Professional Documents
Culture Documents
Standard Data Book by Nhai PDF
Standard Data Book by Nhai PDF
Road Works
The description of items is given briefly and linked with the relevant clause of the
MoRT&H Specifications for Road and Bridge Works, which may be referred for detailed
description, provisions and interpretation.
2.
Mechanical Means
Due to mechanization of construction work, rate analysis for various items have been
prepared using mechanical means. However, manual means have also been provided
for certain cases, where areas may be inaccessible for machines or quantum of work
may not be large enough to justify use of machines.
3.
Overhead Charges
The overhead charges in dude the following elements:
i.
Site accommodation, setting up plant, access road, water supply, electricity and
general site arrangements.
b)
Site supervision
c)
4.
For the purpose of calculation of overhead charges, the projects are categorized into
2 types as under and overhead charges, provided as indicated against each.
Category 1: Cost up to Rs. 50 crores
10 per cent
8 per cent
Contractor Profit:
Basic Inputs
Basic inputs are only given in the standard data book. The rates for material and labour
are to be obtained from local authorities for the area where the project is located.
6.
6.1.
A dozer is proposed for excavation where cutting and filling for the roadway is within
100 m. For longer leads, a combination of hydraulic excavator and tipper is proposed.
6.2.
Keeping in view the job and managerial factors and the age factor of machines, the output
of plant and equipment is taken approximately 70 per cent of the rated capacity given
by manufacture under ideal conditions.
6.3.
It has been assumed that a water tanker would make one trip per hour on an
average. Water charges have not been included fop items where the requirement is
very nominal. It is assumed that the same would be covered under sundries.
6.4.
6.5.
The usage charges for machines include ownership charges, cost of repair and
maintenance including replacement of tyres and running and operating charges
which includes crew, fuel and lubricants.
7.
Materials
7.1.
Quantities of materials given in the rate analysis are approximate for the purpose of
estimating and include normal wastages. Actual consumption would have to be
based on mix design.
7.2.
The rates of material should include basic cost at locations of stone crushers, loading,
unloading, cost of carriage and stacking at plant sites as the case may be.
7.3.
The alternative proposal for curshing own aggregate by installing crusher should be
compared with procurement of crushed aggregates from the market and proposal
found economical may be adopted.
7.4.
8.
Labour
8.1.
8.2.
8.3.
Skilled labour include mason, carpenter, blacksmith, mechanics and other trades.
9.
Carriage of Materials
9.1.
The unit for vehicle for carriage has been taken as under:
a)
In hours where lead is defined including time required for loading and
unloading.
b)
In tonne - km where lead is variable. The loading and unloading for such cases
have been provided separately.
9.2.
10.
General :
10.1. The clause numbers refer to MoRT&H Specifications for Road and Bridge Works.
10.2. Assumptions made have been indicated in respective chapter in the form of notes,
where required.
10.3. Sundries to cater for unforeseen contingency and miscellaneous items have been
added in the overhead charges.
10.4. Arrangement for traffic during construction shall be as per Clause 112 of MoRT&H
Specifications for Road and Bridge Works.
10.5. The supply of materials will be taken either at the location of mixing plant or at the
work site as the case may be.
10.6. Contractor will make his own arrangements for borrowing earth. However,
compensation for earth taken from private land has been included in the rate
analysis for construction of embankment with borrowed earth.
10.7. The requirement of machinery has been worked out assuming effective working
3
which has enhanced strength, better corrosion resistance, ductility, weld ability and
high temperature thermal resistance. Enquiries from these firms can be made on
technical specifications and use of such products considered in works based on
performance in works where these have already been used.
10.32. Provision of fly ash has been made in embankment construction, sub-base
construction and in cement concrete pavement
10.33. The Standard Data Book is for Department use only. It cannot be produced in
Court of Law as reference/authority and thus is a privilege document.
10.34. In case it is decided to include the following items, and their maintenance in the
BOQ, the scope and specifications should be worked out and defined in a detailed
manner in the tender document to avoid any dispute during execution.
MoRT&H Clause
Item
120
122
124
B-Bridge Works
Basic Approach for the Preparation of
Standard Data Book
The basic approach for the preparation of Standard Data Book for Bridge Works is
indicated as under:
Description of items
The description of items is given briefly and linked with relevant clause of Ministry's
Specifications for Road and Bridge Works, which may be referred for detailed description,
provisions and interpretation.
Overhead charges
The overhead charges include the following elements:
1. Site accommodation, setting up plant, access road, water supply, electricity and
general site arrangements
2. Office furniture, equipment and communications
3. Expenditure on:
a) Corporate office of contractor
b) Site supervision
c) Documentation and "as built" drawings
4. Mobilisation/de-mobilisation of resources
5. Labour camps with minimum amenities and transportation to work sites
6. Light vehicles for site supervision including administrative and managerial requirements
7. Laboratory equipment and quality control including field and laboratory testing
8. Minor T&P and survey instruments and setting out works, including verification of line,
dimensions, trial pits and bore holes, where required
9. Watch and ward
10. Traffic management during constructor
11. Expenditure on safeguarding environment
12. Sundries
13. Financing Expenditure
14. Sales/Turn over tax.
25%
20%
30%
For the bridge having more than two lanes, equivalent length and cost can be adjusted
accordingly.
Contractor's Profit
Contractor's profit has been taken uniformly as 10 percent, over the cost of items
including overhead charges.
Basic Inputs
In the Standard Data Book only basic inputs for material, labour and
machinery/equipments are given. The rates for material and labour are to be obtained
from local authorities for the area where the project is located.
Plant and Equipment
The usage/hire charges of machinery/equipment have been worked out based upon
present cost of equipments, repairs, POL and operational charges as indicated in
Chapter-17. These charges are applicable for the base year 2001-2002. For
subsequent years, these are required to be escalated depending upon the market
situation.
In the analysis of rates, for any items of work, capacity of equipment with corresponding
output has been indicated which is most common in use for estimation purpose. Seeing
the volume of job, different capacity equipment with corresponding output as indicated
in Chapter-17 can be provided for preparing the estimate.
Materials
The rates of material should include basic cost at crushing units, cost of carriage
including loading and unloading and stacking of material at site of work and shall be
determined through market enquiries.
Labour
For labour, the general classification is mazdoor for unskilled labour and
mason/fitter/blacksmith etc. for skilled labour.
One mate has been provided for 25 labourers.
Carriage of Materials
The unit for vehicle for carriage has been taken as under:
a) In hours where lead is defined including time required for loading and un-loading.
b) In tonne km where lead is variable. The loading and un-loading for such case,
are to be have been provided separately.
General
Bridge bearing and expansion joints are ready made items commercially produced by
specialized firms and in certain cases using imported technology and parts. The rates of
these items are to be obtained directly from different manufacturers approved by the
Ministry and shall be adopted after comparison.
Normal method of curing has been covered in the schedule. Analysis for steam curing
has been included in the analysis of pre-cast concrete PSC beams.
The testing of materials and finished items of work is covered under overhead charges.
Traffic arrangements during construction are covered under overhead charges.
Provisions of a temporary division, where required shall be governed by Clause 112.3.
In the items for well foundation, provision for nominal island/temporary protection, deep
islands/cofferdams with wooden ballies and sheet piles has been made.
For innovative type of structures like cable stayed bridges, suspension bridges, arch
bridges, bow string girder bridges, erected by innovative techniques where errection
stage is as important as the construction of bridge components in terms of input of
machinery, manpower and materials, special analysis is called for.
For some of the items, certain size/specifications have been assumed. If
size/specifications other than the same are adopted, corresponding modifications may
be made in the inputs of analysis.
The items do not cover all components of bridge projects for all situations. There may
be specialized items for specific cases, which need to be analysed keeping in view the
basic approach.
Guide Bund
The items for the guide bund are excavation, embankment and protection works. The
rates for these items may be taken from the respective chapters.
In case bridge construction works are to be done on wide and deep water channels in
major rivers or in sea creeks etc., provision of floating barrages etc. for taking the
construction materials and equipments inside water shall also be made separately.
Analysis for sinking of wells cover diameters from 6 m to 12 and Twin D Type of size 12
m x 6 m. For other shapes like rectangular or any other size, the rates of sinking may be
worked out on pro-rata basis.
The lift for casting of concrete in well steining may be 2 to 2.5 m restricting the free fall
of concrete to 1.5 m and concreting layer to 450 mm.
The Standard Data Book is for Department use only. It cannot be produced in Court of
Law as reference/ authority and this is a privilege document.
Chapter-1
Carriage of Materials
Preamble:
1. The provision of tipper has been made in hours where lead is known like disposal of the
materials upto 1000 m. In case where lead is variable like carriage of hot mix or
concrete mix from plants or earth from borrow areas, provision has been made in terms
of tonne-kilometer (t-km), which can be adopted as per actual conditions.
2. Provision has been made for a tractor trolley instead of tipper where dismantled
materials of sorts or material having more volume as compared with weight are required to
be transported. This arrangement will be economical.
3. The cost of carriage will vary depending upon the riding surface of the road. Prevision has
accordingly been made considering surface roads, unsurfaced graveled roads and
katcha tracks.
4. Analysis for loading has been done both for manual and mechanical means for adoption
as per actual situations.
5. Where loading is done by mechanical plant like HMP or batching plant and there is
automatic loading in tippers, provision of loading and un-loading has been made at rate of
10 per cent of cost of carriage to account for time taken by the tipper for getting loaded
at the plant and un-loadjng in the paver or otherwise at site.
6. Although the market rates for supply of aggregates at site are generally taken for
estimation purpose, rate for crushing of aggregate have also been analysed as most of
the contractors prefer to crush their own aggregates in case of large projects exceeding
Rs.50 crores in value.
7. The cost of material shall be evaluated considering the cost at crushing plants and cost
of carriage including loading and unloading or the rates for supply at site depending
upon system being followed at particular locations. These rates should be compared with
the rates for own crushing and carriage by the construction agency.
Sr.
No.
1.1
Reference to
MoRT&H
Specifications
Description
Loading and Unloading of Stone
Boulder/Stone
Aggregates/Sand/
Kankar / Moorum
Placing tipper at loading point, loading
with front end loader, dumping, turning
for return trip, excluding time for
haulage and return trip.
Unit
Quantity
Rate
Rs.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading
point
ii) Loading by front end loader 1 cum
bucket capacity @ 25 cum per
hour
iii) Maneuvering, reversing, dumping
and turning for return
iv) Waiting
time,
unforeseen
contingencies, etc.
1 Min
13 Min
2 Min
4 Min
Total
20 Min
a) Machinery
Tipper 5.5 tonnes capacity
Hour
Front end-loader 1 cum bucket
capacity
hour @ 25 cum/hour
Hour
0.33
0.33
b) Overheads % on (a)
c) Contractor's profit @ % on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Note: Unloading will be by tipping.
1.2..
Day
0.11
0.75
Hour
0.75
Note
1.3.
Day
Day
0.08
2.00
Hour
2.00
C) Overheads @ % on (a+b)
d) Contractors profit @ % on (a+b+c)
Cost for tones = a+b+c+d
Rate per tones = (a+b+c+d)/10
1.4.
0.4
0.29
0.5
Hour
0.33
1
0.67
b) Overheads @
% on (a)
c) Contractor's profit @
%on (a+b)
b)
c)
Overheads % on (a)
Contractor's profit @
% on
(a+b)
Cost for 100 t.km = a+b+c
Rate per t.km = (a+b+c)/100
1..5
0.06
1.5
1.10
0.76
2
17
800
c) Machinery
Integrated stone crusher of 200 TPH
including belt conveyor and vibrating Hour
screens
20
20
Hour
d) Overhead charges @
% on
(a+b+c)
e) Contractor's profit @
%on
(a+b+c+d)
Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/600
Note
1.7.
0.76
2
17
b) Material
Stone boulder of size 150mm and
below
c) Machinery
Integrated stone crusher of 200
TPH including belt conveyor and
vibrating screens
Front end loader 1 cum bucket
capacity
Tipper 5.5 cum capacity
d) Over head charges @ % on
(a+b+c)
e) Contractors
(a+b+c+d)
profit
Cum
800
Hour
Hour
20
Hour
20
1.8.
0.76
2
17
Note:
b) Material
Stone Boulder of size 150 mm
and below
c) Machinery
Integrated stone crusher of 200
TPH
Including belt conveyor and
vibrating screens
Front end loader 1 cum bucket
capacity
Tipper 5.5 cum capacity
d) Overhead charges @
% on
(a+b+c)
e) Contractor's profit @
% on
(a+b+c+d)
Cost for 750 cum = (a+b+c+d+e)
x0.85
Rate per cum = (a+b+c+d+e)
x0.85/750
1. 800 cum of stone boulders
are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85 per cent of above cost will
be attributed to the production
of 750 cum of stone
aggregates of 40 mm size and
balance 15 per cent will be for
smaller size aggregates and
stone dust which comes out
as a by product.
3. The integrated stone crusher
includes primary and secondary
crushing units.
Cum
800
Hour
Hour
20
Hour
20
Chapter-2
Site Clearance
Preamble:
1. Unless otherwise stated, the rates include sorting and disposal of unserviceable material and
stacking of serviceable material with all lifts and upto a lead of 1000 m.
2. The rates include T&P and scaffolding required for items of dismantling
3. Carriage of dismantled materials, bushes, branches of tree, etc., has been catered with a
tractor - trolley of 3 tonnes capacity with manual loading and unloading @ 2 trips per hour
within a lead of 1000 m. This will be economical for such works as compared with a tipper.
4. For cutting of trees above 1800 mm girth, 4 mazdoors have been considered to cater for
large size trees, which will fall in this category.
5. Where only grass/wild growth is met, item No. 2 i.e. clearing grass and removal of rubbish
can be applied. As regards wild growth disposal of grass, the same can be dried and burnt.
6. The dismantling of structures has been catered both by manual and mechanical means. The
estimator can use his discretion depending upon quantum of work and particular site
conditions.
7. Cutting of rivets has been provided separately.
8. Dismantling of Hume pipes has been catered manually as pipes can be easily rolled by
men to a suitable stacking place within the right of way.
9. For dismantling of structures, which remain submerged in water, the cost may be enhanced
by 50 percent.
10. Dismantling of utilities is required to be done under the supervision of concerned
departments with prior information to the users.
11. In certain items of dismantling, like, pipe culverts, utilities, etc., excavation in earth and
dismantling of masonry works is not included in this analysis for which suitable notes have
been inserted. These items are required to be priced separately based on actual quantities
at site and nature of work.
12. The dismantled materials should be examined and a realistic assessment and provision
made after due process for the credit for such materials, which can be utilized for works or
auctioned.
13. In case where lead for disposal is more than 1000 m, extra cost of carriage is required to be
added based on tonne-kilometerage.
14. All minor T&P items required for dismantling are already included in overhead charges.
15. For dismantling of utility services like water pipe lines, electric and telephone lines, prior
intimation should be given to users.
Reference to
MoRTH
Sr. No.
Description
Specification
s
2.1.
201
Cutting of Trees, including cutting of Trunks,
Branches and Removal
Unit
Quantity
Day
0.02
Day
0.60
Hour
0.10
Day
0.04
Day
0.90
Hour
0.30
0.08
2.00
0.40
Rate
Rs.
2.2.
2.3.
201
201
a) Labour
Mate
Mazdoors for cutting trees including cutting
refilling, compaction of backfilling and stacking of
serviceable materials within 1000m
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate for each tree = a+b+c+d
Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish upto a
distance of 50 metres outside the periphery of
the area.
