Professional Documents
Culture Documents
Project Close-Out Participant Manual - BUILT
Project Close-Out Participant Manual - BUILT
Participants Manual
(B.U.I.L.T)
Business Unit Instructor Led Training
Table of Contents
Course Overview............................................................................... PM p. 1
Topic 1: Project Launch .................................................................. PM p. 13
Topic 2: Start of Construction.......................................................... PM p. 23
Topic 3: 25% Complete ................................................................... PM p. 30
Topic 4: 50% Complete ................................................................... PM p. 40
Topic 5: 75% Complete ................................................................... PM p. 51
Topic 6: 95% Complete ................................................................... PM p. 63
Topic 7: 98% Substantial Completion ............................................. PM p. 72
Topic 8: Final Completion ............................................................... PM p. 81
Topic 9: Post Construction .............................................................. PM p. 89
Wrap Up .......................................................................................... PM p. 97
Project Close-Out
Presentation
(B.U.I.L.T)
Business Unit Instructor Led Training
Version 1.0
PM p. 1
Course Overview
Welcome
Introductions
Ground rules
Quick Question
Course Objectives
Course Outline
Warm up
PM p. 2
Introductions
Name
Current position
Project or department
PM p. 3
Ground Rules
Safety first
No cell phones, text messaging, or e-mail.
Breaks timing and frequency.
Return from breaks on time.
PM p. 4
Quick Question
At what point during a construction project does
close-out start?
A. 25% construction
B. 50% construction
C. 75% construction
D. none of the above
_______________________________!
PM p. 5
PM p. 6
Course Objectives
By the time you finish this course, you
will be able to:
Think Close-out!
PM p. 7
Course Outline
Topic 1
Topic 2 Topic 3
Topic 4
Topic 5
Topic 6
Project:
The Dunn-Wright Building
PM p. 8
Warm-up
What are the expectations for close-out?
For owners?
For the architect?
For Turner?
For the subcontractors?
What do we
expect?
PM p. 9
10
PM p. 10
Close-Out Process
11
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
PM p. 11
100%
90%
80%
70%
60%
Teamwork = CloseClose-out
50%
40%
30%
20%
10%
Financials
Engineering
Field
12
PM p. 12
13
PM p. 13
Topic 1: Launch
Project Launch
Preconstruction & Procurement
14
PM p. 14
Topic 1: Launch
e.docsTM
Owners Web-based Digital Facilities
Manual
15
PM p. 15
Topic 1: Launch
Turner e.docsTM
Owners web-based digital
facilities manual
Simple, quick & easy access
No physical storage space
required
IntuitiveStaff will use
& like it!
Tool serves as on-going
information depository
Industry best practice!
16
PM p. 16
Quick Question
What does it mean to set strategy?
17
Setting Strategy:
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
____________________________________________________________
PM p. 17
Topic 1: Launch
Close-Out Strategy
Set close-out goals.
Make detailed plan.
Include punch-list procedure.
18
PM p. 18
Topic 1: Launch
19
PM p. 19
Participant worksheet
Exercise: Set Close-Out GoalsDunn-Wright Building
Discuss the following items as a team. Write down your answers on the flipchart, and
identify one person on your team who will present your conclusions to the entire group:
1. Each person at the table will assume the role of a key Turner project jobsite team
member. For this exercise, think and act as if you were assigned to this role on this
project. Starting with the person whose birthday is closest to today, and then going
around the table clock-wise, assign roles as follows: (Note: The roles are listed in priority
order, so if there are four people at the table, assign the first four; if five, assign the first five, and so forth.)
2. As a project team, define your close-out goals. What do you want to accomplish in:
Best Practices What will you do that has worked well in the past?
______________________________________________________________
Pitfalls What will you avoid that has caused problems in the past?
_____________________________________________________________
3. Now that you have identified your goals, what are your first steps getting started?
______________________________________________________________________
______________________________________________________________________
PM p. 20
Topic 1: Launch
Client Expectations
What is your goal for providing a quality close-out
product?
Internal Expectation
What do you expect of each team member?
Best Practices
What will you do that has worked well in the past?
Pitfalls
What will you avoid that has caused problems in the
past?
21
Topic 1: Launch
Key Learnings
22
PM p. 21
Topic 1: LaunchReview
Name three things you have learned
about close-out activities during
launch.
23
1.
2.
3.
