PART-III
PREAMBLE
1. The existing AP Standard data for various constructions items are based on observations made
several decades back, mostly utilising eployment of machinery was at the barest minimum. The
Board of Chief engineers have been adopting almost the same data, duly modifying the rates of
labour; materials, hire charges of limited machinery, every year. The advent of construction
machinery and its usage in construction industry has changed the structure and methodology of
data formulation & rate structure and hence, the present estimation of work item rates are not
reflecting ground reality. The CWC(Ministry of Irrigation) has also recommended that where
standard or schedule of rates are revised or where is necessary to do so, the primary guiding
principle should be escalation in labour and material cost and not on trend of rates quoted by
contractors. But the above recommended principle is not being followed by the Board of Chief
Engineers in Andhra Pradesh.
2. Government, in GO 7326 (GAD-GPM& AR) Dated 26-10-05, has observed that the age old
Standard data requires revision and updation with reference to the latest machinery and
contemporary practices and has constituted a High Level Committee to advise on updating and
revision of standard data and schedule of rates. The work has been taken up by CGG and SPIUirrigation. The secretary (Irrigation ) is the member- convener of the committee Accordingly the
data has been revised adopting the procedures and guidelines given by CWC, Report on
committee on cost control of river valley Projects, BIS specifications, NHAI, MORTH, MORD, CPWD
and Government of Karnataka and revised data and formulated schedule of rates for all
infrastructure Departments (I&CAD, R&B, PR and PH). The team of senior engineers interacted
with the S.R Committee of Karnataka on implementation and improvements needed. For irrigation
works the data pattern as adopted by Karnataka has been considered and for other Departments
the data adopted by MORTH,MORD and NHAI etc., is adopted
3. Sequence followed in revision of standard data is,
(a) The first step is the revision and formulation of standard data for each work
component
(b) The second step is to work out the details of inputs. This enables to generate the unit
work item rates, by incorporating the use rates of machinery, materials, labour charges
and other supplementary parameters
(c) The third step is to develop software tool to generate unit rate using the software
(completed for irrigation works by the SPI Unit of Irrigation)
4. The Detailed draft data was communicated to all the HODs and interacted through many
seminars and discussions and incorporated the relevant features.The Board of chief engineers in
their meetings have recommended for acceptance to the data formulated and schedule of rates.
It was proposed to examine the recommendations on important parameters, to refer to high level
committee, for their specific recommendations for adoption, as they are common to all
departments. The committee made in depth study on the methodology and systems followed by
the reputed National organizations and other States and made detailed deliberations with HODs
and representatives of Builders Association of India and
made
recommendations to the
2)
Brief description of the item of work to cover all important aspects of the work included in the in
the Data . On reading the item description, the user should be in a position to assess the various
cost components involved in the work.
3)
The data reflects various assessments / assumptions made in arriving at the quantities of
materials, machinery, labour and other in-puts. In case of plants and equipment the output of
main plant is worked out and the requirement of all other inputs and assessed to match the
output of the main plant. Cycle time of operations is the criteria for assessing the output of
equipment. Generally the equipment manufacturers furnish the output of machinery under ideal
conditions of working. Suitable job and management efficiency factors are considered while
working out the average output of machinery under field conditions. In case of combination of
machinery and manpower the assessment of manpower shall match the output of machinery.
Though cycle time of operations is the criteria for hourly / daily out-put of machinery work-force
,the actual progress of work depends on several other factors such as power interruptions, minor
break-downs, time for meals and other needs of work-force, stray rains etc. Therefore, it is the
general practice to consider 50 minutes as the actual working time per hour for working out the
hourly / daily out-put of machinery / work-force.CWC / BIS guide-lines stipulate the actual working
hours for the purpose of equipment planning and utilisation. The daily out-put is computed duly
considering the actual available working time and feed back from the field.
For gate and hoist works it is the general practice to specify the quantity of work in
terms of number of sets of embedded parts / gates. The requirement of machinery and workforce for cutting, bending, fabrication, erection, painting etc., is assessed to commensurate with
the task involved.
The data for gates and E.M. Parts is arrived per Ton quantity.
The data for Hoists and Gantry Cranes is worked out on the basis of capacity in tonnage
4) The lead and lift charges provided in PART-I (B) are generally applicable and common to all
Departments. Any item is not covered in this part, the rates as provided in the data of the
relevant works may be adopted in preparation of estimates.
5) The basic material inputs needed for all works are listed and incorporated in the data. The
requirements are analyzed and the specifications adopted shall confirm to Standards published by
the BIS.
The labour and material rates will be communicated by the Board of Chief engineers.
Unless otherwise specified, all material rates shall be inclusive of all taxes, duties, levies,
royalty/seigniorage, transportation and handling costs up to project area.
For sand, gravel , murum, stones , course aggregates etc, the rates are to be fixed for
delivery at Quarry, adding seigniorage ( royality) charges, loading charges by machinery /
manual means and idle hire charges of machinery
For earth/ soil for embankment works from borrow areas, which is not included in the
material list of schedule of rates, seigniorage charges are to be added separately,if
applicable.
For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs, the rates are
to be taken prevailing at major commercial centre near project area. The lead charges, as
applicable are to be added in preparing estimates.
The specifications of the aggregates for sizes and gradation and its adoption shall be as
per IS 383.
No allowance towards labour importation and labour amenities added extra as they are
included in the recommended overheads.
On Labour Component: Certain additional allowances are added extra to the wages of
labour (,i.e. only on labour component in the work item) in the form of percentage, as
recommended by the Government/Board of chief engineers,due to statutory and other
provisions.
However, If more than one area allowances, such as those for (1) Municipalities (2)
Agency / Tribal areas (3) Industrial areas are applicable for a particular situation, only the
maximum out of the allowable percentages is to be allowed.
The hire charge of a machinery / equipment is worked out based on the guidelines
published by CWC and BIS codes.
For the other machinery not covered by the list, the R&B and other users may adopt hire
charges as recommended by the MORTH.
8) Lead Charges
The high level committee has recommended to adopt, for conveyance by head load, a
minimum lead of 50 meters and additional lead up to 150 meters in the intervals of 50
meters. Beyond 150 meters lead ,only machinery rates are to be adopted.
The basic item rates provided in the schedule of rates include 50 m or 1 km as initial lead
and no lead charges shall be allowed where the source of material is within the initial
lead specified in item rate. Additional lead charges shall be allowed for the lead
exceeding initial lead specified in the item rate.
The lead charges per unit quantity for conveyance of the materials are worked out,and
included in the schedule of rates in increment of 50 m for head load and in increment of
1 km for mechanical mode.
The rates for lead charges by head load upto 150 meters and by machinery up to 5 km,
shall be cumulative and inclusive of lead charges for preceding lead. For lead beyond 5
km the lead charges shall be worked out on per km basis.
The data includes initial lift charges of 3 meters ,for materials conveyance by head load,
Additional leads in the interval of 1.0 meters are worked out, as additional labour input
and incorporated in the chapter on Lead and lifts .
Where the conveyance / lifting of material is done by mechanical means, lift charges shall
not be considered, as the cycle time of operation of the machine includes lifts involved.
The data and rates for lift charges is cumulative and are inclusive of rates for preceding
lifts also.
steel : The wastage of steel @ 2.5% is allowed for gates and allied structures. For
RCC works the wastage is @2.5% for the reinforcement rods above 36mm did and
@ 5% for rods below 36mm dia. including overlaps, if they are not welded. If welding
is adopted for the reinforcement rods even for below 36mm dia, 2.5% of wastage is
only recommended.
12) Provision for rate for water:The Committee has recommended not considering the water charges in the Irrigation
Project works. But, it may be considered in specific cases as per the site conditions.
13)
In respect of RCC works the rate for cement concrete for 1 cum is worked separately for
all grades based on Indian Standards. The rate for ton is calculated separately and to be added
separately in the estimates of RCC works as a separate item.
14) Soil classification: The Committee recommended to allow uniform classification of soils for all
Departments and data is worked out accordingly.
1. All soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)
15) Use of Super Plasticizers and Admixtures:
Concrete admixtures such as Air-Entraining Agent (AEA) / Water reducing agent can be
used advantageously for better quality concrete. The high level committee has
recommended adopting for super plasticizers and admixtures at 0.4% on cement for
concrete work as per MORTH standards for batching plants.
16) Contractors overheads, profit and other provisions:
High Level Committee has recommended to add 14% plus 4% towards VAT or as
applicable on item rate towards overheads labour including importation and amenities &
contractor profits, which includes various items recommended in MORTH.
In respect of gates, hoists and allied works excise duty is applicable on the value of
fabricated components supplied to site. Excise duty is not applicable on erection charges.
Further, the excise duty shall not be considered in the rate analysis on material
component, as basic material rates are inclusive of excise duty.
Therefore, excise duty is considered in the rate analysis only on
machinery and labour components required for fabrication of gates and hoists at the
central fabrication yard. It is difficult to determine the machinery and labour components
separately for fabrication and erection.
For the purpose of computation of excise duty to be included in the rate analysis the
machinery and labour components may apportioned at 75 % for central fabrication yard
and 25 % for field erection and commissioning. Therefore, 75 % of the machinery and
labour components may be considered for assessing the extent of excise duty to be
added in the rate analysis.
changes and generation of unit rates, based on basic input rates of Labour, materials and capital
cost of machinery.
A soft ware tool is also developed for auto preparation of estimates based on in put
quantities.
20) For each chapter separate additional details are incorporated for clarity.
USER GUIDELINES OF REVISED STANDARD DATA
i)
Please select the item of work, as given in Index Code, and view the relevant data.
ii)
The common data items like, lead, lift, conveyance and manual excavation (without involving
contracting agencies) is applicable to all Departments (volume-1)
iii) The departments have to adopt the relevant data from other Departments, if such works are
executed by them
iv) The unit rate /hire charges, of machinery not covered in the Irrigation data, the MORTH data
may be taken with the approval of Board of Chief Engineers
v)
For Drinking water Supply works(PART-IV), the data incorporated is generally applicable
only for manual means of execution. The rates deploying machinery have to be worked out
by the Board of Chief engineers and approved for adoption.
The list and capital cost of machinery required to be used in the construction activity, The rate
has to be obtained from major manufacturers and outlet sources and the rate shall be the current market
price inclusive of all taxes, duties and freight charges.
The prevailing fuel charges of petrol and diesel are ascertained and average rate adopted
For the other machinery not covered by the list, the R&B and other users may adopt hire
charges as recommended by the MORTH
b)
The Chairman, Board of Chief Engineers or competent authority
appointed by the Government, based on the approved basic inputs, load the above three basic
parameters in the software program. The unit rate of all works including hire charges of all machinery will
be generated automatically for adoption.
He shall communicate the uniform Schedule of rates arrived from Standard Data, to all users for
uniform and direct adoption in all infrastructure Departments, as applicable
Basic approach and General conditions and assumptions for the preparation of Standard Data
Book for Building Works.
The Basic approach for the preparation of Standard Data for Building works is indicated as under.
1. Description of Items: The description of items is given briefly and linked with the relevant
specifications in AP Standard Specifications.
2. Use of Machinery: For concrete work mixing is proposed with machinery as well as
manually. For laying concrete, lifting is proposed with either by winches or machinery.
Manual means have been proposed for all other items.
3. Working Conditions: The inputs for the Data have been analyzed for the average working
conditions prevailing in the state.
4. Over Heads : This is assumed to include interalia the following elements:
i.
Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements
where required.
10
g) Sundries to cater for unforeseen contingency and miscellaneous items have been added
in the overheads.
h) The various activities of works shall also be documented in photographs and video
cassettes.
i)
The Data for various Earth Work Excavation Items including classification of soils shall be
as in Standard Data for Roads and Bridges.
j)
7. Basic Inputs :
Standard Data Book is based on the requirements of basic inputs of materials, labour and
machineries for various items. The rates for labour, material and usage charges of machinery
for the area where the project is located are to be ascertained from local authorities/enquiries
to prepare Schedule of Rates for the area. The basic rates of materials, such as, stone
boulders, stone for masonry, stone ballast, stone dust, moorum, gravel, lime, manure,
sludge, quarry sweep, kankar, bricks, brick ballast, crushed slag, etc. at quarry / crusher sites
shall be fixed by the Board of Chief Engineers yearly (effective from 1st June to 31st May).
However, the basic rate of materials hand broken / machine broken, crushed aggregates
shall be based on Analysis in Chapter 1 of Roads & Bridges. The cost of materials should
include the cost at source and the cost of their carriage (as per Schedule of rates arrived in
Chapter 1 of Roads & Bridges for conveyance, loading and unloading charges) upto the work
site.
8. Labour
The labour wages should be as per rates fixed by the Board of Chief Engineers keeping the
minimum wages fixed as per Minimum Wages Act. Skilled labour include mason, carpenter,
blacksmith, mechanics and other trades.
9. Materials :
Quantities of materials considered in the rate analysis are approximate for the purpose of
estimation and include normal wastages. Actual consumption would depend on mix design.
The rates of material should include basic cost at locations of stone crushers/factory/rail head
and cost of its carriage to the site of work/plant including loading, unloading and stacking.
Credit for Dismantled Material: The dismantled materials should be examined and a realistic
assessment made for credit for such materials, which can be utilized for works or auctioned.
The basic rates should include all octroi charges, toll tax, sale tax, VAT, municipal taxes and
other local taxes, etc.
10. The Data for the following items of work shall be as per Data Items covered in AP Standard
Data for Roads & Bridges
i. Loading, Unloading, Carriage, Crushing of Materials
ii. Site Clearance
iii. Earth Work Items including classification of Excavated Material.
iv. Horticulture
12
13
BLD-CSTN1-2
BLD-CSTN1-3
BLD-CSTN1-4
Sl
No
1
Description
Unit
Quantity
kg.
cum
cum
1440.00
1.05
1.05
Rate
Rs.
5
Amount
Rs.
6
Rem
arks
7
MORTARS
1
Cement Mortar (1 : 1)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 1.5)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 2)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
day
0.20
kg.
cum
cum
960.00
1.05
1.05
day
0.20
kg.
cum
cum
720.00
1.05
day
0.20
kg.
cum
cum
480.00
1.05
1.05
14
BLD-CSTN1-5
BLD-CSTN1-6
BLD-CSTN1-7
BLD-CSTN1-8
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Excavation for Foundations
day
0.20
kg.
cum
cum
360.00
1.05
1.05
day
0.20
kg.
cum
cum
288.00
1.05
1.05
day
0.20
kg.
cum
cum
240.00
1.05
1.05
day
0.20
kg.
cum
cum
180.00
1.05
1.05
day
0.20
15
BLD-CSTN2
BLD-CSTN2-1
day
Mazdoor (Unskilled)
day
3.64
10
day
Mazdoor (Unskilled)
day
8.32
hour
6.00
b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to
10 per cent of labour cost. Assessment for dewatering shall be made as per site
conditions.
BLD-CSTN2-3
11
Labour
Mate
day
day
8.32
hour
6.00
Mazdoor (Unskilled)
b)
Machinery
16
12
day
Mazdoor (Unskilled)
day
5.20
13
day
Mazdoor (Unskilled)
day
6.24
hour
6.00
b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to
10 per cent of labour cost. Assessment for dewatering shall be made as per site
conditions.
BLD-CSTN2-6
14
day
Driller
day
0.50
Blaster
day
0.25
Mazdoor (Unskilled)
day
8.35
hour
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack
hammers for drilling at 15 cum per hour
c) Material
17
Gelatin 80%
kg
3.50
Nos.
14.00
Mate
day
Mazdoor (Unskilled)
day
5.20
hour
6.00
Mate
day
Mazdoor (Unskilled)
day
0.31
cum
1.00
Detonator electric
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note : 1. Cost of dewatering @ 5 per cent of
(a+b) may be added, where required as per
site condition.
BLD-CSTN2-7
15
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack
hammers of pneumatic breaker at 1 cum per
hour
c) & d) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d)/10
Note : Cost of dewatering up to 5 per cent of
(a+b) may be added, where required as per
site conditions.
Filling with useful available excavated earth
(excluding rock) in trenches, sides of
foundations and basement with initial lead in
layers not exceeding 15 cm thick,
consolidating each deposited layer by
watering and ramming including cost and
conveyance of water to work site and all
operational, incidental, labour charges, hire
charges of T & P etc., complete for finished
item of work. (APSS NO. 309 & 310)
BLD-CSTN2-8
16
Sand filling
Unit = cum
a) Labour
b) Material
Sand
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
BLD-CSTN2-9
17
day
Mazdoor (Unskilled)
day
3.12
18
Kg
cum
cum
cum
cum
400.00
0.90
0.45
0.90
0.45
day
0.10
Mazdoor (unskilled)
day
Water (including for curing)
kl
Grand Total
Note : For Nominal Mix : Considering table 9 IS 456 :
2000, the quantity of cement needed is 405 kgs / cum.
Hence proposed 400 kgs of cement for cum of CC M20
BLD-CSTN3-2
19
2.36
1.20
Kg
cum
cum
cum
cum
kl
220.00
0.90
0.45
0.90
0.45
1.20
hour
1.00
day
0.10
day
1.39
19
BLD-CSTN3-3
BLD-CSTN3-4
BLD-CSTN3-5
BLD-CSTN3-6
20
21
22
23
kg
cum
cum
cum
cum
kl
275.00
0.48
0.54
0.27
0.09
1.20
day
day
0.10
2.36
kg
cum
cum
cum
cum
kl
162.00
0.90
0.45
0.90
0.45
1.20
day
0.10
day
2.36
kg
cum
cum
cum
cum
kl
162.00
0.90
0.45
0.90
0.45
1.20
hour
1.00
day
0.10
day
1.39
-
kg
129.60
20
BLD-CSTN3-7
BLD-CSTN3-8
BLD-CSTN3-9
24
25
26
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
st
Mason 1 class
cum
cum
cum
cum
kl
0.90
0.45
0.90
0.45
1.20
day
0.10
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:5:10) using 40 mm
metal with Concrete mixture. All work upto
plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class
day
2.36
kg
cum
cum
cum
cum
kl
129.60
0.90
0.45
0.90
0.45
1.20
hour
1.00
day
0.10
day
1.39
kg
cum
cum
cum
cum
kl
129.60
0.90
0.54
0.90
0.54
1.20
day
0.10
day
2.36
kg
cum
cum
cum
cum
kl
129.60
0.90
0.54
0.90
0.54
1.20
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:6:10) using 40 mm
metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
st
Mason 1 class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:6:10) using 40 mm
metal with Concrete mixture upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
21
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class
BLD-CSTN3-10
27
Mazdoor (unskilled)
Grand Total
Plain Cement concrete - Nominal Mix (1:3:6)
using 40mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
st
Mason 1 class
BLD-CSTN3-11
28
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (M 20) Nominal Mix
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class
BLD-CSTN3-12
29
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (M 15) Nominal Mix
1:2.5:5
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Coarse aggregate 20mm
Coarse aggregate 10mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
hour
1.00
day
0.10
day
1.39
Kg
cum
cum
cum
cum
kl
220.00
0.90
0.45
0.90
0.45
1.20
day
0.10
day
2.36
Kg
cum
cum
cum
cum
kl
330.00
0.90
0.45
0.90
0.45
1.20
hour
1.00
day
0.10
day
1.39
Kg
cum
cum
cum
cum
cum
cum
275.000
0.540
0.270
0.090
0.480
0.900
0.480
22
BLD-CSTN3-13
30
Mazdoor (unskilled)
Grand Total
R.C.C. M-20 Nominal Mix
kl
1.20
hour
1.000
day
0.100
day
1.390
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.133
0.267
3.600
hour
1.000
hour
kl
1.000
1.200
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.167
0.167
4.700
23
31
BLD-CSTN3-14
hour
1.000
hour
kl
1.000
1.200
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.067
0.133
2.500
hour
0.267
hour
kl
0.267
1.200
cum
cum
0.80
0.40
day
0.133
24
BLD-CSTN3-15
BLD-CSTN3-16
BLD-CSTN3-17
day
day
0.267
4.600
hour
1.333
hour
Kl
1.333
1.200
cum
cum
0.80
0.40
day
day
day
0.167
0.167
5.600
hour
1.333
hour
kl
1.333
1.200
cum
cum
0.80
0.40
day
day
day
0.067
0.133
3.077
hour
0.308
hour
kl
0.308
1.200
cum
cum
cum
cum
kl
0.80
0.40
0.80
0.40
1.20
25
hour
hour
0.222
0.222
day
0.222
day
0.056
Mason 2 class
day
0.056
Mazdoor (unskilled)
Grand Total
Note : Wherever concrete is carried out using
batching plant, transit mixer, concrete pump,
then Admixtures @ 0.4% of weight of cement
may be added for achieving desired slump of
concrete. If concentrated Admixture is
proposed, only 0.04% of weight of Cement
shall be used.
day
0.917
cum
cum
cum
cum
kl
0.80
0.40
0.80
0.40
1.20
hour
hour
0.444
0.444
day
0.444
nd
BLD-CSTN3-18
BLD-CSTN3-19
day
0.111
nd
Mason 2 class
day
0.222
Mazdoor (unskilled)
Grand Total
RCC SLABS, BEAMS
day
1.556
cum
cum
cum
cum
kl
0.80
0.40
0.80
0.40
1.20
hour
hour
0.133
0.133
day
0.133
day
0.033
day
0.067
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto
1km
Concrete Pump
C. LABOUR:
st
Mason 1 class
nd
Mason 2 class
26
Mazdoor (unskilled)
day
Note : Quantity of cement proposed for various
design mixes is for estimating purpose only. Actual
quantity of cement will be as per approved mix design.
