Notes:: Saudi Arabian Oil Company

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

NOTES:

1. ALL INSTRUMENT NUMBERS ON THIS DRAWING SHALL BE


PREFIXED WITH PLANT NUMBER "Q77" UNLESS OTHERWISE
NOTED.
2. DELETED.
3. TWO PHASE FLOW RELIEF LINES ANCHORED PROPERLY.
4. DELETED.
5. ALL RELIEF VALVE LINES (LATERALS) SHALL BE CONNECTED
TO RELIEF HEADER AT AN OBLIQUE ANGLE AS PER
SAES-F-007 PARA. 6. 14.6 AND STANDARD DRAWING AB-03655D.
6. THE LOWEST TEMPERATURE DOWNSTREAM OF PZV/ZV IS -51 F
WHICH SHALL NOT LAST MORE THAN ONE HOUR THE MATERIAL
FOR HP FLARE SYSTEM IS SPECIFIED AS LTCS WITH IMPACT TEST
WHICH SHALL MEET COLUMN B-3 AND NOTE 3 OF ASME
B31.3 TABLE 323.2.2 REQUIRMENTS.
7. Q70-AOV-1005 SHALL AUTOMATICALLY BE OPENED WHEN ONE OR
MORE OF Q70-PV-1223C/2223C/3223C/4223C(REFER TO SHEET 030
OF RA-102910/102920/102930/102940) IS OPENED DURING AN
ABNORMAL OPERATION SUCH AS THE THERMAL OXIDIZERS
SHUTDOWN,START-UP,ETC. IT SHALL SUPPLY COVER GAS TO
THE FLARE SYSTEM TO MEET REQUIRED LHV FOR PROPER
BURNING OF THE RELIEF GAS. THE AOV IS AUTOMATICALLY
OPEND IN CASE OF LOW LHV(350 BTU/SCF) OF THE RELIEF GAS
BY Q70-ASLL-6243 OR MIN. ONE PSHH SIGNAL FROM
Q70-PSHH-1105/2105/3105/4105 OR Q70-HS-1005.
8. REFER TO DWG. Q70-A-RA-102876.009 FOR ANALYZER HOUSE.

G680P10 SGB(SALES GAS BLENDING) SYSTEM in Unit 68


G770P02 HP FLARE SYSTEM in Unit 77

HP FLARE

RA-102857.002

FROM INLET FACILITY


AREA

HP FLARE

FROM GAS
SWEETENING TRAIN
100

RA-102909.010

HP FLARE

FROM GAS
SWEETENING TRAIN
200

RA-102919.010

FROM GAS
SWEETENING TRAIN
300

HP FLARE

RA-102929.010

HP FLARE

FROM GAS
SWEETENING TRAIN
400

RA-102939.010

RA-108628.001

PURGE

G770P02

LEGEND
SIGNAL
RA-102910.030
FROM Q70-PSHH-1105

SIGNAL

56"-RL-1019 -1CA4P1A

32"-RL-1015-1CA4P1

32"-RL-2115-1CA4P1

32"-RL-3115-1CA4P1

32"-RL-4115-1CA4P1

2"-FGL-1190-1CA4P1

RA-102920.030
FROM Q70-PSHH-2105

SIGNAL
RA-102930.030
FROM Q70-PSHH-3105

SIGNAL
RA-102940.030
FROM Q70-PSHH-4105

OPEN
CLOSE

G680P10

IP-WUC-L-00240

0.0-30.0 MMSCFD
+

P
+

IAS

G770P02

8"-P-5166-6CS1P

12"-FH-1213-1CA4P1A

G680P10

COVER GAS
(SWEET DRY GAS)
RA-102857.002
FROM SALES
GAS HEADER
(Q68)

IP-WEC-L-00001
G680P10
IP-WGC-L-00028
V
36"-FH-1009 -1CA4P1

HP FLARE

36"-FH-1024 -1CA4P1

RA-279031.001
FROM NGL FEED AND
PRODUCTS SURGE
AREA

G770P02
D

HP FLARE

42"-FH-1001-1CA4P1

RA-279032.001
FROM NGL FRACTION
AREA

G770P02

.
RA-140981.001

FROM FLARE
HEADER

HP FLARE

30"-RL-1029 -1CA4P1

IP-WGC-L-00031
42"-FH-1008 -1CA4P1

HP FLARE

56"-FH-1001 -1CA4P1

RA-102877.002

G770P02

12"-RL-1010 -1CA4P1

TO HP FLARE KO
DRUM Q77-D-600

HP FLARE
RA-102877.040

G770P02

FROM FGRU

REVISED IFC

SYL

GBL

KSK

REVISED IFC

SYL

GBL

KSK

REVISED IFC

SYL

GBL

KSK

ENGINEERING & CONSTRUCTION

CONTRACTOR JOB NO.

11049D

REVISION VALIDATION
THIS REVISION NO. 4
IS COVERED, FOR ALL APPROVAL AND CERTIFICATION
REQUIREMENTS, PER SAEP-334, UNDER DRAWING COMPLETION CERTIFICATE NO:
10-00914-0002-001
DESIGN CERTIFICATION
(DESIGN AGENCY)
GBL
09/12/13

REVIEW FOR KEY DRAWINGS


REQUIRED
(SAUDI ARAMCO)

OTHER

KSK
09/12/13

09/12/13

REVISED IFC

10-00914-0002

SAUDI ARABIAN OIL COMPANY


PIPING & INSTRUMENTATION DIAGRAM

PID

HP FLARE COLLECTION
FLARE SYSTEM

SAUDI ARABIA

WASIT
PLANT NO.

Q77

INDEX

RA-102877

SHT. NO.

REV. NO.

001