PM p. 22
24
PM p. 23
25
PM p. 24
26
PM p. 25
27
PM p. 26
Other Tools
Detailed submittal delivery schedule
Subcontractor kickoff meeting
Subcontractor Billing Schedule of Values
Close-out documentation
Punch list completion
For CCIP projects, Insurance Cost amount shown on
Form 36, Article 23
28
PM p. 27
PM p. 28
Quick Review
1. What is included in the Contract Items List (CIL)?
2. When should it be compiled?
3. Who should review the CIL?
4. What is the Submittal Log?
5. Are all items on the Submittal Log included in the CIL?
6. To whom should the detailed submittal delivery
schedule be submitted and why?
29
PM p. 29
30
PM p. 30
31
PM p. 31
Quick Question
What do you do about identifying subcontractors
for early close-out if the contract prohibits it?
32
Answer:
____________________________________________________________
____________________________________________________________
____________________________________________________________
PM p. 32
33
PM p. 33
36
Top
Topicic3:3: 25%
25%Co
Compl
mplete
ete
Key
Key Tool:
Tool: Close-Out
Close-Out Matrix
Matrix (continued)
(continued)
Field
Field
Engineering
Engineering
Financials
Financials
Project
Project Close-out--Sept.
Close-out--Sept. 2009
2009
34
34
PM p. 34
100%
90%
80%
70%
60%
Teamwork = Close-out
50%
40%
30%
20%
10%
Financials
Engineering
Field
35
PM p. 35
Other tools
Establish close-out files.
Identify early close-out subcontractors.
Keep current with subcontractor change orders.
Write subcontractor change orders by time period.
36
PM p. 36
O&M Manuals
Establish expectations with client for format,
review and approvals.
Paper, electronic, or both?
Reviewed/approved by owners, maintenance
representatives, commissioning agent?
37
PM p. 37
PM p. 38
39
What key concept have you learned thus far that you can put to use right
away?
PM p. 39
40
PM p. 40
41
PM p. 41
-42-
42
PM p. 42
PCA Tool
43
PM p. 43
44
PM p. 44
45
PM p. 45
Orders
Including Reserve Held
Open Items
From Subcontractor Outstanding Change Order Log
Status of Deliverables
Reference Close-Out Matrix
-46-
46
PM p. 46
100%
90%
80%
70%
60%
Teamwork = Close-out
50%
40%
30%
20%
10%
Financials
Engineering
Field
47
PM p. 47
PM p. 48
49
PM p. 49
50
Quiz Question #1
Answer #1
Quiz Question #2
Answer #2
Quiz Question #3
Answer #3
PM p. 50
51
PM p. 51
52
PM p. 52
53
PM p. 53
Start-Up
Identify systems/ equipment requirements.
Determine milestones for Start-Up activity.
54
PM p. 54
Commissioning
Identify systems/ equipment
requirements.
Understand the Commissioning
process and scope.
55
PM p. 55
Owner Training
56
PM p. 56
(continued)
57
PM p. 57
58
PM p. 58
Work-to-Complete List
Our start to the completion process.
A sharp tool or a dull blade?
59
PM p. 59
Attic Stock
Buy it in the contract.
Pick up requirements in the specs.
Set up with the owner where to stock it.
Turn it over early while the subcontractors are
still on the job.
Attic Stock is the owners property.
Do not confuse with the subcontractors leftovers.
Treat it like the finished product it is.
60
PM p. 60
100%
90%
80%
70%
60%
Teamwork = CloseClose-out
50%
40%
30%
20%
10%
Financials
Engineering
Field
61
Draw a line on the above status check to indicate what you think the status
of each item is at 75% construction.
PM p. 61
62
2.
3.
4.
5.
PM p. 62
63
PM p. 63
64
PM p. 64
65
PM p. 65
Now, with the User Groups getting to see their near-completed space, a second,
unanticipated punch list has been prepared. The Architect has been only too happy to
oblige the Clients end-of-job interest and has been issued this second punch list to
coincide with the time of Substantial Completion. The contract does involve Liquidated
Damages for late turnover, and it is now clear the second punch list may delay final
completion.
Assign roles: (Note: The roles are listed in priority order, so if there are four people at the table, assign the first
four; if five, assign the first five, and so forth.)
Superintendent already tasked with inspections for Substantial Completion; now has
new punch list work to deal with in the race to maintain scheduled final completion
Assistant Supt. has been primarily involved in the site work at this stage
Project Engineer first project of this size.
Project Executive/ Project Manager Project Manager role has single project
responsibility and needs to define his contributing role in this situation; Project Executive
is too busy to do more than dictate we must get done on time, we cannot absorb LDs.
Architect has aligned himself with the Owner in producing the second punch list;
wants to make certain the Owners last impression is very positive of his efforts. To date
has had a good relationship with Turner, but is a stickler for detail.