Similarly quantity for coarse and fine aggregates is for
estimating purpose and the exact quantity shall be as
per the mix design. Nominal mix of grades M20 is to
be used with adequate supervision and quality control
requirements.
For Design mix concrete, allow Cement as
follows (for estimate purpose only) :
BLD-CSTN3-20
32
33
Grade
Kgs
M 20
M 25
M 30
M 35
M 40
350
380
400
420
430
BLD-CSTN3-21
0.433
Mazdoor (unskilled)
D. Grand Total for 25 sqm
Rate per Sqm = D/25
Damp proof course 50mm thick with 1:2:4
cement concrete Nominal mix, using 12mm
hard broken stone aggregate including cost
of all materials, seigniorage charges,
excluding conveyance charges of materials
including the cost of machinery, labour
charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished
item of work. (Using concrete mixer)
kgs
cum
cum
cum
cum
L.S.
320.00
0.90
0.45
0.90
0.45
hour
1.00
day
0.1
day
1.98
Unit = 20 sqm
A. MATERIALS:
27
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate
Seigniorage charges of sand
Form work
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class
BLD-CSTN4-1
34
35
Mazdoor (unskilled)
D. Grand Total for 20 sqm
Rate per Sqm = D/20
Supplying, fitting and placing HYSD bar
reinforcement in foundation complete as per
drawings and technical specifications for Bars
below 36 mm dia including over laps and
wastage, where they are not welded
Unit = MT
(a) Material
HYSD bars including 5 per cent for overlaps
and wastage
Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Blacksmith / Bar bender
Mazdoor (Unskilled)
Sundries on Material
Rate per t = a+b+c+d
Supplying, fitting and placing HYSD bar
reinforcement in VRCC works complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars
36 mm dia and above, where welding
required to be done compulsorily.
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints /
ton)
Welding Charges (Hire charges of Welding
Machine)
Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
kgs
cum
cum
cum
cum
L.S.
320.00
0.90
0.45
0.90
0.45
hour
1.00
day
0.1
day
1.98
MT
1.05
kg
6.00
day
day
2.00
6.40
1.025
each
70.000
Hr
10.00
kg
6.00
day
day
day
2.50
2.00
6.40
28
BLD-CSTN4-2
36
37
BLD-CSTN4-3
38
1.05
kg
6.00
day
day
2.00
6.40
1.025
each
70.000
Hr
10.00
kg
6.00
day
day
day
2.50
2.00
6.40
1.05
kg
6.00
29
BLD-CSTN5
BLD-CSTN5-1
day
day
2.00
6.40
kg
Nos
96.00
512.00
cum
cum
0.20
0.20
day
0.24
Mason 2 class
day
0.56
Mazdoor (unskilled)
Grand Total
Note : For Bricks 2.4 % wastage taken.
Brick Masonry in CM (1:4) with Bricks
traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
day
1.89
kg
Nos
72.00
512.00
cum
cum
0.20
0.20
day
0.24
Mason 2 class
day
0.56
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Bricks
traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
day
1.89
kg
Nos
57.60
512.00
cum
cum
0.20
0.20
BLD-CSTN5-2
40
nd
BLD-CSTN5-3
41
day
0.24
nd
Mason 2 class
day
0.56
Mazdoor (unskilled)
day
1.89
30
BLD-CSTN5-4
42
Grand Total
Brick Masonry in CM (1:6) with 2nd class
Bricks traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
kg
Nos
48.00
512.00
cum
cum
0.20
0.20
day
0.24
Mason 2 class
day
0.56
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Bricks
traditional size 23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
day
1.89
kg
Nos
36.00
512.00
cum
cum
0.20
0.20
day
0.24
day
0.56
nd
BLD-CSTN5-5
43
nd
Mason 2 class
BLD-CSTN5-6
44
Mazdoor (unskilled)
day
Grand Total
Note : 1. When Mortar mix is changed as CM 1:4, 1:5,
1:6 and 1:8, proportionate quantity of cement has to
be substituted. No change in other data.
2. When First class Modular Bricks are used provide
570 nos bricks of size 19 x 9 x 9 cms.
Brick Masonry in CM (1:3) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
kg
Bricks modular size 19 x 9 x 9 cms 2nd class
Nos
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
45
100.60
520.00
cum
cum
0.21
0.21
day
0.24
Mason 2 class
day
0.56
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:4) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
day
1.89
nd
BLD-CSTN5-7
1.89
31
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
kg
Nos
75.60
520.00
cum
cum
0.21
0.21
day
0.24
Mason 2 class
day
0.56
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
day
1.89
kg
Nos
60.48
520.00
cum
cum
0.21
0.21
day
0.24
Mason 2 class
day
0.56
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:6) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
day
1.89
kg
Nos
50.40
520.00
cum
cum
0.21
0.21
day
0.24
Mason 2 class
day
0.56
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
day
1.89
kg
Nos
37.80
520.00
cum
cum
0.21
0.21
nd
BLD-CSTN5-8
46
BLD-CSTN5-9
47
BLD-CSTN5-10
48
day
0.24
Mason 2 class
nd
day
0.56
Mazdoor (unskilled)
day
1.89
32
BLD-CSTN5-11
49
Grand Total
11.5 cm wide Brick masonry for superstructure on ground floor in cm (1:3) using
second class traditional size bricks including
cost of all materials, seigniorage charges,
labour and all operations for constructing
half brick masonry, mixing cement mortar,
curing etc., complete for finished item of
work, but excluding conveyance charges of
materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size
23x11x7cm
Cement
Sand
Seigniorage charges for sand
B. LABOUR:
st
Mason 1 class
nos
565.000
kg.
cum
cum
106.000
0.220
0.220
day
0.600
Mason 2 class
day
0.600
Mazdoor (unskilled)
Add water charges 1%
Grand Total
Reinforced Brick Masonary walls of 11.5cm in
CM(1:6) using 2nd bricks having a crushing
strength of not less than 35.00kg/cm2 and
using two mild steel bars of 6m dia in every
third layer of brick masory, with free joints of
the main block work including cost and
seignorage charges and conveyance of all
materials and water from approved sources
to work site and all operational, incidental,
labour charges such as scaffolding mixing
mortor constructing masonary lift charges,
curing etc. complete but excluding the cost of
steel and its fabrication charges for finished
item of work as per SS 509
day
2.750
1.00%
Nos
cum
512.000
0.200
nd
BLD-CSTN5-12
50
Ground Floor :
A. MATERIALS:
II Class Bricks
C.M.(1:6)
B. LABOUR:
st
Mason 1 class
day
0.600
Mason 2 class
nd
day
0.600
Mazdoor (unskilled)
Grand Total
day
2.750
33
BLD-CSTN5-13
51
nos
520.000
kg.
cum
cum
48.00
0.20
0.20
day
0.57
Mason 2 class
day
0.57
Mazdoor (unskilled)
Add water charges 1%
Grand Total
Note : Compressive strength of individual
2
Brick shall not be less than 70 kg / cm
day
2.54
1.00%
nd
BLD-CSTN5-14
BLD-CSTN5-15
52
53
BLD-CSTN5-16
BLD-CSTN5-17
54
55
BLD-CSTN6
BLD-CSTN6-1
56
a) Material
Brick 2nd class 23 x 11 x 7
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Honey Comb work with Bricks of Modular
Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing
2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Masonry work in CM (1:8) prop with Flyash
Cement solid blocks of size 290 x 225 x 140
mm for manufacturing of flyash solid blocks
using flyash of 80 kgs, cement of 15 kgs.
Gypsum of 5 kgs. and stone dust including
cost and conveyance of all materials, labour
charges, seiniorage charges, scaffolding and
curing etc., cpomplete with a compresive
strength not lessthan 50 kg/sqm for walls for
Superstructure Walls.
Ground Floor
Unit = 1 cum
A. MATERIALS:
No of blocks required for one cum of
Masonry
Cost of Cement Mortar (1:6)
B. LABOUR
Mason 1st class
Mason 2nd class
Man Mazdoor
Woman Mazdoor
Total
STONE MASONRY, DAMP PROOF COURSE,
DRY STONE PACKING, QUARRY RUBBISH &
GRAVEL BACKING
Cut Stone Masonry in CM 1:2
Unit = 1cum
A. MATERIALS:
Cement
Nos.
cum
750.00
0.67
day
day
day
LS
6.60
2.41
6.21
LS
Nos.
cum
790.00
0.67
day
day
day
LS
6.60
2.41
6.21
LS
Nos
110.000
cum
0.100
day
day
day
day
0.420
0.920
0.700
2.100
kg
115.20
35
cum
0.89
Bond Stones
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
cum
cum
cum
0.16
0.16
0.16
day
1.05
day
2.45
nd
Mason 2 class
BLD-CSTN6-2
57
Man mazdoor
day
Woman mazdoor
day
Grand Total
Note : When Mortar mix is changed as CM 1:3, 1:4,
1:5, 1:6 and 1:8, proportionate quantity of cement has
to be substituted. No change in other data.
CRS Masonry in CM (1:2) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
BLD-CSTN6-3
58
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:3) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
BLD-CSTN6-4
59
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:4) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
3.50
2.80
kg
cum
7Nos.
201.60
0.94
0.16
cum
cum
cum
0.28
0.28
1.10
day
2.50
day
2.32
kg
cum
7Nos.
134.40
0.94
0.16
cum
cum
cum
0.28
0.28
1.10
day
2.50
day
2.32
kg
cum
7Nos.
100.80
0.94
0.16
cum
0.28
36
BLD-CSTN6-5
60
cum
cum
0.28
1.10
day
2.50
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:6) 1st Sort
day
2.32
kg
cum
7Nos.
67.20
0.94
0.16
cum
cum
cum
0.28
0.28
1.10
day
2.50
day
2.32
kg
cum
cum
76.80
0.94
0.16
cum
cum
cum
0.32
0.32
1.10
day
1.50
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
BLD-CSTN6-6
61
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:6) 2nd Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted. No change in
other data.
BLD-CSTN6-7
62
2.32
Nos
cum
Nos.
0.94
0.16
cum
0.30
day
3.00
37
Mazdoor (Unskilled)
day
C. Add for centering and shuttering @ 100 %
of (a+b)
Grand Total
Note : 1) In case cement mortar 1:3 is used,
proportionate rate is to be adopted.
2.43
63
kg
cum
57.60
0.89
cum
cum
0.16
0.16
0.16
day
5.05
Mason 2 class
day
2.45
Mazdoor (unskilled)
Centering Charges
Grand Total
Rubble Arch Work in Cement Mortar (1:4)
day
LS
6.30
kg
cum
100.80
1.15
cum
cum
0.28
0.28
day
0.90
Mason 2 class
day
2.10
Mazdoor (unskilled)
Centering Charges
Grand Total
Providing & Laying
reinforced cement
concrete arch complete including centering
and shuttering excluding reinforcement as
per drawings and technical specifications
Clauses 800, 900 and 1205.1
day
LS
2.43
0.40
BLD-CSTN6-9
64
Unit = 1cum
A. MATERIALS:
Cement
Seleted Stone of sizes as per specification
(including Bond Stones)
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
nd
65
BLD-CSTN6-10
Unit = cum
RCC grade M20 nominal mix
a) Material
Cement
38
BLD-CSTN6-11
66
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
d) Add for cost of centering and shuttering as
per the rates worked out on relevant data
items
Grand Total
RCC Grade M 25 (Design mix)
cum
cum
cum
0.45
0.54
0.36
day
day
0.20
2.15
hour
0.40
a) Material
Cement
t
Coarse sand
cum
20 mm aggregate
cum
10 mm aggregate
cum
b) Labour
Mason (1st Class)
day
Mazdoor (Unskilled)
day
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
hour
d) Add for cost of centering and shuttering as
per the rates worked out on relevant data
items
Grand Total
Note : The additional cost of centering and shuttering
@ 50 per cent of cost of material and labour shall hold
good for arch spans of 6 m and above. For lesser
length of spans, the corresponding additional cost can
be taken as 40 per cent for spans above 4 m length
and 30 per cent for spans less than 4 m.
BLD-CSTN6-12
67
68
0.20
2.15
0.40
RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
BLD-CSTN6-13
0.38
0.45
0.54
0.36
Mazdoor (unskilled)
Grand Total
RR Masonry in CM (1:8)
kg
cum
cum
cum
79.20
0.44
0.50
0.16
cum
cum
cum
0.33
0.33
1.10
day
1.20
day
2.00
Unit = 1cum
39
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
kg
cum
cum
cum
59.40
0.44
0.50
0.16
cum
cum
cum
0.33
0.33
1.10
day
1.20
Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted. No change in
other data
BLD-CSTN6-14
69
cum
cum
1.04
0.16
cum
1.20
day
0.33
Mason 2 class
day
0.77
Mazdoor (unskilled)
Grand Total
Dry Stone Masonry for Well steining
day
1.10
cum
cum
cum
1.04
0.16
1.20
nd
BLD-CSTN6-15
70
Unit = 1cum
A. MATERIALS:
Rough Stone
Bond Stones
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
day
0.45
Mason 2 class
day
1.05
Mazdoor (unskilled)
Grand Total
Damp Proof, Course Damp Proof (or anti
Proof) Course with Cuddapah / Shabad slabs
50 mm. thick in CM (1:3) (Unit - 10 sqm)
day
1.10
sqm
cum
10.50
0.15
day
0.90
nd
BLD-CSTN6-16
71
2.00
A. MATERIALS:
Cuddapah / Shabad slabs 50 mm. thick
Cement Mortar 1:3
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class
40
BLD-CSTN7
BLD-CSTN7-1
BLD-CSTN7-2
72
73
Mason 2 class
nd
day
2.10
Mazdoor (unskilled)
Grand Total
POINTING
day
2.00
kg
cum
cum
14.40
0.03
0.03
day
0.50
day
0.74
kg
cum
cum
14.40
0.03
0.03
day
0.50
day
0.74
kg
cum
cum
28.80
0.06
0.06
day
0.50
BLD-CSTN7-3
74
Mazdoor (unskilled)
Grand Total
Raised Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class
BLD-CSTN7-4
75
Mazdoor (unskilled)
day
Grand Total
Raised and cut pointing on coursed or Ashlar
stone masonry or concrete block walling in
white cement mortar 1 : 3 (1 white cement :
3 marble dust).
Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
cum
Labour :
Mason llnd class
day
Mazdoor (unskilled)
day
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Note : When Mortar mix is changed as CM 1:4
0.74
0.038
1.460
2.260
41
BLD-CSTN8
BLD-CSTN8-1
77
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
BLD-CSTN8-3
78
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:5), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
BLD-CSTN8-4
79
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:6), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:6)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
BLD-CSTN8-5
80
to
be
BLD-CSTN8-2
has
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:8), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
cum
cum
0.15
0.15
day
0.60
day
0.96
cum
cum
0.15
0.15
day
0.60
day
0.96
cum
cum
0.150
0.150
day
0.60
day
0.96
cum
cum
0.15
0.15
day
0.60
day
0.96
cum
cum
0.15
0.15
day
0.60
42
BLD-CSTN8-6
81
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 15 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class
BLD-CSTN8-7
82
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class
BLD-CSTN8-8
83
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:3), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class
day
0.96
cum
cum
0.19
0.19
day
0.60
day
0.96
cum
cum
0.210
0.21
day
0.94
day
1.60
cum
cum
0.210
0.21
day
0.94
Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted
BLD-CSTN8-9
84
1.60
kg
cum
43.00
0.18
kg
cum
cum
14.50
0.04
0.22
day
0.63
nd
Mason 2 class
day
1.47
Mazdoor (unskilled)
Grand Total
day
3.90
43
85
Mason 2 class
BLD-CSTN8-11
86
kg
cum
31.70
0.11
kg
cum
cum
19.20
0.04
0.15
day
0.63
day
1.47
Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted
RCM FACIA WORKS
RCM facia 5cm thick in CM (1:3) for drop walls, fins
with rabbit wire mesh & nominal reinforcement as
directed by Engineer-in-charge with dubara sponge
finishing, including cost & conveyance of all materials
to site, seigniorage charges, sales & other taxes on all
materials, operational & incidental, cost and
conveyance of cement, wire mesh, water to work site,
centering, scaffolding and form work, lift charges etc.,
complete for finished items of work but excluding cost
of steel & its fabrication charges, for finished item of
work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M
sqm
drop)
Cement Mortar 1:3 for 25 mm thick
cum
Dry Cement for making Lumps
kg
12 mm Plastering 2 coats in 1:4 & 1:2 cm
sqm
both sides
Excluding HYSD Steel/ Mild steel & Binding
wire
B) LABOUR CHARGES
1st Class Mason
day
Miller Operator
day
Mazdoor (unskilled)
day
c) Machinery
Machine Mixing Mortar with Miller - Hire
Hrs
charges
BASIC COST per 10 sqm
3.90
13.30
0.25
50.00
21.80
8.00
1.00
10.00
32.00
2.00
44
BLD-CSTN8-12
BLD-CSTN8-13
87
88
cum
0.110
kg
cum
day
52.800
0.110
0.020
day
day
1.710
3.270
day
day
0.250
0.250
cum
0.224
cum
0.100
kg
9.280
45
BLD-CSTN8-14
BLD-CSTN8-15
BLD-CSTN8-16
89
90
91
day
day
1.710
3.270
day
day
0.500
1.000
kg
6.000
kg
6.000
cum
kg
0.224
9.280
cum
0.100
day
day
1.710
3.270
46
BLD-CSTN8-17
92
93
94
BLD-CSTN8-18
95
day
day
0.500
0.610
cum
0.023
day
day
0.300
0.350
cum
0.023
day
day
0.300
0.350
cum
0.023
day
day
0.380
0.430
cum
0.224
day
day
2.200
2.700
47
96
97
BLD-CSTN8-19
BLD-CSTN9
BLD-CSTN9-1
98
99
cum
0.224
day
day
2.500
3.000
cum
0.224
day
day
3.000
3.500
cum
0.023
day
day
0.870
0.920
Unit = 10 sqm
A. MATERIALS:
48
100
11.00
21.60
33.00
20.00
0.12
0.12
day
3.10
Mason 2 class
day
1.10
Mazdoor (unskilled)
Add water charges 1%
Grand Total
Flooring with Rough Kadapa/Shahabad ...
mm thick stones, set over base coat of
cement mortar (1 : 8) 12 mm thick over CC
bed already laid or RCC roof slab, including
pointing with cement mortar 1:3 duly filling
joints nearly, including cost of all materials
like flooring stone, cement, sand, and water
etc., complete, including seigniorage charges,
labour charges for dressing of flooring stones
etc., complete for finished item of work, .
day
0.86
sqm
10.50
kg.
21.60
kg.
cum
cum
cum
9.60
0.12
0.02
0.14
day
0.960
Mason 2 class
day
2.240
Mazdoor (unskilled)
Add water charges 1%
Grand Total
day
3.30
nd
BLD-CSTN9-2
sqm
kg.
kg.
kg.
cum
cum
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm
thick) (0.457 x 0.457 m)
Cement for CM (1:8) proportion for base coat
Cement for CM 1:3 proportion for pointing
Sand for CM (1:8) proportion
Sand for CM (1:3) proportion
Seigniorage charges of sand
B. LABOUR:
st
Mason 1 class
nd
49
BLD-CSTN9-3
101
sqm
kg.
kg.
kg.
cum
cum
10.50
48.00
33.00
5.00
0.20
0.20
day
1.00
day
2.10
Mason 2 class
day
3.00
Mazdoor (unskilled)
Add water charges 1%
Grand Total
Flooring with chequrred terrazzo tiles of 22
mm thick (medium shade) set over base coat
of cement mortar (1:6) 12 mm thick over CC
bed already laid or RCC roof slab, including
near cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed with
neat cement to full depth mixed with
pigment of matching shade including cost of
all materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
complete for finished item of work, .
day
5.00
sqm
10.50
kg.
kg.
kg.
kg.
cum
28.80
33.00
6.00
nd
BLD-CSTN9-4
102
Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick
(medium shade)
Cement for CM (1:6) proportion for base coat
Cement for slurry
Cement for jointing & pointing
Pigment
Sand for CM (1:6) proportion
0.12
50
BLD-CSTN9-5
103
cum
0.12
day
0.960
Man mazdoor
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with vitrified tiles of 1st quality, set
over base coat of cement mortar (1:8), 12
mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement
paste to full depth mixed with pigment of
matching shade, including cost of all
materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
etc., complete for finished item of work, .
day
day
2.240
3.30
Unit = 10 sqm
A. MATERIALS:
st
Vitrified tiles of 1 quality of size
sqm
10.50
kg.
21.60
kg.
kg.
cum
cum
cum
33.00
6.000
0.12
0.020
0.140
day
0.96
Mason 2 class
day
2.24
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with ceramic tiles, set over base coat
of cement mortar (1:8), 12 mm thick over CC
bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste to full depth mixed
with pigment of matching shade, including
cost of all materials like cement, sand water
and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of
work, .
day
3.30
1.00%
sqm
kg.
