Group 2 Project Status Report Problems Rwade
Group 2 Project Status Report Problems Rwade
Schedule
Percent Complete:
Cost
Risks
28%
Quality
The project is currently behind schedule. Delays in the Requirement Gathering (WBS 1.2.1)
have caused the rest of the project to be pushed back. In addition, there were delays in the Client
Review and Approval (WBS 1.2.2.6). Although, the scope, risks, and quality, of the project
remain Green it is necessary to convey that these delays have pushed the schedule and the
cost into the yellow zones causing need for concern and explanation, at this point there is no
need for corrective action since the delays have not yet gone beyond the threshold of 0.8 or 1.2.
However, it is cause to note that the delays in the project result from the issue that there have
been delays due to the GENERAL SUPPLIES returning approved and requested materials in a
timely fashion. We request that GENERAL SUPPLIES addresses this issue internally to ensure
that there are no future delays in the project.
The current actual value of the project as of 3/25/2016 is $118,098.25. To date, this falls behind
the planned value of the project (or budgeted cost) of $124,855.00.
As of the date of this report the Cost Performance Index (CPI) rates at 1.01 which is an indication
that the project is working under budget, but this is reflective of work that has been missed.
Schedule Performance Index (SPI) is registering at 0.95 which is an indication that the progress
of the project is running 5% behind schedule.
OPEN ISSUES
Awaiting sign off from client on site design to move forward with Build Phase (WBS 1.4)
OPEN RISKS
Currently there are no open risks
WBS
Planned
Forecasted
Actual
Status
1.1.1
1.1.3
1.2
1.3
1.5
12/22/15
1/14/16
2/24/16
3/25/16
5/26/16
12/22/25
1/14/16
2/24/16
3/25/16
5/26/16
Met
Met
Met
Completed
Completed
Completed
On Schedule
On Schedule
1.6
7/18/16
7/18/16
On Schedule
1.7
8/17/16
8/17/16
On Schedule
Change Request
Number
Request Date
Current Status
1.01