Professional Documents
Culture Documents
UT 0030 Thickness Measurement Surveys PDF
UT 0030 Thickness Measurement Surveys PDF
UT 0030 Thickness Measurement Surveys PDF
TABLE OF CONTENTS
1.0
SCOPE
2.0
3.0
QUALIFICATIONS OF PERSONNEL
4.0
SAFETY
5.0
6.0
7.0
TECHNICAL HAZARDS
8.0
GENERAL PROCEDURE
8.1
Surface Preparation
8.2
8.3
Examination Coverage
8.4
Examination Process
10
8.5
11
8.6
Defect Sizing
12
8.7
Marking
13
9.0
ACCEPTANCE CRITERIA
14
10.0
POST CLEANING
14
11.0
14
12.0
NONCOMPLIANCE
15
Revision Date:
Page: 2 of 15
1.0
2.0
SCOPE
1.1
1.2
3.0
4.0
QUALIFICATIONS OF PERSONNEL
3.1
3.2
A minimum certification to CGSB and SNT Level II shall carry out all final
interpretation.
SAFETY
4.1
All personnel must follow the Acuren safety policies as outlined in Acurens
Safety Manual.
4.2
4.3
4.4
4.5
Equipment must have secure hand and waist straps to ensure units are
not dropped. Extreme care is to be taken when handling calibration step
blocks, couplant and probes to ensure they are not dropped.
4.6
4.7
4.8
Revision Date:
Page: 3 of 15
5.0
6.0
i)
Straight Beam where the angle of pulse from the transducer is zero
degrees. Mode of propagation is longitudinal wave.
j)
Equipment Requirements
a) UT Set
b) Probes (Transducers)
c) Calibration Blocks
d) Couplant
e) Supplies
Pyromarkers
Revision Date:
Page: 4 of 15
f)
6.2
Scrapers.
Wire brushes.
PPE
Fire-retardant coveralls.
Safety glasses.
Wrist protectors.
Calibration
a) Typical for 36DL+ and 37DL+ or equivalent.
b) Determine the pipe nominal thickness and material, then calibrate on a
range of thickness values appropriate to the nominal pipe thickness. A
minimum of two points is required for calibrations. One at the upper
limit and one at the lower limit.
c) The search unit shall be calibrated at a similar temperature as the pipe
to be inspected. This shall be accomplished by placing the calibration
block on the part and allowing the calibration block to achieve the
same temperature as the test piece. Calibrations wi ll be carried out
using a small amount of the same couplant that is to be used during
the procedure.
NOTE
Failure to comply with temperature difference during calibration will result in
measurement errors due to the velocity changes that occur at different
temperatures.
d) Wipe the probe end clean and press [Zero ] often to compensate for
temperature drift.
e) Check the calibration frequently (see tips for improving transducer
longevity).
Revision Date:
Page: 5 of 15
7.0
TECHNICAL HAZARDS
7.1
7.2
7.3
7.4
7.5
Ensure the surface temperature of the test piece does not exceed
the maximum specified temperature for the transducer.
Revision Date:
Page: 6 of 15
c) Surface Conditions
Clean any loose debris (flaking paint, rust, scale, and dirt) from the
specimen with a wire brush or file.
NOTE
If a surface is rough and it is difficult to obtain a reading, it is unlikely that
grinding the transducer into the surface will improve the situation. When the
transducer surface becomes worn, the efficiency of the transducer will diminish
due to the fact that thick couplant layers may build up between the delay
elements of the transducer and the surface. Alternatively, the gage may have
difficulty in performing do zero. If these conditions develop, resurfacing of the
transducer face may be necessary.
d) Transducer Positioning/Alignment
8.0
GENERAL PROCEDURE
8.1
Supervisor Responsibilities
a) Supplying the required number of technicians, the data clerk and the
lead technician.
b) Understanding the job scope and any previously identified trouble
areas or trends before commencing the survey.
c) Keeping the lines of communication with the Project Supervisor during
the duration of the survey.
Revision Date:
Page: 7 of 15
8.2
Client Requirements
a) The following are tasks to be completed by client representati ves prior
to Acuren Personnel arriving on site.