By Manual Means
Unit= Hectare
Taking output = 1 Hectare
a) Labour
Mate
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Rate per Hectare = a+b+c
Clearing and Grubbing Road Land
Day
Day
0.16
4.00
Hour
0.60
Day
Day
2.00
50.00
Day
Day
6.00
150.00
Hour
1.00
Day
Day
8.00
200.00
Hour
2.00
2.4.
202
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per Hectare = a+b+c+d
II. By Mechanical Means :
A. In area of light jungle
a) Labour
Mate
Day
Mazdoor
Day
b) Machinery
Dozer 80 HP with attachment for removal of Hour
trees & stumps
Tractor-trolley
Hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per Hectare = a+b+c+d
B. In area of thorny jungle
a) Labour
Mate
Day
Mazdoor
Day
b) Machinery
Dozer 80 HP with attachment for removal of Hour
trees & stumps
Tractor-trolley
Hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per Hectare = a+b+c+d
Dismantling of Structures
0.16
4.00
10.00
1.00
0.24
6.00
12.00
1.50
2.4. (i)
202
Unit = cum
Taking output = 1.25 cum
(i) Lime/Cement Concrete
I. By Manual Means :
A. Lime concrete, cement concrete grade
M-10 and below
a) Labour
Mate
Mazdoor for dismantling and loading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
B. Cement concrete grade M-15 & M-20
4
Day
Day
0.04
1.00
Hour
0.27
2.4. (ii)
202
a) Labour
Mate
Mazdoor for dismantling and loading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
C. Prestressed/reinforced cement concrete
grade M-20 & above
a) Labour
Mate
Blacksmith
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
II. By Mechanical Means for items No. 202
(B)&(C)
A. Cement concrete grade M-15 & M-20
a) Labour
Mate
Mazdoor for loading and unloading
Mazdoor with pneumatic breaker
b) Machinery
Air Compressor 250 cfm with 2 leads of
pneumatic breaker @ 1.5 cum per hour
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
B. Prestressed / reinforced cement concrete
grade M-20 & above
a) Labour
Mate
Mazdoorwith pneumatic breaker
Blacksmith
Mazdoorfor loading and unloading
b) Machinery
Air Compressor 250 cfm with 2 leads of
pneumatic breaker @ 1.00 cum per hour
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
(ii) Dismantling Brick/Tile Work
A. In lime mortar
5
Day
Day
0.05
1.25
Hour
0.27
Day
Day
Day
0.15
0.25
3.50
Hour
0.27
Day
Day
Day
0.02
0.25
0.25
Hour
0.67
Hour
0.27
Day
Day
Day
Day
0.05
0.66
0.25
0.25
Hour
1.00
Hour
0.27
a) Labour
Mate
Mazdoorfor dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
B. In cement mortar
2.4. (iii)
202
a) Labour
Mate
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
C. In mud mortar
a) Labour
Mate
Mazdoor for dismantling and loading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
D. Dry brick pitching or brick soling
a) Labour
Mate
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
(iii) Dismantling Stone Masonry
A. Rubble stone masonry in lime mortar
a) Labour
Mate
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 125 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
B. Rubble stone masonry in cement mortar
a) Labour
6
Day
Day
0.02
0.5
Hour
0.27
Day
Day
0.03
0.75
Hour
0.27
Day
Day
0.016
0.40
Hour
0.27
Day
Day
0.014
0.35
Hour
0.27
Day
Day
0.024
0.6
Hour
0.27
Mate
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
C. Rubble stone masonry in mud mortar
a) Labour
Mate
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
D. Dry rubble masonry
a) Labour
Mate
Mazdoor for dismantling, loading andunloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum =,(a+b+c+d)/1.25
E. Dismantling stone pitching/dry stone spalls
a) Labour
Mate
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
F. Dismantling boulders laid in wire crates
including opening of crates and stacking
dismantled materials
a) Labour
Mate
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
(iv) Wood Work Wrought Framed and Fixed in
Frames of Trusses upto a Height of 5 m above
Plinth Level
7
Day
Day
0.03
0.75
Hour
0.27
Day
Day
0.02
0.50
Hour
0.27
Day
Day
0.018
0.45
Hour
0.27
Day
Day
0.016
0.40
Hour
0.27
Day
Day
0.02
0.50
Hour
0.27
2.4. (v)
2.4. (vi)
202
202
a) Labour
Mate
Carpenter
Mazdoor for dismantling, loading and unloading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
(v) Steel Work in all types of Sections upto a
Height of 5 m above Plinth Level excluding
Cutting of Rivet
Unit = tonne
Taking output = 1 tonne
A. Including dismembering
a) Labour
Mate
Blacksmith
Mazdoor for dismantling, loading and unloading
Add 2.5 per cent of cost of labour for gas cutting,
ropes, pulleys etc.
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per tonne = a+b+c+d
B. Excluding dismembering
a) Labour
Mate
Mazdoor for dismantling, loading and unloading
Blacksmith
Add 2.5 per cent of cost of labour for gas cutting,
ropes, pulleys etc.
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per tonne = a+b+c+d
C. Extra over item No (v) A and (v) B for cutting
rivets
Unit = each
Taking output = 10 rivets
a) Labour
Mate
Blacksmith
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Cost of 10 rivets = a+b+c
Rate for each rivet = (a+b+c)/10
(vi) Scraping of Bricks Dismantled from Brick
Work including Stacking
8
Day
Day
Day
0.06
0.50
1.00
Hour
0.27
Day
Day
Day
0.14
1.00
2.50
Hour
0.17
Day
Day
Day
0.22
2.00
0.50
Hour
0.17
Day
Day
Day
0.01
0.13
0.13
2.4(viii)
2.4 (ix)
202
202
Unit = numbers
Taking output = 1000 numbers
A. In lime/cement mortar
a) Labour
Mate
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Rate per 1000 Nos. = a+b+c
B. In mud mortar
a) Labour
Mate
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Rate per 1000 Nos. = a+b+c
(vii) Scraping of Stone from Dismantled Stone
Masonry
Unit = cum
Taking output = 1 cum
A. In cement and lime mortar
a) Labour,
Mate
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Rate per cum = a+b+c
B. In mud mortar
a) Labour
Mate
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Rate per cum = a+b+c
(iii) Scarping Plaster in Lime or Cement Mortar
from Brick/Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor for scarping and loading
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100
(ix) Removing all types of Hume Pipes and
Stacking within a lead of 1000 metres including
Earthwork and Dismantling of Masonry Works
Unit = metre
Taking output = 1 metre
A. Upto 600 mm dia
9
Day
Day
0.14
3.50
Day
Day
0.14
3.50
Day
Day
0.06
1.40
Day
Day
0.01
0.30
Day
Day
0.16
4.00
Hour
0.32
a) Labour
Mate
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Rate per metre = a+b+c
B. Above 600 mm to 900 mm dia
a) Labour
Mate
Mazdoor
Note
2.5
202
Day
Day
0.02
0.52
Day
Day
0.03
0.70
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Rate per metre - a+b+c
C. Above 900 mm
a) Labour
Mate
Day
Mazdoor
Day
b) Over-Heads @ % on (a)
c) Contractor's profit @ %on(a+b)
Rate per metre = a+b+c
1. The excavation of earth, dismantling of stone
masonry work in head walls and protection
works is not included which is to be
measured and paid separately.
2. Credit for retrieved stone from masonry work
may be taken as per actual availability.
0.05
1.20
Day
Day
0.06
1.5
Hour
0.38
Day
0.04
2.6
202
Note
2.7
202
b) Machinery
Tractor-trolley
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per cum = a+b+c+d
II. By Mechanical Means :
A. Bituminous courses
a) Labour
Mate
Mazdoor
b) Machinery
Tractor-trolley
Farm tractor with ripper @ 60 cum per hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per cum = a+b+c+d
Dismantling of Cement Concrete Pavement
Dismantling of cement concrete pavement by
mechanical means using pneumatic tools,
breaking to pieces not exceeding 0.02 cum in
volume and stock piling at designated locations
and disposal of dismantled materials upto a lead
of 1000 metres, stacking serviceable and
unserviceable materials separately.
Unit = cum
Taking output = 1 cum
a) Labour
Mate
Semi skilled rnazdoor for operating pneumatic
tools
Mazdoors as helpers including loading and
unloading
b) Machinery
Air compressor 250 cfrn with two leads for
pneumatic cutters/hammers @ 1 cum per hour
Tractor-trolley
Joint Cutting Machine with 2-3 blades
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per cum = a+b+c+d
The above analysis is for removal of complete
pavement. In case full depth repair work is
required to be done after dismantling, provision of
a concrete cutting and sawing machine may be
added for 0.25 hours.
Dismantling of Guard Rails
Dismantling guard rails by manual means and
disposal of dismantled material with all lifts and
upto a lead of 1000 metres, stacking serviceable
11
Day
1.00
Hour
0.33
Day
Day
0.01
0.30
Hour
Hour
0.38
0.017
Day
Day
0.03
0.50
Day
0.50
Hour
1.00
Hour
Hour
0.40
1.00
materials
and
separately.
2.8
2.9
unserviceable
materials
202
202
Day
Day
0.06
0.15
Hour
0.05
0.01
0.15
0.20
2.10
202
Day
Day
0.015
0.225
Hour
0.30
2.11
202
Day
Day
0.13
0.75
Hour
0.15
Day
Day
0.02
0.50
Hour
03
Day
Day
0.004
0.10
Hour
0.02
Day
Day
Day
0.15
3.00
0.75
Hour
0.15
2.12.
202
Note
2.13
202
Day
Day
Day
0.09
2.00
0.25
Hour
Hour
0.25
0.50
Day
Day
0.10
2.50
Note
2.14
202
b) Machinery
Crane 5 tonne capacity
Truck flat body 10 tonne
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 10 metres = a+b+c+d
Rate per metre = (a+b+c+d)/10
The rate analysis does not include any
excavation in earth or dismantling of masonry
works which are to be measured and paid
separately.
Removal of Telephone/Electric Poles and Lines
14
0.30
1.00
15
Day
Day
Day
0.48
10.00
2.00
Hour
1.50
Chapter-3
Earthwork, Erosion Control and Drainage
Preamble:
1.
The rates have been analysed using mechanical means. Manual means for certain
items have also been provided which can be used for areas inaccessible to machines
and for small jobs.
2.
In the rate analyses of earthwork, only compacted volume of earth has been
considered.
3.
4.
Average achievable outputs of machines have been considered taking into account job and
management factors.
5.
Cutting by dozer has been proposed where the cut earth can be utilized for filling for
embankment within a lead of 100 m. A dozer can economically push the earth upto a
distance of 100 m.
6.
Where lead for transporting of earth is more than 100 m, excavator and tipper have
been provided.
7.
A water tanker of 5 KL capacity which is commonly used at construction sites has been
considered.
8.
The rate caters for disposal of unsuitable soil only upto a distance of 1 km. The cost of
transportation beyond the initial lead of 1 km will be paid separately based on tonnekilometerage.
9.
The replacement of unsuitable soil by suitable soil shall be included separately in the
estimate. The rate analyses for removal of unsuitable soil does not provide for
replacement by suitable soil.
10. In cases where embankment is constructed with earth taken from roadway, the cost of
depositing the earth at the site of embankment is already included in the disposal of
excavated earth.
11. For narrow and restricted areas, plate compactor has been proposed for compaction to
achieve the desired density.
12. For small jobs where loading and unloading is required to be done manually, tractortrolley has been proposed for carriage instead of a tipper.
13. In case excavated rock is found suitable for incorporation in works, suitable credit for the
available rock shall be given.
14. The possibility of using the blasted rock fragments for backfilling behind structures or
backfilling of foundation pits or filling in medians / separators or use in service road
shall be examined before proposing disposal of excavated rock.
15. In case of hill roads, the cut earth can be pushed down the valley in case there is no
objection. In that case, cost of disposal is not required to be provided.
1
16. 'L' represents lead in km one way. This will vary from project-to-project and is required
to be ascertained at site at the time of estimation.
17. For inhabited areas, controlled blasting with limited charges of explosives has been
provided. This involves smaller drill holes and additional requirement of electric
detonators. Provision has accordingly been made.
18. Any work involved for water courses at culverts (Clause 312) will be priced under
respective items, like, excavation, grubbing, clearing, etc. for which rate analyses have
separately been made.
19. In the case of embankment made from earth taken from roadway cutting, the input of
dozer for spreading earth can be deleted as the same is already provided in the cost of
excavation.
20. Earth excavated from drains can be used in roadway berms. Hence, carriage for
disposal of same is not provided.
21. In the rate analyses of some items, the quantities of sub-items involved in that
analyses, like, excavation for foundation, foundation concrete, painting, lettering, etc.
have been given. The rates for such items shall be taken from relevant chapters where
the same have already been analysed.
22. In case of rock fill embankment, it is assumed that material is available at site from
rock cutting.
23. The item of preparation and surface treatment of formation (Clause 310) is required to
be added in the cost estimate only if there is substantial time lag between completion
of sub-grade and laying of sub-base. As this item is incidental to works, it is not
required to be included in BOQ.
24. The items filling behind abutments and wing wall and provision of filter media has been
included in Chapter-15.
25. Excavation for structures beyond the depth of 3 m has been included in Chapter-12.
26. In case of high altitudes areas above 2100 m, the percentage addition to the cost of
manpower and usage rates of machines are required to be made as per the Table
given on next page.
Altitude in Mtrs
2 100 to 2400
2401 to 2700
2701 to 3000
3001 to 3300
7 per cent
15 per cent
25 per cent
32 per cent
2
3301 to 3600
3601 to 3900
3901 to 4200
4201 to 4500
4501 to 4800
4801 to 5100
48 per cent
66 per cent
86 per cent
108 per cent
132 per cent
186 per cent
15 per cent
18 per cent
21 percent
24 per cent
27 per cent
30 per cent
The above provisions are based on the report of Defence Institute of Physiology and Allied
Sciences, Delhi Cantt. regarding quantitative reduction in the physical work capacity of
individuals working in high altitude areas and the recommendation of the committee on cost
of construction set up by Border Roads Development Board for reduction in output of
machines while working in high altitudes. These figures are adopted from "Standard
Schedule of Rates" of BRO as applicable to high altitude areas.
Sr.
No.
3.1
Reference to
MoRT&H
Description
Specifications
301
Excavation in Soil by Manual
Unit
Quantity
Note:
3.2
301
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Day
Mazdoor
Day
b)
Machinery
Truck 5.5 cum capacity
Hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost of 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
In case there is a situation where the
cross-section is of cut and fill and cut
earth is required to be used in
embankment in the immediate vicinity, the
item of carriage in the truck shall be
omitted.
1.80
45.00
10.00
Day
2.80
Rate
Rs.
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
3.3
Note:
301
Day
70.00
Hour
10.00
Day
Day
0.08
2.00
Hour
6.00
the
cut
in
the
be
3.4
301
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 30 cum per hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Excavation in Ordinary Rock with lead
upto 100 metres
Excavation for roadway in ordinary rock
by deploying a dozer, 80 HP including
cutting and pushing the cut earth to site of
embankment upto a distance of 100
metres (average lead 50 metres),
trimming bottom and side slopes in
accordance with the requirements of lines,
grades and cross sections.
Unit = cum
Taking output =108 cum
4
3.5.
