Professional Documents
Culture Documents
DMT Test Tank 3 Des 2013
DMT Test Tank 3 Des 2013
:
Your Reff :
021/R00/DMT-CRB/XII/2013
145/DMT-Q/MTP/XII/2013
To
Attn
COMMERCIAL OFFER
Dear Mr. Rahmat,
Thank you for your inqury, we have the pleasure to send herewith our offer with the following description
are below :
No
Description
Supply Material, Fabrication, civil work & instalation of :
"2 unit Tangki Test @250 bbl,
Qty
2 Set
Unit Price
Rp 212.500.000 Rp
Amount
425.000.000
Civil Work
- Lantai Kerja Cor Beton 1:3:5 t 5 cm
- Urugan Pasir : t 10 cm
- Urugan Tanah (dipadatkan) : t 15 cm
- Pondasi Tangki : Cor beton 1:2:3 tebal 20 cm
- Pembesian : dia 15 cm
- Dim Pondasi per tangki : 3.7 m x 3.7 m
- Overal Dim : 16 m x 6 m
- c/w Bund Wall height 1.2 m; parit keliling;
Bak kontrol
- centre to centre Test Tank : 7.9 m
- Piling work 16 position for 2 (two) unit tank,
exclude Pile Pipe material (pipe dia4" - 9 m
depth per point)
- Direksi Kit dim : 3m x 3m
1 Lot
Rp 115.000.000 Rp
Transportation to Site
2 Lot
Rp
3.125.000 Rp
6.250.000
Installation of Tank
2 Lot
Rp
18.750.000 Rp
37.500.000
Rp
583.750.000
TOTAL
115.000.000