10.50
21.60
nd
BLD-CSTN9-6
104
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles
Cement for CM (1:8) proportion for base coat
51
105
day
0.96
day
2.24
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with high polished granite slabs ...
mm thick other than black set over base coat
of cement mortar (1:8), 20 mm thick over CC
bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste mixed with pigment
of matching shade to full depth, including
cost of all materials like cement, sand water
and tilesetc., complete, including seigniorage
charges, labour charges for dressing of
tilesetc., complete for finished item of work,
day
3.30
1.00%
sqm
10.50
kg.
kg.
kg.
kg.
cum
cum
36.00
33.00
6.00
day
3.00
Mason 2 class
day
1.00
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with marble tiles polished 8 mm
thick set over base coat of cement mortar
(1:8), 12 mm thick over CC bed already laid or
RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement
paste mixed with pigment of matching shade
to full depth, including cost of all materials
like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work,
day
8.00
1.00%
Unit = 10 sqm
A. MATERIALS:
High polished granite slab other than black
mm thick
Cement for CM (1:8) proportion for base coat
Cement for slurry
White cement for jointing & pointing
Cement for jointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
nd
BLD-CSTN9-8
106
33.00
2.00
0.12
0.12
Mason 2 class
nd
BLD-CSTN9-7
kg.
kg.
cum
cum
0.20
0.20
Unit = 10 sqm
52
A. MATERIALS:
Marble tiles polished 8 mm thick
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR (including for polishing & rubbing)
sqm
kg.
kg.
kg.
cum
cum
10.50
36.00
33.00
5.00
0.20
0.20
Mason 1 class
day
4.00
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with granite stone tiles 8 mm thick
(mirror polished of all shades) set over base
coat of cement mortar (1:6), 12 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete
for finished item of work, .
day
8.00
1.00%
sqm
10.50
kg.
cum
cum
48.00
0.20
0.20
day
0.96
Mason 2 class
day
2.24
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with decorated white back ground
glazed tiles, set over base coat of cement
mortar (1:6), 12 mm thick over CC bed
already laid or RCC roof slab, including neat
cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste mixed with pigment
of matching shade to full depth, including
cost of all materials like cement, sand water
and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of
work,
day
3.30
1.00%
st
BLD-CSTN9-9
107
Unit = 10 sqm
A. MATERIALS:
Granite stone tiles 8 mm thick (mirror
polished of all shades)
Cement for CM (1:6) for base coat
Sand for CM (1:6)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
nd
BLD-CSTN9-10
108
Unit = 10 sqm
A. MATERIALS:
53
sqm
kg.
kg.
kg.
cum
cum
10.50
28.80
33.00
6.00
0.12
0.12
day
0.96
Mason 2 class
day
2.24
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with pressed clay flooring tiles, set
over base coat of cement mortar (1:8) 12
mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with cement mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work,
day
3.30
1.00%
1000
Nos
kg.
kg.
10sqm
cum
cum
cum
0.255
21.600
6.000
1.000
0.040
0.120
0.120
nd
BLD-CSTN9-11
109
Unit = 10 sqm
A. MATERIALS:
20 X 20 cm pressed clay flooring tiles
Cement for CM (1:8) for base coat
Cement for jointing & pointing
Pointing with CM (1:3)
Deduct CM (1:3)
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
day
0.960
Mason 2 class
day
2.240
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Plain Cement tiles, set over
base coat of cement mortar (1:8) 12 mm
thick over CC bed already laid or RCC roof
slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm &
jointed neatly with cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work,
day
4.30
1.00%
nd
BLD-CSTN9-12
110
54
Unit = 10 sqm
A. MATERIALS:
Plain cement Tiles 20 x 20 cms
Cement for CM (1:8) for base coat
Cement for jointing & pointing
Pointing with CM (1:3)
Deduct CM (1:3)
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
nd
Mason 2 class
BLD-CSTN9-13
111
0.255
day
0.960
day
2.240
3.30
1.00%
cum
0.17
kg
cum
cum
120.00
0.085
0.085
day
1.25
Mason 2 class
day
0.06
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with 100mm thick Cement Concrete
1:6:10, using 40mm metal, 100mm thick and
20 mm Cement Concrete surface (Ellis
Pattern, 1st Sort)
Unit = 10 sqm
A. MATERIALS:
day
3.00
1.00%
nd
112
21.600
6.000
1.000
0.040
0.120
0.120
Mazdoor (unskiled)
day
Add water charges 1%
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted for all above
Flooring Items. The same data holds good for stones
with all colours. Adopt same data for polished Kadapa
Stones and Bethamcherla stones.
Gronolithie Concrete Flooring 20 mm thick
with (1:1:2), using 6mm to 12 mm size hard
granite machine crushed metal laid over CC
bed already laid or RCC roof slab, in alternate
panels of size not exceeding 1.50 m x 1.50 m
and finishing the top surface to required
smoothness and slopes and thread lining
including cost of all materials like cement,
metal, sand and water etc., complete,
including seigniorage charges, etc., complete
for finished item of work,
Unit = 10 sqm
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine
crushed)
Cement
Sand
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
BLD-CSTN9-14
1000
Nos
kg.
kg.
10sqm
cum
cum
cum
55
cum
1.000
cum
kg
0.250
120.000
day
0.150
Mason 2 class
day
0.350
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered
over with 12 mm thick in CM(1:3)
day
5.40
1.00%
cum
1.00
10
sqm
1.00
day
0.150
Mason 2 class
day
0.350
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered
over with 12 mm thick in CM(1:3) using Red
oxid, with polished surface
day
5.40
1.00%
cum
1.00
10
sqm
kg
1.00
10.00
day
0.150
Mason 2 class
day
0.350
Mazdoor (unskiled)
Add water charges 1%
Masons for polishing
Grand Total
day
5.40
1.00%
1.10
nd
BLD-CSTN9-15
113
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete
mixer
Plastering with CM (1:3), 12 mm thick
B. LABOUR
st
Mason 1 class
nd
BLD-CSTN9-16
114
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete
mixer
Plastering with CM (1:3), 12 mm thick
Red oxid
B. LABOUR
st
Mason 1 class
nd
Nos
56
BLD-CSTN9-17
115
kg
cum
kg.
kg.
cum
cum
17.000
0.060
50.000
96.000
0.200
0.200
sqm
10.000
day
0.960
Mason 2 class
day
2.240
Mazdoor (unskiled)
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with ceramic tiles 7.30
mm thick length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and
jointed with white cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work,
day
3.30
sqm
cum
kgs
kgs
kgs
cum
10.50
0.12
57.60
33.00
6.00
0.12
day
0.77
day
0.80
nd
BLD-CSTN9-18
116
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
Mazdoor (unskiled)
Grand Total
57
BLD-CSTN9-19
BLD-CSTN9-20
117
118
sqm
cum
kg
kg
kg
RM
RM
cum
10.50
0.12
57.60
33.00
5.00
66.67
67.67
0.12
day
day
day
2.10
4.90
4.00
day
4.00
sqm
cum
kgs
kgs
kgs
cum
10.50
0.12
34.56
33.00
2.00
0.12
58
BLD-CSTN9-21
119
day
day
0.96
2.24
Mazdoor (unskilled)
Add water charges 1%
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with 8 mm thick mirror
polished granite tiles length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work,
day
3.30
1.00%
sqm
cum
kgs
kgs
kgs
cum
10.50
0.12
57.60
33.00
5.00
0.12
day
day
2.10
0.80
4.90
Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mazdoor (unskiled)
nd
Mason 2 class
BLD-CSTN9-22
120
1.00%
sqm
cum
kgs
kgs
cum
10.50
0.12
57.60
33.00
0.12
59
BLD-CSTN9-23
121
day
day
day
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Shahabad stone
sqm
(White)
Sand for cm 1:3 base coat
cum
Cement for cm 1:3 base coat
kgs
Cement for slurry
kgs
Seigniorage charges of sand
cum
B. LABOUR
Mason Ist class
day
Mason 2nd class
Mazdoor (unskiled)
day
Add water charges 1%
Grand Total
Note : a) When Mortar mix is changed proportionate
quantity of cement has to be substituted for all
Skirting Items.
0.96
2.24
3.10
1.00%
11.00
0.12
57.60
33.00
0.12
0.96
2.24
3.10
1.00%
122
cum
100
Nos
0.44
3.00
60
BLD-CSTN9-25
BLD-CSTN10
BLD-CSTN10-1
123
124
B. LABOUR
Carpenters 1st Class
Carpenters 2nd Class
Man mazdoor
Note : Deduct 4.3 Nos Carpenters if plank rate
tongued and grooved ready planned.
Grand Total
Flooring with Gravel 150 mm thick including
cost of all materials, labour, watering etc.,
complete
Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage)
B. LABOUR
Man mazdoor
Woman mazdoor
Grand Total
ROOFING & CEILING
day
day
day
is for
1.95
4.55
5.40
cum
1.53
day
day
1.10
0.50
kgs
nos
103.09
47.91
nos
nos
43.90
nos
91.82
nos
litre
litre
91.82
0.14
0.20
day
day
0.84
0.91
day
day
0.06
0.06
day
0.14
61
Mazdor (coolie)
Sundries including 50 x 6 mm iron wind ties
white lead etc.
Add for Standard specification 1mm. Thick
ridging and 1.25 mm thick sheet vallyes when
such are required for a particular work.
Average allowance for 10 sqm roofing.
BLD-CSTN10-2
125
day
LS
0.14
LS
Grand Total
Rate per 10 sqm = Grand Total/10
Roofing with corrugated G.I sheets 1.00mm
thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
0
pitch of 60 ) and seigniorage charges,
turnover tax etc., complete, excluding the
cost of purlins, rafters, trusses & cost of
conveyance of all materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 1.00 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos
= 810 nos.
Limpet washers (for scam & J bolts)
884 + 810 = 1694
Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter
Mazdor (coolie)
Grand Total
Rate per 10 sqm = Grand Total/10
kgs
nos
126.07
47.91
nos
43.90
nos
91.82
nos
litre
litre
91.82
0.14
0.20
day
day
0.84
0.91
day
day
0.06
0.06
day
day
0.14
0.14
62
BLD-CSTN10-3
126
BLD-CSTN10-4
127
kgs
nos
154.80
47.91
nos
43.90
nos
91.82
nos
litre
litre
91.82
0.14
0.20
day
day
0.84
0.91
day
day
0.06
0.06
day
day
0.14
0.14
T
/sqm
nos
nos
nos
0.15
22.03
22.03
22.03
day
day
0.43
0.54
63
BLD-CSTN10-5
128
Grand Total
Rate per 10 sqm = Grand Total/10
Best Tiled Roofing with Pan tiles over Flat
Tiles and Lime mortar Borders including Teak
Reapers.
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Flat Tiles 150 x 150 x 15 mm
BLD-CSTN10-6
129
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime
Lime Mortar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including tarring reepers, extra
labour / for pointing the underside of flat
tiles and white washing the same.
Grand Total
Sub Analysis :
Lime Mortar 1:2
lime
Sand
Grinding Lime Mortar
Total
Best Tiled Roofing with Pan tiles and Lime
mortar Borders including Teak Reapers at
100 mm. centres
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total
LS
LS
1000
No
1000
No
10RM
kgs
cum
cum
1560
75.000
0.500
0.008
0.300
day
day
day
day
LS
0.800
2.200
1.100
5.400
LS
cum
cum
day
0.500
1.000
1.000
1000
No
10RM
kgs
cum
1560
107.000
0.700
0.120
day
day
day
day
1.100
1.400
1.100
3.200
470
64
BLD-CSTN10-7
130
BLD-CSTN10-8
131
BLD-CSTN10-9
132
Grand Total
Best Tiled Roofing with Mangalore tiles
including Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification)
Teak Reepers 50 x 12 mm
1000
No
RM
1560
100
No
10
sqm
cum
150
10.500
day
day
day
day
1.100
1.400
1.100
3.200
1000
No
1000
No
10RM
kgs
cum
cum
160
75.000
0.500
0.008
0.380
day
day
day
day
LS
0.800
1.600
1.100
4.300
LS
1000
No
10RM
160
25
0.120
470
36.000
65
BLD-CSTN10-10
133
BLD-CSTN10-11
134
kgs
cum
0.500
0.090
day
day
day
day
0.500
0.500
1.100
2.200
10
sqm
10.000
100
No
156
day
day
0.500
1.100
cum
cum
day
LS
0.670
1.000
1.000
cum
cum
cum
0.180
0.080
0.023
day
day
LS
3.200
6.500
LS
66
BLD-CSTN10-12
135
BLD-CSTN10-13
136
1000
No
100
No
cum
cum
cum
10
sqm
cum
2000
900
0.980
0.380
0.210
1.000
0.240
4.300
6.500
10
sqm
10.000
100
No
cum
10
sqm
900
0.260
1.000
day
day
LS
2.200
2.200
cum
10
sqm
1.250
1.000
Form Work
Total
67
BLD-CSTN10-14
BLD-CSTN10-15
BLD-CSTN10-16
BLD-CSTN10-17
137
138
139
140
10
sqm
1.000
cum
0.150
10
sqm
1.000
cum
0.250
10
sqm
1.000
cum
0.250
10
sqm
1.000
10
sqm
10
sqm
1.000
1.000
68
BLD-CSTN10-18
141
Impermo Compound
Grand Total
Note for Items 204 - 207 :
1. No extra rate will be paid for finishing the
bottom surface of the roofing slab as
described in SS No.
"For estimating purpose the extra allowance
for camber concrete, when such is required
may be given under sundries."
Complete Surface Repairs to Leaky Terrace
Roofs with Flat Tiles
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate vide relevant schedule item)
B. LABOUR
Bricklayers
Man Mazdoor
Clean removal of lime plaster from terraced
roofs and raking out joints 12 mm deep (for
rate - vide relevant schedule item)
BLD-CSTN10-19
142
Sub Analysis :
Mazdoor (unskilled)
Mate
Sundries including crude oil
Grand Total
Best Sloping Bengal Terrace with 3 courses of
Flat Tiles at Top including Teak Wood
Reepers
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm
Lime
Lime Moratar (1:1.5)
Teak Reepers 52 x 12 mm
Wire Nails 40 mm long
Plastering with lime mortar 3 coats (for rate vide relevant schedule item)
B. LABOUR
Carpenter
Bricklayers
Woman mazdoor
Sundries including tarring reepers
Grand Total
Note : 1. Reepers size is for rafter spacing 600
mm. including allowance for eves and valleys.
kgs
1.500
1000
No
cum
10
sqm
450
day
day
10
sqm
0.110
1.000
1.100
1.100
1.000
Day
Day
LS
1000
No
cum
cum
10 RM
kgs
10
sqm
day
day
day
LS
1350
0.008
0.150
75.000
0.500
1.000
0.800
2.200
2.200
69
BLD-CSTN10-20
BLD-CSTN10-21
BLD-CSTN10-22
BLD-CSTN10-23
BLD-CSTN10-24
143
144
145
146
147
1000
No
cum
1560
0.120
day
day
day
LS
1.400
1.100
4.300
day
day
1.100
0.800
10
sqm
LS
1.000
cum
100
No
0.132
300
day
day
LS
6.500
5.400
10
sqm
10.000
70
BLD-CSTN10-25
148
10 RM
100
No
66.000
240
day
LS
1.100
cum
kg
0.210
2.000
day
0.660
Mason 2 class
day
1.540
Mazdoor (unskiled)
Grand Total
Providing & fixing insulating board ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials
day
3.70
sqm
11.00
day
day
2.50
2.00
sqm
11.00
day
day
2.50
2.00
Deduct :
Carpenter
Sundries
Grand Total
Providing impervious coat to exposed RCC
roof slab surface with CM(1:3), 20mm thick
with 1kg of water proof compound per bag of
cement laid over roof when it is green
including cost of all materials, seigniorage
charges, excluding conveyance charges of
materials and including all operational,
incidental and labour charges for mixing
mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall
and slab etc,, complete for finished item of
work
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
Water proof compound
B. LABOUR
st
Mason 1 class
nd
BLD-CSTN10-26
BLD-CSTN10-27
149
150
Unit = 10 sqm
A. MATERIALS:
12 mm thick insulating board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Providing & fixing hard board sheet ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
3 mm thick standard quality of hard board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
71
BLD-CSTN10-28
151
BLD-CSTN10-29
BLD-CSTN10-30
sqm
11.00
day
day
2.50
2.00
sqm
11.00
day
day
2.50
2.00
cum
0.05
Nails
Rabbit wire mesh
Plaster of paris
B. LABOUR
for Jointing the wooden strips including fixing
the rabbit mesh
Carpenter Ist class
Man mazdoor (beldar)
For doing plaster of paris over wooden strips
kg
sqm
kg
0.75
10.20
219.76
day
day
2.60
1.60
day
day
day
2.62
1.62
377.00
152
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Providing & fixing plain AC sheet ceiling of
approved quality with necessary nails etc.,
complete, excluding the cost of frame work
for base and cost of conveyance of all
materials
153
Unit = 10 sqm
A. MATERIALS:
Plain AC sheet for ceiling
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Providing 10 mm thick plaster of paris
(Gypsum anhydrous) ceiling upto a height of
5 m above floor level over first class BT wood
strips 25 x 6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to
wooden frame excluding cost of wooden
frame for base & cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
st
Wooden strips 1 class BT wood 25 x 6 mm
size
72
BLD-CSTN10-31
154
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards
Ceiling Angle
25 mm x 10 mm x 0.55 mm
Connecting Clips
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm
thick
Rawl Plug
Soffit Cleats
Drywall Screws - 25 mm
Jointing Compound
Jointing Paper Tape
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
sqm
1.03
RM
Nos
0.64
1.84
RM
2.30
RM
0.84
RM
0.40
Nos
Nos
Nos
Kgs
RM
Lits
0.64
0.64
18.00
0.55
1.46
0.15
day
day
0.40
0.40
73
BLD-CSTN10-32
155
day
day
day
0.08
0.08
0.04
day
day
0.08
0.24
Hrs
0.32
Hrs
0.64
Scaffolding charges
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling
Supplying and fixing Gyp Board Fine Line Grid
false ceiling (GS-FLC-4.6 as per India Gypsum)
in size 600 mm x 600 mm using 12.5 mm
thick/ 9.5 mm thick Gyp Board sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm conforming to IS 2095 - 1982 fixing to
Gyp steel precoated GI wall angle of size 25
mm x 25 mm x of 0.70 mm thick along the
perimeter of ceiling screw fixed to brick
work/ partition at 610 mm c/c and
suspending the frame work using precoated
GI Tee section (24 mm x 38 mm x 0.7 mm)
from soffit at 1220 mm c/c fixed with GI
Soffit Cleat, rawl plugs and steel expansion
fasteners & connecting clip to the GI T
section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding
clips system at 1200 mm c/c and fixing the
12.5 mm / 9.5 mm Gypboard Sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm and finishing two coats of drywall
topcoat complete for finished item of work
as per Idia Gypsum Ltd specification.