301
a) Labour
Mate
Mazdoor
Day
Day
0.12
3.00
b) Machinery
Dozer, 80 HP @ 20 cum per hour
Hour
6.00
Day
Day
Day
Day
0.22
3.00
2.00
0.25
Hour
6.00
Hour
Hour
Hour
6.00
6.00
11.25
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 108 cum = a+b+c+d
Rate per cum = (a+b+c+d)/108
Excavation in Hard Rock (requiring
blasting) with disposal upto 1000 metres
Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting and
breaking, trimming of bottom and side
slopes in accordance with requirements of
lines, grades and cross sections, loading
and disposal of cut road with in all lifts and
leads upto 1000 metres.
Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor
Driller
Blaster
b) Machinery
Dozer, 80 HP @ 30 cum per hour
Air compressor, 250cfm with 2 jack
hammer
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
c) Materials
Gelatin 80 percent
Kg
Electric Detonators @ 1 detonator for
2 gelatin sticks of 125 gms each
Each
Credit for excavated rock found suitable
for use @ 50 per cent quantity blasted
Cum
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 180 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/180
Note
63.00
252.00
90.00
extent.
3.6
301
Day
Day
b) Machinery
Hydraulic excavator 0.9 cum bucket Hour
capacity @ 60 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour
Hour
0.08
2.00
6.00
16.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
3.7
301
Day
Day
b) Machinery
6
0.08
2.00
6.00
11.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
3.8
301
Excavation
prohibited)
in
Hard
Rock
(blasting
0.40
10.00
6.00
6.50
18.00
a) Labour
Mate
Mazdoor including loading in truck
Chiseller
Blacksmith
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour
Credit for excavated rock found suitable
for use @ 50 per cent of excavated
Day
Day
Day
Day
1.64
16.00
24.00
1.00
Hour
Cum
2.90
8.00
Day
Day
Day
Day
0.22
3.00
2.00
0.50
Hour
Hour
6.00
6.00
Hour
Hour
6.00
8.20
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for t6 cum = a+b+c+d
Rate per cum = (a+b+c+d)/16
3.9
Note
301
c) Materials
Gelatin 80 per cent
Kg
Electric detonators @ 1 detonator for 1/2
gelatin stick of 125 gms each
Each
8
63.00
1008.00
90.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 180 cum =a+b+c+d+e
Rate per cum = (a+b+c+d+e)/180
3.10
Note
301
Day
Day
b) Machinery
Hydraulic excavator 0.9 cum bucket Hour
capacity @ 50 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour
Hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 300 cum = a+b+c+d
Rate per cum = (a+b+c+d)/300
3.11
301
Removal of
Unserviceable Soil with
Disposal upto 1000 metres
Removal of unserviceable soil including
excavation, loading and disposal upto
1000
metres
lead
but
excluding
replacement by suitable soil which shall
be paid separately as per Clause 305.
Unit = cum
Taking output = 360 cum
9
0.08
2.00
6.00
13.64
a) Labour
Mate
Mazdoor
Day
Day
Machinery
Excavator 0.90 cum bucket capacity @ 60 Hour
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour
Hour
0.08
2.00
6.00
16.36
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
3.12
Note
303
Day
Day
b) Machinery
Air compressor 250 cfm with 2 leads @ Hour
20 cum per hour
Dozer, 80 HP
Hour
Front end loader 1 cum bucket capacity
Hour
c) Materials
Gelatin 80 per cent
Kg
Electric detonators @ 1 detonator for 1/2
gelatin stick of 125 gms each
Each
10
0.60
15.00
6.00
6.00
6.00
42.00
672.00
Note
3.13
304
d) Overheads @ % on (a+b)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 400 sqm =a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/400
In case blasted rock is issued to the
contractor
against
payment
for
constructed work, the cost of carriage
shall be reduced to that extent
Excavation for Structures
Earthwork in excavation of foundation of
structures as per drawing and technical
specification, including setting out,
construction of shoring and bracing,
removal of stumps and other deleterious
matter, dressing of sides and bottom,
backfilling the excavation earth to the
extent required and utilising the remaining
earth locally for road work.
I) Ordinary soil
Unit = cum
Taking output = 10 cum
A. Manual Means
(i) Depth upto 3 m
a) Labour
Mate
Mazdoor
b) Overheads @
Day
Day
0.32
8.00
Day
Day
0.32
8.00
% on (a)
Hydraulic
capacity
excavator
1.0
cum
bucket Hour
6.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 300 cum = a+b+c+d
Rate per cum = (a+b+c+d)/300
Note
Day
Day
0.40
10.00
Day
Day
0.24
6.00
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note
1.0
cum
bucket Hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 216 cum =a+b+c+d
Rate per cum = (a+b+c+d)/216
Note
6.00
Day
Day
Day
Day
b) Machinery
Air Compressor 250 cfm with 2 jack Hour
hammer @ 15 cum per hour
c) Material
Blasting Material
Detonator electric
d) Overheads @
Kg
Nos
0.53
0.84
0.40
12.00
0.67
3.50
14.00
% on (a+b+c)
Note
0.20
5.00
10.00
Day
Day
0.40
10.00
b) Machinery
Tractor-trolley
Hour
2.67
Cum
5.00
c) Material
Selected earth for refilling
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 10 cum = a+b+c+d+e
Rate per cum =( a+b+c+d+e)/10
Note
Note
Cum
0.08
2.00
0.17
0.45
5.00
305.4.3
Day
Day
0.20
5.00
b) Machinery
Tractor-trolley
Hour
1.67
Day
Day
0.01
0.25
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100
3.15
Note
305.4.3
b) Machinery
Tractor with ripper attachment @ 60 cum Hour
per hour
Front end loader 1 cum bucket capacity
Hour
@ 25 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour
Hour
15
0.08
0.20
0.23
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100
3.16
305
Day
Day
b) Machinery
Hydraulic Excavator 1 cum
capacity @ 60 cum per hour
Tipper 10 tonne capacity
0.04
1.00
bucket Hour
1.67
t.km.
160xL
Hour
0.50
Hour
1.00
Hour
Hour
4.00
1.00
c) Material
Cost of water
KL
Compensation for earth taken from private Cum
land
24.00
100.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Note
3.17
305
0.02
0.50
Hour
0.50
Hour
1.00
Hour
Hour
4.00
1.00
KL
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
3.18
Day
Day
Note
305
24.00
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor
Day
Day
b) Machinery
Hydraulic excavator 1 cum bucket Hour
capacity @ 60 cum per hour
Tipper 10 tonne capacity
t.km
Add 10 per cent of cost of carriage to
cover cost of loading and unloading Dozer
80 HP for spreading 200 cum per hour
Hour
Motor grader for grading @ 50 cum per
Hour
hour
Water tanker wrth 6 km lead
Hour
Vibratory roller 8-10 tonnes @ 80 cum per Hour
hour
c) Material
Cost of water
Compensation for earth taken from private
land
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
3.19
305.3.4
KL
Cum
0.04
1.00
1.67
175xL
0.50
2.00
4.00
1.25
24.00
100.00
Day
Day
0.12
3.00
b) Machinery
Tractor with ripper attachment
Motor grader for grading
Water tanker 6 KL capacity
Vibratory roller 8-10 tonne @ 80 cum/hour
Hour
Hour
Hour
Hour
9.00
6.00
4.00
7.50
c) Material
18
Cost of water
KL
24.00
a) Labour
Mate
Mazdoor
Day
Day
0.08
2.00
b) Machinery
Tractor with ripper attachment
Vibratory road roller 8-10 tonne capacity
Water tanker hour 4.00
Hour
Hour
Hour
6.00
7.50
4.00
c) Material
Water
KL
24.00
Day
Day
0.20
5.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/600
Case - II: Compacting original ground
supporting embankment
Loosening, levelling and Compacting
original ground supporting embankment to
facilitate placement of first layer of
embankment, scarified to a depth of 150
mm, mixed with water at OMC and then
compacted by rolling so as to achieve
minimum dry density as given in Table
300-2 for embankment construction.
Unit = cum
Taking output = 600 cum
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost fop-600 cum = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/600
3.20
305
b) Machinery
Dozer 80 HP @ 100 cum per hour
Hour
0.10
a) Labour
Mate
Mazdoor
Day
Day
0.08
2.00
b) Machinery
Dozer, 80 HP
Hour
6.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
3.21
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 300 cum = a+b+c+d
Rate per sqm = (a+b+c+d)/300
3.22
307
0.12
3.00
b) Machinery
Water tanker including watering for 3
months
2.00
20
Hour
Tractor-trolley
Hour
c) Material
Farmyard manure @ 0.18 cum per 100 Cum
sqm at site of work
Cost of water
KL
1.00
0.18
12.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per 100 sqm = (a+b+c+d+e)/100
3.23
308
Day
Day
b) Machinery
Water tanker 6 KL capacity including Hour
watering for 3 months
Tractor-trolley
Hour
c) Material
Seeds
Sludge/Farm yard manure @ 0.18 cum
per 100 sqm
Bitumen Emulsion
Jute netting, open weave, 2.5 cm square
opening
Cost of water for 3 months
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 240 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/240
3.24
309
Kg
0.40
10.00
14.00
2.40
3.60
Cum
Ltr
0.43
55.20
Sqm
KL
264.00
84.00
0.01
0.25
0.33
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 10 metres = a+b+c+d
Rate per metre = (a+b+c+d)/10
B. Manual Means
a) Labour
Mate
Mazdoor
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Cost for 10 metres = a+b+c
Rate per metre = (a+b+c)/10
3.25
Note
309
Day
Day
0.08
2.00
0.02
0.50
b) Machinery
Hydraulic Excavator 0.3 cum bucket Hour
capacity @ 15 metres per hour
0.67
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 10 metres = a+b+c+d
Rate per metre = (a+b+c+d)/10
B. Manual Means
a) Labour
Mate
Mazdoor
Day
Day
0.12
3.00
Day
Day
0.04
2.00
b) Overheads @
% on (a)
c) Contractor's profit @ % on (a+b)
Cost for 10 metres = a+b+c
Rate per metre = (a+b+c)/10
3.26
309
3.27
309
c) Material
Perforated pipe of cement concrete, Mtr
internal dia 100mm
Crushed stone as per Table 300-3
Cum
d) Overheads @
% on (a+b+c)
23
10.00
2.40
3.28
Note
309
0.02
1.50
Cum
1.35
Cum
Cum
1.50
0.495
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 10 metres = a+b+c+d
Rate per metre = (a+b+c+d)/10
3.29
309
3.30
310
Day
Day
Day
b) Machinery
Smooth 3 wheeled steel roller 8-10 tonnes Hour
Water tanker 6 KL, one trip per hour
Hour
c) Material
Cost of water
0.28
6.00
1.00
3.00
3.00
KL
18.00
Day
Day
0.04
1.50
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 3500 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/3500
3.31
313
b) Machinery
Dozer 80 HP for spreading @ 200 cum Hour
per hour
Vibratory road roller 8-10 tonnes @ 100 Hour
cum per hour
Water tanker 6 KL, one trip per hour
Hour
c) Material
Cost of water
KL
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
25
0.50
1.00
2.00
12.00
3.32
301
a) Labour
Mate
Day
Mazdoor for trimming slopes and helping Day
in excavation, etc.
b) Machinery
Dozer180HP (D-80A12) @ 43.28 cum per Hour
hour
Front end loader
Hour
Tipper 5.5 cum capacity, 4 trips per hour
Hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 260 cum = a+b+c+d
Rate per cum = (a+b+c+d)/260
3.33
Note
301
0.24
6.00
6.00
6.00
12.00
Unit = cum
Taking output =170 cum
a) Labour
Mate
Mazdoor
Day
Day
b) Machinery
Dozer 180 HP (D-80 A 12) @ 28.32 cum Hour
per hour
Front end loader
Hour
Tipper 5.5 cum capacity, 4 trips per hour
Hour
c) Overheads @ % on (a+b)
Note
3.34
301
0.32
8.00
6.00
7.00
7.00
Day
Day
Day
Day
0.49
10.00
2.00
0.25
Hour
6.00
Hour
5.00
Hour
Hour
7.00
7.00
c) Materials
Gelatine 80 per cent
Kg
Electric detonators @ 1 detonator for 2 Nos
Gelatine sticks of 125 gms each
27
35.00
140.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 170 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/170
Note
3.35
Suggestive
Day
Day
b) Machinery
Hydraulic Excavator 0.9 cum bucket Hour
capacity @ 60 cum/hour
Tipper 10T capacity, flyash 360x1.2 = t.km.
432 tonnes
0.16
4.00
6.00
432xL
% on (a+b)
Hour
1.80
Hour
Hour
Hour
3.60
12.00
3.60
30
Chapter-4
Sub-Bases, Bases (Non-Bituminous) and Shoulders
Preamble:
1. Quantities of materials provided are approximate and are meant for the purpose of
estimating only. Actual quantities shall be as per mix design.
2. For construction of sub-base, two alternatives as under have been provided:
a.
b.
3. Although plant mix method has not been provided in the MoRT&H Specifications, it is
actually being adopted by some of the contractors who are holding the mixing plants to get
better quality of mix. It is also found economical as it can achieve much more progress. It is
recommended that this point may be kept in view during future revision of specifications of
sub-base.
4. In the case of improvement of sub-grade with lime stabilization, soil is assumed to be
available and has not been provided for. Only lime has been catered. In the case of lime
stabilization of sub-base, soil has been provided to form the sub-base.
5. In the case of medians, separators and footpaths, plate compactor has been catered for
compaction due to restricted space.
6. It has been assumed in the case of crushed cement concrete sub-base/base that during the
process of dismantling, 25 per cent of aggregates will get segregated and only the
remaining will have to be broken/crushed from dismantled concrete slab portions.
Transportation of materials has been catered from place of dismantling to work site. In case,
site is the same, transportation cost can be deleted.
7. Separate rate for penetration coat over top layer of crushed cement concrete base has
been provided, as this item is optional.
8. While providing for the rate of materials, detailed local enquiries should be made and
prevailing market rates ascertained from concerned suppliers in the area keeping in view
the location of crushing plants and lead involved.
9. The rate analyses for crushing of aggregates has also been included in Chapter-1. The cost
of procured aggregates and crushed aggregates by own crusher should be compared and
economic alternative adopted. It has generally been observed in practice that contractors
are setting up their own crushing plants where quantities of aggregates are large especially
for projects above Rs.50 crores.
10. The quantity considered in the output is the compacted quantity. The quantities of
aggregates provided in the rate analysis under the head material are the uncompacted
quantities.
Reference to
MoRT&H
Specifications
401
Description
Unit
Quantity
Day
Day
Day
0.40
2.00
8.00
Hour
Hour
Hour
6.00
6.00
4.50
Hour
t.km
6.00
450xL
Hour
Hour
6.00
6.00
Cum
Cum
Cum
KL
144.00
57.00
86.40
27.00
sub-base
Rate.
Rs.
