Backorders
Metro service has improved shed delivered. Shed deliveries happening much
earlier and reliability has increased. Also Saturday shed delivery has
decreased number of PC1s.
EXTRA ACTIVITIES
Co-ordinating with NGBN project. Releasing regular Pick Modules and Hawk
Presenters to Project Team for upgrade. Once upgraded will be received in
stock against the newly created parts numbers to support the project.
CHALLENGES
In AU, areas like North Geelong, East Bendigo, Taree, Tuggerah, Lismore, etc.
having revised ETA all the time. Need visibility on Toll website to confirm
exact status of the shipments. No progress in current situation. Rico should
engage Toll higher management to resolve this.
Need to have Metro service in Brisbane and Perth as well in order to improve