1%
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm Or - 595 mm x 1195 mm GI Angle - Precoated
25 mm x 25 mm x 0.7 mm
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick
GI Rod - 4 mm Dia
Connecting Rod
Rawl Plug
sqm
1.00
RM
0.40
RM
1.60
RM
1.60
RM
Nos
1.28
1.28
74
Soffit Cleats
Unversal Holding Clips
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
BLD-CSTN10-33
156
Nos
Nos
Lits
1.28
5.36
0.15
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
day
day
0.04
0.24
Hrs
0.32
Hrs
0.32
Scaffolding charges
BASIC COST per 1 sqm
Armstrong False ceiling
Providing and fixing in true horizontal level
600 mm x 600 mm 15 mm thick Arm strong
false ceiling system manufactured by M/s
Arm strong world Industries using hot dipped
Galvanised Steel section exposed surface
with pre-coated capping, main Tee of size 24
x 32 mm at every 1200 mm c/c maximum
and rotary stiched cross tee of size 24 x 27
mm at evry 600 mm c/c and sub-cross tee of
size 24 mm x 25 mm at 1200 mm c/c and wall
angle of size 19 x 19 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick pre-straightened GI Wire laying
fine fissured butt edge ceiling tiles of 15 mm
thick mineral fiber Board manufactured by
M/s Arm Strong World Industries Ltd., having
RH 99% and for finished of size 600 x 600 mm
including Cost &conveyance of all materials
and labour charges such as cutting , fixing of
standing of frame work exposing roof making
complete for finished item of work
UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x
600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross
Tee)
1%
sqm
1.00
RM
0.40
RM
1.60
75
BLD-CSTN10-34
157
RM
1.60
RM
Nos
1.28
1.28
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
day
day
0.04
0.24
Hrs
0.32
Hrs
0.32
Scaffolding charges
BASIC COST per 1 sqm
Thermocole False ceiling
Providing and fixing Thermocole False ceiling
in true horizontal level 600 mm x 600 mm
using 15 mm/ 19 mm thick Thermocole
sheet anodised Aluminium Tee sections of
size 24.50 mm x 24.0 mm x 2.4 mm in grid
with cross tee of size 24 x 24.5 mm at every
600 mm c/c and anodised aluminium wall
angle of size 24 x 24 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick GI Wire for finished of size 600
x 600 mm including Cost &conveyance of all
materials and labour charges such as cutting ,
fixing of standing of frame work exposing
roof making complete for finished item of
work
UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600
Alumninium Angle
24 mm x 24 mm
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
Rawl Plugs
B) LABOUR CHARGES
1st Class Carpenter
1%
sqm
1.00
RM
0.40
RM
3.20
Nos
Nos
1.28
1.28
day
0.36
76
BLD-CSTN11
BLD-CSTN11-1
BLD-CSTN11-2
158
159
day
day
day
day
0.36
0.00
0.00
0.02
day
day
0.04
0.20
Hrs
0.16
Hrs
0.32
Scaffolding charges
BASIC COST per 1 sqm
WHITE WASHING, COLOUR WASHING &
DISTEMPERING
White washing one coat with lime of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers
Mazdoor (unskilled)
Sundries including brushes etc.,
Total cost for 10 sqm
White washing two coats with lime of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers
1%
cum
0.005
L.S
day
day
LS
0.11
0.22
cum
0.007
L.S
day
0.160
77
BLD-CSTN11-3
BLD-CSTN11-4
160
161
Mazdoor (unskilled)
Sundries including brushes etc.,
Total cost for 10 sqm
White washing three coats with lime of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
White washer
Brick Layers
Man Mazdoor
Women mazdoor
Mazdoor (unskilled)
Sundries including brushes, ladders etc.,
Total cost for 10 sqm
White washing one coat with whiting of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
day
LS
0.32
cum
0.009
L.S
day
day
day
day
day
LS
0.220
0.43
cum /
kg
1.20
day
day
0.11
0.22
0.50%
78
BLD-CSTN11-5
162
BLD-CSTN11-6
163
BLD-CSTN11-7
164
BLD-CSTN11-8
165
cum /
kg
2.00
L.S
day
day
0.210
0.320
1.00%
cum /
kg
2.800
day
day
0.300
0.430
10
sqm
1.000
79
BLD-CSTN11-9
BLD-CSTN11-10
BLD-CSTN12
BLD-CSTN12-1
BLD-CSTN12-2
166
167
168
169
10
sqm
1.000
kg
1.340
day
day
0.500
1.300
1.000%
kg
1.700
day
1.200
1.000%
Lts
Nos
Nos
Lts
Nos
Nos
0.50
0.08
0.19
1.70
0.36
0.84
kg
1.00
80
Painter
Sundries including brushes, soaps, putty etc.,
BLD-CSTN12-3
BLD-CSTN12-4
BLD-CSTN12-5
BLD-CSTN12-6
170
171
172
173
day
0.700
0.500%
kg
2.000
day
day
0.300
1.500
1.000%
kg
3.500
day
day
0.500
1.500
1.000%
kg
day
day
kg
1.00
0.21
0.49
3.50
day
day
day
0.15
0.35
1.50
81
Wood Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
BLD-CSTN12-7
174
BLD-CSTN12-9
BLD-CSTN12-10
175
176
Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
Varnishing to Wood Work, Two Coats
177
178
0.700
day
0.700
1.000%
0.70
day
0.70
L
L
0.800
0.600
day
day
0.700
0.700
L
L
1.200
1.100
day
day
1.100
1.100
kg
1.600
day
LS
0.700
kg
2.800
BLD-CSTN12-8
Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
Painting with Ready mixed oil paint (all
colours)
i. One Coat - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
82
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
179
180
181
182
183
184
day
LS
1.200
kg
1.500
day
LS
0.700
kg
2.4.
day
LS
1.200
kg
1.200
day
LS
0.700
kg
2.100
day
LS
1.100
kg
3.400
day
LS
1.500
kg
3.900
83
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
BLD-CSTN12-11
185
187
188
189
1.600
0.500
day
0.700
0.400
day
0.700
0.900
day
1.200
0.800
day
1.200
0.800
186
day
LS
84
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
190
191
192
BLD-CSTN12-12
193
194
day
1.100
0.700
day
1.100
1.200
day
1.600
1.100
day
1.500
0.700
day
0.700
0.500
day
0.700
85
195
196
197
198
199
1.200
day
1.200
1.100
day
1.200
1.100
day
1.100
0.900
day
1.100
1.700
day
1.600
200
BLD-CSTN12-13
201
BLD-CSTN12-15
BLD-CSTN13
BLD-CSTN13-1
202
203
204
1.600
day
1.500
kg
0.500
day
day
LS
0.800
0.800
0.650
day
day
LS
0.800
0.800
kg
L
0.228
1.630
day
LS
3.200
cum
1.000
day
day
17.700
8.800
BLD-CSTN12-14
87
BLD-CSTN13-2
BLD-CSTN13-3
BLD-CSTN13-4
BLD-CSTN13-5
205
206
207
208
209
LS
cum
1.000
day
day
17.700
8.800
LS
cum
1.000
day
day
17.700
8.800
LS
cum
kg
1.000
112.000
day
day
26.500
8.800
LS
cum
sqm
0.083
1.600
LS
cum
sqm
0.088
1.800
88
210
211
212
213
214
215
cum
sqm
0.109
2.200
LS
cum
sqm
0.123
2.520
cum
sqm
0.094
1.890
LS
cum
sqm
0.159
3.600
LS
cum
sqm
0.096
1.800
cum
sqm
0.104
2.000
89
216
217
BLD-CSTN13-6
218
219
220
221
1300 x 2200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1400 x 2300 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough plank
Fully Panelled doors - Internal Five Ply - Plywood Panels (Schedule Item No 291)
Single Shutter
800 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1200 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1300 x 2200 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
cum
sqm
0.134
2.860
cum
sqm
0.147
3.220
cum
sqm
sqm
0.068
0.720
1.600
LS
cum
sqm
sqm
0.071
0.870
1.800
cum
sqm
sqm
0.100
1.160
2.520
LS
cum
sqm
sqm
0.106
1.390
2.860
90
222
223
224
225
226
227
cum
sqm
sqm
0.077
0.880
1.890
LS
cum
sqm
sqm
0.091
0.880
2.100
cum
sqm
sqm
0.082
0.710
1.800
cum
sqm
sqm
0.088
0.820
2.000
cum
sqm
sqm
0.090
0.940
2.200
cum
sqm
0.123
1.900
91
228
BLD-CSTN13-7
BLD-CSTN13-8
BLD-CSTN13-9
229
230
231
232
sqm
3.600
cum
sqm
sqm
0.130
1.280
3.600
Nos
Nos
Nos
Nos
Nos
2
2
6
1
2
Nos
Nos
Nos
Nos
1
2
6
2
cum
sqm
sqm
0.072
0.470
1.600
LS
cum
sqm
sqm
0.076
0.560
1.800
LS
92
233
234
235
236
237
238
1200 x 2100 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1300 x 2200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
Double Shutter
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1000 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1100 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1400 x 2300 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
cum
sqm
sqm
0.106
0.760
2.520
LS
cum
sqm
sqm
0.115
0.870
2.860
LS
cum
sqm
sqm
0.087
0.420
1.800
LS
cum
sqm
sqm
0.092
0.510
2.000
LS
cum
sqm
sqm
0.096
0.600
2.200
LS
cum
sqm
sqm
0.123
1.060
3.220
93
239
BLD-CSTN13-10
240
BLD-CSTN13-11
241
242
BLD-CSTN13-12
243
244
LS
cum
sqm
sqm
0.130
1.280
3.600
LS
cum
sqm
0.107
2.000
LS
cum
sqm
0.127
2.520
LS
cum
sqm
0.107
2.000
LS
cum
sqm
0.127
2.520
94
BLD-CSTN13-13
245
BLD-CSTN13-14
246
247
BLD-CSTN13-15
248
249
LS
cum
sqm
0.083
1.600
LS
LS
cum
sqm
0.100
2.100
LS
LS
cum
sqm
0.083
1.600
LS
LS
Country wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for
size - 2 Nos Chain and slopes country make.
BLD-CSTN13-16
250
BLD-CSTN13-17
252
0.100
2.100
LS
LS
251
cum
sqm
cum
sqm
0.035
1.530
sqm
1.800
cum
sqm
0.037
1.820
sqm
2.100
cum
sqm
sqm
0.028
0.390
0.720
96
253
254
255
256
257
BLD-CSTN13-18
258
0.037
0.500
0.960
0.041
0.700
1.200
0.061
0.710
1.440
0.072
0.920
1.800
0.059
0.970
1.700
2
2
2
97
BLD-CSTN13-19
BLD-CSTN13-20
BLD-CSTN13-21
259
260
261
262
263
264
265
Parliament hinges
Furniture for Double Leaf Windows Glazed
without Top Lights (Schedule Item No. 304)
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Parliament hinges
Same for all such windows
Furniture for Single Leaf Windows Glazed
without Top Lights (Schedule Item No. 305)
Top tower bolts 150 mm long
Bottom tower bolts 150 mm long
Parliament hinges
Same for all such windows
Windows Panelled (Schedule Item No. 306)
Single Shutter
600 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
700 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
Double Shutter
800 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
1000 x 12000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
1200 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
each
LS
each
each
each
2
2
4
LS
each
each
each
1
1
2
cum
sqm
0.039
0.720
cum
sqm
0.043
0.840
cum
sqm
0.051
0.960
cum
sqm
0.059
1.200
cum
sqm
0.081
1.440
98
266
BLD-CSTN13-22
267
268
269
270
cum
sqm
0.056
1.080
cum
sqm
sqm
0.036
0.070
0.720
cum
sqm
sqm
0.052
0.100
1.080
cum
sqm
sqm
0.077
0.120
1.440
cum
sqm
sqm
0.094
0.150
1.800
99
271
BLD-CSTN13-23
BLD-CSTN13-24
272
273
274
275
276
each
each
each
each
2
4
1
1
each
each
each
each
4
8
2
2
cum
sqm
0.034
0.720
LS
cum
sqm
0.048
0.960
LS
cum
sqm
0.052
1.080
LS
cum
sqm
0.052
1.200
LS
100
BLD-CSTN13-25
277
278
279
BLD-CSTN13-26
280
281
cum
sqm
sqm
sqm
LS
0.012
0.240
0.190
0.400
cum
sqm
sqm
sqm
LS
0.014
0.310
0.240
0.500
cum
sqm
sqm
sqm
LS
0.018
0.480
0.290
0.720
cum
sqm
sqm
0.021
0.190
0.400
LS
cum
sqm
sqm
0.025
0.024
0.500
LS
282
BLD-CSTN13-27
283
1200 x 600 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty brads sash centres
brass ring iron cleats and window card - vide
relevant standard specifications.
cum
sqm
sqm
0.030
0.390
0.720
LS
Kgs
sqm
Kgs
RM
as per design
as per design
as per design
as per design
day
day
day
0.947
1.158
0.105
day
day
0.211
0.632
Hrs
0.842
Hrs
Nos
1.684
0.211
1%
102
BLD-CSTN13-28
284
BLD-CSTN13-29
285
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminium Anodised Casement windows
Kgs
sqm
sqm
Kgs
RM
as per design
as per design
as per design
as per design
as per design
day
day
day
1.042
1.042
0.104
day
day
0.139
0.347
Hrs
0.833
Hrs
1.111
Nos
0.174
1%
Unit - 1 sqm
103
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Friction stay casement
hinges
Alum.Anodised.PC Handles
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminium
Two/ Three Track Sliding
Windows
Kgs
sqm
Kgs
RM
Each
as per design
as per design
as per design
as per design
as per design
Each
as per design
day
day
day
0.360
1.081
0.360
day
day
0.360
1.081
Hrs
2.883
Hrs
2.883
Nos
0.360
1%
104
BLD-CSTN13-30
286
Kgs
sqm
Kgs
RM
Each
as per design
as per design
as per design
as per design
as per design
day
day
day
0.347
1.042
0.347
day
day
0.347
1.042
Hrs
2.778
Hrs
2.778
Nos
0.347
1%
105
BLD-CSTN13-31
287
BLD-CSTN14
BLD-CSTN14-1
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
DISMANTLING & DEMOLITION
288
Kgs
sqm
Kgs
RM
Each
Each
as per design
as per design
as per design
as per design
as per design
as per design
day
day
day
0.417
0.833
0.417
day
day
0.417
1.250
Hrs
3.333
Hrs
3.333
Nos
0.417
1%
day
day
0.010
0.170
106
BLD-CSTN14-2
289
Scaffolding
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
Removing white wash or colour wash by steel
wire brushing and/or scraping; sand papering
and preparing the ceiling and/or sloping
roofs surface smooth including necessary
repairs to scratches complete
Deatailed cost for 10 sqm
Rate as per above item
BLD-CSTN14-3
290
10
sqm
10
sqm
BLD-CSTN14-4
291
day
0.080
10
sqm
107
BLD-CSTN14-5
292
BLD-CSTN14-6
293
BLD-CSTN14-7
294
BLD-CSTN14-8
295
296
297
day
day
0.010
0.170
day
day
0.010
0.170
day
1.220
day
2.440
day
4.880
108
BLD-CSTN14-9
298
299
BLD-CSTN14-10
BLD-CSTN14-11
BLD-CSTN15
BLD-CSTN15-1
300
301
302
303
day
4.320
day
4.090
day
day
0.500
0.500
day
day
day
0.100
0.200
0.050
day
day
day
0.130
0.270
0.070
BLD-CSTN15-2
BLD-CSTN15-3
BLD-CSTN15-4
304
305
306
3.150
day
day
day
0.090
0.250
0.250
3.150
day
day
day
0.090
0.250
0.250
day
day
1.000
0.100
1.310
110
BLD-CSTN15-5
BLD-CSTN15-6
307
308
Assistant fitter
Mason.
Mazdoor (male).
Sundries
Cost for 1.25 m
Cost per m
Providing and fixing 1.80 metre long RCC
fencing posts with 6 mm bar nibs as per
design in plate No. 22/2/2. (earth work &
concrete to be paid for separately)
Details of cost for 10 pipes 12.5 cm long day
i.e., 1.25 metres
Materials:
Galvanised mild steel tube (light grade) 40
mm nominal bore 10 x 12.5 cm = 1.25 metre
with wastage of 5%
Labour :For cutting and fixing in position
Assistant fitter
Mason.
Mazdoor (male).
Sundries
Cost for 1.25 m
Cost per m
Providing and fixing 1.80 metre long RCC
fencing posts with 6 mm bar bibs as per
design in plate No. 22/2/2. (earth work &
concrete to be paid for separately)
Details of cost for 10 posts, i.e., 0.336 Cu. m
(Details as per Annexure ' X ' at the end of
this item)
Materials:
Cement concrete 1:2:4 (1 cement : 2 coarse
sand :4 graded stone aggregate 12.5 mm
nominal size)
(Rate as per item Concrete work)
M.S. reinforcement 6 mm dia bars
10 x
4 x 1.88 = 75.20 metres
10 x 9 x
0.50 = 45.00 metres./ l20.00 m 120.20 m @
0.22 Kg/m=26.44 Kg
(Rate as per item No.5.51 Section Concrete
work)
Centering and shuttering
(Details as per Annexure 'X')
(Rate as per item No.9.1.8. of Section 9 Form
work).
10 mm cement plaster with cement mortar
1:2 (1 cement: 2 sand)
(Details as per Annexure 'X')
Carriage of R.C.C. posts
6 mm bar bibs
Sundries
day
day
day
0.100
0.400
0.400
1.310
day
day
day
0.100
0.400
0.400
cum
0.336
kg
26.440
cum
0.336
sqm
9.880
111
day
day
day
0.120
0.120
0.250
10
sqm
cum
cum
1.000
0.025
30.000
112
BLD-CSTN15-7
BLD-CSTN15-8
BLD-CSTN16
309
310
kg
9.380
LS
day
day
day
0.150
0.150
0.300
kg
cum
19.500
0.040
day
day
0.080
0.160
113
BLD-CSTN16-1
BLD-CSTN17
BLD-CSTN17-1
311
Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable
concentrate of 20%
1 liter : 19 Parts water Therefore: 868.55 L
/20
Add 12%wastage
Total Quantity
B) Add Water Charges @ 1%
C) Labour Charges
Man Mazdoor
Sprayer
D) Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
Add OH & CP
BASIC COST per 1 sqm
CENTERING, FORM WORK etc.
312
Lit
4.100
Liters
0.41
4.51
1%
day
day
3.0
0.22
10%
3%
1.50%
114
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Wall Plate Brackets / beam bottom supports
313
314
Nos
2.40
Nos
1.44
Nos
RM
1.44
16.00
sqm
1.86
day
day
day
day
0.16
0.28
0.48
0.04
1%
1%
1%
Nos
4.32
Nos
1.44
Nos
RM
1.44
16.00
sqm
1.86
Nos
Nos
Nos
Nos
0.20
0.36
0.68
0.06
1%
1%
1%
Nos
5.76
Nos
1.44
Nos
RM
1.44
16.00
115
BLD-CSTN17-2
315
sqm
1.86
Nos
Nos
Nos
Nos
0.28
0.52
1.08
0.08
1%
1%
1%
Kgs
62.51
day
day
day
0.22
0.38
0.72
116
316
BLD-CSTN17-3
317
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Unsupported Roof Height up to - 7.32 M
(24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Span Beams - 2.4 M Long (Acro Spans) Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates 9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Providing STAGE SCAFFOLD with staging
using Casurina balli props and bracings
supporting wooden brackets, wooden stage
scaffold boards including hire charges for
Casurina ballies, wooden baords, scaffolds
etc., and cost and conveyance of all other
consumable accessories, taxes etc complete
for finished item of work for PLAN AREA
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Scaffold Boards - Bamboo scaffolds Bamboos - 8'0" long
B) LABOUR CHARGES
day
0.04
1%
1%
1%
Kgs
112.635
day
day
day
day
0.32
0.52
1.28
0.06
1%
1%
1%
Nos
2.40
Nos
2.70
117
318
319
BLD-CSTN17-4
320
day
day
day
day
0.04
0.30
0.48
0.04
1%
1%
1%
Nos
4.32
Nos
2.70
day
day
day
day
0.08
0.38
0.68
0.06
1%
1%
1%
Nos
5.76
Nos
2.70
day
day
day
day
0.12
0.54
1.08
0.08
1%
1%
1%
UNIT 1 sqm
118
BLD-CSTN17-5
321
322
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Scaffold Boards - Bamboo scaffolds Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
Providing STAGE SCAFFOLD using Steel
Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for PLAN AREA
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B
Class Pipes
for vertical props placed @ 3'0" c/c in
bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 7.32 M
(24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Lock Pins
Nos
1.74
Nos
0.72
day
day
day
day
0.07
0.11
0.2
0.04
1%
1%
1%
Kgs
39.26
day
day
day
day
0.04
0.34
0.60
0.04
1%
1%
1%
119
BLD-CSTN17-6
323
324
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Providing ACCESS SCAFFOLD using Steel
Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for ELEVATION AREA
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Kgs
112.635
day
day
day
day
0.12
0.58
1.20
0.08
1%
1%
1%
Kgs
19.7496
day
day
day
day
0.07
0.11
0.24
0.04
1%
1%
1%
120
BLD-CSTN17-7
325
Kgs
19.14
day
day
day
day
0.12
0.22
0.44
0.04
1%
1%
1%
9445
Kgs
day
64.00
day
32.00
121
BLD-CSTN17-8
326
BLD-CSTN17-9
327
B) LABOUR CHARGES
Unskilled Mazdoor
Consumables like Rope, Nails
Conveyance, loading & unloading etc
Tools like Hammers etc.,
BASIC COST per 100 RM
3 - TIER (3 Nos Horizontals- 6'-0" long - 1 No
Vertical -4'-0" High)
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - (75 Nos-4
RM & 55 Nos-2 RM = 300+110=410 RM/3.66
= 112 Nos, if 12'-0" long ballies are used)
B) LABOUR CHARGES
Unskilled Mazdoor
Consumables like Rope, Nails
Conveyance, loading & unloading etc
Tools like Hammers etc.,
BASIC COST per 100 RM
BLD-CSTN17-10
328
Nos
85
day
12
1%
1%
1%
Nos
130
day
12.5
1%
1%
1%
cum
Kgs
1.00
95.00
day
0.10
day
2.36
122
Casurina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., (As per relevant data item)
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%)
Number of uses of Scaffolding materials =
U
(Rs. A - Rs. B)
U
Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates,etc., (As per relevant data item)
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%)
Period of Hire of Scaffolding materials, in years =
C
Life of Scaffolding materials, in years =
D
[(Rs. A - Rs. B)*C]
D
Sl
RATE ANALYSIS FOR HIRE CHARGES OF CENTRING & SCAFFOLDING MATERIALS FOR ALL R.C.C. STRUCTURAL MEMBERS - ANY HEIGHT
Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10
Rs.
Labour Charges
Rs.
Qty
Unit
(a)
1
FOOTINGS
(c)
3.880
(d)
sqm
PEDESTALS
6.170
sqm
PLINTH BEAMS
9.350
sqm
LINTELS
7.940
sqm
CHAJJAS - SUNSHADES
1.220
sqm
COLUMNS
11.150
sqm
Hire
Charges
H
(e)
Labour
Charges
L
(f)
SubTotal
(H + L)
(g)
Duty Factor
C1
C1
(h)
Centring
Charges
(c)*(g)*(h)
(i)
Unit of Measurement
(j)
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 sqm of concrete
member
per 1 cum of concrete
123
BEAMS
9.350
sqm
1.050
sqm
1.090
sqm
10
1.140
sqm
11
3.850
sqm
12
2.700
sqm
13
10.630
sqm
14
10.780
sqm
15
DOME SLABS
17.190
sqm
16
HELICAL STAIRCASES
1.310
sqm
member
per 1 cum of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 sqm of concrete
member
124
RATE ANALYSIS FOR HIRE CHARGES SCAFFOLDING MATERIALS FOR BRICK & STONE MASONRY
H
L
Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items
Labour Charges - as per Access Scaffolds items
Sl
(a)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
(b)
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
6th Floor
7th Floor
8th Floor
9th Floor
10th Floor
11th Floor
12th Floor
13th Floor
14th Floor
15th Floor
16
....
Qty
Unit
(c)
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
(d)
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
...
...