Or
For Grading II Material
Cum
Cum
Cum
KL
100.80
72.00
115.20
27.00
Cum
Cum
Cum
KL
100.80
36.00
151.20
27.00
a) Labour
Mate
Mazdoor skilled
Mazdoor unskilled
Day
Day
Day
0.48
2.00
10.00
b) Machinery
Motor grader 110 HP @ 50 cum
Vibratory roller 8-10 tonne
Tractor-Rotavator
Water tanker
Hour
Hour
Hour
Hour
6.00
6.00
12.00
3.00
c) Material
Close
graded
granular
material as per Table 400-1
sub-base
Cum
Cum
Cum
KL
192.00
76.00
115.20
18.00
Or
For Grading II Material
26.5 mm to 9.5 mm @ 35 per cent
9.5 mm to 2.36 mm @ 25 per cent
2.36 mm below @ 40 per cent
Cost of water
134.40
96.00
153.60
18.00
Or
For Grading III Material
9.5 mm to 4.75 mm @ 35 per cent
4.75 mm to 2.36 mm @ 12.5 per cent
2.36 mm below @ 52.5 per cent
Cost of water
Cum
Cum
Cum
KL
134.40
48.00
201.60
18.00
Day
Day
Day
0.40
2.00
8.00
Hour
Hour
Hour
6.00
6.00
3.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @
% on
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
4.2
401
c) Material
For coarse graded granular sub-base
Materials as per Table 400-2
For grading I Material
53 mm to 26.5 mm @ 35 percent
26.5 mm to 4.75 mm @ 45 percent
2.36 mm below @ 20 per cent
Cost of water
Cum
Cum
Cum
KL
134.40
172.80
76.80
18.00
Cum
Cum
KL
288.00
96.00
18.00
Cum
Cum
KL
255.00
129.00
18.00
Day
Day
0.36
1.00
Or
For Grading II Material
26.5 mm to 4.75 mm @ 75 per cent
2.36 mm below @ 25 per cent
Cost of water
Or
For Grading III Material
9.5 mm to 4.75 mm @ 66 percent
2.36 mm below @ 34 per cent
Cost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @
% on
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note
Any one of the grading for material may
be adopted as per design
4.3
402
Lime
Stabilisation
for
Improving
Subgrade
Laying and spreading available soil in
the subgrade on a prepared surface,
pulverising, mixing the spread soil in
place with rotavator with 3 per cent
slaked lime having minimum content of
70 per cent of CaO, grading with motor
grader and compacting with the road
roller at OMC to the desired density to
form a layer of improved subgrade.
Unit = cum
Taking output = 300 cum (525 tonne)
A. By Mechanical Means
a) Labour
Mate
Skilled mazdoor for alignment
5
and
geometerics
Mazdoor for spraying lime
b) Machinery
Tractor with ripper and rotavator
attachments @ 60 cum per hour for
ripping and 25 cum per hour for mixing
Motor Grader 110 HP @ 50 cum per
hour Vibratory roller 8-10 tonne capacity
Water tanker
c) Material
Lime at site
Cost of water
Day
8.00
Hour
12.00
Hour
Hour
Hour
6.00
6.00x0.65*
12.00
Tonne
KL
15.75
72.00
Day
Day
Day
1.44
1.00
35.00
Hour
2.50
Hour
6.00
Tonne
KL
8.00
36.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 300 cum =a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note
4.4
402
Day
Day
Day
0.48
2.00
10.00
b) Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil
Hour
t.km
6.00
525xL
Hour
6.00
Hour
6.00
Hour
Hour
12.00
12.00
Tonne
KL
15.75
72.00
403
Unit = cum
Taking output = 300 cum (525 tonne)
Day
Day
Day
0.48
2.00
10.00
b) Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil
Hour
t.km
6.00
525xL
Hour
6.00
Hour
Hour
6.00
12.00
Hour
12.00
Tonne
21.00
KL
72.00
403
Day
Day
Day
b) Machinery
Motor Grader 110 HP @ 50 cum per
hour
Vibratory roller 8-10 tonne
Tractor with rotavator and blade @ 25
cum per hour
Water tanker
c) Material
Cement at site @ 4 per cent by weight of
crushed aggregate (600 tonne)
0.48
2.00
10.00
6.00
6.00
12.00
10.00
Tonne
24.00
Cum
Cum
Cum
KL
211.20
76.80
96.00
60.00
Cum
Cum
Cum
KL
124.80
19.20
240.00
60.00
4.7
Note
404.3.1
Making 50 mm x 50 mm furrows, 25 mm
deep, 45 to the center line of the road
and at one metre interval in the existing
thin bituminous wearing coarse including
sweeping and disposal of excavated
material within 1000 metres lead.
Unit = sqm
Taking output = 30mx7m = 210 sqm
9
a) Labour
Mate
Mazdoor
Day
Day
0.08
2.00
b) Machinery
Tractor- trolley
Hour
0.20
Day
Day
Day
0.92
2.00
21.00
Hour
Hour
6.00
6.00
Hour
18.00
Cum
KL
720.00
108.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 210 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/210
4.8
404.3.2
Inverted Choke
Construction of inverted choke by
providing,
laying,
spreading
and
compacting screening B type/coarse
sand of specified grade in uniform layer
on a prepared surface with motor grader
and compacting with power roller etc.
Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Motor Grader 110 HP
Vibratory roller8-10tonnes @ 60cum per
hour
Water tanker
c) Material
Screening type 'B' or coarse sand
Cost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d]
Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/600
4.9
404
Day
Day
Day
10.08
2.00
250.00
Hour
6.00
Hour
12.00
Hour
24.00
Cum
435.60
Cum
435.60
Cum
435.60
Cum
97.20
Cum
57.60
Or
Smooth 3-wheeled steel roller @ 30
cum/hour
Water tanker
c) Material (Refer Table 400-7, 8 & 9)
Aggregate
Grading I 90 mm to 45 mm @ 1.21 cum
per 10 sqm for compacted thickness of
100mm
Or
Grading II 63 mm to 45 mm/Grading III
53 mm to 22.4 mm @ 0.91 cum per 10
sqm for compacted thickness of 75 mm
Or
Grading III 53 mm to 22.4 mm
@ 0.91 cum per 10 sqm for compacted
thickness of 75 mm
Stone Screening
Type A 13.2 mm for grading I @ 0.27
cum per 10 sqm
Or
Type A 13.2 mm for grading II @ 0.12
cum per 10 sqm
11
Or
Type B 11.2 mm for grading II @ 0.20
cum per 10 sqm
Cum
96.01
Cum
86.40
Cum
108.00
Cum
105.59
Cum
28.80
Cum
28.80
KL
144.00
Day
Day
Day
0.68
2.00
15.00
Hour
7.20
Hour
6.00
Or
Type B 11.2 mm for grading III @ 0.18
cum per 10 sqm
Or
Binding material
Binding Material @ 0.08 cum per 10
sqm for grading I material
Or
Binding Material @ 0.06 cum per 10
sqm for grading II material
(Any one of the aggregate grading,
screening and binding material may be
used as per design)
Cost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360 B.
B. By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Motor grader 110 HP @ 50 cum/hr. for
spreading
Vibratory roller 8-10 tonne @ 60 cum/hr.
12
Or
Smooth 3-wheeled steel roller @ 30
cum/hr.
Water tanker 6 KL capacity
Hour
12.00
Hour
24.00
a) Labour
Mate
Mazdoor skilled
Mazdoor for crushing broken cement
concrete pavement/slabs into aggregate
Day
Day
Day
4.16
2.00
102.00
b) Machinery
Motor grader 110 HP @ 50 cum/hr.
Vibratory roller 8-10 tonne @ 60 cum
per hour
Hour
Hour
6.00
6.00
Hour
12.00
Hour
t.km
6.00
720xL
c) Material
Same as in case of manual means
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
4.10
Note
405
Crushed
Cement
Base/Base
Concrete
Sub-
Or
Smooth 3-wheeled steel roller @ 30
cum/hr.
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to
13
Hour
12.00
KL
72.00
Day
Day
0.56
2.00
c) Material
Material available from dismantled
concrete slab after crushing/breaking
and only carriage is required to be
provided
Cost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
4.11
Note
405.2
Mazdoor
b) Machinery
Mechanical broom hydraulic @ 1250
sqm per hour
Hydraulic self propelled chips spreader
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Vibratory roller 8-10 tonne @ 30 cum
per hour
Bitumen pressure distributor @ 1750
sqm per hour
c) Material
Crushed stone aggregate 11.2 mm size
Bitumen
Day
12.00
Hour
6.00
Hour
Hour
Hour
Hour
6.00
6.00
6.00
6.00x0.65*
Hour
4.28
Cum
Tonne
97.50
0.25
Day
Day
Day
0.48
2.00
10.00
Hour
6.60
Hour
6.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
4.12
Note
406
Hour
Hour
Hour
6.00
6.00
6.00x0.65*
Hour
12.00
Hour
t.km
3.00
495xL
Cum
Cum
Cum
KL
89.10
118.80
89.10
18.00
Day
Day
0.24
6.00
Or
Smooth 3-wheeled steel roller @ 8-10
tonne
Water tanker
Tipper
Add 10 per cent of cost of carriage to
cover cost of loading and unloading
c) Material (Table 400-11)
45 mm to 22.4 mm @ 30 per cent
22.4 mm to 2.36 mm @ 40 per cent
2.36 mm to 75 micron @ 30 per cent
Cost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225
Note
4.13
407
b)
Machinery
Water tanker 6 KL with 5 km lead and 1
trip per hour
Plate compactor @ 3.5 cum per hour
c) Material
Cost of water
Hour
1.00
Hour
6.00
KL
6.00
Day
Day
0.16
4.00
Hour
Hour
Hour
1.00
6.00
0.50
t.km
52.5xL
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 21 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/21
4.14
Note
407
KL
17
6.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 21 cum = a+b+*c+d+e
Rate per cum = (a+b+c+d+e)/21
Note
4.15
4.16
409
Day
Day
Day
18
1.36
4.00
30.00
b) Machinery
Vibratory road roller 8-10 tonne @ 60
cum per hour
Water tanker 6 KL capacity @ 1 trip per
hour
Concrete mixer 0.4/0.28 cum per hour
c)
Material
i) For granular sub-base material
53 mm to 26.5 mm @ 35 percent
26.5 mm to 4.75 mm @ 45 per cent
2.36 mm below @ 20 per cent
Hour
0.75
Hour
2.00
Hour
6.00
Cum
Cum
Cum
20.79
26.73
11.88
Cum
6.75
Cum
Tonne
3.38
1.88
Cum
Tonne
3.84
1.83
Nos
3300.00
Mtr
22.50
KL
12.00
Day
0.48
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 300 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/300
4.17
410
Mazdoor skilled
Mazdoor
Day
Day
2.00
10.00
Hour
12.00
Hour
Hour
6.00
6.00
Hour
6.00
Cum
Cum
Cum
KL
157.46
151.06
166.68
36.00
Cum
Cum
Cum
KL
24.12
237.60
213.48
36.00
a) Labour
Mate
Mazdoor skilled
Mazdoor
Day
Day
Day
0.28
1.00
6.00
b) Machinery
Wet mix plant @ 75 tonne per hour
Electric generator set, 125 KVA
Front end loader 1 cum bucket capacity
Motor grader 110 HP
Vibratory roller 8-10 tonne
Water tanker
Hour
Hour
Hour
Hour
Hour
Hour
6.00
6.00
6.00
6.00
6.00
3.00
b) Machinery
Tractor attached with rotavator @ 25
cum per hour
Motor grader 110 HP
Vibratory roller 8-10 tonne @ 60 cum
per hour
Water tanker
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent
22.5 mm to 5.6 mm @ 32 per cent
Below 5.6 mm @ 35 per cent
Cost of water
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm @ 5 per cent
22.4 mm to 5.6 mm @ 50 per cent
Below 5.6 mm @ 45 per cent
Cost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
Note
20
Tipper
t.km
450xL
Cum
Cum
Cum
98.40
94.41
104.18
Cum
Cum
Cum
KL
15.06
148.50
133.43
18.00
Suggestive
a) Labour
Mate
Mazdoor
Mazdoor (Skilled)
b) Machinery
Hydraulic excavator 0.90 cum bucket
capacity @ 60 cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil
578 tonnes
Tipper 10T capacity for carriage of 115
tonnes flyash
Tipper 10T capacity for carriage of 29
tonnes of lime from store to work site
Day
Day
Day
0.24
6.00
1.00
Hour
6.00
t.km
578xL
t.km
115xL
Hour
3.00
Hour
6.00
Hour
9.60
Hour
Hour
6.00
12.00
Tonne
Cum
29.00
360.00
23
Chapter-5
Bases and Surface Course (Bituminous)
Preamble:
1.
Various alternatives for machines and materials have been provided. The one that
suits a particular situation and design may be adopted.
2.
The Clauses of MoRT&H Specifications, which have been mentioned for each item, may
be referred for detailed specifications and construction procedure. The rate analyses
mention only brief description.
3.
The machinery and equipment included in various analysis are as per various
specifications of MoRT&H and are mandatory. As per the present trend, contractors are
procuring machinery and equipment of higher capacity. Provision has accordingly been
made.
4.
The outputs taken for the construction equipment are for the compacted quantities of
the relevant items and not for loose quantities.
5.
In case of prime coat and tack coat, minimum quantities of binder indicated in
specifications have been taken. Adjustment, plus or minus, can be made for the
variation between this quantity and the actual quantity approved by the Engineer after
the preliminary trials.
6.
The items of bituminous works required under maintenance have been added in the
Chapter on Maintenance.
7.
Tack coat and prime coat, wherever provided, are required to be measured and paid
separately.
8.
Cleaning of surface is a part of the prime coat and tack coat. As such cleaning of surface
has not been provided for bituminous courses as the same is already catered in
prime/tack coat. However, for those cases where such coats are not required to be done,
cleaning of surface shall be included.
9.
It is presumed that tack coat, where required, will be provided immediately preceding the
bituminous layer.
10. Rolling of bituminous courses is required to be done as per Clause 501.6. Provision in
the analyses has accordingly been made.
It has been observed during actual
practice at work sites, that the availability of road roller is generally inadequate. As
compaction is the key to good construction, this point is being specifically highlighted to
ensure that road rollers are deployed at site as per provision in the rate analyses.
11. Spreading of bituminous materials shall be done by mechanical means except in
areas where a mechanical paver cannot have access.
12. The source of all materials to be used on the project must be tested and expressly
approved by the Engineer.
13. Quantities of materials taken in the analyses are for the purpose of cost estimate only.
The actual quantity shall be as per job mix formula.
1
14. Choice of grade of bitumen shall be made as per the guidelines given in Appendix-4 of
MoRT&H Specifications.
15. The specification and requirements for modified binder with various type of modifiers
have been laid down in Clause 521 of MoRT&H Specifications and IRC: SP: 53-2002
which shall be followed.
16. The guidelines given vide Annexure - A to Clause 501 of MoRT&H Specifications in
regard to protection of environment shall be followed for a particular situation.
17. The quantities taken as output of the item in the rate analysis are the compacted
quantities and the quantities of aggregates taken under the head 'material' are the uncompacted quantities for the procurement purposes.
18. The approximate proportions by weight of different aggregates and bitumen (or by
volume in unavoidable cases) necessary to produce the intended mix satisfying the job
requirements and meeting the designated specifications are for estimating purpose
only. The actual quantities should be worked out on the basis of job mix formula
adopted for the job after working out the same in the laboratory for particular
aggregates and bitumen approved by the Engineer.
Sr.
No.
