City Center Office Building Addition

Activity ID
Activity Name

Original Duration

EC00515 City Center Office

Remaining
Duration

681
Building Addition

EC00515.D&E Design and Engineering


EC1000

Design Building Addition

EC1010

Start Office Building Addition Project

EC1030

Review and Approve Designs

EC1050

Assemble Technical Data for Heat Pump

EC1160

Review Technical Data on Heat Pumps

EC00515.Found Foundation

554

Classic Schedule Layout


Schedule % Start
Complete

Finish

Total
Qtr 1,Float
2013
Mar

107

16.67% 01-Nov-10 03-Jul-13


A
100% 01-Nov-10 A 06-Apr-11 A

55

100% 01-Nov-10 A 19-Jan-11 A

100% 01-Nov-10 A

22

100% 17-Jan-11 A 17-Feb-11 A

100% 16-Feb-11 A 25-Feb-11 A

27

146

98

100% 24-Feb-11 A 06-Apr-11 A


22.02% 23-Feb-11 A 19-Sep-11

175

EC1090

Begin Building Construction

EC1100

Site Preparation

43

EC1230

Excavation

24

24

41.67% 02-May-11

06-Jun-11

127

EC1320

Install Underground Water Lines

12

12

0% 03-Jun-11

21-Jun-11

127

EC1330

Install Underground Electric Conduit

12

12

0% 03-Jun-11

21-Jun-11

127

EC1340

Form/Pour Concrete Footings

24

24

0% 21-Jun-11

26-Jul-11

127

EC1350

Concrete Foundation Walls

24

24

0% 25-Jul-11

26-Aug-11

127

EC1360

Form and Pour Slab

12

12

0% 26-Aug-11

14-Sep-11

127

EC1370

Backfill and Compact Walls

0% 13-Sep-11

19-Sep-11

127

EC1380

Foundation Phase Complete

EC00515.Structure Structure

100% 28-Feb-11 A
100% 23-Feb-11 A 18-Apr-11 A

0%

19-Sep-11

178

151

151

0% 19-Sep-11

20-Apr-12

306

25-Nov-11

127

EC1390

Erect Structural Frame

48

48

0% 19-Sep-11

EC1410

Begin Structural Phase

0% 25-Nov-11

EC1420

Floor Decking

34

34

0% 25-Nov-11

13-Jan-12

127

EC1430

Concrete First Floor

36

36

0% 11-Jan-12

01-Mar-12

127

EC1460

Erect Stairwell and Elevator Walls

24

24

0% 01-Mar-12

04-Apr-12

139

EC1470

Concrete Basement Slab

24

24

0% 01-Mar-12

04-Apr-12

139

EC1480

Concrete Second Floor

36

36

0% 01-Mar-12

20-Apr-12

127

EC1540

Structure Complete

0%

20-Apr-12

127

2.63% 14-Apr-11 A 26-Jun-13

562Systems
EC00515.Mechanicals Mechanical/Electrical

549

418

EC1490

Rough-In Phase Begins

0% 12-Mar-12

EC1690

Rough In Complete

0%

05-Feb-13

218

218

0% 04-Apr-12

12-Feb-13

EC00515.Mechanicals.Lifts Elevator
Actual Level of Effort

Remaining Work

Actual Work

Critical Remaining W...

Apr

26-Oct-15 23:45
Qtr 3, 2013
Qtr 2, 2013
Jul
May
Jun

Page 1 of 6

26-Jun-13, EC00515.M

234
Rough
0 In Complete,
12-Feb-13,
90
EC00515.Mechanicals.Lifts Elevator
TASK filter: All Activities
Oracle Corporation

City Center Office Building Addition


Qtr 3, 2013
Jul

Aug

Sep

Classic Schedule Layout


Qtr 1, 2014

Qtr 4, 2013
Oct

Nov

Dec

Jan

Feb

Mar

26-Oct-15 23:45
Qtr 3, 2014

Qtr 2, 2014
Apr

May

Jun

Jul

Aug

Sep

03-Jul-13, EC00515 City Center Office Building Addition

26-Jun-13, EC00515.Mechanicals Mechanical/Electrical Systems

Actual Level of Effort

Remaining Work

Actual Work

Critical Remaining W...