Hire
Charges
H
(e)
Labour Charges
L
(f)
(g)
100%
150%
200%
250%
300%
350%
400%
450%
500%
550%
600%
650%
700%
750%
800%
Lift Charges
(f) * (g)
(h)
Rs.
Rs.
Duty
Factor C1
C1
(i)
Scaffolding Charges
[(e)+(h)]*(i)
(j)
...
125
RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR WALL PLASTERINGS, RCM WORKS - ANY THICK
H
Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items
Rs.
Rs.
Sl
(a)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
(b)
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
6th Floor
7th Floor
8th Floor
9th Floor
10th Floor
11th Floor
12th Floor
13th Floor
14th Floor
15th Floor
16
....
Qty
Unit
(c)
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
(d)
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
...
...
Hire
Charges
H
(e)
Labour Charges
L
(f)
(g)
100%
150%
200%
250%
300%
350%
400%
450%
500%
550%
600%
650%
700%
750%
800%
Lift Charges
(f) * (g)
(h)
Duty
Factor C1
C1
(i)
Scaffolding Charges
[(e)+(h)]*(i)
(j)
...
126
RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR CEILING PLASTERINGS - ANY THICK
H
L
(a)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Stage Scaffold items
Labour Charges - as per Stage Scaffolds items
Hire
Labour Charges
Lift Charges
SCAFFOLDING CHARGES FOR BRICK / STONE
Qty
Unit Charges
MASONRY
H
L
(f) * (g)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
1st Floor
10.00
sqm
100%
2nd Floor
10.00
sqm
150%
3rd Floor
10.00
sqm
200%
4th Floor
10.00
sqm
250%
5th Floor
10.00
sqm
300%
6th Floor
10.00
sqm
350%
7th Floor
10.00
sqm
400%
8th Floor
10.00
sqm
450%
9th Floor
10.00
sqm
500%
10th Floor
10.00
sqm
550%
11th Floor
10.00
sqm
600%
12th Floor
10.00
sqm
650%
13th Floor
10.00
sqm
700%
14th Floor
10.00
sqm
750%
15th Floor
10.00
sqm
800%
16
....
Sl
...
...
Rs.
Rs.
Duty
Factor C1
C1
(i)
Scaffolding Charges
[(e)+(h)]*(i)
(j)
...
127
Note
1
2
a
b
c
d
e
f
3
For Material Lift Charges & Labour rate for scaffolding above 7.32 M - increase @ 50% on labour component for each upper
floor on First Floor Rate (7.32 M)
For Hire Charges of scaffolding Materials following ratesmay be allowed:
Number of uses of Scaffolding materials (C )
Wooden Materials - No of Uses - 10 Times (C)
Period of Hire of Steel Scaffolding materials, in years =
1.64 (C )
Life of Steel Forms & Scaffolding Material - 3
Years (D)
Duty Factor - Steel Scaffolding
C1
0.500
Duty Factor - Wooden Scaffolding
C1
0.333
Add Area Allowances as applicable on labour
charges
128
Steel Barricading G.I. Pipes, Mild Steel IS Angles (As per relevant data item)
Cost of Barricading materials = Rs. A
Scrap value of Barricading materials = Rs. B (Usually B = A * 10%)
Period of Hire of Barricading materials, in years =
C
Life of Barricading materials, in years =
D
[(Rs. A - Rs. B)*C]
D
Sl
(a)
1
3
4
Hire Charges of Steel Barricading: a/365 (OR) Wooden Barricading: b/10 - as per Barricading Item
Labour Charges: as per Barricading work
data items
Qty
Unit
(c)
1000.00
(d)
RM
100.00
100.00
RM
RM
Hire
Charges
H
(e)
No of
Days of
Hire
R
(f)
Rs.
Rs.
Duty
Factor
MaterialHire
charges
Labour
Charges
Barricading Charges
C1
(g)
(e*f*g)
(h)
L
(i)
(h) + (i)
(j)
129
Note
1
2
a
b
c
d
e
f
3
25% extra over the corresponding labour rates in respect of the work to be done during night time subject to issue of
certificate accordingly by the concerned estimate sanctioning authority for providing in the data and by concerned
Executive Engineer in charge of the work for payment. The night time allowance is applicable only to the works done under
Greater Hyderabad Municipal Corporation limits only
For Hire Charges of Barricading Materials following ratesmay be allowed:
Number of uses of woodenBarricading
materials (U )
Wooden Materials - No of Uses - 10 Times (U)
Period of Hire of Steel Barricading materials, in years =
1.64 (C )
Life of Steel Forms & Barricading Material - 3
Years (D)
Duty Factor - Steel Barricading
C1
0.500
Duty Factor - Wooden Barricading
C1
0.333
Add Area Allowances as applicable on labour
charges
130
Description of Structure
a. FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)
b. COLUMNS, LINTELS, WATER TANKS, RCC WALLS
c. RCC SLABS, BEAMS
Hrs
Hrs
LIFT CHARGES - for Brick Masonry, all Plastering items, all Flooring items, HYSD Steel fabrication, impervious coats, RCM Works
1
For Lift Charges of Labour, increase @ 10% on labour charges of respective item for each upper floor on Ground Floor Rate
9
1
2
131
COM-LDLFT-1
Unit
Quantity
day
day
day
day
day
Rate Rs.
Amount
Rs.
132
COM-LDLFT-2
10
LEAD UP TO 150 m
A) LABOUR
Mazdoor
Cost for 5.5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
(Lead) Conveyance charges for machinery
per kilometer for transporting materials
by tippers and trucks excluding loading,
unloading and hire charges of machinery
Earth / Sand / Gravel / Murrum /
Lime / Surki /Coarse aggregate /
Rubble stone / Size stone / Cut
stone
LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
day
Hr
Hr
Hr
0.15
0.15
0.15
Hr
Hr
Hr
0.21
0.21
0.21
Hr
Hr
Hr
0.28
0.28
0.28
Hr
Hr
Hr
0.34
0.34
0.34
133
12
13
14
15
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD BEYOND 30 KM/ EVERY KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
Cement/ Steel/ Pipes/ RCC poles/
AC & GI sheets/ Packed materials
LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Hr
Hr
Hr
0.40
0.40
0.40
Hr
Hr
Hr
0.06
0.06
0.06
Hr
Hr
Hr
0.05
0.05
0.05
Hr
Hr
Hr
0.15
0.15
0.15
Hr
Hr
0.21
0.21
134
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
16
17
18
19
20
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD BEYOND 30 KM/ EVERY KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Hr
0.21
Hr
Hr
Hr
0.28
0.28
0.28
Hr
Hr
Hr
0.34
0.34
0.34
Hr
Hr
Hr
0.40
0.40
0.40
Hr
Hr
Hr
0.06
0.06
0.06
Hr
Hr
Hr
0.05
0.05
0.05
135
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
PCC slabs/ Shahabad slabs/ BS
slabs/ CC & Laterite blocks/ Wood
21
22
23
24
25
LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Hr
Hr
Hr
0.15
0.15
0.15
Hr
Hr
Hr
0.21
0.21
0.21
Hr
Hr
Hr
0.28
0.28
0.28
Hr
Hr
Hr
0.34
0.34
0.34
Hr
Hr
Hr
0.40
0.40
0.40
136
27
28
29
30
Hr
Hr
Hr
0.06
0.06
0.06
Hr
Hr
Hr
0.05
0.05
0.05
Hr
Hr
Hr
0.15
0.15
0.15
Hr
Hr
Hr
0.21
0.21
0.21
Hr
Hr
Hr
0.28
0.28
0.28
137
32
33
34
35
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD BEYOND 30 KM/ EVERY KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
BRICKS
LEAD UP TO 1 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Hr
Hr
Hr
0.34
0.34
0.34
Hr
Hr
Hr
0.40
0.40
0.40
Hr
Hr
Hr
0.06
0.06
0.06
Hr
Hr
Hr
0.05
0.05
0.05
Hr
Hr
Hr
0.15
0.15
0.15
138
37
38
39
40
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Hr
Hr
Hr
0.21
0.21
0.21
Hr
Hr
Hr
0.28
0.28
0.28
Hr
Hr
Hr
0.34
0.34
0.34
Hr
Hr
Hr
0.40
0.40
0.40
Hr
Hr
Hr
0.06
0.06
0.06
139
COM-LDLFT-3
Hr
Hr
Hr
0.05
0.05
0.05
LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks
are not added)
42
LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 CUM
43
UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM
44
LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 CUM
45
day
day
0.02
0.50
day
day
0.01
0.25
UNLOADING
50% of the loading charges i.e.,
140
LOADING
Loading
of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1000 Nos
47
48
LOADING
Loading of Cement by manual
means including a lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 MT
49
50
LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 MT
51
day
day
0.01
0.25
day
day
0.06
1.50
day
day
0.07
1.80
COM-LDLFT-4
LOADING AND UNLOADING CHARGES BY MANUAL MEANS (Including idle hire charges
of trucks )
52
LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 CUM
53
UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM
54
LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 CUM
55
UNLOADING
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 CUM
day
day
0.02
0.50
Hour
0.50
day
day
0.01
0.25
Hour
0.500
day
day
0.005
0.125
Hour
0.166
142
56
57
58
LOADING
Loading
of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1000 Nos
UNLOADING & STACKING
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1000 Nos
0.01
0.25
Hour
0.33
day
day
0.06
1.50
Hour
1.00
day
day
0.06
1.50
Hour
1.00
day
day
0.07
1.80
Hour
1.00
LOADING
Loading of Cement by manual
means including a lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 MT
59
day
day
143
61
COM-LDLFT-5
LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 MT
day
day
0.07
1.80
Hour
1.00
62
LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone by mechanical
means including a lead upto 30 m
placing a tipper at loading point ,
loading with front end loader
excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading
point
ii) Loading by front end loader 1
cum bucket capacity
@ 45 / 25 cum per hour
iii) Manoevouring, reversing,
dumping and turning
for return
iv) Waiting time, unforeseen
contingencies, etc.
Total
A) MACHIENRY
Tipper 10 t capacity
Min
1.00
Min
7.33
Min
Min
2.00
Min
10.33
hour
0.17
144
0.12
64
hour
Min
1.00
Min
3.30
Min
2.00
Min
6.30
hour
hour
0.11
0.06
UNLOADING
Unloading
of Earth, Sand,
Murrum, Gravel, Manure, Fly-Ash,
Lime, Aggregate, Stone Boulder,
Brick Aggregate, Kankar, Building
Rubbish, Building Rubbish, Crushed
Slag, Stone by mechanical means
including a lead upto 30 m placing
a tipper at loading point , loading
with front end loader excluding
time for haulage and return trip
Placing tipper at unloading point,
excluding time
for haulage and return trip.
Taking output = 5.5 cum
Time required for
145
Min
1.00
Min
2.00
Min
2.00
5.00
hour
0.08
66
60 M/
minute
min
0.12
4000
cum
cum
0.015
60
day
1.00
146
68
69
25 M/
Minute
min
0.29
1655
kgs
50
tons
83
day
1.00
147
25 M/
Minute
min
0.18
2667
cum
0.017
cum
45
day
1.00
148
For Phases
-----
For Neutral
For Earth
All Switch boards for neutral conduit wiring shall be fabricated with CRCA Sheet
Steel from 1.6 mm (16 SWG) thick with 7 tank process and powder coating or Hot dip
galvanized boxes.
The mounting height of boards (Bottom of Box) shall be as follows :
a) All Switch Boards
b) 16 A Power Plugs
and Metal Sockets
c) 16 A Power Plugs
and Metal Sockets in Kitchen :
Above 30 cm on Platform
2 m from FFL
Installation Resistance
(ii)
Earth Continuity
149
---
(ii) OLCOS
---
(iii) MCCB
---
(iv) MCB
---
IS : 8828 : 96
(v) Isolator
---
---
IS : 12640 - 1 : 2000
The height of the panel board should not be more than 2400 mm. The depth of the
panel should be adequate to cater proper cable termination.
151
All the Steel Work used in the construction of the panel boards should have
undergone a rigorous metal treatment process i.e. 7- tank process.
of 63 KVA / 100 KVA shall be proposed. Where HT supply is required, only copper wound
distribution transformers are to be proposed.
The lightening arrestors shall confirm to IS : 3070 and the protection against the
lightening shall be in accordance with Rule 92 of IE Rules.
153
Specifica
tion No.
1
BLD-ELEC-1
BLD-ELEC-1
BLD-ELEC-11
1
1.1
1.1.1
1.1.2
Description
2
Conduit Laying
MS / PVC / Trunks Coduit Laying
M.S.CONDUIT (Surface)
Unit
Quant
ity
Rate
Rs.
Amou
nt Rs.
Remarks
Note for
All Items
for
Coduit
Laying
100 M
100 Nos
100 Nos
100 Nos
100 Nos
100 Nos
Dozen
Dozen
Each
1
2
2
2
4
2
1
1
3
kg
12.5
day
day
day
3
3
3
100 M
100 Nos
100 Nos
100 Nos
1
1.5
1.5
1.5
154
1.1.3
BLD-ELEC-12
1.2
1.2.1
12mm Screws
25mm Saddles MS
25mm 1,2,3 & 4 way Junction box
25mm dia HG bends
Cement (As per civil SSR)
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 32mm dia 16 SWG
(ISI MARK) MS Surface pipe duly
threading at Joints with all required
accessories fixing on T.W. Seperators
with chromium plated base saddles
and No.18 SWG MS box for run of
mains including cost of Cement, all
materials, accessories and all labour
charges etc., complete.
Unit = 1Metre
Taking Output = 100 M
a) Material
32mm dia 16 SWG MS conduit
T.W seperators
38mm Screws No.8
Rawal Plugs
12mm Screws
32mm Saddles MS
32mm 1,2,3 & 4 way Junction box
32mm dia HG bends
Cement (As per civil SSR)
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
MS Conduit Concealed
100 Nos
100 Nos
Dozen
Dozen
kg
3
1.5
0.5
1
12.5
day
day
day
3
3
3
100 M
100 Nos
100 Nos
100 Nos
100 Nos
100 Nos
Dozen
Dozen
kg
1
1.5
1.5
1.5
3
1.5
0.5
1
12.5
day
day
day
3
3
3
1.2.2
1.2.3
100 M
100 Nos
Each
1
2
3
Dozen
kg
1
12.5
day
day
day
day
3
3
3
3
100 M
100 Nos
Dozen
Dozen
kg
1
2
1
1
50
day
day
day
day
3
3
3
3
100 M
100 Nos
Dozen
Dozen
kg
1
2
1
1
50
day
day
3
3
156
BLD-ELEC-13
1.3
1.3.1
1.3.2
Helpers
day
Mason Ist class
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
NOTE : For Laying MS Concealed Conduit pipe in roof
Slab, deduct the Cost of Cement and U' Nails.
P.V.C. Conduit (Surface)
3
3
100 M
100 Nos
100 Nos
Each
Each
Each
Each
kg
1
2
2
200
12
12
3
25
day
day
day
2
2
2
100 M
100 Nos
100 Nos
Each
Each
Each
kg
1
2
2
200
12
12
25
day
day
day
2
2
2
157
1.3.3
1.3.4
1.3.5
100 M
100 Nos
100 Nos
Each
Each
Each
kg
1
2
2
200
12
12
25
day
day
day
2
2
2
100 M
100 Nos
100 Nos
Each
Each
Each
kg
1
2
2
200
12
12
25
day
day
day
2
2
2
BLD-ELEC-14
1.4
1.4.1 (a)
(b)
a) Material
50mm dia 1.5mm thick PVC pipe
Rawl Plugs
35mm Screws
Chromium Plated saddles with base
50mm 1,2,3, & 4 way Junction boxes
50mm PVC Bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
P.V.C. Conduit (Concealed)
100 M
100 Nos
100 Nos
Each
Each
Each
kg
1
2
2
200
12
12
25
day
day
day
2
2
2
100 M
100 Nos
Each
Each
1
2
3
12
Each
kg
12
50
day
day
day
day
2
2
2
2
100 M
100 Nos
Each
1
2
3
159
1.4.2
(a)
(b)
Each
12
Each
kg
12
50
day
day
day
day
2
2
2
2
100 M
100 Nos
Each
1
2
12
Each
kg
12
50
day
day
day
day
2
2
2
2
100 M
100 Nos
Each
1
2
12
Each
kg
12
50
day
day
day
day
2
2
2
2
160
BLD-ELEC-15
1.5
1.5.1
1.5.2
1
12
12
2
2
2
100 M
day
day
day
LS
1
1
2
161
1.5.3
1.5.4
100 M
day
day
day
LS
1
1
2
100 M
day
day
day
LS
1
1
2
100 M
day
day
day
LS
1
1
2
162
BLD-ELEC-2
BLD-ELEC-21
2
2.1
2.1.1
2.1.2
Note for
All Items
for
Wiring
The R&B
Departm
ent
Proposed
Labour,
for both
piping &
wiring
consideri
ng 40%
Labour,
for Wire
draw.
Keeping
this, the
labour is
proposed
for
wiring
100 RM.
100 M
each
each
sqm
1
6
6
0.05
day
day
day
0.6
1.2
0.6
100 M
each
each
sqm
1
7
7
0.05
163
2.1.3
2.1.4
2.1.5
Skilled Electrician
Semi skilled Electrician
Helpers
C) Cost for 7 Points
Rate per Points = C/7
Wiring with 2 of 14/0.3mm (1.0
Sq.mm) P.V.C. insulated F.R. flexible
copper cable (ISI MARK) in existing
pipe with 6A switch control and 3/2 pin
sockets fixing on separate board
including all labour charges etc.,
complete.
Taking Output = 15 Points
a) Material
14/0.3mm PVC FR flexible copper wire
6A switches @16/each
6A 3 pin / 2 Pin Socket
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
C) Cost for 15 Points
Rate per Points = C/15
Supply and fixing of 6A 3 pin wall plug
socket with 6A switch control on a
common switch board with earth
continuity including wire leads, earth
connections along with all labour
charges etc., complete.
day
day
day
0.7
1.4
0.7
100 M
each
each
1
15
15
day
day
day
1.5
1.5
1.5
each
each
1
1
day
day
0.067
0.067
1point
each
each
164
2.1.6
2.1.7
2.1.8
Skilled Electrician
day
Helpers
day
Rate per each
Note : Labour Charges proposed for 1point
considering 10 per day
Supply and Fixing of 16A 3pin and 6A
3pin plug socket with indicator lamp
and 16A fuse unit and 16A switch
control (5 in 1) duly recessed in wall
with wooden deep box of 6" x8" x2
1/2" size covered with hylam sheet
including earth connections and all
labour charges etc., complete.
Taking Output = each
a) Material
20 x 15 cms (8" x6") Wooden deep box
each
21.6 x 16.6 cms (8.5 x 6.5") 3mm thick
each
hylam sheet
16A 3 pin / 6A 3pin plug socket (5 in 1)
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Rate per each
Note : Labour Charges proposed for 10 jobs per day
Supply and fixing of batten holder /
slanting holder in lieu of ceiling rose of
light point complete with all
connections and all labour charges
with 40W bulb (for new installation).
Taking Output = each
a) Material
PVC batten holder
each
40W bulb
each
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
Note : 1. The Cost of Ceiling Rose may be deducted in
view of holder.
2. Labour Charges proposed for 20 jobs per day
Supply and fixing of batten holder /
angle holder on existing block, but
without bulb including all connections
etc., complete (For replacement).
Taking Output = each
a) Material
PVC batten holder
each
Less : Cost of ceiling Rose
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
0.1
0.1
1
1
1
0.1
0.1
0.1
1
1
0.05
0.05
0.05
0.05
165
2.1.9
2.1.10
2.1.11
5
1
1
0.125
0.125
0.125
1
1
1
0.05
0.05
1
1
1
1
0.05
0.05
166
2.1.12
2.1.13
2.1.14
BLD-ELEC-3
BLD-ELEC-31
3
3.1
3.1.1
100 M
1
1
0.062
0.062
1
1
0.062
0.062
1
1
0.062
0.062
2
167
3.1.2
3.1.3
3.1.4
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 1 of 14 /0.3mm (1.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity including all labour charges
etc., complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire
100 M
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 2 of 22/0.3mm (1.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
22/0.3mm FR PVC copper wire
100 M
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 2 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper
wire
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers
0.67
2
0.67
1
0.34
1
0.34
2
0.67
2
0.67
100 M
day
day
day
0.67
2
0.67
168
3.1.4 (a)
3.1.5
3.1.6
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 1 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper
100 M
wire
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 2 of 56/0.3mm (4
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
56 /0.3mm (4 sqmm)FR PVC flexible
100 M
copper wire.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
Supply and run of 2 of 84/0.3mm (6.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
84 /0.3mm (6 Sq.mm) FR PVC flexible
copper wire.
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
0.34
1
0.34
1
3
1
100 M
day
day
day
1
3
1
169
3.3.7
3.3.8
BLD-ELEC-4
4
4.1
4.1.1
1
3
1
1
3
1
each
day
day
0.167
0.167
170
4.1.2
4.1.3
4.1.4
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type 60 / 63A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
60 / 63A TPN 415V, 50 Hz. switchs
each
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type 125A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
125A TPN 415V, 50 Hz. switchs
each
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type 200A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
200A TPN 415V, 50 Hz. switchs
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
0.333
0.167
0.167
0.333
0.167
0.167
0.333
each
day
0.2
171
4.1.5
4.1.6
4.1.7
each
0.4
0.4
0.2
0.4
0.4
0.25
0.5
0.5
172
BLD-ELEC-42
4.2
4.2.1
4.2.2
4.2.3
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
Panel Mounting Cubical type, 4pole
onload change over switch confirming
to IS 13947-3-1993.
