Name of Contract: Repair and Maintenance of Malapaao Flood Cont

Location of Contract: Malapaao, Langiden, Abra

COMPUTATION OF QUANTITIES
ITEM 506: Stone Masonry
SITE 1
LEFT SIDE
Sta. L
H
Distance
0
1.5
5
1.5
5
9.4
1.5
4.4
12.2
15
1.5
2.8
20
1.5
5
24.1
1.5
4.1
25
1.5
0.9
30
1.5
5
35
1.5
5
40
1.5
5
43.3
1.5
3.3
44.3
1.5
1
45
1.5
0.7
50
1.5
5
55
1.5
5
60
1.5
5
65
1.5
5
66
1.5
1
68.3
70
1.5
1.7
75
1.5
5
80
1.5
5
85
1.5
5
90
1.5
5
95
1.5
5
100
1.5
5
105
1.5
5
110
1.5
5
115
1.5
5
120
1.5
5
125
1.5
5

Area Stem
1.125
1.125
1.125

Area Foofting
1
1
1

1.125
1.1625
1.125
1.125
1.125
1.125
1.125
1.125
1.125
1.125
1.125
1.1625
1.125
1.125
1.125

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

1.125
1.125
1.125
1.1625
1.125
1.125
1.125
1.125
1.125
1.1625
1.125
1.125

1
1
1
1
1
1
1
1
1
1
1
1

125.5
RIGHT SIDE
Sta. R
0
5
7.7
12
15
20
25
30
33
34.6
35
40
45
50
50.9

1.5

0.5

H
1.5
1.5
1.5

Distance

1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5

3
5
5
5
3
1.6
0.4
5
5
5
0.9

5
2.7

1.125

Area Stem Area Foofting


1.125
1
1.125
1
1.125
1
1.1625
1.125
1.125
1.125
1.125
1.1625
1.125
1.125
1.1625
1.1625
1.1625

TOTAL VOLUME OF STONE MASONRY =


ITEM 103: EXCAVATION
VOLUME= 1 X 1 X 167 =
1 X 1 X 123 =

Prepared By:
Socorro Lito S. Benedito
Project Engineer I

167
123
290 cu.m.

1
1
1
1
1
1
1
1
1
1
1

Malapaao Flood Control

ATION OF QUANTITIES

AreaTotal
2.125
2.125
2.125

Ave. Area

Vol. StoneMasonry

2.125
2.125

10.625
9.35

2.125
2.1625
2.125
2.125
2.125
2.125
2.125
2.125
2.125
2.125
2.125
2.1625
2.125
2.125
2.125

2.125
2.14375
2.14375
2.125
2.125
2.125
2.125
2.125
2.125
2.125
2.125
2.14375
2.14375
2.125
2.125

5.95
10.71875
8.789375
1.9125
10.625
10.625
10.625
7.0125
2.125
1.4875
10.625
10.71875
10.71875
10.625
2.125

2.125
2.125
2.125
2.1625
2.125
2.125
2.125
2.125
2.125
2.1625
2.125
2.125

2.125
2.125
2.125
2.14375
2.14375
2.125
2.125
2.125
2.125
2.14375
2.14375
2.125

3.6125
10.625
10.625
10.71875
10.71875
10.625
10.625
10.625
10.625
10.71875
10.71875
10.625

2.125

2.125

1.0625
256.58

AreaTotal
2.125
2.125
2.125

Ave. Area

Vol. StoneMasonry

2.125
2.125

10.625
5.7375

2.1625
2.125
2.125
2.125
2.125
2.1625
2.125
2.125
2.1625
2.1625
2.1625

2.1625
2.14375
2.125
2.125
2.125
2.14375
2.125
2.125
2.14375
2.1625
2.1625

6.4875
10.71875
10.625
10.625
6.375
3.43
0.85
10.625
10.71875
10.8125
1.94625
99.58

356.16 cu.m.

cu.m.

cu.m.