Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

AUTHORIZATION AND RECORD

Rev

Prepared
By

Description
Method Statement for Cold Water
Services

Approved
By

PJSB

CONTENTS
1.

Introduction

Revision: 0

Page No: 1

Date

2.
3.
4.
5.
6.
7.
8.
9.

Scope Of Work
Work Sequences
Methods Statement
Testing
Plant, Machinery And Equipment
Manpower
Safety & Environment
Inspection / Test plan

1.

Introduction

3
3
3
4
5
5
5
6

This work method statement is to describe the materials and procedures for the installation of
tiling works. This method statement also describes the technical method of application and the

Revision: 0

Page No: 2

sequence of works to be carried out to ensure compliance with contract requirements, drawings,
technical specification and quality control.
2.

Scope of Work

The method statement covers the supply, delivery, installation, testing and putting into
satisfactory operating condition of a cold water plumbing system for all water distribution
fixtures, equipment and fittings.
3.

Work Sequences

Both specialist and general worker experienced in this type of work will execute the works. The
piping work installation will be carried out concurrently with physical site progress to ensure that
the construction works can be complete as per schedule.
4.

Method Statement
4.1

Transport, Delivery and Storage

a)

All pipes shall be stored in proper storage conditions, which are free from dust,
sunlight and extreme temperatures. For long-term storage, the pipes shall be
stacked in rack with adequate spacing and supports and with larger diameter pipes
placed at bottom.
Upon delivery, piping materials and fittings used for installation shall be checked
by site supervisor to ensure the delivered materials are conformance to
specification and approved material.

b)

4.2 Preparation Work


a)
b)
c)

Upon the installation work, all pipe routing and setting out shall be checking and
studying base on approved shop drawing.
The coordination between Civil and Structural and others M&E works shall be
carried out closely prior to installation work.
All pipe and fittings should be inspected. Any defective items should clearly
marked as rejected and forthwith remove from site.

4.3

Installation Work

a)

Upon determination of the pipe size, level and pipe routing, mark on the brick
wall the area need to be hacked for installing the concealed pipework
Make a square cut to the pipe to be installed into the required length by using fine
toothed saw or pipe cutter.
Clean the pipe to ensure that is free from burrs, swarf, dirt and grease.
Connection of pipe to pipe or pipe to fitting shall be via fitting.
Once the pipe has been cut to the required length and having determined the type
of fitting to use, push the fittings into the pipe up to the circlip housing.

b)
c)
d)
e)

Revision: 0

Page No: 3

f)
g)
h)
5.

Wind the nut onto the pipe a few turns by hand and tighten with a spanner until
fully engaged against circlip housing.
When the pipework had been completed, secure the pipe by patching the trench
with cement.
Pressure testing of the pipe work is then ready to be carried out.

Testing
All piping system shall be tested to pressure equivalent 1.5 times the maximum working
pressure. The indicated pressure shall be maintain for the required holding period without
further application of pressure and without visible leakage or a drop in the indicated pressure.
Any modification made in the piping system after a successful test shall cal for re-testing of
the affected portion of the piping system. All pipe installation shall be inspected and recorded
in accordance to the Inspection test plan and checklist.
5.1

Pressure and Leakage Test

a)

Seal the open ends of the pipes with PVC plug. The lowest and highest end of the
pipes shall be equipped with stop valves to control the filling in of water into the
pipes and releasing of air.
A pressure gauge with dial of 100 mm diameter and read up to 150 psi shall be
installed at the valve inlet pipe.
Fill up the pipeline with water. During filling, provision shall be made for the air
to escape from the pipeline.
After the pipeline has been filled with water, more water shall be pump into the
pipeline to raise the pressure to 80 psi.
The tested pipe pressure shall be maintained for 8 hours with allowance of 5%
drop in pressure.
Inspection Form is then submitted to the consultant / C.O.W for inspection and
endorsement.

b)
c)
d)
e)
f)
6

Plant, Machinery And Equipment


a)
b)
c)
d)

Fine toothed saw


Pipe cutter
Circlip housing
Scaffolding

Man Power
a)
b)
c)

Revision: 0

Scaffolder
Plumber
General Workers
Page No: 4

Safety & Environment


It is our policy to perform all our works with due regard to safety, practice safe working
methods and create a risk free, healthy working environment. The following key areas
construction shall be adhered by all personal, working on-site. There are not all inclusive set
of rules, but guidance of the level of care and attention on safety matters that every site
personals shall observed and follow.
iPersonal Protective Equipment
The personal protective equipment which will be provided to the workers on site
includes of following:
- Safety Helmets
- Safety Vest
ii-

iii-

Housekeeping is an essential part of the construct safety. This should be part of


our daily routine. Housekeeping would include the following items :
- Store all materials in safe and orderly manner.
- Avoid littering around the jobsite.
- Do not leave any equipment and material scattered around site area.
Night Work
For night work, the area of work shall be adequately lit the facilitate production
works and movements on site. Warning lights, directive signs, reflective aids and
barriers shall be placed at suitable location to forewarn all potential hazards.

In summation, in order to achieve safe, free risk and healthy working environment, including
loss prevention, every practicable step must be taken by each and everyone engaged in this
project site.
9 Inspection / Test plan
Refer Appendix C.
-: Cold Water Plumbing Works Checklist
-: Pressure Testing (Pipework)

Revision: 0

Page No: 5

You might also like