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 60 / 63A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
60 / 63A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 125A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
125A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 200A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
200A, 4 Pole, 415V, 50 Hz. On load
cubical type C.O.S
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
0.25
0.5
0.5
0.167
0.167
0.333
0.167
0.167
0.333
each
day
day
0.2
0.4
173
4.2.4
4.2.5
4.2.6
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 250A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
250A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 400A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
400A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 630A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
630A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
0.4
0.2
0.4
0.4
0.25
0.5
0.5
0.25
0.5
0.5
174
4.2.7
4.2.8
BLD-ELEC-43
4.3
4.3.1
each
day
day
day
LS
1
1
1
each
day
day
day
LS
1
1
1
1
0.167
0.167
0.333
175
4.3.2
4.3.3
4.3.4
0.167
0.167
0.333
0.167
0.167
0.333
0.167
0.167
0.333
176
4.3.5
4.3.6
BLD-ELEC-44
4.4
4.4.1
each
0.2
0.4
0.4
0.2
0.4
0.4
177
4.4.2
1
4
0.5
0.5
1
1
6
0.5
0.5
1
1
8
0.5
0.5
1
178
complete.
1
4
0.5
0.5
1
1
6
0.5
0.5
1
1
8
179
4.4.3
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware, cement
LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing TPN Distribution
board with IP-20 protection suitable
for 3 phase ELCB / RCCB / FP Isolator as
incomer and 10kA SP MCBs as outing
going including internal connection
and labour charges for surface / flush
mounting etc., complete.
40A FP Isolator/ RCCB / ELCB - 1 No
for incomer,
10kA-6-32A SP
MCBs - 12Nos for outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection
each
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
40A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
63A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection
each
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
63A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
80A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 18Nos for
0.5
0.5
1
1
12
0.5
1
1
1
12
0.5
1
1
180
outgoing.
4.4.4
1
18
0.5
1
1
1
12
0.5
1
1
1
12
181
4.4.5
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
80A FP Isolator - 1 No for incomer, 632A SP MCBs - 18Nos for outgoing.
Taking Output = each
a) Material
6 way TPN, D.B with IP-42 Protection
each
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
80A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing TPN - Vertical type
Distribution board with IP - 20
Protection suitable for 3 phase ELCB /
RCCB / FP Isolator as incomer and 10
kA TP / SP MCBs as outing going
including internal connection and
labour charges for surface / flush
mounting etc., complete.
Incomer : 63A FP Isolator / ELCB /
RCCB
Outgoing : 32A TP MCBs 2 Nos and
6-32A SP MCBs 6 Nos
a) Material
4way TPN - Vertical type DB with IP-20
Nos
protection suitable for 3 Phase ELCB /
RCCB / 4 Pole Isolator as in commer
and TP / SP MCBs as outgoing with
Bus-bar arrangment etc.,
63Apms, 4 Pole Isolator / ELCB / RCCB
32A TP MCBs
10kA -6-32A SP MCBs
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers
Sundries, suchas T.W plugs, Screws,
Cement etc,
Rate per each
0.5
1
1
1
18
0.5
1
1
Nos
Nos
Nos
1
2
6
day
day
day
LS
0.5
1
1
182
4.4.6
1
4
8
0.5
1
1
1
2
6
0.5
1
1
183
4.4.7
Nos
1
4
8
0.5
1
1
1
3
12
0.5
1
1
184
4.4.8
4.4.9
1
3
12
1
1
1
1
4
12
1
1
1
185
4.4.10
BLD-ELEC-5
BLD-ELEC-51
5
5.1
5.1.1
a) Material
1 Phase Distribution board with 20A
Nos
plug and socket.
10/16/20A SP MCB
Nos
b) Labour charges :
Skilled Electrician
Nos
Semi skilled Electrician
Nos
Helpers
Nos
Sundries such as Cement, Sand, T.W.
LS
Plugs, Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 4 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
Supply and fixing Distribution board
with 20A 3 phase plug and Socket, in
sheet steel enclosure with 16/20A TP
MCB including internal connection and
labour charges for surface / flush
mounting etc., complete.
a) Material
Distribution board with 3 Ph. 20A Plug
Each
and Socket .
32A TP MCB, 10 kA
Each
b) Labour charges :
Skilled Electrician
Nos
Semi skilled Electrician
Nos
Helpers
Nos
Sundries such as Cement, T.W. Plugs,
Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 3 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
EARTHING
EARTHING
1
1
0.25
0.25
0.25
1
1
0.33
0.33
0.33
186
5.1.2
cum
0.85
cum
0.9
Mtr
Each
2.5
1
Each
16
Set
Each
Kg
Kg
Each
4
1
40
20
Nos
Nos
0.5
0.5
cum
1.27
cum
1.87
cum
0.9
187
5.1.3
cum
0.23
sqm
2.09
Mtr
Mtr
Each
Each
Each
2.5
0.3
1
1
1
Each
16
Set
kg
kg
L.S
4
4
20
Nos
cum
1.27
cum
1.87
cum
0.9
cum
0.23
sqm
2.09
188
SSR).
BLD-ELEC-52
5.2
5.2.1
5.2.2
5.2.3
Mtr
Mtr
Each
Each
Each
2.5
0.3
1
1
1
kg
10.00
Each
16
Set
kg
kg
L.S
4
4
20
Nos
10.4
Kg
100Nos
1.5
day
6.7
Kg
100Nos
1.5
day
189
5.2.4
5.2.5
5.2.6
5.2.7
4.4
Kg
100Nos
1.5
day
2.6
Kg
100Nos
1.5
day
kg
118
Nos
Nos
2
2
kg
188
Nos
Nos
2
2
kg
236
Nos
Nos
2
2
190
BLD-ELEC-53
5.3
5.3.1
5.3.2
5.3.3
5.3.4
Kg
45.5
Nos
Nos
Nos
1
1
1
Kg
11.55
Nos
Nos
Nos
1
1
1
Kg
2.8
Nos
Nos
Nos
1
1
1
Kg
66.3
Nos
2
191
5.3.5
BLD-ELEC-6
BLD-ELEC-61
6
6.1
6.1.1
6.1.2
Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 32mm x 6mm
copper strip including cost of all
accessories and labour charges etc.,
complete.
a) Material
32mmx 6mm Copper strip (1.697 Kg /
Mtr) 100 M Length
b) labour charges
Skilled Electrician
Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
SERVICE MAINS & LTOH Lines
WPSC (Weather Prrof Single Core)
(PVC Cleats)
Supply and Run of 2 of 2.5 Sq.mm
WPSC (Whether Proof Single Core)
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
2.5 Sq.mm WPSC Aluminium cable
No.10 SWG G.I wire. (0.026 Kg / Mtr)
Length 100 RM
PVC Cleats
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 2 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
6 Sq.mm WPSC Aluminium cable
No.10 SWG G.I wire. (0.026 Kg / Mtr)
Length 100 RM
PVC Cleats
b) labour charges
Skilled Electrician
Semi skilled
Nos
LS
Kg
169.7
Nos
Nos
2
2
100 M
kg
2
6.7
100 Nos
day
day
day
1
1
1
100 M
kg
2
6.7
100 Nos
day
day
1
1
192
6.1.3
6.1.4
6.1.5
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 2 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable
No.10 SWG G.I wire. (0.026 Kg / Mtr
)Length 100 RM
PVC Cleats
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 4 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire on both sides
through PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
6 Sq.mm WPSC Aluminium cable
No.10 SWG GI Wire (6.7kg x 2) Length
200 RM
Binding wire
PVC Cleats / Separters 4 W.
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 4 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire on both
sides through PVC cleats with all
accessories including labour charges
etc., complete for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable
day
100 M
kg
2
6.7
100 Nos
day
day
day
1
1
1
100 M
kg
4
13.4
kg
100 Nos
0.25
1
day
day
day
2
2
2
100 M
193
6.1.6
BLD-ELEC-62
6.2
6.2.1
kg
13.4
kg
100 Nos
0.25
1
day
day
day
2
2
2
100 M
kg
4
13.4
kg
100 Nos
0.25
1
day
day
day
2
2
2
100 M
kg
each
box
1
6.7
2
2
day
day
day
1
1
1
194
6.2.2
6.2.3
6.2.4
100 M
kg
each
box
6.7
2
2
day
day
day
1
1
1
100 M
kg
each
box
2
6.7
4
2
day
day
day
1
1
1
100 M
kg
each
box
6.7
4
2
day
day
day
1
1
1
195
6.2.5
BLD-ELEC-63
6.3
6.3.1
6.3.2
100 M
kg
each
box
6.7
4
2
day
day
day
1
1
1
4.27
6
1
3
1
0.125
0.125
kg
2.13
each
each
4
1
196
6.3.3
6.3.4
1
1
0.1
0.1
1
1
0.142
0.675
1
1
0.5
1
kg
5.32
kg
1.57
each
kg
0.8
day
day
0.25
0.25
197
6.3.5
6.3.5 (a)
6.3.5 (b)
6.3.5 (c)
Helper
day
Sundires such as bolts, nuts including
soldering.
Rate per Each
Note : 1. Labour Charges considered for 4 jobs / day
OH Conductors
Supply and erecting 7/2.00 AAAC (All
Aluminium Annealed Conductor) /
Squirrel (20 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete
a) Material
7/2.0 AAAC (Squirrel)
7/2.0 AAAC for binding and Jumpering.
Aluminium Clamps
b) labour charges
Skilled Electrician
Helper
For special T&P
Sundires and rounding off
Rate per km
Supply and erecting 7/2.50 AAAC /
Weasel (34 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/2.5 AAAC / Weasel (34 Sq.mm)
7/2.5 AAAC for binding and Jumpering.
Aluminium Clamps
b) labour charges
Skilled Electrician
Helper
For special T&P
Sundires and rounding off
Rate per km
Supply and erecting 7/3.15 AAAC /
Rabbit (55 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/3.15 AAAC / Rabbit (55 Sq.mm)
7/3.15 AAAC for binding and
Jumpering.
Aluminium Clamps
b) labour charges
Skilled Electrician
Helper
For special T&P
Sundires and rounding off
Rate per km
0.5
km
km
each
1
0.1
10
day
day
LS
2
8
km
km
each
1
0.1
10
day
day
LS
2
8
km
km
1
0.1
each
10
day
day
LS
2
8
198
6.3.6
6.3.7
6.3.8 (a)
cum
cum
Nos
512
cum
0.20
day
0.24
day
0.56
Mazdoor (unskilled)
Scaffolding charges
Add 25% extra on labour for isolated
work
Rate per cum
Plastering with CM (1:5), 12 mm thick
day
1.88
cum
0.15
Unit = 10 sqm
a) Material
Cement Mortor (1:5)
b) labour charges
st
Mason 1 class
6.3.8 (c)
0.2
Mason 2 class
nd
6.3.8 (b)
Mazdoor (unskilled)
Rate per cum
CRS Masonry in CM (1:6) 2nd Sort
day
0.6
day
0.96
Unit = 1cum
a) Material
199
cum
cum
0.94
0.16
cum
0.32
day
0.45
Mason 2 class
day
1.05
Mazdoor (unskilled)
Add 25% extra on labour for isolated
work
Rate per cum
Supply Transportation and unloading
the 9.1mtr long PSCC poles with 300kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
day
2.32
nd
6.3.9 (a)
6.3.9 (b)
6.3.9 (c)
a) Material
9.1 Mtr PSCC pole of 300 Kg working
each
load
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
Supply Transportation and unloading
the 9.1mtr long PSCC poles with 280kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
9.1 Mtr PSCC pole of 280 Kg working
each
load
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
Supply Transportation and unloading
the 8.0mtr long PSCC poles with 200kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
8 Mtr PSCC pole of 200 Kg working
each
load
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
0.5
0.5
0.5
200
6.3.9 (d)
6.3.10
(a)
6.3.10
(b)
BLD-ELEC-7
BLD-ELEC-71
7
7.1
7.1.1
each
0.5
176.4
0.33
120
0.33
201
7.1.2
7.1.3
BLD-ELEC-72
7.2
7.2.1
7.2.2
BLD-ELEC-73
7.3
each
each
each
1
1
each
each
each
each
each
each
202
7.3.1
7.3.2
7.3.3
BLD-ELEC-74
7.4
7.4.1
each
each
each
each
each
each
7.4.2
7.4.3
7.4.4
BLD-ELEC-75
7.5
each
each
each
each
each
each
each
each
204
7.5.1
7.5.2
7.5.3
7.5.4
7.5.6
each
each
1
1
each
each
1
1
each
each
1
1
each
each
each
each
1
1
205
7.5.7
BLD-ELEC-76
7.6
7.6.1
7.6.2
BLD-ELEC-77
7.7
7.7.1
7.7.2
each
each
each
each
1
1
each
each
1
1
each
each
1
1
each
each
1
1
206
7.7.3
7.7.4
BLD-ELEC-78
7.8
7.8.1
7.9.2
each
each
1
1
each
each
1
1
1
2
0.066
0.066
a) Material
207
7.9.3
7.9.4
7.9.5
each
LS
day
day
0.125
0.125
a) Material
23/0060 twin core flexible copper
M
cable
screws with rawal plugs
each
T.W round blocks
each
Cement and sand etc.,
LS
b) Labour charges
Skilled Electrician/carpenter
day
Semi skilled Electrician / Helper
day
Rate per each
Note : Labour Charges considered for 10 fixtures /
day .
Fixing of 40W tube lights with 1/2 Mtr
conduit suspension arrangements from
ceiling with hooks etc., including giving
connections and all labour charges
etc., complete.
a) Material
20mm dia No.16 gauge conduit pipe .
23/0060 twin core flexible copper
cable
Anchor screws / Hooks / Sockets &
Check
b) Labour charges
Skilled Electrician/carpenter
Semi skilled Electrician / Helper
Rate per each
Note : Labour Charges considered for 6
fixtures / day .
Fixing of 40W street light luminaire to
the wall with 1.0 Mtr., 25mm dia GI
pipe bracket and anti tilting MS flat
etc., including giving connections and
labour charges etc., complete.
a) Material
25mm dia G.I pipe
23/0060 twin core flexible copper
1
2
2
0.1
0.1
M
each
1
1
each
day
day
0.166
0.166
M
M
1
2
208
7.9.6
7.9.7
7.9.8
cable
Pipe bending charges
M.S flat and welding charges
b) Labour charges
Skilled Electrician/carpenter
Mason
Semi skilled Electrician / Helper
Rate per each
Note : Labour Charges considered for 5
fixtures / day .
Fixing of CFL street light luminary with
1.0 Mtr., 25mm dia GI pipe bracket
and anti tilting MS flat etc., including
giving connections and labour charges
etc., complete.
LS
LS
day
day
day
a) Material
25mm dia G.I pipe
M
23/0060 twin core flexible copper
M
cable
Pipe bending charges
LS
M.S flat and welding charges
LS
b) Labour charges
Skilled Electrician/carpenter
day
Mason
day
Helper
day
Rate per each
Note : Labour Charges considered for 8
fixtures / day .
Fixing of mirror optic tube light
luminaire in false ceiling / pop with
necessary arrangment including giving
connections and all labour charges
etc., complete.
a) Material
28/0060 twin core flexible copper
M
cable
Aluminium flat (as per requirment)
LS
b) Labour charges for cutting P.O.P /
false ceiling and Fixing MOT
Skilled Electrician
day
Carpenter
day
Semi skilled Electrician / Helper
day
Rate per each
Note : Labour Charges considered for 8 Nos MOT
lights in a day
Fixing of MV / SV/MH luminaire on
wall with 1.0mt 40mm dia GI pipe
bracket and anti-tilting MS flat, 2.5
Sq.mm
flexible
copper
cable
etc.,including all labour charges for
mason work and giving connections
etc., complete.
a) Material
40mm G.I pipe for Bracket
M
0.2
0.2
0.2
1
2
0.125
0.125
0.125
0.125
0.125
0.125
1
209
Bldngs_Elec8
8
8.1.1
Bldngs_Elec8-1
8.1.2
8.1.3
0.25
0.25
0.25
0.25
1
1
0.04
0.04
1
2
0.05
0.05
1
1
0.05
0.05
210
8.1.4
Bldngs_Elec8-2
8.2
8.2.1
8.2.2
8.2.3
8.2.4
each
each
1
1
day
day
0.083
0.083
each
each
1
1
each
each
1
1
each
each
1
2
211
Bldngs_Elec8-3
8.3
8.3.1
8.3.2
Bldngs_Elec8-4
8.4
8.4.1
8.4.2
a) Material
1x40 patty type T.L. fitting
40W FTL
Sundires and rounding off
Rate per each
INDUSTRIAL luminaire
Supply and Transportation of white
vitreous 1x36 / 40W industrial box
type luminaire with Copper / VPIT
Choke, Condensor, Starters etc., with
reflector including 1No 40W tube etc.,
complete.
a) Material
1x36/40W Industrial box type T.L.
fitting
36/40W FTL
Sundries and rounding off
Rate per each
Supply and Transportation of white
vitreous 2x36 / 40W industrial box
type luminaire with 2Nos Copper /
VPIT Choke, Condensor, Starters
etc.,complete with reflector including
2Nos 40W tube etc., complete.
a) Material
2x36/40W Industrial box type T.L.
fitting
36/40W FTL
Sundries and rounding off
Rate per each
MIRROR OPTIC luminaire
Supply and Transportation of 2x36 /
40W surface mounting mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror reflectors with VPIT chokes,
Starters, Condensor etc., complete
with
2Nos
36/40W
tubes
etc.,complete.
a) Material
2x36/40 Surface M.O.L fitting
40/36 FTL
Sundries and rounding off
Rate per each
Supply
and
transportation
of
2x36/40W recessed mounting mirror
optic (darklite) luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror reflector with VPIT
Chokes, Starter, Condensor etc.,
complete with 2Nos 36/40W tubes
etc., complete.
each
each
1
1
each
each
each
each
each
each
1
2
212
8.4.3
a) Material
2x36/40 Recessed M.O. L fitting
36/40 FTL
Sundries and rounding off
Rate per each
Supply and transportation of 2x11W
surface
mounting
mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror refector with VPIT Chokes and
2Nos 11W CFL lamps etc., complete.
8.4.4
a) Material
2x11W CFL surface M.O.L fitting
11W CFL
Sundries and rounding off
Rate per each
Supply and transportation of 2x11W
Recessed type luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror refector with VPIT
Chokes and 2Nos 11W CFL lamps etc.,
complete.