Owner Owner now has become very interested due to the User Group input received.
He does not see this second punch list as a big deal, and very anxious to occupy.
Subcontractorhas already done one punch list and is not interested in doing it again.
Using the tasks/questions on the next page, conduct the role play and then discuss.
PM p. 66
67
PM p. 67
Roles:
Project Engineer Was very much in control, but now has been transferred.
Superintendent Seasoned and skillful builder.
Project Executive/Project Manager Both are multi-project responsible and this
project to date has not demanded of them.
Assistant Engineer An up and coming administrator, but lacking in experience particularly in close out activities.
Assistant Superintendent Has broad project experience and is ready for promotion.
Accountant Very skilled and independent operator. Solid performer with the original
Superintendent Engineer team.
Tasks:
1. How does the Project Executive/Project Manager reallocate the project
engineers responsibilities?
2. Who should assume the COR and A/L processing?
3. Who should pick up the As-built and O&M collection?
4. What can the Superintendent do to lighten the engineering load?
5. Who can handle the dwindling submittal tasks for the interior finishes?
PM p. 68
From project launch the project staff at the Dunn Write Building have
properly set-up and planned their project with close-out in mind.
The project is on time and on budget and staff have their sights for a
timely close-out.
The owner recently walked the site and noticed that he would like to
reconfigure his office. This would require removing adjacent walls, the
introduction of an above ceiling AC Unit, (the unit carries a 12 week
lead time from receipt of approved product data), sprinkler head,
lighting relocations and carpet replacement.
Questions:
What is the impact of owners decision on close-out?
What is the project teams next course of action to try and maintain the
close-out schedule?
69
PM p. 69
100%
90%
80%
70%
60%
Teamwork = Close-out
50%
40%
30%
20%
10%
Financials
Engineering
Field
70
PM p. 70
71
What have you learned so far that you want to teach to others? Why?
PM p. 71
72
PM p. 72
73
PM p. 73
75
PM p. 74
76
PM p. 75
77
PM p. 76
74
PM p. 77
Certificate of Occupancy
Issued by authority having jurisdiction to Owner
Recognize remaining activities necessary for the
Certificate of Occupancy, including Owners.
Maintain relationships with all authorities
involved in inspections.
Turner plans, coordinates, leads, and documents.
78
PM p. 78
100%
90%
80%
70%
60%
Teamwork = Close-out
50%
40%
30%
20%
10%
Financials
Engineering
Field
80
PM p. 79
81
1.
6.
2.
7.
3.
8.
4.
9.
5.
10.
PM p. 80
82
PM p. 81
83
PM p. 82
As-Builts
Start with Contract Items List.
Consider 3D BIM Model, for coordination.
Confirm that final As-Builts comply with project
requirements established at 50%.
Follow-up for receipt and acceptance of final AsBuilts (transmittal process)
84
PM p. 83
Turnover Manual
Keep copies of key turnover documents in a
smaller Quick Reference manual:
Turner).
85
PM p. 84
Form 540
86
PM p. 85
-87-
87
PM p. 86
100%
90%
80%
70%
60%
Teamwork = Close-out
50%
40%
30%
20%
10%
Financials
Engineering
Field
93
PM p. 87
89
PM p. 88
90
PM p. 89
92
PM p. 90
93
PM p. 91
Warranty Management
Objectives:
Streamlined, transparent process for
owner issue reporting and resolution
Accountability/Risk Management
Promptly identify & resolve issues,
especially
Moisture and water events and Life Safety issues
Anything impacting owner operations
94
PM p. 92
95
PM p.93
96
PM p.94
Records Retention
Comply with contract and state statutes
Use Turners Uniform Filing Code
Consider electronic archiving
Cost savings
Easy access, searchable
Turner e.docs or simply electronic pdf files
97
PM p. 95
98
PM p. 96
Wrap-Up
Wrap-Up
How
How do
do you
you eat
eat an
an elephant?
elephant?
ANSWER:
ANSWER: ___________________________________
___________________________________
Project
Project Close-out--Sept.
Close-out--Sept. 2009
2009
99
99
PM p. 97
Wrap-Up
Close-out_________________________!
100
PM p.98
Wrap-Up
102
PM p. 99
Wrap-Up
103
Course Objectives
Describe the tasks required in all phases of the close-out process.
Define the type of documents and key tools related to close-out
their use and importance.
Set and track goals for close-out.
Identify recovery strategies to get close-out back on track.
PM p.100
Wrap-Up
PM p.101
Wrap-Up
PM p. 102
Wrap-Up