Page 2 of 6

TASK filter: All Activities


Oracle Corporation

City Center Office Building Addition


Activity ID
Activity Name

Original Duration

EC1520

Install Elevator Rails and Equipment

EC1710

Install Elevator Cab and Finishes

EC00515.Mechanicals.HVAC HVAC

Remaining
Duration
3

562

549

Classic Schedule Layout


Schedule % Start
Complete

Finish

26-Oct-15 23:45
Qtr 3, 2013
Qtr 2, 2013
Jul
May
Jun

Total
Qtr 1,Float
2013
Mar

Apr

0% 04-Apr-12

06-Apr-12

217

0% 05-Feb-13

12-Feb-13

Install
91 Elevator Cab and Finishes

3.85% 14-Apr-11 A 26-Jun-13

100% 14-Apr-11 A 04-May-11

26-Jun-13, EC00515.M

EC1190

Prepare and Solicit Bids for Heat Pump

15

EC1240

Review Bids for Heat Pump

10

10

79.17% 04-May-11

17-May-11

EC1270

Award Contract for Heat Pump

0% 17-May-11

25-May-11

EC1290

Fabricate and Deliver Heat Pump and Controls


422

422

0% 25-May-11

23-Jan-13 Fabricate and


0 Deliver Heat Pump and Controls

EC1500

Install HVAC Ducts

24

24

0% 12-Mar-12

13-Apr-12

186

EC1630

Insulate Ducts

0% 18-Jun-12

25-Jun-12

140

EC1650

Set Heat Pump

12

12

0% 04-Jan-13

22-Jan-13 Set Heat Pump


0

EC1670

Relocate HVAC Chiller

0% 22-Jan-13

01-Feb-13

EC1680

Startup and Test HVAC

0% 01-Feb-13

05-Feb-13

EC1770

Install AC Grills and Registers

0% 08-Apr-13

15-Apr-13

23

EC1830

Test and Balance HVAC Equipment

0% 21-Jun-13

26-Jun-13

258

0% 20-Jan-12

23-Jan-13 23-Jan-13, EC00515.Mechanicals.Systems


6
Plumbing and Electrical

36

36

0% 20-Jan-12

12-Mar-12

186

0% 24-Aug-12

29-Aug-12

72

36

36

0% 31-Aug-12

23-Oct-12

72

0% 22-Jan-13

23-Jan-13 Connect Equipment


6

336

289

258
EC00515.Mechanicals.Systems Plumbing and Electrical
EC1440

Set Mechanical and Electrical Equipment

EC1510

Rough-In Plumbing/Piping

EC1640

Install Wiring and Cable

EC1660

Connect Equipment

EC00515.Ex-Finish Exterior Finishes


EC1590

Close-In Phase Begins

EC1620

Building Enclosed

EC00515.Ex-Finish.Brick Brick

43.02% 17-Feb-11 A 19-Jun-12


0% 15-May-12

312

265

0%

100% 17-Feb-11 A

Relocate
0 HVAC Chiller
Startup
0 and Test HVAC

296
18-Jun-12

127

59.15% 17-Feb-11 A 15-May-12

124

Assemble Brick Samples

EC1070

Review and Approve Brick Samples

30

100% 28-Feb-11 A 13-Apr-11 A

EC1180

Prepare and Solicit Bids for Brick Exterior

15

100% 18-Mar-11 A 13-Apr-11 A

EC1220

Review Bids for Brick

15

100% 08-Apr-11 A 28-Apr-11 A

EC1260

Award Contract for Brick

8.33% 21-Apr-11 A 05-May-11

EC1280

Deliver Brick

0% 05-May-11

06-May-11

377

EC1550

Brick Exterior Walls

17

17

0% 20-Apr-12

15-May-12

127

24

24

0% 15-May-12

19-Jun-12

124

24

24

0% 15-May-12

19-Jun-12

127

EC1600

Insulation and Built-up Roofing

Actual Level of Effort

Remaining Work

Actual Work

Critical Remaining W...

Page 3 of 6

Test and Balance HVA

266

EC1040

EC00515.Ex-Finish.Roof Roof

Install AC Grills and Registers

377

TASK filter: All Activities


Oracle Corporation

City Center Office Building Addition


Qtr 3, 2013
Jul

Aug

Sep

Classic Schedule Layout


Qtr 1, 2014

Qtr 4, 2013
Oct

Nov

Dec

Jan

Feb

Mar

26-Oct-15 23:45
Qtr 3, 2014

Qtr 2, 2014
Apr

May

Jun

Jul

Aug

Sep

26-Jun-13, EC00515.Mechanicals.HVAC HVAC

Test and Balance HVAC Equipment

Actual Level of Effort

Remaining Work

Actual Work

Critical Remaining W...

