HISTORY OF BETTERGROUND
History of Betterground
1901-1970
1900
1958
1938
1978
1974
1986
1980
Betterground Ltd.
(Switzerland) was founded
in early 2009 and was
immediately joined by the
most experienced technical
experts in the world.
1994-2001
1990 - 1996
2009
2001 - 2009
2009 - 2013
2012 - 2013
Licence agreements
between Soletanche
S.A., in France and
Vibroflotation AG and a
Joint venture between
Vibroflotation AG and
Bachy-Soletanche were
established in Hong Kong.
S a l es , Re n ta l , J oi n t Ve nt u re s
Betterground Ltd.
Specialized Equipment
Service & Repair
Methods Expertise
S a l es , Re n ta l , J oi n t Ve nt u re s
Soilmechanics GmbH
Betterground Ltd.
Design Support
Specialized Equipment
Methods Expertise
S a l es , Re n ta l , J oi n t Ve nt u re s
Local Contractor
Soilmechanics GmbH
Betterground Ltd.
Design Support
Specialized Equipment
Methods Expertise
S a l es , Re n ta l , J oi n t Ve nt u re s
PROJECT
Local Contractor
Soilmechanics GmbH
Betterground Ltd.
Design Support
Specialized Equipment
Methods Expertise
S a l es , Re n ta l , J oi n t Ve nt u re s
PROJECT
Local Contractor
Soilmechanics GmbH
Betterground Ltd.
Design Support
Specialized Equipment
Methods Expertise
Financing
Standard equipment
Local market knowledge
Specialty equipment & service
Vibro Methods Expert
Soil mechanical design & site support
S a l es , Re n ta l , J oi n t Ve nt u re s
5
Engineered Ground Improvement
Saturday, November 29, 14
6
Engineered Ground Improvement
Saturday, November 29, 14
7
Saturday, November 29, 14
7
Saturday, November 29, 14
7
Saturday, November 29, 14
7
Saturday, November 29, 14
7
Saturday, November 29, 14
7
Saturday, November 29, 14
7
Saturday, November 29, 14
7
Saturday, November 29, 14
Slope stability, but also liquefaction prevention and static settlement reduction
7
Saturday, November 29, 14
Slope stability, but also liquefaction prevention and static settlement reduction
7
Saturday, November 29, 14
Slope stability, but also liquefaction prevention and static settlement reduction
Quality Control
7
Saturday, November 29, 14
Slope stability, but also liquefaction prevention and static settlement reduction
Quality Control
7
Saturday, November 29, 14
Slope stability, but also liquefaction prevention and static settlement reduction
Quality Control
7
Saturday, November 29, 14
Slope stability, but also liquefaction prevention and static settlement reduction
Quality Control
7
Saturday, November 29, 14
Slope stability, but also liquefaction prevention and static settlement reduction
Quality Control
7
Saturday, November 29, 14
Wet Top Feed Method: Why it doesn't work well under water
8
Saturday, November 29, 14
Wet Top Feed Method: Why it doesn't work well under water
8
Saturday, November 29, 14
Wet Top Feed Method: Why it doesn't work well under water
8
Saturday, November 29, 14
Wet Top Feed Method: Why it doesn't work well under water
8
Saturday, November 29, 14
Wet Top Feed Method: Why it doesn't work well under water
8
Saturday, November 29, 14
9
Saturday, November 29, 14
11
10
Saturday, November 29, 14
11
10
Saturday, November 29, 14
11
10
Saturday, November 29, 14
11
10
Saturday, November 29, 14
11
10
Saturday, November 29, 14
11
Saturday, November 29, 14
Slope Stability
with Stone Columns
12
Saturday, November 29, 14
13
Saturday, November 29, 14
13
Saturday, November 29, 14
13
Saturday, November 29, 14
13
Saturday, November 29, 14
13
Saturday, November 29, 14
13
Saturday, November 29, 14
13
Saturday, November 29, 14
Gravelpump GP1
60
Saturday, November 29, 14
15
Saturday, November 29, 14
15
Saturday, November 29, 14
15
Saturday, November 29, 14
16
Saturday, November 29, 14
17
Saturday, November 29, 14
18
Saturday, November 29, 14
19
Saturday, November 29, 14
HKBCF Cross Section: Stone Columns over an approx. 70 wide zone under the slopes of the embankment
20
Saturday, November 29, 14
21
Saturday, November 29, 14
22
Saturday, November 29, 14
Betterground offshore rig for extreme and for moderate AHR requirement
Non usable
length = ZERO
Additional
submersible
length: 6 m