8.3
Identify the line contents and hazard (s) level(s) of each line.
Personnel
a) The number of Acuren personnel will be based upon the survey scope
and duration.
b) The duties of the data clerk shall inc lude but are not limited to:
Obtaining the line contents and hazard(s) level(s) for each line.
Revision Date:
Page: 8 of 15
e) Supervisor:
8.4
Preparation
a) Review all Isometric drawings for flow direction and clear identification
of locations to be surveyed.
b) The Lead Technician shall discuss the following with the client
representative:
Number of locations.
When they would like final reports: i.e. as they are completed or at
the end of the job.
Revision Date:
Page: 9 of 15
8.5
Data Acquisition
a) Set up the UT set and data numbering convention as explained in this
technique or as requested by the client.
b) Make a drawing of the area ensuring that both the direction of flow and
the numbering convention are identified.
c) Using a data logger perform the initial thickness measurement survey.
d) Review the data on the instrument prior to leaving the location to
ensure that no data points have been missed. If the data appears to
be incomplete, perform additional data logging for any remaining
survey locations.
e) Automated methods of obtaining thickness information (i.e. UT B-Scan
and C-scan) may be employed when requested by the client.
8.6
NOTE
The data must be reviewed within two days of the initial survey or as required
by the client.
b) If any areas are to be rechecked the lead technician will assign a
different technician than the one who performed the initial survey to remeasure the areas of concern.
NOTE
This must be done within 3 days of the initial survey or as required by the client.
c) If the review did not reveal any low areas the field report will be
prepared for each survey site location.
d) A field copy of the survey report shall be printed given to the client
area representative.
NOTE
The final report shall be completed as soon as possible, and it must be within 5
days of the initial survey or as required by the client.
e) All applicable updates and new drawings to the corrosion surveys shall
be carried out by Acuren Group Inc.
Revision Date:
Page: 10 of 15
8.7
Data Logging
a) Setting up a Matrix
Looking in the direction of flow, the grids start at the upstream side
of the initial circumferential weld and progress alphabetically as the
bands move downstream.
The second axis for the matrix shall make up the numeric portion
of the alphanumeric grid and is also referenced to the direction of
flow.
Revision Date:
Page: 11 of 15
c)
For pipe ranging in size from 2.54 cm (1) to 35.56 cm (14) shall
be 2.54 x 2.54 cm (1x 1) squares. The grid shall start 2.54 cm
(1) after the closest upstream weld (see fig.1) and continue for a
longitudinal distance designated by the client.
Figure 1
Figure 2
Revision Date:
Page: 12 of 15
Figure 3
d) Set up a table with the numerical grid designation as column headings
and the alpha designation as row headings. For Example, an NPS 4
standard wall pipe would have a 1 x 12 grid for a total of 12 thickness
readings and the grid would be as shown table 2.
1
10
11
12
Table 2
NOTE
It is important to maintain the above convention for naming both columns
and rows even if a portion of the grid is not accessible. For example, if
there was no access to Column 3 of Table 2, all other areas would be
inspected and no data would be entered in Column 3. Make note in the
report the reason for no data in that location (i.e. A nozzle, B restricted
access, etc.).
8.8
Revision Date:
Page: 13 of 15
Figure 4
8.9
Care of Equipment
a) In order to ensure accurate thickness measurements and reliable
inspection results, equipment must be properly maintained.
b) Keep the unit clean and protect from the environment.
c) Follow the manufacturers manual for routine care and maintenance.
d) Equipment to be red tagged if unit is not operating properly and
returned to the Acuren Repair Facility in Edmonton.
9.0
ACCEPTANCE CRITERIA
9.1
10.0
POST CLEANING
10.1 If necessary final cleaning shall be accomplished with an approved
manufacture rs cleaner or a cleaner approved by the referencing code
section or customer specification.
Revision Date:
Page: 14 of 15
11.0
g) Material.
h) Pipe temperature at time of examination.
i)
j)
Survey date.
NONCOMPLIANCE
12.1
Revision Date:
Page: 15 of 15