Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

ITEM

PILE CAP
A. Excavation

METHOD

QTY

1. Not exceeding 1.50m 108m3 Excavator


deep. (Provisional)
2. Exceeding 1.50m deep 44m3
but not exceeding 3.0m
deep. (Provisional)

B. Lean Concrete 50mm thick grade 15 as 72m2


described, spread, levelled
to receive concrete.
C. Formwork

Mobile crane
Concrete skip

LABOUR

High Tensile Steel Bar


Mobile crane
Reinforcement
Bending machine
1. 12mm diameter as 3427kg
main bar
2. 12mm diameter as 760kg
loops

Vibrated reinforced concrete 40m3


Grade 30 as described.

WORK BELOW LOWEST FLOOR FINISHES

Mobile crane
Concrete skip
Concrete mixer

OUTPUT

DURATION
(DAYS)

APPENDIX

8 days
5

2.80hr/m3

3 days

1 (a)

=11 days

Sawn
formwork
as 201m2 Hammer
described to sides of pile
Saw
caps.

D. Reinforcement

E. Concreting

PLANT

2.88hr/m3

9 days

1 (b)

4 days
8

1.25hr/m2

1 (c)

23 days
3

0.16hr/kg

5 days

1 (d)

= 28 days
5

9.00hr/m3

9 days

1 (e)

WORK BELOW LOWEST FLOOR FINISHES (CONTD)


ITEM
PAD FOOTING
A. Excavation

METHOD

QTY

1. Not exceeding 1.50m 8m3


deep (Provisional)
2. Exceeding 1.50m deep 2m3
but not exceeding 3.0m
deep. (Provisional)

PLANT

LABOUR

OUTPUT

DURATION
(DAYS)

APPENDIX

1 day
Excavator

2.80hr/m3

1 day

1 (f)

= 2 days

B. Lean Concrete 50mm thick Grade 15 as 5m2


described,
spread
and
levelled to receive concrete.

Mobile crane
Concrete skip

2.88hr/m3

1 day

1 (g)

C. Formwork

Hammer
Saw

1.25hr/m3

1 day

1 (h)

D. Reinforcemen
t

E. Concreting

Sawn
formwork
as 7m2
described to sides of pad
footing.

High Tensile Steel Bar


Reinforcement
1. 12mm diameter as 92kg
main bar.
2. 10mm diameter as 15kg
main bar.

Vibrated reinforced concrete 1m3


Grade 30 as described.

Mobile crane
Bending
machine

1 day
3

0.16hr/kg

1 day

1 (i)

= 2 days
Mobile crane
Concrete skip
Concrete mixer

9.00hr/m3

1 day

1 (j)

WORK BELOW LOWEST FLOOR FINISHES (CONTD)


ITEM
COLUMN
STUMP
A. Formwork

B. Reinforcemen
t

C. Concreting

METHOD

QTY

Sawn
formwork
as 264m2
described to sides of
column
stump.
(Provisional)

Mild
Steel
Bar
Reinforcement
1. 6mm diameter as 25kg
links. (Provisional)

High Tensile Steel Bar


Reinforcement
1. 25mm diameter as
main bar.
2. 20mm diameter as
main bar.
3. 16mm diameter as
main bar.
4. 12mm diameter as
main bar.
5. 10mm diameter as
links

Vibrated

reinforced

296kg
122kg

PLANT

Hammer
Saw

LABOUR

OUTPUT

1.25hr/m2

DURATION
(DAYS)

14 days

APPENDIX

1 (k)

1 day

Mobile crane
Bending
machine

1 day
8

0.16hr/kg

1 day

1 (l)

3 days

1028kg

1 day

340kg

1 day

57kg

= 8 days
Mobile crane

9.00hr/m3

5 days

1 (m)

Concrete skip
Concrete mixer
WORK BELOW LOWEST FLOOR FINISHES (CONTD)
concrete Grade 30 as
described. (Provisional)
22m3

ITEM
GROUND
BEAM
A. Formwork

METHOD

Sawn
formwork
as
described to sides and soffit. 865m2
(Provisional).

B. Reinforcement

3. Concreting

QTY

PLANT

Hammer
Saw

LABOUR

OUTPUT

DURATION
(DAYS)

APPENDIX

1.25hr/m2

27 days

1 (n)

Mild
Steel
Bar
Reinforcement
1. 10mm diameter as 1870kg
stirrups.
2. 6mm diameter as 1666kg
stirrups.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.

4 days
3 days

Mobile crane
Bending
machine
3859kg

10

0.16hr/kg

1 (o)

4 days

1772kg

2 days

827kg

5 days

2497kg

Vibrated reinforced concrete 77m3

8 days

= 26 days
Mobile crane

9.00hr/m3

17 days

1 (p)

Concrete skip
Concrete mixer
WORK BELOW LOWEST FLOOR FINISHES (CONTD)
Grade 30 as described

ITEM
GROUND
FLOOR SLAB
A. Formwork

B. Reinforcement

C. Concreting

METHOD

QTY

Sawn
formwork
as
described to:
1. Soffit.
887m2
2. Edge of slab not 81m
exceeding 100mm high.
3. Edge of slab exceeding 452m
100mm
but
not
exceeding 200mm high.

