMATING
PROJECT & SITE MANAGEMENT
ENGINEERING
FINANCE, ADMINISTRATION & CONTROL
PLANNING
SUPPLY CHAIN
MANUFACTURING
QUALITY
(fill others as applicable)

335081696.xlsx - CHECKLISTS

page 194 of 247

project sponsor approval

335081696.xlsx - CHECKLISTS

name

page 195 of 247

M1010 Project Kick-off checklis


< project_name >
#

item

has the Project Charter been developed and signed?

has the Job Order been opened in the ERP system (SAP, Baan, )?

is the Project Management Team identified and assigned?


(PMT org chart should have been prepared and been presented during the meeting)

are all resources (other than PMT) needed for project planning phase identified and assigned?

is the PMIS initialized and has the complete contractual and Proposal documentation been filed therein?

has the PMT gone through the contractual and Proposal documentation and been aligned on their content?

has the Stakeholder Register been prepared?

Project Management Team (refer to PMT org chart and fill in names and roles as applicable)
name
role

attendees
signatures

name

SALES
PROPOSAL
ESTIMATING
PROJECT & SITE MANAGEMENT
ENGINEERING
FINANCE, ADMINISTRATION & CONTROL
PLANNING
SUPPLY CHAIN
MANUFACTURING
QUALITY
(fill others as applicable)

335081696.xlsx - CHECKLISTS

page 196 of 247

project sponsor approval

335081696.xlsx - CHECKLISTS

name

page 197 of 247

M1020 Initial Project Baseline Approval


< project_name >
#

item

1
1.1

Project Management Plan, including subsidiary plans:


has the project management approach been defined?

1.2

has the Change Management procedure with the Customer defined and approved?

1.3

has the Project Quality Management Plan been developed and approved?

1.4

has the Project Human Resource Management Plan been developed and approved?

1.5

has the Project Communications Management Plan been developed and approved?

1.6

has the Project Risk Management Plan been developed and approved?

1.7

has the Project Quality Management Plan been developed and approved?

1.8

has the Project Procurement Management Plan been developed and approved?

2
2.1

Project Baseline:
has the Project Scope Statement been developed and approved?

2.2

has the WBS (and WBS dictionary) been developed and approved?

2.3

has the Schedule Baseline been developed and approved?

2.4

has the Cost Baseline been developed and approved?

2.5

are both Schedule and Cost Baselines considering Technical Contingency for identified risks?

2.5

is the approved project Schedule aligned with the customer milestones?

2.6

have the targets (cost, time, ) set by Project Sponsor in the Project Charter been met?

Project Management Team (refer to PMT org chart and fill in names and roles as applicable)
name
role

335081696.xlsx - CHECKLISTS

page 198 of 247

attendees
signatures

name

SALES
PROPOSAL
ESTIMATING
PROJECT & SITE MANAGEMENT
ENGINEERING
FINANCE, ADMINISTRATION & CONTROL
PLANNING
SUPPLY CHAIN
MANUFACTURING
QUALITY

project sponsor approval

name

Milestone passed
Milestone passed, conditioned to open issues closing
Milestone NOT passed

335081696.xlsx - CHECKLISTS

re-planned for

page 199 of 247

M1070 Request for Final Acceptance c


< project_name >
#

item

1.

are the contractual Buy-Off requirements clearly defined and measurable?

2.

have any Customer Checklists and all elements of the Customer Buy-Off procedure been completed?

3.

have all Customer open issues been resolved (except those agreed with the Customer)?

4.

have all outstanding open issues been documented with an agreed resolution plan and timing?

5.

are all manuals (User, R&M, Maintenance) and CE certification (or equivalent, if applicable) complete and available to Customer End User/Plant?

6.

have the Customer personnel been trained as per contractual requirements?

7.

have the equipment safety and ergonomic related to Customer personnel been reviewed and signed-off?

8.

have all technical documentation been delivered to Customer as per contractual requirements?

9.

has the cycle-time been measured and conform to what is contractually required?

10.

has the technical availability been measured and conform to what is contractually required?

Project Management Team (refer to PMT org chart and fill in names and roles as applicable)
name
role

335081696.xlsx - CHECKLISTS

page 200 of 247

attendees
signatures

name

SALES
PROPOSAL
ESTIMATING
PROJECT & SITE MANAGEMENT
ENGINEERING
FINANCE, ADMINISTRATION & CONTROL
PLANNING
SUPPLY CHAIN
MANUFACTURING
QUALITY

project sponsor approval

name

Milestone passed
Milestone passed, conditioned to open issues closing
Milestone NOT passed

335081696.xlsx - CHECKLISTS

re-planned for

page 201 of 247

M1080 Handover to After Sales chec


< project_name >
#

item

has the Final Acceptance been signed by customer?

1.1

(if not) has a list of remaining works been clearly defined and agreed with the customer?

1.2

(if not) has a suitable budget been reserved for completion of remaining works?

2
2.1

is the Warranty Period expiry date defined?


(if not) is it clearly defined when the Warranty Period will start and its duration?

are spare parts available at site?

has the Contract Price been completely invoiced?

have the following topics been discussed during the meeting and relevant information been made available to After-Sales?