Non usable
length
23
Saturday, November 29, 14
24
Saturday, November 29, 14
24
Saturday, November 29, 14
24
Saturday, November 29, 14
24
Saturday, November 29, 14
25
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
3. Wait for 80% consolidation in wick drain treated zone
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
3. Wait for 80% consolidation in wick drain treated zone
4. Install tapered stone columns
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
3. Wait for 80% consolidation in wick drain treated zone
4. Install tapered stone columns
5. Fill to +2.5 mPD
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
3. Wait for 80% consolidation in wick drain treated zone
4. Install tapered stone columns
5. Fill to +2.5 mPD
6. Wait for 50% consolidation in Stone Column zone
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Wick Drains & Surcharge as preparation for later Stone Column treatment
1. Apply 2 m of fill
2. Install Wick Drains to only 10 m depth
3. Wait for 80% consolidation in wick drain treated zone
4. Install tapered stone columns
5. Fill to +2.5 mPD
6. Wait for 50% consolidation in Stone Column zone
7. Fill to +5.5 mPD and surcharge in Hinterland
10
15
20
25
Cu [kPa]
10
20
Depth [m]
26
Saturday, November 29, 14
Quality Control
27
Saturday, November 29, 14
Quality Control
Visual inspection
27
Saturday, November 29, 14
Quality Control
Visual inspection
Digital records of installed column geometry
27
Saturday, November 29, 14
Quality Control
Visual inspection
Digital records of installed column geometry
Cone penetration test, vane shear test, before and after treatment
27
Saturday, November 29, 14
Quality Control
Visual inspection
Digital records of installed column geometry
Cone penetration test, vane shear test, before and after treatment
Monitoring of induced settlement after treatment
27
Saturday, November 29, 14
Quality Control
Visual inspection
Digital records of installed column geometry
Cone penetration test, vane shear test, before and after treatment
Monitoring of induced settlement after treatment
Full scale load test or very well instrumented smaller scale test
27
Saturday, November 29, 14
Quality Control
Visual inspection
Digital records of installed column geometry
Cone penetration test, vane shear test, before and after treatment
Monitoring of induced settlement after treatment
Full scale load test or very well instrumented smaller scale test
27
Saturday, November 29, 14
Visual Inspection
28
Saturday, November 29, 14
29
Saturday, November 29, 14
30
Saturday, November 29, 14
31
Saturday, November 29, 14
10 m
20 m
31
Saturday, November 29, 14
10 m
20 m
31
Saturday, November 29, 14
10 m
20 m
31
Saturday, November 29, 14
10 m
20 m
31
Saturday, November 29, 14
32
Saturday, November 29, 14
Load Testing
Load Testing
33
Saturday, November 29, 14
Surcharge load test: Can be done easily also for underwater treatment areas.
34
Saturday, November 29, 14
Zone load test using jack and dial gauges: Next to impossible to do under water
35
Saturday, November 29, 14
5 m x 5 m trial load with the aim to extrapolate the behavior of a large diameter (over 70 m) oil tank
36
Saturday, November 29, 14
37
Saturday, November 29, 14
Load Test 5 m x 5 m Plate and 150 kPa, Soil layering from CPT and borehole information
38
Saturday, November 29, 14
5 m x 5 m Trial Pad: Instrumentation necessary to gain information for back-calculation with Plaxis 3D
39
Saturday, November 29, 14
Plaxis 3D: Columns at working load level, outward deformation of perimeter columns already visible
40
Saturday, November 29, 14
41
Saturday, November 29, 14
Crosses
show
Sigma
1
(mainly
ver4cal)
and
Sigma
3
(mainly
horizontal)
stresses.
Under
foo4ng
Sigma
1
is
150
kPa,
as
it
should
be.
In
the
upper
Clay
(purple)
the
stresses
in
the
Columns
reach
400
kPa.
400
kPa
means
stress
concentra4on
factor
400/150
=
2.66.
In
the
silty
and
sandy
soils
stresses
distribute
almost
equally
between
columns
and
soil.
In
the
lower
Clay
(9.5
m
down,
blue
layer)
the
columns
again
concentrate
stresses
on
themselves.
