Cementing Calculation
Cementing Calculation
Cementing Calculation
Previous
Casing
Open Hole
Collar
Shoe
Previous
Casing
Open Hole
Collar
Shoe
Previous
Casing
3. Inside casing
(between collar and shoe)
2
3
3
Open Hole
Collar
Shoe
Cement Calculations
Volume of open hole below the casing shoe is
not calculated.
Cement circulates out of the shoe and up the
annulus.
Any cement displacing the mud below by gravity
is considered negligible.
Problem 1
Casing
7 - 32 LB/Ft
Shoe
4600
4510
Collar
Previous casing :
9 5/8 - 47 LB/Ft
Shoe
2670
Open hole
8.5
Top of cement
1000
Solution
Capacities
1. Cas-Cas
- 0.1438 cuft/ft
2. Cas - OH
- 0.1268 cuft/ft
1000ft
1
3. Cas
Volumes
2670ft
2
3
3
4510ft
4600ft
Solution
Capacities
1. Cas-Cas
- 0.1438 cuft/ft
2. Cas - OH
- 0.1268 cuft/ft
1000ft
1
3. Cas
Volumes
2670ft
3
3
4510ft
4600ft
Solution
Capacities
1. Cas-Cas
- 0.1438 cuft/ft
2. Cas - OH
- 0.1268 cuft/ft
1000ft
1
3. Cas
Volumes
2670ft
4510ft
4600ft
Solution
Capacities
1. Cas-Cas
- 0.1438 cuft/ft
2. Cas - OH
- 0.1268 cuft/ft
1000ft
1
3. Cas
Volumes
2670ft
3
3
4510ft
4600ft
Solution
Capacities
1. Cas-Cas
- 0.1438 cuft/ft
2. Cas - OH
- 0.1268 cuft/ft
1000ft
1
3. Cas
Volumes
2670ft
3
3
4510ft
4600ft
Excess
Example: Problem 1
OH 50% Excess
Excess Volume:
Total OH Volume:
OR
244.7 cuft
YIELD
CEMENT
CEMENT
WATER
CEMENT
WATER
SLURRY
Note:
1 sack of cement
of 94 lbs
= 1 cuft
= 0.66 cuft
Note:
1 sack of cement
of 94 lbs
= 1 cuft
= 0.66 cuft
= 1.66 cuft
Note:
1 sack of cement
of 94 lbs
= 1 cuft
= 0.66 cuft
But the
Handbook states:
1.15 cuft/sack
WHY ?
1 cuft + 0.66 cuft
= 1.66 cuft
Bulk vs Absolute
One drum full
of dry cement
(1 drum = 1 cuft)
Bulk vs Absolute
One drum full
of dry cement
(1 drum = 1 cuft)
Pour water
into cement
Same size drum
0.66 of water
Air in pore spaces will
be displaced by water
22 Single Stage Cementing
Note
Yield varies with density
Basically, when you change the density you alter the
Normally ........
as you increase the water content the yield increases
23 Single Stage Cementing
240.2 cuft
240.2 cuft
Use:
Lead Slurry
240.2 cuft
Use:
Lead Slurry
15.8 ppg
= 145.2 sacks
240.2 cuft
Use:
Lead Slurry
15.8 ppg
= 145.2 sacks
1.655 cuft/sack
Cement volume Tail:
385.25 cuft
1.15 cuft/sack
= 335.0 sacks
CONVERT TO BBLS
(Your displacement tanks are in bbls)
1241.2 gal
42 gal/bbl
29.55 bbls
1241.2 gal
42 gal/bbl
29.55 bbls
1241.2 gal
29.55 bbls
42 gal/bbl
1664.95 gal
42 gal/bbl
39.64 bbls
1241.2 gal
29.55 bbls
42 gal/bbl
1664.95 gal
42 gal/bbl
69.19 bbls
39.64 bbls
1241.2 gal
29.55 bbls
42 gal/bbl
Tail mix water
1664.95 gal
42 gal/bbl
69.19 bbls
66.19 bbl x 20/100 =
13.84 bbls
39.64 bbls
1241.2 gal
29.55 bbls
42 gal/bbl
Tail mix water
1664.95 gal
42 gal/bbl
69.19 bbls
66.19 bbl x 20/100 =
13.84 bbls
0 bbls
39.64 bbls
1241.2 gal
29.55 bbls
42 gal/bbl
Tail mix water
1664.95 gal
42 gal/bbl
69.19 bbls
66.19 bbl x 20/100 =
13.84 bbls
0 bbls
20 bbls
39.64 bbls
1241.2 gal
29.55 bbls