5.1

customer contact information

5.2

plant technical characteristics

5.3

list of remaining works (punch list,)

5.4

spare parts list

5.5

list of local subcontractors, with contact information

5.6

list of main suppliers, with suppliers warranty conditions and contact information

5.7

other (specify)
Project Management Team (refer to PMT org chart and fill in names and roles as applicable)
name
role

attendees
signatures

name

SALES
PROPOSAL
ESTIMATING
PROJECT & SITE MANAGEMENT
ENGINEERING
FINANCE, ADMINISTRATION & CONTROL
PLANNING
SUPPLY CHAIN

335081696.xlsx - CHECKLISTS

page 202 of 247

MANUFACTURING
QUALITY

After Sales

name

Milestone passed
Milestone passed, conditioned to open issues closing
Milestone NOT passed

335081696.xlsx - CHECKLISTS

re-planned for

page 203 of 247

M1090 Project Close-out_checkli


< project_name >
#

item

has the Project Close-out Report been presented during the meeting and is it available?

1.1

is the executive summary compiled?

1.2

are the detailed report for project execution phases (engineering, procurement, manufacturing,) compiled?

1.3

are the lessons learned compiled?

1.4

is the COF analysis compiled?

1.5

is the Quality Management Report compiled?

1.6

is the Final Cost Report compiled?

2.

have PMT issues, concerns and proposals been discussed during the meeting?

3.

will action plans be implemented on:

3.1

standards

3.2

processes and procedures

3.3

knowledge base (historical information such as cost estimate database, vendor lists, ...)

3.4

lessons learned / enterprise database

3.5

new infrastructure/working tools

3.6

human resources skills & behaviours

3.7

other (specify)
Project Management Team (refer to PMT org chart and fill in names and roles as applicable)
name
role

attendees
signatures

name

SALES
PROPOSAL

335081696.xlsx - CHECKLISTS

page 204 of 247

ESTIMATING
PROJECT & SITE MANAGEMENT
ENGINEERING
FINANCE, ADMINISTRATION & CONTROL
PLANNING
SUPPLY CHAIN
MANUFACTURING
QUALITY

project sponsor approval

name

Milestone passed
Milestone passed, conditioned to open issues closing
Milestone NOT passed

335081696.xlsx - CHECKLISTS

re-planned for

page 205 of 247

from Sales checklist


< date >
YES

NO

n/a

remarks

ies, "as built" drawings, ...)

strategy) been presented during the meeting

standard and specifications) or have been the

title

signature

335081696.xlsx - CHECKLISTS

page 206 of 247

title

signature

335081696.xlsx - CHECKLISTS

page 207 of 247

Kick-off checklist
< date >
YES

NO

n/a

remarks

n?

tent?

signature

title

signature

335081696.xlsx - CHECKLISTS

page 208 of 247

title

signature

335081696.xlsx - CHECKLISTS

page 209 of 247

Baseline Approval checklist


< date >
YES

NO

n/a

remarks

signature

335081696.xlsx - CHECKLISTS

page 210 of 247

title

signature

title

signature

<date>

335081696.xlsx - CHECKLISTS

page 211 of 247

nal Acceptance checklist


< date >
YES

NO

n/a

remarks

and available to Customer End User/Plant?

ff?

signature

335081696.xlsx - CHECKLISTS

page 212 of 247

title

signature

title

signature

<date>

335081696.xlsx - CHECKLISTS

page 213 of 247

o After Sales checklist


< date >
YES

NO

n/a

remarks

lable to After-Sales?

signature

title

signature

335081696.xlsx - CHECKLISTS

page 214 of 247

title

signature

<date>

335081696.xlsx - CHECKLISTS

page 215 of 247

Close-out_checklist
< date >
YES

NO

n/a

remarks

piled?

signature

title

signature

335081696.xlsx - CHECKLISTS

page 216 of 247

title

signature

<date>

335081696.xlsx - CHECKLISTS

page 217 of 247

integration management

quality management

procurement managemen

ment

sc

nt

human

ment

scope management

man resource management

time management

communications managemen

co

ment

ri

cost management

risk management

initiating

planning

executing

monitoring

closing

& controlling

develop Project Charter

Project Charter
project_ID

direct & manage Project


Execution

develop WBS

WBS structure

estimate Costs and determine


Budget
Q00
B00 proposal

approve Project Baseline

B00 approved by
Project Sponsor

identify, analyse and plan


response to Risks
Technical Contingency
for identified Risks
Management Contingency
for "unknown" Risks

work performance data


(incurred costs)
ACU

distribute Information and


manage Stakeholders
Expectations

control Costs

close Project

work performance information


(ETC)
ACU

perform Integrated Change


Control

project performance report


presentation (PPR)

develop and manage Project


Team
work authorization

QCU (from Customer changes)


BCU (from internal changes
approved by Project Sponsor)

monitor & control Risks

updated Technical Contingency


for identified Risks

project closing form

initiating

planning

develop Procurements
Management Plan

executing

Procurements
ement Plan

conduct Procurements

Procurements Management Plan


(make/buy
vendor list
expediting & inspection requirements)

sourcing plan
PO

monitoring

closing

& controlling

administer Procurements

close Procurements

sourcing plan updates

closed procuremen

closed procurements

G.6. Communications with the


customer (eg., mail pst)