Quotation for 4 KMS Transmission line

Sl No

Description

Uom

Qty

Unit supply

Unit Erection

Total supply

Total Erection

supply and Erection of PSCC poles 11.0 mtr,365 kg

nos

74

8500

3000

629000

222000

Supply and Erection of 15 Mts Towers

nos

170000

50000

510000

150000

supply and Erection of PSCC poles 9.0 mtr, 280 kg

nos

10

4300

1500

43000

15000

supply and Erection of 33 KV 'V' cross arms with


clamps

nos

87

1500

300

130500

26100

supply and Erection of 33 KV Top cleat with clamps

nos

74

550

68

40700

5032

supply and Erection of 33 KV Pin insulators with GI


pins

nos

231

580

56

133980

12936

supply and Erection of 33 KV metal parts

nos

30

850

90

25500

2700

supply and Stringing of AAA DOG conductor

km

12

45000

5000

540000

60000

supply and Erection of 33 KV M.S stay sets with


clamps including soil excavation,concreting.

nos

20

2700

618

54000

12360

supply and Erection of Coil earthing for poles

nos

77

250

150

19250

11550

10

supply and Erection 33 KV Polymer insulators

nos

30

500

100

15000

3000

11

Mass concreting of poles including supports with


cement, sand and gravel(1:4:8)

nos

74

3500

700

259000

51800

12

supply and Horizontal cut points for 33 KV line

nos

13

supply and Vertical cut points for 33 KV line

nos

10

5000

1000

50000

10000

Numbering of poles including paint,Danger boards,

nos

77

150

50

11550

3850

Detailed survey & tree clearances

KM

1800

7200

2461480

593528

2
2

14
15

Grand Total
Discount
Grand Total After Discount
Note:
a) Price is exclusive of all taxes. All taxes are extra

3055008
555008
2500000