42 gal/bbl
Tail mix water
1664.95 gal
42 gal/bbl
69.19 bbls
66.19 bbl x 20/100 =
13.84 bbls
0 bbls
Priming, washing up
Total water needed
41 Single Stage Cementing
20 bbls
103 bbls
39.64 bbls
Additives - Step E
Solid Additives
Liquid Additives
(145 sks)
= 817.8 lbs
Liquid Additives
335 sacks x 0.2 gal/sack
= 67 gal
=1664.95 gal
Displacement
To FLOAT COLLAR unless otherwise stated
Exceptions
1. STAB-IN CEMENTING:
Displacement to 10-15 before stab-in shoe
Check returns - OK - pull out and circulate
2. GUIDE SHOE:
Displacement
To FLOAT COLLAR unless otherwise stated
Exceptions
1. STAB-IN CEMENTING:
Displacement to 10-15 before stab-in shoe
Check returns - OK - pull out and circulate
2. GUIDE SHOE:
Displace to 20-30 before shoe
NEVER OVERDISPLACE
45 Single Stage Cementing
1 HOUR (SAFETY)
= MINIMUM THICKENING TIME
46 Single Stage Cementing
42.8 :
68.6 :
Displacement:
Dropping Plugs
Total
4 bpm
8bpm
10.5 mins
8.5 mins
11mins
9 mins
Examples - Example 1
Calculate : Slurry Volumes, Cement Volumes,
Mix Water, Additives, Displacement
Job Time
Well Data: 9 5/8 53.5 lb/ft casing, shoe at 9800,
collar at 9760, OH 12 1/4 + 25% excess,
previous casing 13 3/8 68 lb/ft at 2900
Slurries: Lead: 5 bpm 9300 - surface
Examples - Example 1
Calculate : Slurry Volumes, Cement Volumes,
13 3/8" , 68 lbs/ft
2900'
9300'
3
4
12 1/4" OH
9760'
3
9800'
Solution - Example 1
Capacities
CAS/CAS
: 0.3354 cuft/ft
CAS OH
: 0.3132 cuft/ft
CAS : 0.3973 cuft/ft , 0.0708 bbl/ft
1. Volumes
Solution - Example 1
Capacities
CAS/CAS
: 0.3354 cuft/ft
CAS OH
: 0.3132 cuft/ft
CAS : 0.3973 cuft/ft , 0.0708 bbl/ft
1. Volumes
Lead
(1) 2900ft x 0.3354 cuft/ft
(2) 9300ft - 2900ft x 0.3132
= 972.7 cuft
= 2004 cuft
501 cuft
Tail
(3) 9800ft - 9300ft x 0.3132 cuft/ft = 156.cuft
(4) 40ft x 0.3973 cuft/ft
= 15.9 cuft
Excess 156.6 cuft x 0.25
= 39.2 cuft
Solution - Example 1
Capacities
CAS/CAS :0.3354 CUFT/FT
CAS OH
:0.3132 CUFT/FT
CAS :
0.3973 CUFT/FT, 0.0708 BBL/FT
1. Volumes
Lead
(1) 2900ft x 0.3354 cuft/ft
(2) 9300ft - 2900ft x 0.3132
= 972.7 cuft
= 2004 cuft
501 cuft
Tail
(3) 9800ft - 9300ft x 0.3132 cuft/ft = 156.cuft
(4) 40ft x 0.3973 cuft/ft
= 15.9 cuft
Excess 156.6 cuft x 0.25
2. Yield
Handbook 700.013
700.006
52 Single Stage Cementing
= 39.2 cuft
Solution - Example 1
3. Cement
Lead :
3477 cuft
= 1606 sacks
2.165 cuft/sk
Tail :
211.7 cuft
184 sacks
1.15 cuft/sk
4. Mix Fluid
Lead :
Tail :
21.8 bbls
Solution - Example 1
5. Additives
Lead :
Tail :
= 18116 lbs
= 453 lbs
= 8.6 lbs
= 86 lbs
Solution - Example 1
6. Displacement
9760ft x 0.0708 bbl/ft = 691 bbls
Example 2
Data :
Casing
Open hole
Cement
Calculate :
Slurry Volume
Cement Volume
Mix water
Additives
Displacement @ 7 bpm
Job Time
Solution - Example 2
9 5/8" , 53.5 lbs/ft
8600'
8.5" OH
7", 29 lbs/ft
10200'
10800' 9" OH
44
3
5
11507'
14230'
14300'
Capacities
Solution - Example 2
1. Volumes
Tail : Yield is 1.475 cuft/sk
250 sacks
---> 250 x 1.475
= 368.75 cuft
