Gantt Chart: NO Timeline October November December Activities W 1 W 2 W 3 W 4 W1 W2 W3 W4 W1 W 2 W 3 W4 1

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

GANTT CHART

NO

TIMELINE
ACTIVITIES
Finalized Project Team Members
Grouping
Ice-Breaking session Among Team
Members
Literature and Patent Review and
Benchmarking
To Research and determine
about the Baby, weight, size
and height.
To investigate types of Baby
stroller available in the
market and to determine the
type we want to develop.
To investigate and know
about the foldablity suitable
for the Baby Stroller
To determine and Study about
the Mechanism that is going
to be developed
To study and develop the
Safety Regulations required
for the design of the Baby
Stroller
To conduct at least 3 patent
reviews and benchmarking

OCTOBER
W W W W
1
2
3
4

NOVEMBER
W1 W2 W3 W4

DECEMBER
W1 W W W4
2
3

among the baby stroller


available in market

Survey
To create a questionnaire to
determine the design of Baby Stroller
that parents are expecting.
To conduct survey and collect
feedback from parents and also
dealers who sell Baby Strollers in
the market
Exploring Options and Combinations in

Design

To come out with at least 3


combinations of design ideas
for the existing and patent
product

To examine the options and


decide on the best proposed
design from the concept
evaluation

Design and Optimization

To deliver the detailed drawings


based on the chosen design using
suitable software.
To perform design analysis using
suitable software.
To run the optimization to fulfil
parameters based on House of
Quality.

Finalizing Product Design and


Specifications

To finalize the design process and


specifications of the product.
To prepare and divide the tasks in the
team for the MDP week suspension
system design competition

Preparation of Report
To attend and present the detailed
design of suspension system for
stroller in MDP week suspension
system design competition.
To prepare and divide the tasks in the
team for the final report.
To prepare and divide the tasks in the
team for the final presentation.
Final Presentation
To submit the final report.
To present technical presentation for
the detailed design of suspension
system for stroller.