5.1
Reference to
MoRT&H
specifications
502
Prime Coat
Description
Unit
Quantity
Day
Day
b) Machinery
Mechanical broom @ 1250 sqm per Hour
hour
Hour
Air compressor 250 cfm
Hour
Bitumen pressure distributor @ 1750
sqm per hour
Hour
Water tanker 6 KL capacity @ 1 trip per
hour
c) Material
Bitumen emulsion @ 0.6 kg per sqm
Tonne
Cost of water
KL
d) Overhead charges @ % on (a+b+c)
2
0.08
2.00
2.80
2.80
2.00
1.00
2.10
6.00
Rate
Rs.
e) Contractor's profit @
% on
(a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
5.2
Note
503
Tack Coat
Providing and applying tack coat with
bitumen emulsion using emulsion
pressure distributor at the rate of 0.20
kg per sqm on the prepared
bituminous/granular surface cleaned
with mechanical, broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per
hour Air compressor 250 cfm
Emulsion pressure distributor @ 1750
sqm per hour
c) Material
Bitumen emulsion @ 0.2 kg per sqm
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @
%on
(a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note
1. Bitumen
emulsion
has
been
provided @ 0.20 kg per sqm as per
Clause 503.8. Payment shall be
made with adjustment, plus or
minus, for the variation between this
quantity
and
actual
quantity
approved by the Engineer after
preliminary trials referred to in
Clause 503.4.3.
3
Day
Day
0.08
2.00
Hour
Hour
Hour
2.80
2.80
2.00
Tonne
0.70
504
Bituminous Macadam
Providing and laying bituminous
macadam with 100-120 TPH hot mix
plant producing an average output of 75
tonnes per hour using crushed
aggregates
of
specified
grading
premixed with bituminous binder,
transported to site, laid over a
previously prepared surface with paver
finisher to the required grade, level and
alignment and rolled as per Clauses
501.6 and 501.7 to achieve the desired
compaction
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate
Mazdoor
working
with
HMP,
mechanical broom, paver, roller,
asphalt cutter and assistance for setting
out lines, levels and layout of
construction
Skilled mazdoor for checking line and
levels,
b) Machinery
Batch mix HMP 100-120 TPH @ 75
tonne per hour actual output
Mechanical broom hydraulic @ 1250
sqm per hour
Air compressor 250 cfm
Paver finisher hydrostatic with sensor
control @ 75 cum per hour
Generator 250 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Day
Day
0.84
16.00
Day
5.00
Hour
6.00
Hour
2.20
Hour
Hour
2.20
6.00
Hour
Hour
t.km
6.00
6.00
450xL
Hour
600x065*
Hour
600x065*
Hour
600x065*
14.85
1.5
Cum
Cum
Cum
Cum
43.51
130.55
72.53
43.51
Cum
Cum
Cum
116.04
116.04
58.02
Or
Grading II (19 mm nominal size)
25-10 mm
40 per cent
10-5 mm
40 per cent
5 mm and below
20 per cent
*Any one of the alternative may be
adopted as per approved design
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @
% on
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
Note
505
Day
Day
0.32
6.00
Day
2.00
Hour
6.00
Hour
2.57
Hour
10.00
Hour
Hour
6.00
6.00
c) Material
Bitumen @ 5 kg per sqm
Tonne
Crushed stone coarse aggregate Cum
passing
45 mm and retained on 2.8 mm sieve @
0.06 cum per sqm
Cum
Key aggregates passing 22.4 mm and
6
22.50
270.00
67.50
Day
Day
0.40
8.00
Day
2.00
Hour
6.00
Hour
2.57
Hour
10.00
Hour
Hour
6.00
6.00
c) Material
Bitumen @ 6.8 kg per sqm
Tonne
Crushed stone coarse aggregate (loose) Cum
passing 63 mm and retained on 2.8 mm
sieve @ 0.09 cum per sqm
Key aggregates passing 26.5 mm and Cum
retained on 2.8 mm sieve @ 0.018 cum
per sqm
d) Overhead charges @ % on (a+btc)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4500
Note
30.60
405.00
81.00
5.5
506
Day
Day
0.40
8.00
Day
2.00
Hour
6.00
Hour
3.43
Hour
Hour
Hour
10.00
6.00
6.00
b) Machinery
Hydraulic self propelled chip spreader
both for aggregates and key aggregates
@ 1500 sqm per hour for 3000 x 3 sqm
Bitumen pressure distributor for 3000 x
2 sqm @ 1750 sqm per hour
Tipper 5.5 cum capacity
Vibratory roller 8 tonnes
Front end loader 1 cum bucket capacity
c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per Tonne
10 sqm for each layer
Crushed stone coarse aggregate Cum
passing 53 mm and retained on 2.8 mm
sieve @ 0.5 cum per 10 sqm for each
layer
Cum
Key aggregates passing 22.4 mm and
retained on 2.8 mm sieve @ 0.13 cum
per 10 sqm
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @
% on
(a+b+c+d)
Cost for 3000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3000
Note
9.00
300.00
39.00
507
Day
Day
0.84
16.00
Day
5.00
Hour
Hour
6.00
6.00
Hour
Hour
t.km
6.00
6.00
450xL
Hour
6.00x065*
Hour
600x0.65*
Hour
600x0.65*
c) Materials
i) Bitumen @ 4.25 per cent of weight Tonne
9
19.13
of mix
ii) Aggregate
Total weight of mix = 450 tonne
Weight of bitumen = 19.13 tonne
Weight of aggregate = 450-19.13 =
430.8"
Taking density of aggregate = 1.5
ton/cum
Volume of aggregate = 287.25 cum
Grading -1 40 mm (Nominal Size)
37.5-25 mm 22 per cent
25-10 mm
13 per cent
10-4.75 mm 19 per cent
4.75 mm and below. 44 per cent
Filler @2 per cent of weight
aggregates
Or
Cum
Cum
Cum
Cum
of Tonne
63.19
37.34
54.58
126.39
8.62
86.16
80.43
114.90
8.62
508
Day
Day
0.84
16.00
Day
5.00
Hour
Hour
6.00
6.00
Hour
Hour
t.km
6.00
6.00
450xL
Hour
6.00x0.65*
Hour
6.00x0.65*
Hour
6.00x0.65*
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen @ 4.5 per cent of weight of Tonne
mix
20.25
ii) Aggregate
Total weight of mix = 450 tonne
Weight of bitumen = 20.25 tonne
Weight of aggregate =450-20.25
= 429.75tonne
Taking density of aggregate = 1.5 ton
Volume of aggregate = 286.5 cum
13.2-10 mm 20 per cent
57.30
10-5 mm
38 per cent
108.87
5 mm and below 40 per cent
114.60
Filler @ 2 per cent of weight of 8.62
aggregate
Or
Grading II: 10 mm
i) Bitumen @ 5 per cent of weight of Tonne
weight of mix = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonne
Weight of bitumen = 22.5 tonne
Weight of aggregate = 450 -22.50= 42 /
tonne
12
22.50
5.8
509
Bituminous Concrete
Providing and laying bituminous
concrete with 100-120 TPH batch type
hot mix plant producing an average
output of 75 tonne per hour using
13
162.45
116.85
8.62
Day
Day
0.84
16.00
Day
5.00
Hour
Hour
6.00
6.00
Hour
Hour
t.km
6.00
6.00
450xL
Hour
600x0.65*
Hour
6.00x0.65*
Hour
6.00x0.65*
c) Material
i) Bitumen @ 5 per cent of weight of
mix
ii) Aggregate
Total weight of mix = 450 tonne
Weight of bitumen = 22.5 tonne
Weight of aggregate = 450 -22.50 =
427.50
14
Tonne
22.50
Cum
Cum
Cum
Tonne
99.75
65.55
114.00
8.62
Cum
Cum
Cum
Tonne
85.50
71.25
122.55
8.62
Or
Grading - II 13 mm (Nominal Size)
13.2 -10 mm 30 per cent
10-5 mm
25 per cent
5 mm and below
43 per cent
Filler @ 2 per cent of weight of
aggregates
*Any one of the alternatives may be
adopted as per approved design.
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 191 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/191
*1. Although the rollers are required
only for 3 hours as per norms of
output, but the same have to be
available at site for six hours as the
hot mix plant and paver will take six
hours for mixing and paving the
output of 450 tonne considered in
this analysis. To cater for the idle
period of these rollers, their usage
rates have been multiplied by a
factor of 0.65.
2. Quantity of Bitumen has been taken
for analysis purpose. The actual
quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and
ward and other miscellaneous
duties at site including sundries
have
been
included
in
administrative overheads of the
contractor.
4. In case BC is laid over freshly laid
15
510
Surface Dressing
Providing and laying surface dressing
as wearing course in single coat using
crushed stone aggregates of specified
size on a layer of bituminous binder laid
on prepared surface and rolling with 810 tonne smooth wheeled steel roller.
Unit = sqm
Taking output = 9000 sqm
Case -1:- 19 mm nominal chipping size
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm per
hour
Air compressor 250 cfm
Hydraulic self propelled chip spreader
@ 1500 sqm per hour
Tipper 10 tonne capacity for carriage of
stone chips from stockpile on road side
to chip spreader
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Smooth wheeled roller 8-10 tonne
16
Day
Day
Day
0.44
9.00
2.00
Hour
7.20
Hour
Hour
7.20
6.00
Hour
6.00
Hour
Hour
Hour
6.00
6.00
6.00
weight
c) Material
Bitumen @ 1.20 kg per sqm
Crushed stone chipping, 19 mm
nominal size @ 0.015 cum per sqm
Tonne
Cum
10.80
135.00
Day
Day
Day
0.44
9.00
2.00
Hour
7.20
Hour
Hour
7.20
6.00
Hour
6.00
Hour
Hour
6.00
6.00
Hour
6.00
Tonne
Cum
9.00
90.00
511
Day
Day
0.84
16.00
Day
5.00
Hour
Hour
Hour
6.00
6.00
6.00
t.km
450xL
Hour
6.00
Hour
6.00
Tonne
Cum
14.97
276.75
Day
Day
Day
0.80
18.00
2.00
b) Machinery
Concrete mixer 0.4/0.28 cum capacity
Smooth wheeled steel roller 8-10 tonne
Hour
Hour
6.00
6.00
Tonne
1.94
Cum
24.30
c) Material
Cationic Bitumen Emulsion @ 21.50 kg
per 10 sqm
Crushed stone aggregates 13.2 mm to
5.6 mm @ 0.27 cum per 10 sqm
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
5.11
512
tonne/hour.
Providing, laying and rolling of closegraded premix surfacing material of 20
mm thickness composed of 11.2 mm to
0.09 mm (Type-A) or 13.2 mm to 0.09
mm
(Type-B)
aggregates
using
penetration grade bitumen to the
required line, grade and level to serve
as wearing course on a previously
prepared base, including mixing in a
suitable plant, laying and rolling with a
smooth wheeled roller 8-10 tonne
capacity, and finishing to required level
and grade.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate
Mazdoor working with HMP, road
sweeper, paver and roller
Skilled mazdoor for checking line and
levels
b) Machinery
i) HMP of appropicate capacity
ii) Electric Generator Set 250 KVA
iii) Front end loader 1 cum bucket
capacity
iv) Tipper 10 tonne capacity
Day
Day
0.84
16.00
Day
5.00
Hour
Hour
Hour
6.00
6.00
6.00
t.km
450xL
Hour
6.00
Hour
6.00
Tonne
Cum
22.50
276.75
Tonne
Cum
19.48
276.75
Or
Type -B
Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to
0.09 mm @ 0.27 cum per 10 sqm
20
513
Seal Coat
Providing and laying seal coat sealing
the voids in a bituminous surface laid to
the specified levels, grade and cross fall
using Type A and B seal coats
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
Case -1: Type A
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic self propelled chip spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor @ 1750
sqm per hour
Smooth wheeled roller 8-10 tonne
weight
c) Material
Bitumen @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size
defined as 100 per cent passing 11.2
mm sieve and retained on 2.36 mm
sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @ %on (a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Note
Day
Day
0.24
6.00
Hour
Hour
Hour
Hour
6.00
6.00
6.00
6.00
Hour
6.00
Tonne
Cum
10.05
92.25
Day
Day
0.16
4.00
b) Machinery
HMP of 75 tonnes/hour
Electric generator set 250 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Hour
Hour
Hour
t.km
2.00
2.00
2.00
104 x L
Hour
2.00
Hour
2.00
Tonne
Cum
5.34
47.16
c) Material
Bitumen @ 6.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size
defined as passing 11.2 mm sieve and
retained on 2.36 mm sieve applied @
0.06 cum per 10 sqm
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 7858 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7858
5.13
Note
514
Supply of Stone
Pavement Courses
Aggregates
for
515
Mastic Asphalt
Providing and laying 25 mm thick
mastic asphalt wearing course with
paving grade bitumen meeting the
requirements given in Table 500-29,
prepared by using mastic cooker and
laid to required level and slope after
cleaning
the
surface,
including
providing antiskid surface with bitumen
precoated fine grained hard stone
chipping of 13.2 mm nominal size at the
rate of 0.005 cum per 10 sqm and at an
approximate spacing of 10 cm center to
center in both directions, pressed into
surface when the temperature of
surfaces is not less than 100C,
protruding 1 mm to 4 mm over mastic
surface, all complete as per Clause
515.
Unit = sqm
Taking output = 35.00 sqm (0.87 cum)
assuming a density of 2.3 tonne/cum-2
tonne
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm per
hour
Air compressor 250 cfm
Mastic cooker 1 tonne capacity
Bitumen boiler 1500 litres capacity
Tractor for towing and positioning of
23
Day
Day
Day
0.44
10.00
1.00
Hour
0.06
Hour
Hour
Hour
Hour
0.06
6.00
6.00
1.00
Tonne
0.20
Cum
0.39
MT
0.36
Cum
0.55
Cum
0.02
Kg
0.50
516
Slurry Seal
Providing and laying slurry seal
consisting of a mixture of fine
aggregates, portland cement filler,
bituminous emulsion and water on a
road surface including cleaning of
surface, mixing of slurry seal in a
suitable mobile plant, laying and
compacting to provide even riding
surface
Case -1: 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonne per cum
Weight of mix = 176 tonne
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity for carriage of
aggregate from stockpile on road side
to slurry equipment, bitumen emulsion
and filler
Pneumatic tyred roller with individual
wheel load not exceeding 1.5 tonne
Water tanker 6 KL capacity
c) Material
Residual Binder @ 11 per cent of mix
80 x2.2xO.11
Fine aggregate 4.75 mm and below 87
per cent of total mix, 80 x 2.2 x 0.87 =
153.12 tonne. Taking density 1.5=
153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix =
80x2.2x0.02
Cost of water
25
Day
Day
0.24
6.00
Hour
Hour
Hour
Hour
Hour
6.00
6.00
6.00
6.00
6.00
Hour
6.00
Hour
2.00
Tonne
Cum
Tonne
KL
19.36
102.08
3.52
12.00
Day
Day
0.20
5.00
Hour
Hour
Hour
Hour
Hour
6.00
6.00
6.00
6.00
6.00
Hour
2.00
Tonne
17.16
Cum
74.80
Tonne
2.64
KL
12.00
a) Labour
Mate
Mazdoor
Day
Day
0.20
5.00
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity
Hour
Hour
Hour
Hour
6.00
6.00
6.00
6.00
26
Hour
6.00
Hour
2.00
Tonne
12.67
Cum
43.30
Tonne
1.58
KL
12.00
a) Labour
Mate
Mazdoor
Mazdoor skilled
Day
Day
Day
0.48
10.00
2.00
b) Machinery
Cold milling machine @ 20 cum per
Hour
6.00
c) Material
Residual Binder @ 16 per cent of mix
36x2.2x0.16
Fine aggregate 2.36 mm and below, 82
per cent of total mix 36 x 2.2 x 0.82 =
64.94 tonne. Taking density 1.5
Filler @ 2 per cent of total mix = 36 x
2.2 x 0.02
Cost of water
d) Overhead charges @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 24000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/24000
5.16
Note
517
27
hour
Mechanical broom @ 1250 sqm per
hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750
sqm per hour
Hot mix plant 100-120 TPH producing
an average of 75 tonne per hour
Electric generator set 250 KVA
Front end loader 1.00 cum bucket
capacity
Tipper 5.5 cum capacity
Smooth wheeled roller 8-10 tonne
Vibratory roller 8 tonne
Smooth wheeled tandem roller 6-8
tonne
Hour
1.28
Hour
Hour
1.28
0.91
Hour
3.00
Hour
Hour
3.00
3.00
Hour
Hour
Hour
Hour
18.00
3.00x0.65*
3.00x0.65*
3.00x0.65*
c) Material
i) Bitumen
A bitumen content is 4.5 per cent by
weight of mix. For reclaimed material,
fresh bitumen will be required to the
extent of 60 per cent of normal
requirement.