Page 4 of 6

TASK filter: All Activities


Oracle Corporation

City Center Office Building Addition


Activity ID
Activity Name

Classic Schedule Layout


Schedule % Start
Complete

Original Duration

Remaining
Duration

0% 27-Apr-12

08-May-12

152

EC00515.Ex-Finish.Win Doors and Windows

Finish

Mar

EC1560

Install Door and Window Frames

0% 27-Apr-12

01-May-12

156

EC1580

Install Exterior Doors and Windows

0% 01-May-12

08-May-12

156

EC00515.Int-Finish Interior Finishes

601

554

10.68% 25-Feb-11 A 03-Jul-13

Drywall in Offices

36

36

0% 05-Feb-13

27-Mar-13

EC1820

Touch-up and Clean-up

0% 19-Jun-13

24-Jun-13

EC1840

Finishes Complete

0%

26-Jun-13

EC1850

Punch List

0% 26-Jun-13

03-Jul-13

EC1860

Building Addition Complete

0%

03-Jul-13

44

0% 08-Apr-13

10-Jun-13

EC1760

Install Lighting Fixtures

0% 08-Apr-13

17-Apr-13

21

EC1810

Install Plumbing Fixtures

0% 03-Jun-13

10-Jun-13

581
EC00515.Int-Finish.Coverings Floor and Carpeting

534

20.72% 25-Feb-11 A 04-Jun-13

EC1060

Assemble and Submit Flooring Samples

EC1080
EC1170

100% 25-Feb-11 A

Review and Approve Flooring

28

100% 25-Feb-11 A 11-Apr-11 A

Prepare and Solicit Bids for Flooring

24

100% 04-Apr-11 A 06-May-11

EC1250

Review Bids for Flooring

15

15

36.11% 06-May-11

27-May-11

231

EC1300

Award Contract for Flooring

0% 27-May-11

06-Jun-11

231

EC1310

Fabricate and Deliver Flooring

279

279

0% 03-Jun-11

06-Jul-12

231

EC1790

Install Floor and Carpeting

12

12

0% 16-May-13

04-Jun-13

59

59

0% 27-Mar-13

19-Jun-13

EC00515.Int-Finish.Carp Carpentry

Apr

EC1700

EC00515.Int-Finish.Fixtures Plumbing and Lighting44Fixtures

26-Oct-15 23:45
Qtr 3, 2013
Qtr 2, 2013
Jul
May
Jun

Total
Qtr 1,Float
2013

Drywall in Offices

Touch-up and Clean-up


Finishes Complete,

10-Jun-13, EC00515.Int-Finis
Install Lighting Fixtures
Install Plumbing Fixtures

04-Jun-13, EC00515.Int-Finish.C

231

Install Floor and Carpeting

19-Jun-13, EC00515.Int-F

EC1740

Install Ceiling Grid

36

36

0% 27-Mar-13

16-May-13

EC1800

Finish Carpentry and Millwork

12

12

0% 03-Jun-13

19-Jun-13

12

12

0% 14-Feb-13

04-Mar-13

76

04-Mar-13, EC00515.Int-Finish.Paint Paint

12

12

0% 14-Feb-13

04-Mar-13

77

Paint Building Interior

EC00515.Int-Finish.Paint Paint
EC1720

Paint Building Interior

Actual Level of Effort

Remaining Work

Actual Work

Critical Remaining W...

Page 5 of 6

Install Ceiling Grid

Finish Carpentry and Millw

TASK filter: All Activities


Oracle Corporation

City Center Office Building Addition


Qtr 3, 2013
Jul

Aug

Sep

Classic Schedule Layout


Qtr 1, 2014

Qtr 4, 2013
Oct

Nov

Dec

Jan

Feb

Mar

26-Oct-15 23:45
Qtr 3, 2014

Qtr 2, 2014
Apr

May

Jun

Jul

Aug

Sep

03-Jul-13, EC00515.Int-Finish Interior Finishes

Touch-up and Clean-up


Finishes Complete,
Punch List
Building Addition Complete,
10-Jun-13, EC00515.Int-Finish.Fixtures Plumbing and Lighting Fixtures
Install Plumbing Fixtures

4-Jun-13, EC00515.Int-Finish.Coverings Floor and Carpeting

stall Floor and Carpeting


19-Jun-13, EC00515.Int-Finish.Carp Carpentry
Finish Carpentry and Millwork

Actual Level of Effort

Remaining Work

Actual Work

Critical Remaining W...

Page 6 of 6