PNEUMATIC PLAN

REFERENCE DRAWINGS:
0305-PID-0004
0305-ID-0003
0305-ID-0001

P&IDS
INSTRUMENT ELECTRICAL LOCATION PLAN
INSTRUMENT INDEX

Notes:
1. ALL INSTRUMENT TAG NUMBERS ARE PRECEDED BY 0305- PREFIX.
2. AIR LINES SHALL BE 8 DIAMETER PIPE, SIZE CHUCHU
3. FIELD SHALL FABRICATE AND INSTALL MISCELLANEOUS SUPPORTS AS
REQUIRED TO SUPPORT PIPING AND TUBING. FIELD SSHALL ROUTE TUBING
TO NEARET AIR HEADER AS NOTED IN THIS DRAWING

ELECTRICAL PLAN

REFERENCE DRAWINGS:
0305-PID-0004
0305-ID-0002
0305-ID-0001

P&IDS
INSTRUMENT PNEUMATIC LOCATION PLAN
INSTRUMENT INDEX

Notes:
1. ALL INSTRUMENT TAG NUMBERS ARE PRECEDED BY 0305- PREFIX.
2. FIELD SHALL INSTALL MISCELLANEOUS SUPPORTS AS REQUIRED TO SUPPORT
DEVICES AND CONDUIT, FIELD SHALL DETERMINE BEST POSSIBLE CONDUIT
ROUTING TO LOCAL JUNCTION BOXES.
3. ALL WIRING AND TUBING AND TUBING SHOWN DIAGRAMATICALLY ONLY.
EXACT LOCATION AND ROUTING SHALL BE DETERMINED BY FIELD.
4. FIELD SHALL FABRICATE A J-BOX SUPPORT STAND AND MOUNT THE J-BOX SO
ITS 4-6 ABOVE GROUND. IF J-BOX IS FACING OFF MODULE MOUNTING
HEIGHT SHALL BE ADJUSTED ACCORDINGLY.
P&ID

1. ALL INSTRUMENT TAG NUMBERS ARE PRECEDED BY 0305- PREFIX.


2. PUMP AND MOTOR CONTROLS WILL BE MONITORED AND CONTROLLED BY
FIELD WORKER.