In a mix of 276 tonne, 82.8 tonne is
reclaimed and balance 193.2 tonne is
fresh mix.
Bitumen required for reclaimed mix of
82.8 tonne @ 60 per cent = 82.8 x
0.60x0.04=1.99
Bitumen required for fresh mix of 193.2
tonnes =193.2x0.04 = 7.73
Tonne
1.99
Tonne
7.73
Cum
Cum
Cum
Cum
Tonne
28.44
18.55
24.73
49.46
5.52
ii) Aggregates
Percentage of mix requiring fresh
aggregates - 70 per cent
Weight of fresh mix = 276 x 0.70 =
193.2 tonne
Weight of fresh aggregate in the mix =
193.2x0.96 = 185.47 tonne
Taking average density of 1.5
tonne/cum, total volume of aggregate
=123.65 cum
Size wise requirement of fresh
aggregates
37.5 - 25 mm @ 23 per cent
25 -10 mm @ 15 percent
10 - 5mm @ 20 per cent
Below 5 mm @ 40 per cent
Filler (cement) @ 2 per cent = 5.52
tonne of 276 tonne
28
5.17
Note
518
Fog Spray
Providing and applying low viscosity
bitumen emulsion for sealing cracks
less than 3 mm wide or incipient fretting
or disintegration in an existing
bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per
hour
Air compressor 250 cfm
Bitumen emulsion pressure distributor
@ 1750 sqm per hour
c) Material
Bitumen emulsion @ 0.75 kg per sqm
Day
Day
0.12
3.00
Hour
6.00
Hour
Tonne
6.00
6.00
Tonne
7.88
Day
Day
0.16
4.00
29
b) Material
Crushed stone grit 3 mm size @ 3.75
kg per sqm
Bitumen emulsion for pre-coating grit @
2 per cent of grit, 39.38 x 0.02
5.18
519
Cum
26.25
Tonne
0.79
8 per cent
90 per cent
Proportion of aggregates
19 mm to 9.5 mm
25 per cent
9.5 mm to 6 mm
29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes of
appropriate capacity but not less than
75 tonne/hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to
cover cost of loading and unloading
Paver finisher
Pneumatic tyred roller 12-15 tonne
30
Day
Day
Day
0.84
16.00
5.00
Hour
6.00
Hour
Hour
t.km
6.00
6.00
450xL
Hour
Hour
6.00
6.00x0.65*
on
8 per cent
90 per cent
Proportion of aggregates
37.5 mm to 19 mm 25percent
19 mm to 6 mm
30 per cent
6 mm to 0.075 mm 35 per cent
31
Hour
6.00x0.65*
Tonne
Tonne
Cum
36.00
9.00
75.00
Cum
87.00
Cum
108.00
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90
tonne per hour producing average
output of 75 tonne per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Day
Day
Day
0.84
16.00
5.00
Hour
6.00
Hour
Hour
t.km
6.00
6.00
450xL
Hour
Hour
Hour
6.00
6.00x0.65*
6.00x0.65*
Tonne
Tonne
Cum
36.00
9.00
75.00
Cum
90.00
Cum
105.00
Day
Day
Day
0.84
16.00
5.00
Hour
6.00
Hour
Hour
t.km.
6.00
6.00
450xL
Hour
Hour
Hour
6.00
6.00x0.65*
6.00x0.65*
Tonne
Tonne
Cum
22.50
9.00
78.00
Cum
93.00
Cum
108.00
5 per cent
93 per cent
Proportion of aggregates
37.5 mm to 19 mm 25 percent
19 mm to 6 mm
30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90
tonne per hour producing output of 75
tonne per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Day
Day
Day
0.84
16.00
5.00
Hour
6.00
Hour
Hour
t.km
6.00
6.00
450xL
Hour
Hour
Hour
6.00
6.00x0.65*
6.00x0.65*
Tonne
Tonne
Cum
22.50
9.00
75.00
Cum
90.00
Cum
114.00
Day
Day
Day
0.84
16.00
5.00
Hour
6.00
Hour
Hour
6.00
6.00
t.Km
450xL
5.19
Note
520
unloading
Paver finisher
Smooth wheeled roller 8-10 tonne
for initial break down rolling
Vibratory roller 8 tonne for
intermediate rolling
Finish rolling with 6-8 tonne smooth
wheeled tandom rollers
Hour
Hour
6.00
6.00x0.65*
Hour
6.00x0.65*
hour
6.00x0.65*
c) Material
Composition of mix (450 tonne) is
assumed to be as under:
Density
2.20 tonne per cum
Weight
450 tonne
Bitumen
5 per cent
Filler
2 per cent
Sand of size 4.75 to
93 per cent
0.075 mm
Bitumen @ 5 per cent
Filler (lime) @ 2 per cent
Sand of size 4.75 to 0.075 mm 450x0.93x1/1.5
d) Overhead charges @ % on
(a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
Note:
5.20
521
Modified Binder
Supply of modified binder produced
by mixing bitumen with modifier
such as natural rubber or crumb
36
Tonne
Tonne
cum
22.50
9.00
288.62
5.21
522
profit
on
Day
Day
0.24
6.00
Hour
6.00
Hour
6.00
Hour
Hour
6.00
6.00
Tonne
Cum
6.00
6.00
profit
% on
on
Day
Day
0.24
6.00
Hour
6.00
Hour
Hour
6.00
6.00
Hour
Hour
6.00
6.00
Tonne
Cum
11.55
105.00
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm
per hour
Air compressor 250 cfm capacity
Bitumen pressure distributor @
1750 sqm per hour
Hydraulic chip spreader
Smooth wheeled road roller 8-10
tonne
c) Material
Modified binder
Crushed stone aggregates 11.2
mm size
d) Overhead charges @
(a+b+c)
e) Contractor's
(a+b+c+d)
profit
% on
on
41
Day
Day
Day
0.24
6.00
2.00
Hour
6.00
Hour
Hour
6.00
6.00
Hour
Hour
6.00
6.00
Tonne
cum
15.75
126.00
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm
per hour
Air compressor 250 cfm capacity
Bitumen pressure distributor @
1750 sqm per hour
Pneumatic roller
c) Material
Paving grade bitumen of 80-100
penetration @ 1.05 kg per sqm
Geotextile including 10 per cent for
overlaps
d) Overhead charges @
(a+b+c)
e) Contractor's
(a+b+c+d)
profit
% on
on
5.22.
Note:
519.3
Day
Day
Day
0.56
12.00
2.00
Hour
2.80
Hour
Hour
2.80
2.00
Hour
2.00
Tonne
3.68
sqm
3850.00
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Batch type cold mixing plant 100120 TPH capacity producing an
average output of 75 tonne per
hour
Electric generator 125 KVA
Front end loader 1 cum capacity
Paver finisher with electronic
sensor, 75 tonne per hour
Tipper 10 tonne capacity
Day
Day
Day
1.00
12.00
5.00
Hour
6.00
Hour
Hour
Hour
6.00
6.00
6.00
t.Km
450xL
Hour
Hour
6.00x0.65*
6.00x0.65*
Hour
1.00
Tonne
20.25
Cum
297.00
profit
% on
on
(case I to III)
1. These mixes are considered
suitable for minor repair work and
temporary
road
surface
improvement.
2. In case concrete mixtures are
required to be used for mixing, a
number of these will be needed to
43
KL
6.00
Day
Day
Day
1.00
12.00
5.00
Hour
6.00
Hour
Hour
Hour
6.00
6.00
6.00
t.Km
450L
Hour
Hour
6.00x065*
6.00x065*
Hour
1.00
Tonne
31.50
Cum
287.00
profit
% on
on
KL
6.00
Day
Day
Day
1.00
12.00
5.00
Hour
6.00
Hour
Hour
Hour
6.00
6.00
6.00
t.Km
450xL
Hour
Hour
Hour
6.00x0.65*
6.00x0.65*
1.00
profit
% on
45
on
Tonne
Cum
KL
38.25
270.00
6.00
Chapter 6
Cement Concrete Pavement
Preamble
1. High capacity batch mix plants of 75 cum/hour (effective output) have been considered
in the rate analysis of cement concrete pavement works.
2. While tippers have been provided for transportation of dry lean cement concrete and
rolled cement concrete, transit truck mixers have been considered for the cement
concrete pavement.
3. Super plasticizer admixture has been provided to improve workability with reduced
water cement ratio.
4. Cement 43 grade has been catered for the cement concrete pavement i.e., for
pavement quality concrete to get higher strength. However, for dry lean concrete,
cement of 33 grades may be preferred.
5. While a slip form paver has been catered for the top layer of concrete pavement, a
mechanical paver has been provided for dry lean and rolled cement concrete.
6. The letter Lrepresents lead in km one way. This will vary from project to project and is
required to be ascertained at site to provide for the cost of carriage of the mix to the
work site.
7. Materials provided in the rate analysis are for estimating purpose. Exact quantity of
materials will be determined from the job mix formula.
8. Fibre Reinforced Concrete for Pavements
Fibre reinforcement concrete is a recent development in the field of cement concrete
pavements. In industrialized countries, it has been in use for nearly 20 years now for
cement concrete pavements and overlays. In India, it is still on an experimental stage.
IRC have already published a code, IRC: SP: 46-1997 for "Steel Fibre Reinforced
Concrete for Pavements" which specifies a fibre content of 0.75 to 1.5 per cent and
brings out the design aspects, material to be used, mix design and construction procedure.
Some firms have developed Polypropylene fibres to be used in place of steel fibres.
These fibres reduce permeability in concrete and prevent shrinkage cracks, which
eliminate chances of corrosion of steel.
The organizations concerned with the construction of cement concrete pavements and
overlays on roads and airfields who have experimented on fibre reinforcement should
give a feed back to the Ministry of Road Transport and Highways so that this item can
be included in the Specifications laid down by the Ministry and eventually included in
the Standard Data Book for Analysis of Rates.
9. Ultra - Thin White Topping
Some of the firms in developed countries, in the recent past have come-up with a
1
innovative idea: laying 50 to 100 mm thick overlay of high strength fibre reinforced
cement concrete over a distressed asphalt pavement. They claim to have achieved 2 to
3 times layer durability than asphalt overlays. There is a need to gather more details of
the work and include in the-specifications in case Ml suitable to conditions in our
country.
Sr.
No.
6.1
Reference to
MoRT&H
Specifications
601
Description
Unit
Quantity
Day
Day
Day
1.12
6.00
22.00
Hour
6.00
Hour
Hour
Hour
Hour
t.km.
6.00
6.00
6.00
6.00
990xL
Rate
Rs.
405.00
% on (a+b+c)
e) Contractor's profit @
(a+b+c+d)
% on
6.2
Note:
602
Day
Day
Day
2.00
15.00
35.00
Hour
2.80
Hour
18.00
Hour
Hour
Hour
Hour
6.00
6.00
6.00
36.00
t.km.
2415xL
12.00
12.00
c)
Material
Crushed
stone
coarse
aggregates of 25 mm and 12.5
mm nominal size
@ 0.90 cum/cum of concrete
conforming to Clause 602.2.4
Sand as per IS: 383 and
conforming to Clause 602.2.4 @
0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum
of concrete
32 mm mild steel dowel bars of
grade S240
16 mm deformed steel tie bars of
grade S415
Separation
Membrane
of
impermeable plastic sheeting
125 micron thick
% on (a+b+c)
profit
on
Cum
945.00
Cum
473.00
Tonne 414.00
Tonne 9.45
Tonne 1.17
Sqm
3675.00
Sqm
16.33
Kg
Kg
Sqm
875.00
116.67
46.67
Liter
Kg
1850.00
2070.00
KL
216.00
6.3
Note:
603
Day
Day
Day
1.20
7.00
23.00
Hour
6.00
Hour
6.00
Hour
Hour
6.00
6.00
Hour
Hour
8.00
8.00
t.km
990xL
c) Material
Crushed
stone
coarse
aggregates of 25 mm and 12.5
mm nominal size @ 0.90
cum/cum of concrete conforming
to Clause 602.2.3.
Sand as per IS: 383 and
conforming to Clause 602.2.3 @
0.45 cum/cum of concrete
Cement @ 200 kg/cum of
concrete
Cost of water
d) Overheads @
% on (a+b+c)
e) Contractor's profit @
(a+b+c+d)
% on
6.4
Note:
New
Cum
405.00
Cum
203.00
Tonne 90.00
KL
48.00
Construction of Base/Sub-Base of
Pavement with Lean Concrete
Flyash
Construction of base/sub-base using
cement, sand, flyash and coarse
aggregates proportioned as per
Table 4 of IRC: 74-1979 and with
water content ratio, slump and
compressive strength as defined in
the said Table, mix prepared in a
batching and mixing plant and
compacted with a vibratory roller 810 tonnes capacity within the time
limit laid down vide Clause 7.6.3 of
IRC: 74-1979, construction joints
properly formed at the end of day's
work, cured for 14 days, all as
specified in IRC: 74-1979 and as per
approved plans.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Front end loader 1 cum bucket
capacity
Cement concrete batch mix plant
@ 75 cum per hour
Electric generator 100 KVA
Paver finisher with electronic
sensor
Vibratory roller 8-101 capacity
Water tanker 6 KL capacity
Tipper 101 capacity
Add 10 per cent of cost of carriage to
cover cost of loading and unloading
Day
Day
Day
1.12
6.00
22.00
Hour
6.00
Hour
6.00
Hour
Hour
6.00
6.00
Hour
Hour
t.km
6.00
6.00
990xL
c)
Material
Crushed stone coarse aggregate
of 40 mm nominal size @ 0.90
cum/cum of concrete conforming
to Table 2 of IRC: 74-197.9
Coarse sand as per 13:383-1970
Cement @ 150 kg/cum of
concrete
Flyash conforming to IS: 3812
(Part II) (Total fine aggregates =
450 x 0.45 = 202.50 cum, To be
divided in ratio of 2 sand:
1.65flyash, Refer Table 4 of IRC:
74-1979).
d) Overheads @ % on (a+b+c)
e)
Contractor's
(a+b+c+d)
profit
on
1. Depending
upon
approved
designs,
crushed
stone
aggregates of nominal size 20
mm can also be used as per
gradation given in Table 2 of
IRC: 74-1979.
2. The ratio of specific gravities of
flyash and sand has been
assumed to be 0.827.
3. The quantities of materials given
in the analysis are for estimating
purpose. Actual quantities shall
be as per job mix formula.
4. Construction procedure as laid
down in Clause of IRC: 74-1979
shall be followed.
