Performance
Physical Target
Accomplishment/Status
Variance Remarks
Measures/
FY 2016
Indicators
Major Final Output : Technical Advisory and Support Services on the Comprehensive Peace Process
Negotiated political settlement of all internal armed conflicts achieved
On 14-15 June 2016, an exploratory talks were conducted in Oslo,
Peace Process with the
Peace tables with Adoption and
CPP/NPA/NDF
GPH consensus on execution of GPH Norway and resulted to the parties agreement to resume formal talks
and commitment from the GPH Panel to recommend the following to
the negotiating
political agenda
the President:
framework/agenda on the reduction
- immediate release of NDF consultants and other JASIG-protected
of armed violence
persons to enable them to participate in the peace negotiations;
against civilians
and,
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
Accomplishment/Status
Variance Remarks
On the ceasefire:
President Duterte declared a unilateral ceasefire effective
indefinitely from 21 August 2016
NDF declared their own unilateral ceasefire on 27 August.
Parties agreed to reconcile and develop the unilateral ceasefire
into a unified bilateral ceasefire which will be deemed interim in
relation to EOH/DOF
Peace Process with the
Moro Islamic Liberation
Front (MILF)
Peace Tables
with GPH
consensus on the
implementation
of agreements
GPH-MILF:
-Assistance in the
establishment of
the Bangsamoro
Transition
Authority;
- Continuing
monitoring of the
implementation of
the
Comprehensive
Agreement on the
Bangsamoro; and,
- Monitoring
implementation of
the Annex on
Normalization
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
Accomplishment/Status
Variance Remarks
Peace Tables
with GPH
consensus on the
implementation
of agreements
Representation of
the MNLF in the
Transition
Authority
GPH-Cordillera Bodong
AdministrationCordillera Peoples
Peace Tables
with GPH
consensus on the
Mechanisms for
transformation
sustained
Of the eleven (11) projects from the Aquino administration which were
reported as ongoing during the start of the Duterte administration, six
(6) have been reported as physically completed as of September 2016
Page 3 of 11
Program/Activity/Project
GPH-Rebolusyonaryong
Partidong
Manggagawang
Pilipinas/Revolutionary
Proletarian Army/Alex
Boncayao Brigade (RPMP/RPA/ABB) Closure
Program
Performance
Measures/
Indicators
implementation
of agreements
Physical Target
FY 2016
Peace Tables
with GPH
consensus on the
implementation
of agreements
GPH-RPMP/RPA/ABB:
-Closure MOA
with Tabara
Paduano Group
(TPG) signed and
fully implemented
Accomplishment/Status
Variance Remarks
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
Accomplishment/Status
Variance Remarks
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
Accomplishment/Status
Variance Remarks
Monitoring and
early warning
system for conflict
triggers
implemented and
sustained
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
Accomplishment/Status
Variance Remarks
Peace and Order, and Public Safety Plan (POPSP). Their project
partner, the EU-Philippines Justice Support Programme (EP-JUST II),
is currently undertaking efforts to integrate said peace, security and
development indicators in the POPSP Manual.
Conflict
sensitivity,
gender
responsiveness
and peace
promotion
mainstreamed in
governance
Five (5)
Transparency and
Accountability
Mechanisms
(TAM) made fully
operational in
PAMANA
implementation
The PAMANA TAM has five (5) components that provide information on
the different mechanisms established to ensure transparency and
accountability in PAMANA implementation:
Completed:
1. Project and Community Billboards;
2. Performance-based Fund Releases;
3. Web Posting; Pilot Tested: and,
Ongoing Development:
4. PAMANA Feedback and Response System (PFRS);
5. Third Party Monitoring / Citizens Led Monitoring initiative
-100% of agency
programs related
to the Peace
Process
capacitated on
conflict sensitive
tools and
processes
-100% of the 43
provinces with
communities
affected by and
vulnerable to
conflict enabled
with tools and
National Action Plan on Women, Peace and Security (NAPWPS). In collaboration with the NAP-WPS Secretariat and
National Project Officer for Support to the Implementation of the
Bangsamoro Peace Agreement and Gender-Sensitive Transitional
Justice, United Nations Women, the OPAPP-MEU revised and
provided inputs on the NAP-WPS Resource Kit. The resource kit
will be used in building the capacity of local government units in
planning, implementing, and monitoring and evaluating NAPWPS initiatives.
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
processes for
conflict-sensitive
peace-promoting
and genderresponsive
planning and
programming
increased
Accomplishment/Status
Variance Remarks
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
Accomplishment/Status
Variance Remarks
Access to basic
services
improved in
conflict affected
areas
Phillippine
National Action
Plan (PNAP) on
Women, Peace
and Security
mainstreamed in
- 100% of
programmed
PAMANA areas
with improved
access to basic
service
- 100% of Pillar 2
(Building
Resilient
Communities)
and Pillar 3
(Regional and
Sub-Regional
Developments)
interventions
implemented in
targeted
PAMANA areas
17 NGAs and
LGUs in 43
PAMANA
provinces
mainstreamed
NAP policies/
The nine (9) NSC members are as follows: Philippine Commission on Women (PCW), Department of Social Welfare and Development (DSWD), Department of Justice (DOJ), Department of Interior and Local
Government (DILG), Department of Foreign Affairs (DFA), Department of National Defense (DND), National Commission on Indigenous Peoples (NCIP) and the National Commission of Muslim Filipinos
(NCMF).
Page 9 of 11
Program/Activity/Project
Performance
Measures/
Indicators
NGAs and LGUs
Physical Target
FY 2016
Accomplishment/Status
programs/ services
in their respective
plans
Variance Remarks
ii.
iii.
Orientation on Women, Peace, and Security for Batch 3-PreDeparture Orientation/Seminar(PDOS) organized by the
Foreign Service Institute was held on 27 July 2016. The
Page 10 of 11
Program/Activity/Project
Performance
Measures/
Indicators
Physical Target
FY 2016
Accomplishment/Status
Variance Remarks
OPAPP accepted the role of Focal Point for the Focal Point
Network for Women, Peace, and Security.
The NAP
Secretariat convened the National Steering Committee (NSC)TWG on 7 September 2016 to validate the findings on the
program review of the NAPWPS. The findings formed part of
the Philippine Statement, which was delivered by the
Philippine Governemnt Focal Point during the Foundational
Meeting of the Focal Point Network in the sidelines of the 21st
United Nations General Assembly on 23 September 2016.
Page 11 of 11