42
Saturday, November 29, 14
Soil Sounding
Soil Sounding
43
Saturday, November 29, 14
44
Saturday, November 29, 14
44
Saturday, November 29, 14
44
Saturday, November 29, 14
44
Saturday, November 29, 14
In Marine Clays Post CPTs instantly after treatment would not show any improvement of tip resistance as
this can be shown for the more sandy layers in the below example from Pier 400 in Los Angeles.
44
Saturday, November 29, 14
In Marine Clays Post CPTs instantly after treatment would not show any improvement of tip resistance as
this can be shown for the more sandy layers in the below example from Pier 400 in Los Angeles.
In Marine Clays the instant improvement provided is accelerated drainage and instant increase in shear
strength of the compound material Soil & Column, not an increase in tip resistance of the soil itself.
44
Saturday, November 29, 14
In Marine Clays Post CPTs instantly after treatment would not show any improvement of tip resistance as
this can be shown for the more sandy layers in the below example from Pier 400 in Los Angeles.
In Marine Clays the instant improvement provided is accelerated drainage and instant increase in shear
strength of the compound material Soil & Column, not an increase in tip resistance of the soil itself.
Field vane tests, done months after treatment, can give valuable confirmation of soil strengthening.
44
Saturday, November 29, 14
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
In soft Marine Deposits tapered stone columns (in top thicker diameter than bottom) in combination with
wick drains and surcharge are a way to save time and cost.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
In soft Marine Deposits tapered stone columns (in top thicker diameter than bottom) in combination with
wick drains and surcharge are a way to save time and cost.
Under water visual inspection of columns is not possible. This makes logging of installation parameters
more important.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
In soft Marine Deposits tapered stone columns (in top thicker diameter than bottom) in combination with
wick drains and surcharge are a way to save time and cost.
Under water visual inspection of columns is not possible. This makes logging of installation parameters
more important.
To identify defective columns, printout of process parameters must be over time not over depth.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
In soft Marine Deposits tapered stone columns (in top thicker diameter than bottom) in combination with
wick drains and surcharge are a way to save time and cost.
Under water visual inspection of columns is not possible. This makes logging of installation parameters
more important.
To identify defective columns, printout of process parameters must be over time not over depth.
The patented Betterground Operator Guidance System makes it obsolete to use operators with many
years of experience. Operators with zero stone column experience built equally good columns.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
In soft Marine Deposits tapered stone columns (in top thicker diameter than bottom) in combination with
wick drains and surcharge are a way to save time and cost.
Under water visual inspection of columns is not possible. This makes logging of installation parameters
more important.
To identify defective columns, printout of process parameters must be over time not over depth.
The patented Betterground Operator Guidance System makes it obsolete to use operators with many
years of experience. Operators with zero stone column experience built equally good columns.
Load testing of stone columns over a limited area needs to be well instrumented to allow for proper back
calculations with 3D simulation software.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
In soft Marine Deposits tapered stone columns (in top thicker diameter than bottom) in combination with
wick drains and surcharge are a way to save time and cost.
Under water visual inspection of columns is not possible. This makes logging of installation parameters
more important.
To identify defective columns, printout of process parameters must be over time not over depth.
The patented Betterground Operator Guidance System makes it obsolete to use operators with many
years of experience. Operators with zero stone column experience built equally good columns.
Load testing of stone columns over a limited area needs to be well instrumented to allow for proper back
calculations with 3D simulation software.
Load needs to be applied gradually and not instantly onto Stone Columns to allow for drainage of soil
around columns. It is the matrix of Soil & Columns that bears the load, not the columns alone.
45
Saturday, November 29, 14
Wet Top Feed Stone Columns are not recommended for offshore projects due to quality concerns.
Extreme Airport Height Restriction requires custom built equipment. A few meters more height clearance
would go a long way in saving cost.
In soft Marine Deposits tapered stone columns (in top thicker diameter than bottom) in combination with
wick drains and surcharge are a way to save time and cost.
Under water visual inspection of columns is not possible. This makes logging of installation parameters
more important.
To identify defective columns, printout of process parameters must be over time not over depth.
The patented Betterground Operator Guidance System makes it obsolete to use operators with many
years of experience. Operators with zero stone column experience built equally good columns.
Load testing of stone columns over a limited area needs to be well instrumented to allow for proper back
calculations with 3D simulation software.
Load needs to be applied gradually and not instantly onto Stone Columns to allow for drainage of soil
around columns. It is the matrix of Soil & Columns that bears the load, not the columns alone.
45
Saturday, November 29, 14