Cement
Pavement
Flyash
Concrete
Cum
405.00
Cum
110.96
Tonne 67.50
Cum
91.54
put
1050
cum
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Road sweeper @ 1250 sqm per
hour
Front end loader 1 cum bucket
capacity
Cement concrete batch mix plant
@ 175 cum per hour (effective
output)
Electric generator 250 KVA
Slip form paver with electronic
sensor
Water tanker
Transit truck agitator 5 cum
capacity
10
Day
Day
Day
2.00
15.00
35.00
Hour
2.80
Hour
18.00
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km
36.00
2415xL
machine Hour
Hour
c) Material
Crushed
stone
coarse
aggregates of 25 mm and 12.5
mm nominal size @ 0.90
cum/cum of concrete conforming
to Clause 602.2.4.
Sand as per IS: 383 and
conforming to
Clause 602.2.4
Cement 43 grade
Flyash conforming to 18:38121966 (Part-l)
32 mm mild steel dowel bars of
grade S 240
16 mm deformed steel tie bars of
grade S 415
Separation
Membrane
of
impermeable plastic sheeting
125 micron thick
Pre-moulded joint filler, 25 mm
thick for expansion joint
Joint sealant
Sealant primer
Plastic sheath, 1.25 mm thick for
dowel bars
Curing compound
Super plasticizer admixture IS
marked as per 9103-1999 @ 0.5
per cent by weight of cement
Cost of water
Add 1 per cent of material for cost of
miscellaneous
materials
like
tarpauline, Hessian cloth, metal cap,
cotton/ compressible sponge and
cradle for dowel bars, work bridges
for men to approach concrete
surface without walking over it,
cutting blades and bites, minor
equipments like scabbling machine,
threads, ropes, guidewires and any
other unforeseen items.
d) Overheads @ % on (a+b+c)
11
12.00
12.00
Cum
945.00
Cum
425*
Tonne 357*
Tonne 109*
Tonne 9.45
Tonne 1.17
Sqm
3675.00
Sqm
16.33
Kg
Kg
Sqm
875.00
116.67
46.67
Liter
Kg
1850.00
2070.00
KL
216.00
e) Contractor's profit @
(a+b+c+d)
% on
12
Chapter-7
Geosynthetic and Reinforced Earth
Preamble:
1. The specifications for geosynthetics which includes geotextiles, geogrids, geonets,
geomembranes and geocomposites shall be as per section 700 of MoRT&H
Specifications.
2. The geotextile proposed for sub-surface drain shall satisfy the requirements given in
Clause 702.2.3.
3. Care shall be taken to ensure that the geotextile or core material is not exposed to dry
light for more than a cumulative total of 50 hours.
4. Bitumen overlay shall follow on the same day where paving fabric is laid.
5. The size of mesh opening for gabions and mattresses laid with geogrids and geonets
shall be between 35 mm and 100 mm.
6. The size of the boulders shall be at least 100 mm or double the size of the aperture
whichever is larger.
7. The boulders shall be laid in crates as per the methodology given in Clause 2503.3.
8. The usual size of gabions in aprons is 1 m x 5 m with a height of 600 mm and baffles
at 1 m centers.
Sr.
No.
7.1.
Reference to
MoRT&H
Specifications
702
Description
Unit
Quantity
Rate
Rs.
a) Labour
Mate
Mazdoor skilled
Mazdoor
Day
Day
Day
0.04
0.25
0.50
Sqm
Sqm
Sqm
1.00
1.00
1.00
Day
Day
Day
0.04
0.25
0.50
b) Material
Geonets, geomembrane and
geotextile
to
make
planar
geocomposite stable network for
sub-surface
drain
including
wrapping of joints with 160 mm
over lapping with geotextile.
Geonets
Geomembrane
Geotextile
Add 2 per cent cost of material
for miscellaneous items like
synthetic cord
Note:
7.2.
702.4
c) Overheads @ % on (a+b)
d) Contractor's profit @
% on
(a+b+c)
Rate per metre = a+b+c+d
Surplus excavated material to be
used at site. Hence separate cost for
disposal not added.
Narrow Filter Sub-Surface Drain
Construction of a narrow filter subsurface drain consisting of porous or
perforated pipe laid in narrow trench
surrounded by a geotextile filter
fabric, with a minimum of 450 mm
overlap of fabric and installed as per
Clauses 702.3 and 309.3.5 including
excavation and backfilling.
Unit = Running metre length
Taking output = one metre
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Material
Perforated geosynthetic pipe 150
mm dia.
Geotextile filter fabric
Add 2 per cent cost of material
for miscell aneous item like
synthetic cord
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Note:
7.3.
703
Metre
1.00
Sqm
1.25
a) Labour
Mate
Mazdoor
Day
Day
b) Machinery
Road sweeper 1250 sqm per
hour
Pneumatic roller 14 tonne, 2000
sqm per hour
Bitumen pressure distributor
1750 sqm per hour
c) Material
Paving Fabric
Paving Bitumen 80-100
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
7.4.
704
0.80
20.00
Hour 2.24
Hour 1.40
Hour 1.68
Sqm 2940.00
Tonne 2.80
Day
Day
Day
b) Material
Geogrids
Sqm
Connectors/Staples
Each
Polymer braids
Metre
Stones with minimum size of 200 Cum
mm
Stones spall for filling voids
Cum
c) Overheads @ % on (a+b+c)
d) Contractor's profit @ % on
(a+b+c)
Cost for 3 cum = a+b+c+d
Rate per cum = (a+b+c+d)/3
0.06
0.50
1.50
21.00
50.00
20.00
3.45
0.45
7.5.
3100
7.5.
(i)
3102
Day
Day
Day
0.36
6.00
3.00
b) Material
@ Reinforcement strips 60 mm
wide 5 mm thick as per Clause
3102.
1. Galvanised carbon steel strips
or
2. Copper strips
or
3. Aluminium strips
or
4. Stainless steel strips
or
5. Glass reinforced polymer/fibre
reinforced polymer/polymeric
strips @ Any one of the above
alternative may be adopted as
per approved design.
Add 10 per cent of the cost of
reinforcing strip towards
accessories like tie-strips, nuts
and bolts and loops/ lugs for
joining reinforcing elements
with the facia pannels,
overlaps, heat bonding or
extension.
c) Overhead @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost of 450 m = a+b+c+d
Rate per metre =(a+b+c+d)/450
B. With reinforcing elements of
synthetic geogrids
Unit = sqm
Taking output = 300 sqm
450
450
450
450
450
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Synthetic Geogrids as per
Clause 3102.8 and approved
design and specifications
Day
Day
Day
0.36
6.00
3.00
Sqm
300
Day
Day
Day
0.18
3.00
1.50
Hour
6.00
3104
c) Material
Pre-cast RCC M-35 facing
elements of size as per design
and 18 cm thick for 75 sqm
HYSD steel @ 5 kg/sqm
Add 2 per cent of cost of facia
pannels, for all necessary
temporary formwork, scaffolding
and provision of loops/lugs for
lifting of pannels and joining the
reinforcing elements.
d) Overheads @ % on (a+b)
e) Contractor's profit @ % on
(a+b+d)
Cost for 75 sqm = a+b+c+d+e
Rate per cum = (arb+c+d+e)/75
Note:
Cum
13.50
Tonne 0.38
10
11
Chapter-8
Traffic Signs, Markings and other Road Appurtenances
Preamble:
1.
Rate analysis for fencing has been done for two different heights, i.e., 1.20mand
1.80m. Any of these two can be adopted depending upon a particular situation
and design.
2.
3.
Kerbstone laying and road marking has been provided for laying by mechanical
means.
4.
Back filling of foundation of boundary pillars has been proposed with stone spalls,
tightly packed and compacted.
5.
The item pertaining to road traffic signals has not been analysed as this is a
specialized work and rates can be obtained from firms having specialization for
design and installation of this work.
6.
For metal beam crash barrier, a W shaped beam of size 311 x 83 mm flange
width made with structural steel corrugated plat3 3 mm thick and having a length
of 4.5 m has been provided, over a channel post of 150 x 75 x 5 mm with a
spacer of channel section 150 x 75 x 5 mm, 330 mm long.
7.
8.
Two supports have been provided for direction and place identification signs
where size is more than 0.9 sqm. Only one support is provided for size upto 0.9
sqm.
9.
10.
11.
The analysis for rigid, semi-rigid and flexible crash barriers have been included.
12.
Provision has been made for a crane for installation of overhead signs.
13.
Separate rate analysis have been made for Tubular steel railing with RCC posts
and MS steel posts
14.
15.
The rate for the message display board for gantry mounted variable message sign
1
The rate analysis for traffic impact attenuators at abutments and piers have been
included.
17.
In the case of road signs and direction boards the depth of foundation and quantity
of cement concrete provided in the rate analysis are indicative. These may be
suitably increased in areas of higher wind velocities like coastal areas.
18.
19.
Noise Barriers:
Noise barrier can be provided in the form of a brick wall of a suitable height as per
the site requirement and approved design. The items involved for the construction
of this barrier like earthwork, brick masonry, plain cement concrete, etc. are
available in the Data Book, which can be applied to arrive at the cost of noise
barrier based on the design adopted.
Alternatively, wherever space permits, cluster of trees, shrubs and plants can be
grown by the road side 6 m away from the edge of the roadway. This will intercept
the annoying sound waves and fumes from road vehicles.
Sr.
No.
8.1.
Reference to
MoRT&H
Specifications
408
Description
Cast-in-Situ Cement Concrete M 20
Kerb
Construction of cement concrete
kerb with top and bottom width 115
and 165 mm respectively, 250 mm
high in M 20 grade PCC on M-10
grade foundation 150 mm thick,
foundation having 50 mm projection
beyond kerb stone, kerb stone laid
with
kerb
laying
machine,
foundation concrete laid manually,
all complete as per Clause 408.
Unit = Running metre
Taking output = 360 metre
2
Unit
Quantity
Rate
Rs.
Day
Day
Day
b) Machinery
Kerb casting machine @ 60 Hour
metre/hour
Concrete mixer 0.48/0.28 cum Hour
capacity
Water tanker 6 KL capacity
Hour
c) Material
Crushed stone aggregate 20 Cum
mm nominal size 59%
Coarse sand 30%
Cum
Cement 11%
Tonne
Cost of water
Cum
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 360 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360
B. Using Concrete Batching and
Mixing Plant
Cement Concrete
Cement concrete of grade M20
= 12.60 cum
Cement concrete of grade M10
for base =11.61 cum
Total Concrete = 24.21 cum
0.72
2.00
16.00
6.00
12.00
5.00
21.79
10.9
5.7
30.00
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60
metre/hour
Concrete batching and mixing
plant @ 15 cum/hr.
Water tanker 6 KL capacity
Tipper 5.5 cum capacity
Day
Day
Day
0.12
1.00
2.00
Hour
6.00
Hour
1.60
Hour
Hour
5.00
6
c) Material
Crushed stone aggregate 20 Cum
mm nominal size 59%
Coarse sand 30%
Cum
Cement 11%
Tonne
Cost of water
KL
d) Overheads @ % on (a+b+c)
e) Contractor's
(a+b+c+d)
profit
on
408
21.79
10.9
5.7
30.00
Day
Day
Day
b) Machinery
Kerb casting machine @ 50 Hour
metre/hour for laying kerb and
channel
Concrete mixer 0.48/0.28
Hour
Water tanker 6 KL capacity
Hour
c) Material
Crushed stone aggregate 20 Cum
mm nominal size 60%
Coarse sand 30%
Cum
Cement 10%
Tonne
Cost of water
KL
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 300 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/300
B. Using Concrete Batching and
Mixing Plant
0.72
2.00
16.00
6.00
16.00
6.00
36.59
18.3
9.01
36.00
Day
Day
Day
0.12
1.00
2.00
Hour
6.00
Hour
2.70
Hour
Hour
6.00
6.00
c) Material
Crushed stone aggregate 20 Cum
mm nominal size 60%
Coarse sand 30%
Cum
Cement 10%
Tonne
Cost of water
KL
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 300 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/300
8.3.
801
36.59
18.3
9.01
36.00
Day
Day
Day
0.12
2.00
1.00
b) Material
Paint
Litre
0.7
a) Labour
Mate
Painter 1st class
Mazdoor
Day
Day
Day
0.07
1.25
0.50
b) Material
Paint
Litre
0.5
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 1600 cm = a+b+c+d
Rate per cm height per letter =
(a+b+c+d)/ 1600
ii) English and Roman
Hyphens and the like not to be
measured and paid for
Detail for 100 letters of 16 cm
height i.e. 1600cm
Unit = per cm height per letter
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 1600 cm = a+b+c+d
Rate per cm height per letter =
(a+b+c +d)/1600
8.4.
801
Day
Day
b) Material
Mild steel angle iron 75 x 75 x 6 Kg
mm
0.216
0.12
0.43
0.01
0.25
19.00
Sqm
0.35
sqm
0.156
OR
ii) 60 cm equilateral triangle
OR
iii) 60 cm circular
Sqm
0.283
OR
iii) 80 mm x 60 mm rectangular Sqm
0.48
OR
iv) 60 cm x 45 cm rectangular
Sqm
0.27
Sqm
0.36
Sqm
0.672
Hour
0.01
OR
v) 60 cm x 60 cm square
OR
vi) 90 cm high octagon
c) Machinery
Tractor-trolley
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Rate
per
traffic
sign
=
(i)+ii)+iii)+a+b+c+d+e)
Note:
8.5.
801
1.
2.
3.
Day
Day
b) Material
Mild steel angle iron 75 mm x 75 Kg
mm x 6 mm, 2.85 metres long
Aluminium sheeting fixed with Sqm
encapsulated
lens
type
reflective sheeting of size 0.9
sqm
Add 2 per cent of cost of
materials for drilling holes, nuts,
bolts, fabrication etc.
10
0.216
0.12
0.43
0.01
0.20
19.00
0.90
c) Machinery
Tractor-trolley
Hour
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost
for
0.9
i)+ii)+iii)+a+b+c+d+e
sqm
8.6.
801
11
0.02
0.43
0.24
0.86
0.01
0.3
Day
Day
b) Material
Mild steel angle iron 75 mm x 75 Kg
mm x 6 mm, 2.85 metre long, 2
nos
Aluminium sheeting fixed with Sqm
encapsulated
lens
type
reflective sheeting
38.00
1.50
12
Hour
0.02
8.7.
802
Overhead Signs
Providing and erecting overhead
signs with a corrosion resistant 2
mm thick aluminium alloy sheet
with high intensity grade retroreflective sheeting of encapsulated
lens type with vertical and lateral
clearance given in Clauses 802.2
and 802.3 and installed as per
Clause 802.7 over a designed
support system of aluminium alloy
or galvanised steel trestles and
trusses of sections and type as per
structural design requirements and
approved plans.
A. Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate
Day
Blacksmith
Day
Mazdoor including for handling Day
and fixing at site
0.24
2.00
4.00
b) Material
Aluminium
alloy/galvanized Tonne 1.05
steel including 5 per cent
wastage
Add 1 per cent on cost of
material for nuts, bolts and
drilling
and
welding
consumables
Add 15 per cent on cost of
material for fabrication of
trusses as per approved design
c) Machinery
Crane 3 tonne capacity
Truck
13
Hour
Hour
3.00
0.50
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d) Rate per tonne =
(a+b+c+d+e)
B. Aluminium Alloy Plate for Over
Head Sign
Unit = sqm
Taking output =s 1 sqm
a) Labour
Mate
Blacksmith
Mazdoor
Day
Day
Day
b) Material
Aluminium alloy plate, 2 mm Sqm
thick, fixed with high intensity
grade sheeting vide Clause
801.3
Miscellaneous
Add 1 per cent of cost of labour for
lifting arrangement, like ladders,
pulleys, ropes etc.