8.4.5
8.4.6
Bldngs_Elec8-5
8.5
a) Material
2x11W CFL recessed M.O.L fitting
11W cfl
Sundries and rounding off
Rate per each
Supply and transportation of 2x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 36w CFL lamps.
a) Material
2x36 CFL PS paralite Louvars fitting
36w CFL
Sundries and rounding off
Rate per each
Supply and transportation of 3x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 3x36w CFL
lamps.
a) Material
3x36 CFL PS paralite Louvars fitting
36w CFL
Sundries and rounding off
Rate per each
T- 5 Luminaires.
each
each
1
2
each
each
1
2
each
each
1
2
each
each
1
2
each
each
1
3
213
8.5.1
8.5.2
Bldngs_Elec8-6
8.6
8.6.1
8.6.2
8.6.3
each
each
1
1
each
each
1
2
each
each
1
1
each
each
1
2
each
each
1
1
214
8.6.4
8.6.5
8.6.6
8.6.7
Bldngs_Elec8-7
8.7
8.7.1
each
each
1
2
each
each
1
1
each
each
1
1
each
each
1
2
each
each
1
1
215
8.7.2
Bldngs_Elec9
Bldngs_Elec9-1
9
9.1
9.1.1(a)
9.1.1(b)
9.1.2 (a)
each
each
1
1
Air-Conditioners
Supply and Transportation of Window
mounted type, Room Air-Conditioner
1.5 Ton confirming to IS : 1391,
Suitable for operation on 230V + 10%
50 Hz.., Single phase, A.C. Supply
capable for performing Cooling,
Dehumidifying, Air Circulating, Filtering
and Ventilation etc., complete.
a) Material
1.5 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material
Rate per each
Supply and Transportation of Window
mounted type, Room Air-Conditioner
2.0 Ton confirming to IS : 1391,
Suitable for operation on 230V + 10%
50 Hz.., Single phase, A.C. Supply
capable for performing Cooling,
Dehumidifying, Air Circulating, Filtering
and Ventilation etc., complete.
a) Material
2.0 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material
Rate per each
Supply and Transportation of 1.5 Ton
Split type Air-Conditiner, fitted with
Hermetically
sealed
compressor,
Operating on refrigerant R-22 / Non CFC High wall mounting confirming to
IS : 1391, suitable for operation on
230V, 50 Hz.., Single phase, A.C Supply
capable of performing Cooling,
Dehumidifying, Air Circulating, Filtering
with cooling and condensing units,
with 5 Mtr of required size of copper
piping duly insulated and 3 core copper
flexible chord of required length etc.,
complete.
a) Material
2%
2%
216
9.1.2 (b)
9.1.3
9.1.4
9.1.5
2%
2%
cum
0.018
217
9.1.6
9.1.7
Bldngs_Elec9-2
9.2
9.2.1
day
day
day
LS
0.5
0.5
0.5
kg
10.5
kg
10.5
day
day
day
LS
0.25
0.25
0.25
day
day
0.04
0.04
each
day
0.5
218
9.2.2
9.2.3
9.2.5
9.2.6
Helper
Transportation on Material
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Replacement of defective compressor
by supply of 2.0 Ton brand new sealed
compressor ISI Mark
a) Material
Supply of brand new 2.0 Ton
compressor by brand new ISI Mark
b) Labour charges
Skilled Electrician
Helper
Transportation on Material
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Replacement of old and Unserviceable
Fan Motor by supply and Installation of
new 1/6th H.P multi speed Fan Motor
suitable for 1.0 / 1.5 / 2.0 Ton Window
A.C.Unit.
a) Material
Supply of 1/6th H.P multispeed Fan
Motor for 1.0 / 1.5 / 2.0 T A.C.Unit.
b) Labour charges
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Replacement of Unserviceable fan
motor capacitor 6 mfd by new
capacitor for A.C machine of 1.0 1.5 /
Ton Capacity.
a) Material
6 MFD motor capacitor
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement
of
Unserviceable
Thermostat switch by supply and
installation of new thermostat switch
suitable for 1.0 / 1.5 / 2.0 Ton
A.C.Unit.
a) Material
Thermostat switch for 1.0 / 1.5 / 2.0
Ton A.C.Unit.
day
0.5
2%
each
day
day
0.5
0.5
2%
each
day
day
0.5
0.5
each
day
0.2
each
219
9.2.7
9.2.8
9.2.9
9.2.10
day
0.2
each
day
0.2
each
day
0.2
each
day
0.2
a) Material
220
9.2.11
9.2.11(a)
Bldngs_Elec9-3
9.3
9.3.1
Bldngs_Elec9-4
9.6
each
day
0.2
each
day
0.2
each
day
0.2
each
1
2%
2%
221
9.6.1
9.6.2
9.6.3
each
day
day
0.044
0.044
2%
each
day
day
0.044
0.044
2%
222
Bldngs_Elec9-5
9.7
9.7.2
9.7.7
9.7.10
9.7.16
a) Material
3 KVA / 4 KVA / 5 KVA Stabilizer
b) Labour Charges
Skilled Electrician
Helper
Transportation Charges on Unit Cost
Rate per Each
Note : Labour is Considered for 10
jobs / day
Fans
each
day
day
0.1
0.1
2%
each
1%
each
day
day
0.1
0.1
each
1
2%
each
1
1%
223
9.7.18
9.7.24
9.7.25
9.7.26
9.7.33
each
1
1%
each
LS
day
day
0.166
0.166
day
0.1
day
0.1
day
0.2
224
9.7.34
9.7.35
9.7.36
0.166
0.166
0.125
0.125
1
25
0.25
0.25
0.25
225
Bldngs_Elec10
10
10.1.2
Bldngs_Elec10-1
10.1.5
Bldngs_Elec10-2
10.2
10.2.1
WATER HEATERS
Supply and Transportation of stove
enamelled storage / pressure type
vertical / Horizontal water heater with
copper tank 25 / 35 / 50 Ltrs. Capacity
with non return valve on inlet side and
dead weight pressure reducing valve
on outlet side 230/ 250V, single phase
2000
watts
heating
element,
thermostat control, fusible plug, pilot
lamp etc., erected and tested complete
with ISI specifications etc., including all
materials, transportation, and labour
charges complete.
a) Material
25 / 35 / 50 Ltrs. Water Heater
Transportation Charges on Unit Cost
Rate per Each
Labour charges for erection of storage
water heater with 2Nos Nylon / PVC /
Metalic hose pipe etc., on wall duly
making necessary fixing arrangments
including connections etc., complete.
a) Material
Flexible Nylon / PVC / Metallic hose
pipe
50 / 100 mm (2" / 4") long bolt and nut
with washers
Towards wooden plugs, cement etc.,
b) Labour charges.
Skilled Electrician
Helper
Semi skilled Mason
Rate per Each
Note : Labour is Considered for 4 jobs
/ day
INSTANT WATER HEATERS
each
1
2%
each
each
LS
day
day
day
0.25
0.5
0.25
each
1
2%
2
each
226
Bldngs_Elec10-3
10.4
10.4.1
10.4.2
10.4.5
Bldngs_Elec11
Bldngs_Elec11-1
11
11.1
LS
day
day
0.25
0.25
each
day
LS
0.2
each
day
LS
0.2
each
day
LS
0.2
Mono-Block Pumps
227
11.1.1
11.1.2
each
2%
day
day
day
LS
0.5
1
0.5
each
2%
day
day
0.5
1
228
11.1.3
11.1.4
Plumber
Sundries and rounding off
Rate per Each
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 1.5 HP exculding suction
/ delivery pipe with nuts duly grouted
on existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
1.5 HP, 230V, single phase A.C 50Hz.
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost
b) Labour charges.
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 2.0 HP exculding suction
/ delivery pipe with nuts duly grouted
on existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
2 HP, 230V, single phase A.C 50Hz.
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
day
LS
0.5
each
2%
day
day
day
LS
0.5
1
0.5
each
2%
day
day
day
0.5
1
0.5
229
11.1.5
11.1.6
LS
each
1
2%
day
day
day
LS
1
1
1
each
1
2%
day
day
day
LS
1
1
1
230
11.1.7
11.1.8
each
2%
day
day
day
LS
1
1
1
each
2%
day
day
day
LS
1
1
1
231
11.1.9
Bldngs_Elec11-2
11.2
11.2.1
each
1
2%
day
day
day
LS
1
3
1
each
each
2
2%
day
day
day
LS
0.5
1
0.5
232
11.2.2
11.2.3
each
each
2
2%
day
day
day
LS
0.5
1
0.5
each
each
2
2%
day
day
day
LS
0.5
1
0.5
233
11.2.4
11.2.6
each
each
2
2%
day
day
day
LS
0.5
1
0.5
each
each
2
2%
day
day
day
LS
0.5
1
0.5
234
11.2.7
Bldngs_Elec11-3
11.3
11.3.1
(a)
each
each
2
2%
day
day
day
LS
0.5
1.5
0.5
each
each
2
2%
day
day
day
LS
0.5
1
0.5
235
11.3.1
(b)
11.3.1 (c)
each
each
2
2%
day
day
day
LS
0.5
1
0.5
each
each
2
2%
236
11.3.2
11.3.3
day
day
day
LS
0.5
1
0.5
each
each
2
2%
day
day
day
1
2
1
LS
237
11.3.4
a) Material
3HP, 3 Ph 4 stage submerisible pump
set. Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 3 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump
set. Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
each
each
2
2%
day
day
day
1
2
1
LS
each
each
2
2%
day
day
day
1
2
1
LS
238
11.3.5
11.3.6
each
each
2
2%
day
day
day
1
2
1
LS
each
each
2
2%
day
day
1
2
239
11.3.7
11.3.8
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 6 stage submerisible pump
set including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 12 stages submerisible pump
set Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
day
LS
each
each
2
2%
day
day
day
1
2
1
LS
each
each
2
2%
240
11.3.10
11.3.11
day
day
day
1
2
1
LS
each
each
1
2
2%
day
day
day
2
3
1
LS
241
11.3.12
each
each
1
2
2%
day
day
day
2
3
1
LS
each
each
1
2
2%
day
day
day
2
3
1
LS
242
11.3.13
11.3.15
each
each
1
2
2%
day
day
day
2
3
1
LS
each
each
1
2
2%
day
day
day
2
3
1
243
11.3.16
11.3.17
LS
each
each
1
2
2%
day
day
day
2
3
1
LS
each
each
1
2
2%
244
Bldngs_Elec11-4
11.4
11.4.1
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
SUB MERSIBLE PUMPS (OPEN WELL)
Supply
and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant
dynamically
balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings, 3
HP pump erected with necessary Htype clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 3HP Submersible motor
Special clamps with nut and bolis
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
day
day
day
2
4
1
LS
each
each
1
2
2%
day
day
day
1
2
1
LS
245
11.4.2
11.4.3
Supply
and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant
dynamically
balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings, 5
HP pump erected with necessary Htype clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 5HP Submersible motor
Special clamps with nut and bolis
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply
and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant
dynamically
balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings,
7.5 HP pump erected with necessary
H-type clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 7.5HP Submersible motor
Special clamps with nut and bolis
each
each
1
2
2%
day
day
day
1
2
1
LS
each
each
1
2
246
11.4.4
Bldngs_Elec11-5
11.5
2%
1
2
1
1
2
2%
1
3
1
247
11.5.1
11.5.2
11.5.2(a)
11.5.3
each
day
day
0.33
0.33
each
day
day
0.33
0.33
248
11.5.4
11.5.5
each
day
day
0.5
0.5
each
each
day
day
0.5
0.5
each
each
day
day
0.5
0.5
249
11.5.6
11.5.7
Bldngs_Elec12
Bldngs_Elec13
12
13
13.1
Bldngs_Elec13-1
each
each
day
day
0.5
0.5
each
day
day
0.2
0.2
3.40 x 10
2.80 x 50
2.20 x 156
15.50 /
Tonne
12.00 /
Tonne
7.00 /
Tonne
Rate per Kg
D A T A F O R M . S S W A G E D P O L E S C O N F I R M I N G TO I.S : 2713 /1980
Data
No.
Specification of pole
length of pole.
as per IS 2713 / 1980
Overall
2
3
13.1.1
410 SP.2
13.1.2
410 SP.3
13.1.3
410 SP.5
13.1.4
410 SP.6
13.1.5
410 SP.11
13.1.6
410 SP.12
13.1.7
410 SP.26
13.1.8
410 SP.27
13.1.9
410 SP.41
13.1.10
410 SP.42
13.1.11
410 SP.50
13.1.12
410 SP.51
13.1.13
410 SP.59
13.1.14
410 SP.60
13.1.15
410 SP.73
13.1.16
410 SP.74
13.1.17
410 SP.77
13.1.18
410 SP.78
O.D and thickness
Pole in Kgs
of sections
Bottom
Middle
7 Mtrs.
7 Mtrs.
7.5 Mtrs.
7.5 Mtrs.
8 Mtrs.
8 Mtrs.
9 Mtrs.
9 Mtrs.
10 Mtrs.
10 Mtrs.
11 Mtrs.
11 Mtrs.
12 Mtrs.
12 Mtrs.
14.5 Mtrs.
14.5 Mtrs.
16 Mtrs.
16 Mtrs.
Weight of
Planting
depth in
mtrs.
Length of Sections
In Mtrs.
Botto Mid
Top
m
dle
5a
5b
5c
1.25
1.25
1.25
1.25
1.50
1.50
1.50
1.50
1.80
1.80
1.80
1.80
2.00
2.00
2.00
2.00
2.30
2.30
Weight of
Base plate
in Kgs.
4.00
4.00
4.50
4.50
4.50
4.50
5.00
5.00
5.20
5.20
5.60
5.60
5.80
5.80
6.50
6.50
7.00
7.00
Total
weigh
t in
Kgs.
1.50
1.50
1.50
1.50
1.75
1.75
2.00
2.00
2.40
2.40
2.70
2.70
3.10
3.10
4.00
4.00
4.50
4.50
Rate
/ Kg
inclu
ding
Tran
1.50
1.50
1.50
1.50
1.75
1.75
2.00
2.00
2.40
2.40
2.70
2.70
3.10
3.10
4.00
4.00
4.50
4.50
Total
cost
of
pole
251
Top
6a
114.3x4.5
114.3x5.4
114.3x4.5
114.3x5.4
114.3x4.5
114.3x5.4
114.3x45
114.3x5.4
139.7x4.85
139.7x5.4
139.7x4.85
139.7x5.4
165.1x4.85
165.1x5.4
193.7x5.4
193.7x5.9
193.7x5.4
193.7x5.9
Bldngs_Elec13-2
13.2
13.2.1
13.2.2
Bldngs_Elec-
13.3
6b
88.9x4.05
88.9x4.85
88.9x4.05
88.9x4.85
88.9x4.05
88.9x4.85
88.9x4.05
88.9x4.85
114.3x4.5
114.3x4.5
114.3x4.5
114.3x4.5
139.7x4.5
139.7x4.5
165.1x4.85
165.1x5.4
165.1x4.85
165.1x5.4
6c
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
88.9x3.25
88.9x3.25
88.9x3.25
88.9x3.25
114.3x3.65
114.3x3.65
139.7x4.50
139.7x4.50
139.7x4.50
139.7x4.50
7
73
85
79
93
83
97
92
108
135
144
147
164
197
208
312
336
341
367
8
5
5
5
5
5
5
5
5
5
5
5
5
5
5
10
10
10
10
9
78
90
84
98
88
102
97
113
140
149
152
169
202
213
322
346
351
377
Kg
24.8
Kg
37.2
spor
tatio
n
and
Fabr
icati
on
10
11
Garden Posts
Fabrication and Supply of M.S. Poles
for garden posts with 'B' class 4mtrs
long 60.25mm outer dia with base
plate and suitable pole cap including
cost and conveyance of all material
including fixing of luminaire and labour
charges etc., complete.
a) Material
4Mtrs 'B' Class M.S. pipe of 60.25mm
dia with base plate and suitable pole
cap
Rate per Each
Fabrication and Supply of M.S. Poles
for garden posts with 'B' class 6 mtrs
long 60.25mm outer dia with base
plate and suitable pole cap including
cost and conveyance of all material
including fixing of luminaire and labour
charges etc., complete.
a) Material
6Mtrs 'B' Class M.S. pipe of 60.25mm
dia with base plate and suitable pole
cap
Rate per Each
Brackets
252
13-3
13.3.1
13.3.2
13.3.3
Kg
Kg
job
2.55
5.4
1
day
day
0.2
0.2
Kg
Kg
job
5.1
5.4
1
day
day
0.33
0.33
Kg
Kg
job
7.65
5.4
1
day
day
0.5
0.5
253
13.3.4
13.3.5
13.3.6
Kg
Kg
job
5.1
5.4
1
day
day
0.2
0.2
Kg
10.2
Kg
job
5.4
1
day
day
0.33
0.33
Kg
15.3
Kg
job
5.4
1
day
0.5
254
13.3.7
13.3.8
13.3.9
Helper
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
1.5 Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
2 x 1.5Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 1.5Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
day
0.5
Kg
7.65
Kg
job
5.4
1
day
day
0.2
0.2
Kg
15.3
Kg
job
5.4
1
day
day
0.33
0.33
Kg
22.95
Kg
job
5.4
1
255
13.3.10
13.3.11
day
day
0.5
0.5
Kg
7.65
Kg
job
5.4
1
day
day
job
0.2
0.2
1
Kg
15.3
Kg
job
5.4
1
day
day
job
0.33
0.33
1
256
13.3.12
Bldngs_Elec13-4
13.4
13.4.1
Kg
22.95
Kg
job
5.4
1
day
day
job
0.5
0.5
1
cum
0.54
cum
cum
M
0.54
0.054
6.2
each
day
day
day
0.33
2.67
0.33
257
13.4.2(a)
13.4.2(b)
cum
0.72
cum
cum
M
0.72
0.054
8.35
each
day
day
day
0.33
2.67
0.33
cum
cum
cum
M
2
2
0.054
12
each
day
day
day
0.5
4
0.5
258
13.4.3
13.4.4
cum
cum
cum
M
2.3
2.3
0.054
14
each
day
day
day
0.5
4
0.5
6.2
each
Kg
1
3.54
cum
0.135
day
day
day
kgs
0.33
2.67
0.33
3.54
259
13.4.5
13.4.6
13.4.7
cum
M
0.16
2.5
cum
0.16
day
day
0.2
0.4
cum
cum
M
0.25
0.25
4.75
day
day
0.2
0.4
Kg
29.07
Kg
13
Kg
13
260
Bldngs_Elec13-5
13.5
13.5.1
13.5.2
13.5.3
each
Job
12
1
day
day
0.5
4
sqm
0.35
sqm
0.29
each
each
1
1
day
0.066
261
13.5.4
Bldngs_Elec14
Bldngs_Elec14-1
14
each
each
2
1
day
0.066
kg
1.56
14.1
14.1.1
1)
14.1.2
CONTROL PANEL
Supply, Transportation, fabrication and
erection of following guage CRCA sheet
steel enclosure for power control
cubicle panel / boxes etc., including
cutting, bending drilling, welding and
reveting etc., complete with cleaning
with 7 tank process and painting with
powder coating including cost and
conveyance of all materials and labour
charges.
14 SWG CRCA sheet steel enclosure
a) Material
14 SWG (2mm) CRCA sheet - 1 sft (Wt
of 8 x 4 feet sheet, 50Kg)
Transportation charges on Material
cost
Fabrication including cutting, bending,
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank
process
Painting with powder coating.
Erection charges
Sundires such as hardware etc.,
Rate per sft
Rate per sqm
16 SWG CRCA sheet steel enclosure
a) Material
16 SWG (2mm) CRCA sheet - 1sft (Wt
of 8 x 4 feet sheet, 39Kg)
Transportation charges
Fabrication including cutting, bending,
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank
process
Painting with powder coating.
Erection charges
2%
30%
40%
40%
30%
kg
1.218
2%
30%
40%
40%
30%
262
14.1.3
Bldngs_Elec14-2
14.2
14.2.1
14.2.2
14.2.3
kg
0.937
2%
30%
40%
40%
30%
each
day
0.2
each
day
0.2
each
263
14.2.4
14.2.5
14.2.6
14.2.7
day
0.2
each
day
0.2
each
day
0.33
each
day
0.2
each
264
14.2.8
14.2.9
14.2.10
Skilled Electrician
Rate per Each
Note : Labour is Considered for 10
jobs / day
Supply and erection of LT current
transformer with bar primary 100/5A
to 1000 / 5A ratio in the existing box /
panel including connections etc.,
complete.
a) Material
L.T. C.T with bar primary 100 / 5A to
1000 / 5A
b) Labour charges for fixing and
connections.
Skilled Electrician
Rate per Each
Note : Labour is Considered for 10
jobs / day
Supply and fixing of single phase
energy Meter,240V AC,50 HZ as per
IS13010 with 2.5-5 /5-10/10-20 Amps
range with 200% over load capacity
complete with connections etc.,
complete on the existing board.
a) Material
cost of single phase energy meter
b) Labour charges for fixing and
connections.
Skilled Electrician
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and fixing of three phase
energy Meter,415V AC,50 HZ as per
IS13010 with 2.5-5 /5-10/10-20 Amps
range with 200% over load capacity
complete with connections etc.,
complete on the existing board.
a) Material
Cost of three phase energy meter
b) Labour charges for fixing and
connections.
Skilled Electrician
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Bldngs_Elec15
Bldngs_Elec15-1
day
0.1
each
day
0.1
each
day
0.33
each
day
0.33
15
15.3
265
15.3.1
15.3.2
15.3.3
15.3.4
each
day
0.066
each
day
0.066
each
day
0.066
each
day
0.066
266
15.3.5
15.3.6
15.3.7
15.3.8
each
day
0.066
each
day
day
0.066
0.066
each
day
day
0.066
0.066
each
day
day
0.066
0.066
267
15.3.9
15.3.10
15.3.11
15.3.12
each
day
day
0.083
0.083
each
day
day
0.083
0.083
each
day
day
0.083
0.083
each
268
15.3.13
Bldngs_Elec15-2
day
day
0.1
0.1
each
day
day
0.1
0.1
each
day
day
0.01
0.01
each
day
day
0.01
0.01
15.4
15.4.1
15.4.2
CABLE LUGS:
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable upto 16 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 16 Sq.mm.
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 25 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 25 Sq.mm.
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
269
15.4.3
15.4.4
15.4.5
15.4.6
each
day
day
0.013
0.013
each
day
day
0.013
0.013
each
day
day
0.013
0.013
each
day
day
0.016
0.016
270
15.4.7
15.4.8
15.4.9
15.4.11
each
day
day
0.02
0.02
each
day
day
0.033
0.033
each
day
day
0.033
0.033
each
day
day
0.04
0.04
271
15.4.12
15.4.13
15.4.14
15.4.15
each
day
day
0.05
0.05
each
day
day
0.062
0.062
each
day
day
0.01
0.01
each
1
272
15.4.16
15.4.17
15.4.18
day
day
0.01
0.01
each
day
day
0.013
0.013
each
day
day
0.013
0.013
each
day
day
0.013
0.013
273
15.4.19
15.4.20
15.4.21
15.4.22
each
day
day
0.016
0.016
each
day
day
0.02
0.02
each
day
day
0.04
0.04
each
day
day
0.04
0.04
274
15.4.24
15.4.25
15.4.26
Bldngs_Elec15-3
15.5
each
day
day
0.04
0.04
each
day
day
0.05
0.05
each
day
day
0.062
0.062
275
15.5.1
(a)
(b)
(c )
(d)
each
day
day
0.5
0.5
each
day
day
0.5
0.5
each
day
day
0.5
0.5
each
day
day
0.5
0.5
276
(e)
(f)
(g)
Bldngs_Elec15-4
15.6
15.6.1
each
day
day
1
1
each
day
day
1
1
each
day
day
1
1
cum
1000 Nos
27
0.92
cum
Kg
each
LS
6
25
12
each
2.5
day
1
277
15.6.2
15.6.3
Helper
Man Mazdoor for concreting and
embedding of cable way indicators
Sundires and Rounding off
Rate per 100mts
Note : Labour Charges Considered for
100 Mts / day
Earth work excavation of Trench in
hard ground soil, laying of U.G cables
from 70 sqmm to 400 Sq,mm on sand
cushion covering the cable with bricks
and back filling of Trench duly
providing route indicator embedded in
C.C including cost and conveyance of
materials and labour charges etc.,
complete.
a) Material
Excavation of earth 100 x 0.3 X 0.9 m
Cost of bricks (Civil SSR)
day
day
2
2
cum
1000 Nos
27
0.92
each
100 nos
100 nos
kg
200
2
4
7
278
15.6.4
Bldngs_Elec16
16
Bldngs_Elec17
17
b) Labour charges
Skilled Electrician
Helper
Sundires such as Cement, Sand etc.,
Rate per Each
Note : Labour Charges Considered for
100 Mts / day
Supply and laying of one number
double walled corrugated (DWC) HDPE
pipe of following sizes having
corrugation on the outer wall and plain
surface inner wall confirming to IS :
14930 Part - I and II complete with
necessary HDPE fittings for protection
of 1.1 KV grade U.G cable directly in
ground at a depth of 60Cms including
excavation and refilling the trench as
required.
a) 50mm outer dia nominal size
b) 78mm outer dia nominal size
c) 90mm outer dia nominal size
d) 120mm outer dia nominal size
a) Material
Double wall corrugated HDPE pipe
confirming to IS : 14930.
