Microsoft Project
Microsoft Project
INTRODUCTION
What is project planning?
Project planning is the process of identifying all the
activities necessary to successfully complete the
project. It is also the process of determining the
workable work scheme to achieve project objectives.
What is project scheduling?
Project scheduling is a process to identify sequence of
work or activities involve and determine realistic time
for each activities with start time and finish time.
INTRODUCTION
REVISED/CONTROL
PROJECT GOAL
MONITOR
PLAN
QUALITY
COST
EVALUATE
PLANNING TOOL
Microsoft Project/Primavera-planning tools
Uses to do the planning and for project
monitoring and control
Types of planning file:
baseline file (initial planning)
tracking file (Monitoring and control)
new baseline file/Schedule Updating (Revise
program)
Project Information
Project Title: Construction of Dream House at
Parit Raja
Project Start Date: 1st November 2016
Project Finish Date : 30 April 2017
Project Duration: 6 months
Contract Sum: RM 200,000.00
Working Calendar: Sunday is non-working day
Holiday: State and Federal
WBS List
Bungalow in Parit Raja
Project Start
Preliminaries
Performance Bond/Insurance
Establish and Removal of Site
Office
Progress Report
Land Acquisition
Earthwork
Site Clearing
Excavation , Backfilling and
Leveling
Piling Work
Building Work
Structure
Sub Structure
Super Structure
Roof Trusses
- Architecture
Wall
Floor Finishes
Painting
Internal
external
- M&E
Electrical
Wiring
Switches and Sockets
Plumbing
Piping
Sanitary Fixtures
Infrastructure
- Road and drainage
- TNB and Water Meter Supply
Testing and Commissioning
Project Finish
File>New>Blank Project
Project>Change Working Time>Exceptions> List all the agreed public holidays for project
Id no 1 (Project name)
Id no 2 (Project Startcritical milestone)
Final Id (Project Finishcritical milestone)
Project Start (0
days)
Land acquisition
(0days)
TNB and Water
Meter Supply
(0days)
Project Finish
(0days)
Recurring Task
RECURRING TASK
Choose
frequency of
the recurrent
Retype the
task name
Recurring is
task that occur
at a fixed
frequency and
continuously
e.g: weekly staff
Decide duration
meetings,
allocated for the
preparation of the
quarterly
document
reports or
Decide
reporting
monthly budget
date in the
calendar
review.
Enables you to
Set the range
create the
in between
meeting task
the contract
period (finish
once and assign
date)
a frequency and
timing to it.
RECURRING TASK
Activity Sequencing
How to decide?
Experience
Method Statements
Drawings
Detail Bill of Quantity (BQ)
Using Experience
Parametric Estimation
D=Q/PR
Quantity
Earthwork
10,000m3
+10%
11 days
Structural Works
2000m3
Testing +7 days
17 days
Architectural
Works
3,000m2
Delivery + 5 days
20 days
M&E Works
400nos
Procurement + 5
days
25 days
Building Works
Production rate
Earthwork Team
[1]
1000m3/day/gang
Structure Team
[2]
100m3/day/gang
Architecture Team
[2]
100m2/day/gang
M&E Team
[2]
10nos/day/gang
Resource Planning
Value of Work
Work
Preliminaries
Performance Bond/Insurance
Establish and Removal of Site Office
Progress Report
Earthwork
Piling
Building Work
Value (RM)
10,000
10,000
3,000
10,000
12,000
Sub Structure
Super Structure
Roofing
Architecture
25,000
30,000
7,000
Wall
Floor
Painting
M&E
Electrical
Plumbing
Road and Drainage
Total
28,000
20,000
5,000
15,000
15,000
10,000
200,000
Payment
Method, choose
Start, Prorated or
End
View>Table>Cost
Cost Calculated
(Baseline) must
equal to Total
Cost
Financial S-Curve
Cash Flow Report
Cost
Cumulative Cost
14000
250000
12000
200000
150000
Cost
8000
6000
100000
4000
50000
2000
0
Week
Week
9 Week
10Week
11Week
12Week
13Week
14Week
15Week
16Week
17Week
18Week
19Week
20Week
21Week
22Week
23Week
24Week
25Week
26Week
27Week
28Week
29Week
30Week
31Week
32Week
33Week
34Week
35Week
36 37
Q1
Q2
Q3
2013
Cumulative Cost
10000
View>Tasks>Tracking
View>Task Usage>Detail Styles>insert the Percent Complete and Cumulative Percent Complete
> ok!
% complete
cum %
complete
0 1% 3% 3% 2% 4% 2% 2% 2% 3% 2% 2% 2% 2% 4% 5% 3% 2% 6% 5% 4% 5% 8% 5% 3% 5% 2% 6% 2%
1%
0 1% 4% 7% 9% 13% 15% 18% 20% 24% 26% 28% 31% 33% 37% 42% 45% 48% 53% 58% 62% 67% 75% 80% 83% 88% 91% 97% 99% 100%
Physical S-Curve
1.2
0.8
% complete
0.6
cum % complete
0.4
0.2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Physical S-Curve
Physical S-Curve
1.2
0.8
% complete
0.6
cum % complete
0.4
0.2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Thank You
End of Course