Professional Documents
Culture Documents
PWA Comments Contractor Answer: Testing Iru3613Hqvwrfn - Mar-2016 /7 - Mar-2016 1$ 1$ $ssuryhg 1 00 MM 3HQVWRFN
PWA Comments Contractor Answer: Testing Iru3613Hqvwrfn - Mar-2016 /7 - Mar-2016 1$ 1$ $ssuryhg 1 00 MM 3HQVWRFN
reference
PWA
comments
date
Testing IRU3613HQVWRFN
RFI-01 details:
MQ
280151000- MOL-PWA-/7-
reference
PWA CTS
1$
reference
Date of
Monday, th March 2016 on 8.30 am @ PS-1
testing
Testing for PS-1 00 mm 3HQVWRFN
PWA Comments
Submitting
date
Receiving
date
-Mar-2016
-Mar-2016
1$
Status
$SSURYHG
Reply date
14-Mar-2016
Contractor Answer
4
Page 1 of
All the leakage records were taken with filling of upstream manhole
with water column height is .6 m as per attached network layout.
a. Verticality of headstock to be checked and confirmed.
Confirmed.
b. Penstock extension spindle is not aligned properly in the
intermediate guide locations and appeared to be abnormally
bent.