Padcal Kick Off Meeting Oct 28 Updates
Padcal Kick Off Meeting Oct 28 Updates
Type of Meeting:
Attendees:
Apologies:
Distribution:
Meeting No:
Date:
28-Oct-15
Who
When
Attendees
No Agenda
Item
Action / Comment
Status
1.0 QHSE -
ASAP
Already in place
Plan in place; Risk register
ongoing
02-Nov-15
Sir Val
Sir Val and Sir
Nelson
06-Nov-15
06-Nov-15
Agreement to be made on
November 6, 2015
Info
30-Oct-15
2.0 Corporate
2.1.1
Notice to Proceed signed last week so programme has now commenced. Contract is to be signed soon and is
remesurable
2.2.1
Introduction of Sir Ulrich Dienstbach as the AVP for Operations (padcal) and he'll be working with Sir Nelson on the Padcal
project starting Nov 2.
3.0 Operations
3.1 Program Started Oct 14, 2015 and target end date Oct 1, 2016
3.1.2
Prepare detailed program Schedule and discuss with Sir Ulrich within the day
3.1.3
3.1.4
3.1.5
Structured drawings of the temporary facilities and others should be presented and discussed with Sir Ulrich
People would work 7 days a week even on holidays until project completed
Preparation and proper documentation flow chart for outlining of daily Accomplishment reports, detailed with person
involved, tasks, activities, hours and instructions of the client
3.1.6
3.1.7
Water Supply to Batch plant will be acquired from existing Pond- Check Temperature quality
Temporary Facilities: Drawings- Quality need to be further discussed and approved
3.1.7
3.1.8
Batch Plant: Foundation design; Customs already paid (Oct 21, 2015)
3.1.8
This Week
on going
This Week
Info
30-Oct-15
This Week
Already in place
Temporary Work: PM propose mix on site with truck mixer; Check local supplier for concrete
ongoing
ASAP
Already in place
4.1.3
Identify the role of the HR onsite and prepare a strategy of recruitment with the help of HR Head office
4.1.4
HR Team
ASAP
4.1.5
4.1.6
HR Team
HR Team
ASAP
ASAP
Update on going
Already hired one Autocad
operator; continuous pooling
Sir Ramez
28-Oct-15
This Week
5.0 Plant/Assets
5.1.1
5.1.2
5.1.3
Capex and Mobilization equipment and Rental Rates to be discussed in a separate meeting with Sir Ben Martin
Sort out the Current rate of equipment rentals from Galeo and make sure that all are presented in writing
Finalize the needed equipment and send to Sir Ben Martin. Setup and finalise foundation design of batch plant. Need to
ensure we use bulk loader for cement, not tonner bags
A separate bank account set up for Padcal to be used only by the project to ensure no more delays in payments for
materials and equipments
Prepare a Cash flow report/projection on Cash position with monthly expenses and revenues, less Down payment and
6.1.3
retention to job completion
6.1.4
Cost codes breakdown not yet agreed - Budget split
6.2 Commercial
6.2.2
Prepare a list of every permit needed with timeline, cost, person responsible and separately indicate San R permits from
Philex
6.2.3
Info
Sir Nelson
Sir Nelson
Sir Nelson
Done
02-Nov-15
Document everything especially transmittals and communications with Clients and align with the contract; Prepare flow
chart of documents from whom and where to transmit indicating timeline of signing of documents and person involve
6.3 Procurement
Set up separate meeting with Procurement team to clarify issues on who would raise P.O's and the status. A procurement Nelson/Allan/Eddie
6.3.2
schedule to be developed and distributed weekly for updates. Need to talk with counterparts at philex by next week to
M
agree the purchasing arrangment of free issue materials, how the process works, the time taken and the way we bill
these through the progress claim and invoice.
6.3.3
Prepare a Procurement flow chart indicating person involve and timeline for signing of documents.
6.3.4
Fuel not to be purchased by san R, but rather to Philex account and instead source a much cheaper supplier (Total
Philippines Php 20 per liter)
Done
28-Oct-15
Sir Nelson
ASAP
Info
29-Aug-2015
Page 1 of 1