Snap-fit coupler
Excavation of earth work & Refilling for
a size of 1.0x0.3x0.6Mtr.
Rate per Metre
day
day
1
4
RM
each
cum
1
0.18
TEMPORARY ILLUMINATION
data shown seperately at the end.
Bldngs_Elec17-1
A
17.1
17.1.3
(a)
17.1.3
(b)
Switch
3. MCCB / MCB incomer of suitable rating
4. P.F. Meter and frequency
Meter
5. Indication Lamp Set
6. KWH Meter of required
rating
7. Instrument and control fuses.
ACOUSTIC ENCLOSURE
Supply & providing & installation of acoustic enclosure (sound proof enclosure
cum container) for the above Genset with the following specification.
Construction : The panel of acoustic enclosure shall consists of self supporting
frame work put together with help of fasteners, which is for assembling and
dismantling. The vertical and Horizontal structure 8is to be fabricated with
14/16 SWG CRCA sheet and should be fixed on heavy duty MS Channel which
will form the base frame of the acoustic enclosure. the paneling of ht container
is to be carried out using 18 SWG CRCA sheets. the enclosure should be self
supporting type and does not require any grouting or separate foundation. But
it should be the independent of the DG set and to placed around the DG set.
The frame work shall also have provision for fitting hinged / sliding doors to
open either sides of the enclosure.
Generating Sets
Supply, Transportation, erection of 3
Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz.,
D.G.Set.
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2% on unit cost
Sundires and Rounding off
Rate per Each
Supply, Transportation, erection of 3
Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz.,
D.G.Set
cost of acoustic enclosure
Erection and commissioning charges :
the
cost of the DG set.
cost
of acoustic enclosure
Transportation at 2% on unit cost
Sundires and Rounding off
Rate per Each
each
1
10%
2%
each
each
1
10%
5%
2%
280
17.1.3 (c)
17.1.3
(d)
17.1.3
(e)
17.1.3 (f)
each
1
10%
2%
each
each
1
10%
5%
2%
each
1
10%
2%
each
each
1
1
10%
281
17.1.3
(g)
17.1.3
(h)
17.1.3 (i)
17.1.3 (j)
cost
of acoustic enclosure
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation , erection of 3
Phase Water cooled / Air Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., as per
specifications mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation , erection of 3
Phase Water Cooled / Air-Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., with
acoustic enclosure as per specifications
mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set
Cost of Acoustic enclosure
Erection and commissioning charges :
the
cost of the DG set.
cost
of acoustic enclosure
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation , erection of 3
Phase Water cooled 125 KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., as per specifications
mentioned above.
a) Material
125KVA, Water Cooled, 3Ph, 415V
D.G.Set.
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation, erection of 3
Phase Water-Cooled 125KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., with acoustic enclosure as
per specifications mentioned above.
5%
2%
each
1
10%
2%
each
each
1
1
10%
5%
2%
each
1
10%
2%
a) Material
282
Bldngs_Elec17-2
17.2
17.2.1
(a)
each
each
1
10%
5%
2%
(b)
2%
10%
each
(c )
2%
10%
283
a) Material
each
(d )
2%
10%
each
(e)
10%
10%
1
2%
10%
each
(h)
1
2%
each
(g)
1
2%
each
(f)
1
2%
10%
each
(i)
2%
10%
each
(j)
2%
10%
each
Bldngs_Elec17-3
17.3
17.3.7
1
2%
10%
each
each
each
each
1
1
1
1
2%
5%
285
17.3.8
17.3.9
Bldngs_Elec17-4
17.4
17.4.1
each
each
each
each
1
1
1
1
2%
5%
each
each
each
each
1
1
1
1
2%
5%
each
286
17.4.2
17.4.3
17.4.4
17.4.5
17.4.6
Dielectric
150%
each
each
each
set
1
1
each
sqm
1
0.5
cum
0.13
287
17.4.7
17.4.8
17.4.9
kg
17.5
50%
each
each
day
0.2
each
each
day
0.2
288
17.4.10
17.4.11
kg
20.97
kg
4.25
sqm
kg
2.4
25.22
cum
0.018
sqm
5.88
kg
8.74
cum
0.018
10%
289
17.4.12
Bldngs_Elec17-5
RM
14
kg
20.06
kg
43.7
kg
33.32
each
sqm
each
kg
1
5.55
1
118
sqm
5%
17.5
17.5.1
(a)
SUB-STATION MAINTENANCE
Filteration of transformer oil as per ISS
for removal of moisture, carbon slurry
etc. by means of circulating oil
through vaccum pump from heating
elements and filters to withstand the
dielectric strength of the oil above
40KV beyond one minute tested in oil
testing Kit.
On site.
a) Material
Labour charges for filterations at site
Data
shall be
arrived
based on
observed
Data
290
17.5.1
(b)
17.5.3
17.5.4
Data
shall be
arrived
based on
observed
Data
3
3
6
a) Material
Removing all the doors of switches,
busbar chamber and back doors.
Clearing by using power blower.
Tightening all the terminations and
cleaning and servicing the contacts of
switches.
291
2
1
2
17.6
17.6.1
17.6.3
17.6.5
PROTECTIVE GEAR
Supply and erecting approved make
11KV, 5KA metal oxide
lightning
arrestors suitable for 11 KV supply with
necessary materials on existing cross
arm.
a) Material
Cost of 11 KV 5KA metal oxide lighting
arrester.
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is considered for 3 jobs /
day
Supply and erecting porcelain disc type
insulator suitable for 11KV line with
suitable hardware on existing cross
arms.
a) Material
Cost of porcelain disc type insulator
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day
Supply and erecting porcelain pin type
insulator suitable for 11KV line with
suitable hardware on existing cross
arms.
a) Material
Cost of porcelain pin type insulator
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day
each
day
day
0.33
0.33
each
day
day
0.125
0.25
each
day
day
0.125
0.25
292
17.6.6
17.6.8
17.6.10
each
day
day
0.125
0.25
each
day
day
1
1
each
day
day
day
1
1
1
293
17.6.11
17.6.12
17.6.13
17.6.14
each
day
day
day
1
1
1
each
day
day
day
1
1
1
each
day
day
1
1
Kvar
294
17.6.15
Skilled Electrician
Helper
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs /
day
Supply and erecting of bank of
mixdielectric condensors with the
standard capacities of 2,3,5,7,10,12.5
and 15 KVAR units for PF correction for
operation on 3 phase 50 cycles
400/440V (+10%) with externally
discharging
resistances,
earthing
terminals etc., complete.
a) Material
Cost of of mixed Dielectric capacitor
operation on 3 Ph. 415V.
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs /
day
Bldngs_Elec18
0.04
0.08
Kvar
day
day
0.04
0.08
kg
0.3
18
18.1.1
Bldngs_Elec18-1
day
day
50%
100%
40%
kg
0.3
295
18.1.2
18.1.3
18.1.4
kg
0.2
50%
100%
40%
kg
0.2
kg
0.05
50%
100%
40%
kg
0.05
kg
0.45
50%
100%
296
18.1.5
18.1.6
18.1.7
40%
kg
0.45
kg
2.7
5%
12%
2%
kg
2.7
kg
3.2
5%
12%
2%
kg
3.2
kg
4.5
297
18.1.8
18.1.9
5%
12%
2%
kg
4.5
kg
5.7
5%
12%
2%
kg
5.7
kg
6.5
5%
12%
2%
kg
6.5
298
18.1.10
18.1.11
18.1.12
kg
10
5%
12%
2%
kg
10
kg
12
5%
12%
2%
kg
12
kg
15
5%
299
18.1.13
18.1.14
Bldngs_Elec18-2
12%
2%
kg
15
kg
18
5%
12%
2%
kg
18
kg
18
10%
15%
5%
kg
18
18.2
Bearings
300
18.2.1
18.2.2
50%
each
1
50%
18.2.4
18.2.3
each
each
1
50%
each
301
18.2.5
18.2.6
18.2.7
18.2.8
50%
each
1
50%
each
1
50%
each
1
50%
each
302
day
0.1
303
12
12.1
12.1.1
BUS BARS
Copper Bus Bars
Supply and fabrication and erection of following sizes of 4Nos of copper bus bars in the existing sheet steel enclosure with resin cast
insulator supports etc., complete including cost and conveyance of all materials all labour charges.
D.No.
No.of 1
mtr
bars
Current
rating in
each bar
Weight /
mtr in Kg
a
b
20x3
20x6
4 Nos
4 Nos
220A
300A
0.529 Kg
1.072
25x3
4 Nos
270A
0.663
25x6
4 Nos
350A
1.34
30x6
4 Nos
400A
1.608
40x6
4 Nos
520A
2.144
50x6
4 Nos
630A
2.68
60x6
4 Nos
760A
3.216
75x6
4 Nos
970A
4.02
100x6
4 Nos
1380A
5.36
Rate per Kg
Cost of
copper
bars
Cost of
8Nos.
Resin cast
insulator.
@ Rs.35/Each
Total
Amount
mtr
Rounding
off
304
12.2
12.2.1
Aluminum Bus
Bars
Supply and fabrication and erection of following sizes of 4Nos of aluminum bus bars in the existing sheet steel enclosure with resin
cast insulator supports etc., complete including cost and conveyance of all materials all labour charges.
D.No.
No.of 1
mtr
bars
Current
rating in
each bar
Weight /
mtr in Kg
20x3
4 Nos
145A
0.161 Kg
20x6
4 Nos
195A
0.322
25x3
4 Nos
180A
0.201
25x6
4 Nos
230A
0.402
40x6
4 Nos
350A
0.644
50x6
4 Nos
425A
0.805
60x6
4 Nos
500A
0.966
75x6
4 Nos
680A
1.207
100x6
4 Nos
900A
1.61
Rate per Kg
Cost of
copper
bars
Cost of
8Nos.
Resin cast
insulator.
@ Rs.35/Each
Total
Amount
mtr
Rounding
off
Note : Labour charges are as per the rates allowed for Copper bus bar since, there is no difference in the requirement of Labour
305
Data
No.
1
16
16.1
16.2
Mainten
ance
50% of
deprecia
tion
Interest
@ 12%
on
Capital
cost/days
in a year
Description
Capital Cost
Life in
days
Depreciation:
Capital cost
/Life in days
2
TEMPORARY ILLUMINATION
Hire
charges
for
Temporary
illumination, consisting of 6.2 strip
lights (navar patta) complete with
1000 Nos required wire leads duly
erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of 6.2 strip
lights (navar patta) complete with
1000 Nos required wire leads duly
erected
and
dismantled
with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
1000 Nos
bulbs & 30
Mtrs 7/20
service wire
1 year i.e
60 days
1.Skill
electrician
1.Helper
1000 Nos
bulbs & 30
Mtrs 7/20
service wire
1 year i.e
60 days
1.Skill
electrician
1.1Helper
Labour
charges
Storage
charges
@ 1%
on
capital
cost/N
o.of
days in
a year
9
Transport
ation
charges @
2% on
capital
cost/No.o
f days in a
year
Hire
charges
per day
10
11
306
16.3
16.4
16.5 a
16.5 b
Hire
charges
for
Temporary
illumination, consisting of tube light
with patti type 4'-40W complete with
required wire leads duly erected and
dismantled
without
scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire
charges
for
Temporary
illumination, consisting of tube light
with patti type 4'-40W complete with
required wire leads duly erected and
dismantled with scaffolding including
cost and conveyance of all materials
and labour charges etc., complete for
one day.
Hire
charges
for
Temporary
illumination, consisting of flood light
1000W hallogen with lamp complete
with required wire leads duly erected
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire
charges
for
Temporary
illumination, consisting of flood light
500W hallogen with lamp complete
with required wire leads duly erected
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
1 No tube
light, 4 Mtrs
7/20 service
wire
3years i.e
3 x 60 =
180 days
0.06 Skill
electrician
0.06Helper
1 No tube
light, 4 Mtrs
7/20 service
wire
3years i.e
3 x 60 =
180 days
0.06 Skill
electrician
0.10Helper
1 No 1000W
Halogen, 30
Mtrs 7/20
service wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.25Helper
1 No 500W
Halogen, 30
Mtrs 7/20
service wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.25Helper
307
16.5 c
16.5 5
16.6 a
16.6 b
Hire
charges
for
Temporary
illumination, consisting of flood light
250W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of flood light
400W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of flood light
1000W hallogen with lamp complete
with required wire leads duly erected
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire
charges
for
Temporary
illumination, consisting of flood light
500W hallogen with lamp complete
with required wire leads duly erected
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
1 No 250W
Metal halide,
30 Mtrs
7/20 service
wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.25Helper
1 No 400W
Metal halide,
30 Mtrs
7/20 service
wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.25Helper
1 No 1000W
Halogen, 30
Mtrs 7/20
service wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.30Helper
1 No 500W
Halogen, 30
Mtrs 7/20
service wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.30Helper
308
16.6 c
16.6 d
16.7
16.8
Hire
charges
for
Temporary
illumination, consisting of flood light
250W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of flood light
400W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of white /
colour series light 6.2v complete with
1000 Nos. with required wire leads
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of white /
colour series light 6.2v complete with
1000 Nos. with required wire leads
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
1 No 250W
Metal halide,
30 Mtrs
7/20 service
wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.30Helper
1 No 400W
Metal halide,
30 Mtrs
7/20 service
wire
3years i.e
3 x 60 =
180 days
0.25 Skill
electrician
0.30
Helper
1000 Nos
bulbs & 30
Mtrs 7/20
service wire
1 year i.e
60 days
0.5 Skill
electrician
0.5Helper
1000 Nos
bulbs & 30
Mtrs 7/20
service wire
1 year i.e
60 days
0.5 Skill
electrician
1.0 Helper
309
16.9
16.10
16.1
16.12
Cost of 10
KW rotating
machine
5 years
i.e 5 x 30
= 150
days
0.25
Helper
18" pedestal
fan, 30
Mtrs 7/20
service wire
3years i.e
3 x 40 =
120 days
0.10
Helper
Air cooler,
30 Mtrs
7/20 service
wire
3years i.e
3 x 40 =
120 days
0.20 semiskilled
electrician
Air
conditioned,
stabilizer
8years
i.e. 8 x 15
= 120
days
1 skilled
electrician,
2 Helpers,
1 carpenter
310
16.1
16.14 a
16.14 b
16 Amps 5 in
one power
plug, 30
Mtrs 7/20
service wire
3years i.e
3 x 40 =
120 days
0.05 semiskilled
electrician
125 KVA DG
Set, 200
Amps main
switch
10years
i.e 10 x
60 = 600
days
1.Skill
Electrician
82.5 KVA DG
Set, 200
Amps main
switch
10years
i.e 10 x
60 = 600
days
1.Skill
Electrician,
311
16.14 c
16.14 d
16.14 e
16.2
1.Skill
Electrician,
1.Skill
Electrician,
1.Skill
Electrician,
1.Skill
Electrician,
312
16.16 a
16.16 b
16.16 c
16.16 d
16.16 e
16.16 f
16.16 g
2 of 6 sq mm
WPTC cable
1 mtr
3years i.e
3 x 60 =
180 days
0.015
Helper
2 of 10 sq
mm WPTC
cable 1 mtr
3years i.e
3 x 60 =
180 days
0.02
Helper
35 sq mm x
3 1/2 UG
cable 1 mtr
3years i.e
3 x 60 =
180 days
0.05
Helper
50 sq mm x
3 1/2 UG
cable 1 mtr
3years i.e
3 x 60 =
180 days
0.05
Helper
95 sq mm x
3 1/2 UG
cable 1 mtr
3years i.e
3 x 60 =
180 days
0.05
Helper
120 sq mm x
3 1/2 UG
cable 1 mtr
3years i.e
3 x 60 =
180 days
0.05
Helper
185 sq mm x
3 1/2 UG
cable 1 mtr
3years i.e
3 x 60 =
180 days
0.05
Helper
313
16.2
16.18 a
16.18 b
16.18 c
250 Amps
bus bar, 250
TPN/MCCB,
12 nos 100
Amps fuse
units
10years
i.e 10 x
15 = 150
days
0.5 Skilled
electrician,
1 Helper
100 Amps
COS/ TPN
10years
i.e 10 x
15 = 150
days
0.125
Skilled
electrician,
0.125
Helper
200 Amps
COS/ TPN
10years
i.e 10 x
15 = 150
days
0.125
Skilled
electrician,
0.125
Helper
400 Amps
COS/ TPN
10years
i.e 10 x
15 = 150
days
0.2 Skilled
electrician,
0.2 Helper
314
16.19 a
16.19 b
0.5 fitter,
0.5 skilled
electrician,
2 Helpers,
54 Cum.
0.5 fitter,
0.5 skilled
electrician,
2 Helpers,
54 Cum.
315
STANDARD DATA-ANNEXURE
ORDER:
The basic components for preparing any estimate are Standard Specifications, Standard Data,
and Schedule of Rates for construction materials, skilled and un-skilled labour and hire charges of
machinery utilized on works. To get the work done, as per the standard specifications, required
quantities of recommended materials, requirement of specific need based manpower, deployment of
proper utility based machinery and duration of its utilization are to be observed and quantified for
each unit of work, and this is called Standard Data. Thus, the Standard Data gives the details of
various inputs in terms of quantities required for one Unit of any work. Schedule of rates for material,
skilled and unskilled labour are fixed and revised by the Board of Chief Engineers once in a year and
these are called Standard Schedule of Rates. When the Standard Schedule of Rates and Hire charges
of machinery are incorporated in the inputs of Standard Data and Standard Schedule of Rates it will
have direct bearing on the preparation of project Estimates and consequent finalization of Tenders.
2. The existing AP Standard Data for various construction items were based on observations made
several decades back mostly by utilizing manpower for execution of all items of works, and
deployment of machinery was at the barest minimum. The advent of latest machinery and their
extensive use has changed the structure and methodology of data formulation and rate structure.
There is a need to revise the present Standard Data for all items of worksdealing with Public works.
Realizing the urgency and importance to haverealistic data, Government in the GO.Rt.No.7326 G.A
(GPM & AR) Departmentdated 26-10-2005 constituted a High Level Committee under the
chairmanshipof Special Chief Secretary, General Administration (GPM&AR) Department, to advise on
Updating and Revising the A.P.Standard Data. A project for Standard Data (revision) and Schedule of
Rates was conceived and entrusted to the Centre for Good Governance. Keeping in view the strategy,
factors considered and classification of works, a number of High Level Committee meetings and
review meetings were conducted at Centre for Good Governance/ A.P.Secretariat and in the offices of
concerned Engineers-in-Chief I&CAD, Public Health, Panchayati Raj and Roads & Buildings
Departments etc. Their specific views, suggestions and recommendations were taken into account,
besides collecting the data from various sources while finalizing the Draft AP standard Data and
Standard Schedule of Rates. This has been cleared by the Board of Chief Engineers and finally by the
High level Committee. The Standard Data has been revised and updated in four parts considering
nature of work, location of work and magnitude of work as indicated below.
1. PART I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
3.
The revision of Standard Data and Schedule of Rates in respect of works items of Irrigation
Department has been taken up by the SPIU (Irrigation) and completed as per the C.W.C guidelines and
B.I.S standards and also observations and recommendations made by the High Level Committee. In
316
STANDARD DATA-ANNEXURE
respect of other Departments, MORTH data is adopted for Roads & Bridges, where higher capacity
machinery can be deployed and MORD data is adopted for Roads & Bridges in Rural areas. For other
works data as per MORTH, MORD, and C.P.W.D. etc., is adopted. The comparative estimates have
been prepared by the T.R. &B Dept. , Engineering-in-Chief (Irrigation) and MA & UD Department for
various types of works of a magnitude of Rs.15-20 crores, based upon the earlier data and the newly
revised and proposed data .
4.
After detailed deliberations and discussion on the above issue, the Govt. accept the
recommendations of Board of Chief Engineers and High level Committee and accordingly issue the
orders for adoption of the Revised and Updated Standard data in all Engineering/ Public works
Department and other organisations in four parts considering nature of work, location of work and
magnitude of work as indicated below. The four parts of Standard Data booklets are forwarded to
Engineer-in-Chief (AW), who in turn will publish the authenticated version and circulate a copy to all
works Departments.
1. PART I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
5.
The Revised Data now approved is to be adopted by all Engineering Departments/ all Public
Works Department and other organisations, duly superseding all the earlier orders issued on the
subject. 6. These orders shall come into force from the date of issue.
7.
This order issues with the concurrence
U.O.No.5532/520/Exp.PW.I Dept/08, dated 13-5-2008.
of
Finance
Department
vide
their
317