Volume (5) + (6)
= 368.75 cuft
(6)
= 70 x 0.2086
= 14.6
cuft
(5)
= 368.75 - 14.6
= 354.15 cuft
Height in annulus
354.15 cuft
= 2793
0.1268 cuft/ft
14300 - 2793'
= 11, 507'
Lead: Surface - 11, 507'
(1) 8600 x 0.1301
= 1118.86 cuft
(2) (10200 - 8600) x 0.1268 = 202.88 cuft
(3) (10800 - 10200) x 0.1745 = 104.70 cuft
(4) (11507 - 10800) x 0.1268 = 89.64 cuft
Total Lead = 1516.1 cu ft
Solution - Example 2
2. Cement sacks
Lead
:
Tail
3. Mix fluid
Lead
Tail
:
:
831 sacks
193.1 bbls
36.6 bbls
Solution
Example
2
4. Additives
Lead:
Tail:
5. Mix water
Lead:
Tail:
D20
: 831 sks x 94 x 0.08
= 6249 lbs
D109
: 831 sks x 0.05 gals/sk = 41.5 gals
D80
: 831 sks x 0.1 gals/sk = 83.1 gals
Total fluid = 124.6 gals
D66
: 250 sks x 94 x 0.3
= 7050 lbs
D81
: 250 sks x 0.1 gals/sk
= 25 gals
D603
: 250 sks x 0.5 gals/sk
= 125 gals
Total fluid = 150 gals
Solution - Example 2
6. Displacement
14230ft' x 0.0371 bbl/ft
= 527.9 bbl
Lead
Tail
: 270 bbls
: 65.7 bbls
Plugs
Displacement 527.9 bbls
Safety Margin
7 bpm
38.5
5 bpm
13.1
min
10
75
min
60
:
:
7 bpm
min
min
min
Job Pressures
Example No 1
13 3/8" , 68 lbs/ft
surface
12 1/4" OH
9300'
3
4
9760'
3
9800'
13 3/8" , 68 lbs/ft
2900'
9 5/8", 53.5 lbs/ft
9300'
3
4
12 1/4" OH
9760'
3
9800'
13 3/8" , 77 lbs/ft
Mud @ 11.3 ppg
1
2100
2
12 1/4" OH
9480'
3
4
9900'
Tail Slurry @ 15.8 ppg
9980'
Capacities
Csg/OH Ann = 0.0558 bbls/ft
Csg/Csg Ann = 0.0564 bbls/ft
9 5/8 Csg cap (40 #/ft) = 0.0758 bbls/ft
Tail volume = Vol of Shoe track
+ Vol outside csg (with XS)
= 0.0758 x (9980 - 9900)
+ 0.0558 x (9980 - 9480) x 1.10
= 6.06 + 30.69 = 36.75 = 37 Bbls
= 206.3 cuft
Lead volume = Vol in Csg/OH Ann (with XS)
+ Vol in Csg/Csg Ann
= 0.0558 x (9480 - 3150) x 1.10
+ 0.0564 x (3150 - 2100)
= 388.53 + 59.22 = 447.75
= 448 Bbls
= 2514.04 cuft
13 3/8" , 77 lbs/ft
Mud @ 11.3 ppg
1
2100
2
12 1/4" OH
9480'
3
4
9900'
Tail Slurry @ 15.8 ppg
9980'
Capacities
Csg/OH Ann = 0.0558 bbls/ft
Csg/Csg Ann = 0.0564 bbls/ft
9 5/8 Csg cap (40 #/ft) = 0.0758
bbls/ft
Displacement volume = Csg Vol to
float
collar
= 0.0758 x 9900
= 750 Bbls
Differential pressure at end of Job :
= Hydrostatic of Lead and tail cement
columns + Hydrostatic of wash +
Hydrostatic of remaining mud in
annulus LESS Hydrostatic of
displacing fluid + Hydrostatic of Tail
cement in shoe joint
13 3/8" , 77 lbs/ft
Mud @ 11.3 ppg
1
2100
2
12 1/4" OH
9480'
3
4
9900'
Tail Slurry @ 15.8 ppg
9980'
Capacities
Csg/OH Ann = 0.0558 bbls/ft
Csg/Csg Ann = 0.0564 bbls/ft
9 5/8 Csg cap (40 #/ft) = 0.0758
bbls/ft
Height of Chemical wash in Csg/Csg
Ann
= 50 / 0.0564
= 886 ft
Height of Tail = 9980 - 9480 = 500 ft
Height of Lead = 9480 - 2100 = 7380
ft
Height of Chem Wash = 886 ft
Remainder is Mud behind casing
= 9900 - (420 + 7380 + 886)
= 1214 ft
13 3/8" , 77 lbs/ft
Mud @ 11.3 ppg
1
2100
2
12 1/4" OH
9480'
3
4
9900'
Tail Slurry @ 15.8 ppg
9980'
13 3/8" , 77 lbs/ft
Mud @ 11.3 ppg
1
2100
2
12 1/4" OH
9480'
3
4
9900'
Tail Slurry @ 15.8 ppg
9980'