PLANT

Hammer
Saw

OUTPUT

1.25hr/m2
5

1.00hr/m
1.25hr/m

DURATION
(DAYS)

APPENDIX

28 days
2 days

1 (q)

14 days
= 44 days

Mild
steel
fabric
Mobile crane
reinforcement as described,
Bending
including laps, cutting,
machine
bending
and
notching
around obstructions.
1. A7 (weight 3.02kg/m2)
937m2
2. A8 (weight 3.95kg/m2)
1321m2
1. 150mm thick vibrated 663m2
reinforced
concrete
Grade 30 as described.
2. 125mm thick vibrated 413m2
reinforced
concrete
Grade 30 as described.

LABOUR

Mobile crane
Concrete skip
Concrete mixer

2 days
10

0.2hr/m2

1 (r)
3 days
= 5 days
14 days

9.00hr/m3

7 days
= 21 dyas

1 (s)

FRAME
ITEM

METHOD

LABOUR

OUTPUT

DURATION
(DAYS)

APPENDIX

1.08hr/m2

13 days

3 (a)

46hr/tonne

1 day

20hr/tonne

1 day

20hr/tonne

1 day

5373kg

32hr/tonne

4 day

379kg

22hr/tonne

1 day

513kg

46hr/tonne

1 day

QTY

COLUMN
A. Formwork
Sawn
formwork
described to sides
columns.
B. Reinforcement

C. Concreting

as 777m2
of

Mild
Steel
Bar
Reinforcement
1. 6mm diameter as 511kg
links.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.
5. 10mm diameter as
links.

PLANT

Hammer
Saw
Mobile crane
Bending machine

142kg
5

342kg

Vibrated reinforced concrete 54m3

3 (b)

= 9 days
Mobile crane

4.40hr/m3

4 days

3 (c)

Concrete skip
Concrete mixer

Grade 30 as described.

FRAME (CONTD)
ITEM
BEAM
A. Formwork

METHOD
Sawn
formwork
described to sides
soffits of beams.

B. Reinforcement

LABOUR

OUTPUT

DURATION
(DAYS)

APPENDIX

0.94hr/m2

18 days

3 (d)

24hr/tonne

1 day

24hr/tonne

1 day

12hr/tonne

2 days

1205kg

12hr/tonne

1 day

2112kg

16hr/tonne

1 day

2315kg

22hr/tonne

1 day

QTY

PLANT

as
Hammer
and 1198m2 Saw

Mild
Steel
Bar
Mobile crane
Reinforcement
Bending machine
1. 6mm diameter as 1088kg
stirrups.
2. 10mm diameter as 1969kg
stirrups.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.

8005kg

= 7 days

3 (e)

C. Concreting

Vibrated reinforced concrete 90m3


Grade 30 as described.

Mobile crane
Concrete skip
Concrete mixer

4.40hr/m3

6 days

3 (f)

LABOUR

OUTPUT

DURATION
(DAYS)

APPENDIX

0.94hr/m2

11 days

3 (g)

FRAME (CONTD)
ITEM
ROOF BEAM
A. Formwork

METHOD
Sawn
formwork
described to sides
soffits of beams.

B. Reinforcement

QTY
as
and 747m2

PLANT
Hammer
Saw

Mild
Steel
Bar
Mobile crane
Reinforcement
Bending machine
1. 6mm diameter as 1109kg
stirrups.
2. 10mm diameter as 267kg
stirrups.
High Tensile Steel Bar
Reinforcement
1. 25mm diameter as
main bars.
2. 20mm diameter as
main bars.
3. 16mm diameter as
main bars.
4. 12mm diameter as
main bars.

3 (h)
24hr/tonne

1 day

24hr/tonne

1 day

1674kg

12hr/tonne

1 day

559kg

12hr/tonne

1 day

559kg

16hr/tonne

1 day

1501kg

22hr/tonne

1 day

= 6 days
C. Concreting

Vibrated reinforced concrete 63m3


Grade 30 as described.

Mobile crane
Concrete skip
Concrete mixer

4.40hr/m3

7 days

3 (i)

LABOUR

OUTPUT

DURATION
(DAYS)

APPENDIX

0.94hr/m2

2 days

0.94hr/m2

8 days

1.00hr/m

12 days

FRAME (CONTD)
ITEM

METHOD

QTY

UPPER FLOOR
SLABS
A. Formwork
1. Wrot
formwork
as 132m2
described to soffit of
floor slabs.
2. Sawn
formwork
as 564m2
described to soffit of
floor slabs.
3. Sawn
formwork
as 797m
described to edge of
slab, not exceeding
100mm high.
B. Reinforcement 1. Mild
steel
fabric 724m2
reinforcement
A7
(weight 3.02kg/m2) as
described,
including
laps, cutting, bending
and notching around
obstructions.

PLANT

Hammer
Saw
8

3 (j)

= 22 days
Mobile crane
Bending machine

10

0.2hr/m2

4 days

6 days

3 (k)

2. Mild
steel
fabric 1168m2
reinforcement
A8
(weight 3.95kg/m2) as
described,
including
laps, cutting, bending
and notching around
obstructions.
C. Concreting

1. 150mm thick vibrated 531m3


reinforced
concrete
Grade 30 as described.
2. 125mm thick vibrated 328m3
reinforced
concrete
Grade 30 as described.

= 10 days

Mobile crane
Concrete skip
Concrete mixer

11 days
8

1.35hr/m3

7 days
= 18 days

3 (l)

You might also like