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c) Rate per sqm =
(a+b+c+d)
Note:
14
0.02
0.1
0.15
1.00
803
on
New
Day
Day
Day
0.12
2.00
1.00
b) Material
Paint conforming to requirement Litre
of Clause 803.3.
6.00
15
8.9.
803
Day
Day
Day
0.03
0.45
0.25
b) Material
Paint ready mixed approved Litre
brand
1.25
16
a) Labour
Mate
Painter
Mazdoor
Day
Day
Day
b) Material
Paint ready mixed of approved Litre
brand
Add @ 1 per cent on cost of
material for scaffolding
c) Overheads @ % on (a+b)
e) Contractor's profit @ % on
(a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
8.11. 803
Day
Day
Day
17
0.09
0.55
1.55
b) Material
Road marking Paint as per IS: Litre
164
1.48
d) Overheads @ % on (a+b)
e) Contractor's profit @ % on
(a+b+c)
Cost for 10 sqm = a+b+c+d Rate
per sqm = (a+b+c+d)/10
ii) Upto 10 cm in width
Unit = sqm
Taking output =10 sqm
a) Labour
Mate
Painter
Mazdoor
Day
Day
Day
0.07
0.35
1.35
b) Material
Road marking paint
Litre
1.48
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
8.12. 803
18
i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate
Painter 1st class
Mazdoor
Day
Day
Day
0.06
0.30
1.25
b) Material
Road marking paint
Litre
0.90
a) Labour
Mate
Painter 1st class
Mazdoor
Day
Day
Day
0.07
0.35
1.35
b) Material
Road marking paint
Litre
0.90
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
ii) Upto 10 cm in width
Unit = sqm
Taking output = 10 sqm
c) Overheads @ % on (a+b)
e) Contractor's profit @ % on
(a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
19
8.13. 803
Day
Day
b) Machinery
Road marking machine @ 60 Hour
sqm per hour
Tractor-trolley
Hour
c) Material
Hot
applied
thermoplastic Litre
compound
Reflectorising glass beads
Kg
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 600 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/600
Note:
20
0.03
0.75
10.00
0.50
1500.00
150.00
Kilometre Stone
Reinforced cement concrete M 15
grade kilometre stone of standard
design as per IRC:8-1980, fixing in
position including painting and
printing etc.
i) 5th kilometre stone (precast)
Unit=Nos.
Taking output = 6 Nos.
a) M 15 grade of concrete
Cum
2.35
22.08
1.68
9.85
1800
Day
Day
including Day
g) Machinery
Tractor-trolley
h) Overheads @ % on (f+g)
i) Contractor's profit @ % on
(f+g+h)
Cost for 6 Nos. 5th km stone =
a+b+c+d+e+f+g+h+i
Rate for each 5th km stone =
(a+b+c+d+e+f+g+h+i)/6
21
0.26
0.60
6.00
Hours 6.00
ii) Ordinary
(precast)
kilometre
stone
Unit = Nos.
Taking output = 14 Nos.
a) M 15 grade of concrete
Cum
3.77
26.32
2.77
Cum
11.41
1680
Day
Day
0.32
1.00
g) Machinery
Tractor-trolley
Hour
6.00
h) Overheads @ % on (f+g)
i) Contractor's
(f+g+h)
profit
on
22
a) M 15 grade of concrete
Cum
1.58
66.00
1.39
6.27
330.00
Day
Day
Day
0.34
1.5
7.00
g) Machinery
Tractor-trolley
Hour
6.00
h) Overheads @ % on (f+g+h)
i) Contractor's profit @ % on (f+g)
Cost for 33 Nos. Hectometre stone
= a+b+c+d+e+f+g+h+i
Rate for each Hectometre stone =
(a+b+c+d+e+f+g+h+i)/33
Note:
8.15. 805
Unit = Each
Taking output = 30 Nos.
a) Labour
Mate
Mazdoor for fixing
Day
Day
b) Material
Cost of approved type of Each
delineators from ISI certified firm
as per the standard drawing
given in IRC:79
0.040
1.00
30.00
8.16. 806
1.25
b) Steel reinforcement
Kg
79.80
c) Excavation in soil
Cum
10.72
Per
letter
Per
high
2280.00
Transportation and
24 fixing
e) Labour
Mate
Mazdoor
f)
Machinery
Tractor-trolley
g) Material
Stone spall
h) Overheads
@
(a+b+c+e+f+g)
i)
on
Contractor's profit @ % on
(a+b+c+ e+f+g+h)
25
Day
Day
0.57
14.25
Hour
6.00
Cum
11.97
a) Labour
Mate
Blacksmith
Mazdoor
Day
Day
Day
b) Material
Barbed wire 335 metre length @ Kg
9.38 kg per 100 metre
MS angle iron 40 mm x 40 mm x Kg
6 mm, 23 metre in length @ 3.5
kg per metre
0.09
0.25
2.00
31.42
80.5
profit
Cost for 30
a+b+c+d+e
metre
fencing
on
8.18. 807
26
2.11
Day
Day
Day
b) Material
Barbed wire 428 metre length @ Kg
9.38 kg per 100 metre
MS angle iron 50 mm x 50 mm x Kg
6 mm, 33.8 metre in length @
4.5 kg per metre
0.12
0.40
2.50
40.15
152.00
profit
Cost for 30
a+b+c+d+e
metre
fencing
Rate
per
metre
(a+b+c+d+e)/30
27
fencing
on
3.96
Note:
8.19. Suggestive
Day
Day
Day
b) Material
i) Angle iron for posts 50 x 50 x Kg
6 mm
ii) Runner flat 50x5 mm
Kg
iii) Welded steel wire fabric 75 x Kg
50 mm mesh @ 4 kg/sqm, 4
x 30 x 1.2 + 5 per cent
wastage
0.12
1.00
2.00
106.00
26.00
151.00
OR
Welded steel wire fabric 75 x Kg
25 mm mesh @ 7.75 kg/sqm,
7.75 x 30 x 1.2 + 5 per cent
wastage
28
293.00
Hour
d) Painting
Painting two coats including sqm
priming
f) Overheads @ % on (a+b+c)
g) Contractor's
(a+b+c+e)
profit
on
8.20 808
29
0.10
8.00
1.296
0.648
Sqm
4.71
2.16
Day
Day
Day
b) Material
Steel pipe 50 mm external dia Mtr
as per IS: 1239
Medium weight steel channel (ISMC Kg
series) 100 mm x 50 mm, 10.8
metre length @ 9.2 kg per m
0.01
0.25
0.01
30
99.36
Hour
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost
for
10
metre
i)+ii)+iii)+iv)+a+b+c+d+e
Rate
per
metre
(i)+ii)+iii)+iv)+a+b+c+d+e)/10
30
0.04
8.21. 808
1.296
0.648
0.32
Sqm
4.71
a) Labour
Mate
Mazdoor
Plumber
Day
Day
Day
0.014
0.35
0.01
b) Material
Steel pipe 50 mm dia as per IS: Mtr
1239
c) Machinery
Tractor-trolley
Hour
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost
for
10
metre
i)+ii)+iii)+iv)+a+b+c+d+e
Rate
per
metre
(i)+ii)+iii)+iv)+a+b+c+d+e)/10
31
30.00
0.25
8.22. 809
Cum
3.00
b) Labour
Mate
Mazdoor
Day
Day
0.04
1.00
c) Material
HYSD
steel
reinforcement
including dowel bars
Pre-moulded asphalt filler board Sqm
0.32
d) Overheads @ % on (b+c)
e) Contractor's profit @ % on
(b+c+d)
Cost for 10 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10
32
Note:
8.23. 810
Day
Day
Day
0.06
0.50
1.00
b) Machinery
Tractor-trolley
Hour
0.10
c) Material
Corrugated sheet, 3 mm thick, Kg
"W" beam section railing, 4.5 m
in length
Channel post 150 x 75 x 5 mm, Kg
1.8 m long, 3 Nos. @ 16.4 kg
per mtr
33
41.21
88.56
Day
Day
Day
0.06
0.50
1.00
b) Machinery
Tractor-trolley
Hour
0.10
34
c) Material
Corrugated sheet, 3 mm thick,
"Thrie" beam section railing, 4.5
m in length
Channel post 150 x 75 x 5 mm,
2 m long, 3Nos. @16.4kgpermtr
Spacer 150 x 75 x 5 mm
channel 0.546 m long,3 Nos.
Nuts and bolts
Add 15 per cent of the cost of
material for fabrication, nuts,
bolts, washers, etc.
d) Overheads @ % on (a+b+c)
e) Contractor's
(a+b+c+d)
profit
on
8.24. 811
Note:
35
8.25. Suggestive
Day
Day
Day
b) Material
i) RS Joist 100x75 mm-16.5m @ Kg
11.5 kg per metre
ii) Struts - 2 Nos. for terminal Kg
posts, 2 m long each 2x2x11.50
iii) Tie 2 Nos. of 8 mm steel plate, Kg
1.5 sqm each for terminal posts
@ 62.80 kg/sqm (2x 1.5)
36
0.12
2.00
1.00
190.00
46.00
188.40
65.00
8.26. Suggestive
37
Hour
16.5
0.25
Day
Day
0.004
0.10
b) Material
i) 25 mm steel pipe
Mtr
16.0
4.32
4.80
38
c) Painting
Applying 2 coats of painting on Sqm
exposed surface
1.83
d) Overheads @ % on (a+b)
e) Contractor's
(a+b+d)
profit
on
Day
Day
b) Material
i) Angle iron post, 50 x 50 x 6 Kg
mm, length 2.35 m
ii) MS sheet 3 mm thick @ 24 Kg
kg/sqm
Add 5 per cent of cost of material
for fabrication, nuts, bolts etc
39
0.004
0.10
10.58
9.00
c) Machinery
Tractor-trolley
Hour
0.10
d) Painting
Applying 2 coats of painting
Sqm
0.85
Day
Day
Day
0.03
0.50
0.25
e) Overheads @ % on (a+b+c)
f) Contractor's profit @ % on
(a+b+c+e)
Cost for 1.5 m = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/
1.50
The items of excavation and
cement concrete as per approved
design to be measured and paid
separately. Rate of painting has
been analysed separately in this
Chapter.
Street Lighting
Providing and erecting street light
mounted on a steel circular hollow
pole of standard specifications for
street lighting, 9 m high spaced 40
m apart, 1.8 m overhang on both
sides if fixed in the median and on
one side if fixed on the footpath;
fitted with sodium vapour lamp and
fixed firmly in concrete foundation.
Unit = Each
Taking output = one light
a) Labour
Mate
Mazdoor
Electrician
b) Material
i) Steel circular hollow pole of Each
standard specification for
street lighting to mount light
at 9 m height above road
level
ii) Sodium vapour lamp - 250 Each
Watt
40
1.00
1.00
% on (a+b)
e) Contractor's profit @ % on
(a+b+d)
Rate per light = a+b+c+d+e
Note:
8.28. Suggestive
41
a) Labour
Mate
Mazdoor
Electrician
Day
Day
Day
b) Material
i) Steel circular hollow pole of Each
standard
specification
for
street lighting to mount light at
5 m above deck level
ii) Sodium vapour lamp - 70 Watt Each
0.02
0.40
0.20
1.00
1.00
% on (a+b)
e) Contractor's, profit @ % on
(a+b+d)
Rate per light = a+b+c+d+e
Note:
42
2.76
8.29. Suggestive
Day
Day
Day
0.05
1.00
0.25
43
2.36
7.20
9.00
0.02
d) Machinery
Tractor-trolley
Hour
0.50
3.37
e) Overheads @ % on (b+c+d)
f) Contractor's profit @ % on
(b+c+d+e)
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20
Case - II: Double row for two utilitiy
services
Unit= Running metre
Taking output = 20 metre
b) Labour
Mate
Mazdoor
Skilled mazdoor
c) Material
Reinforced cement
pipe 300 mm dia
Day
Day
Day
44
0.05
2.00
0.25
Hour
14.40
18.00
0.04
1.00
45
Day
Day
Day
4.38
0.16
3.00
1.00
Metre 60.00
Cum
21.60
Nos.
Cum
27.00
0.06
Hour
1.50
8.30. Suggestive
8.32. Suggestive
Traffic
Control
System
Communication System
and
46
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate
Mazdoor
Blacksmith
Day
Day
Day
47
0.12
2.00
1.00
b) Material
Alluminium
alloy/galvanised Tonne 1.05
steel including 5 per cent
wastage
Add 15 per cent of cost of
material for fabrication and
erection
Add 1 per cent of cost of
material for nuts, bolts and
welding
c) Machinery
Truck Idtonne
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Rate per tonne = a+b+c+d+e
ii) Message
Display
Message display board 6 sqm
electronically
operated
with
complete electronic fitments for
flashing
the
pre-determined
messages.
This is a specilised commercial
product and the lumpsum rate
including erection at site is required
to be ascertained from the market
and including in the rate analysis.
The size of the board will vary
depending upon specific location.
The rate for the gantry mounted
variable sign would be the addition
of cost of gantry support system as
per approved design determined at
(i) above and the cost of message
display board ascertained from the
market at (ii) above
48
Hour
1.00
8.34. Suggestive
at
Day
Day
Day
0.08
1.50
0.25
b) Material
Scrap tyres of size 900 x 20
20 mm steel wire rope
Nos.
Kg
80.00
150.00
Hour
3.00
49
Day
Day
Day
0.13
3.00
0.25
Nos.
50.00
Nos.
Cum
Kg
50.00
8.00
15.00
Hour
2.00
50
Day
Day
b) Material
Plastic tubes 50 cm dia, 1.2m Nos.
high
Water
KL
20 mm steel wire rope
Kg
0.1
2.50
40.00
12.00
100.00
51
Hour
Hour
2.00
2.00
8.35. Suggestive
Day
Day
b) Material
Aluminium studs 100 x 100 mm Nos.
fitted with lense reflectors
Add 10 per cent of cost of
material
for
fixing
and
installation
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 50 studs = a+b+c+d
Rate per studs = (a+b+c+d)/50
8.36. Suggestive
Traffic Cone
Provision of red fluorescent with
white reflective sleeve traffic cone
made of low density polyethylene
(LDPE) material with a square base
of 390 x 390 x 35 mm and a height
of 770 mm, 4 kg in weight, placed
at 1.5 m interval, all as per BS: 873.
Unit= Running metre
Taking output = 68 Nos.
52
0.04
1.00
50.00
a) Labour
Mate
Mazdoor
Day
Day
b) Material
Traffic cones with
reflective sleeve
150
mm Nos.
c) Machinery
Tractor-trolley
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 68 Nos. = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/68
8.37. Suggestive
Roadside Amenities
A. Rest areas
Providing
plainly
furnished
accommodation for rest rooms,
dormitories, restaurants, stalls,
shops, petrol pump, telephone
booth, first aid room, traffic aid
post, police assistance booth,
including electricity, toilet and
sewerage system.
Pricing may be done based on
current plinth area rates approved
by
PWD/CPWD/MES
for
a
particular zone. Area is required to
be assessed for specific location as
per actual site conditions.
B. Parking areas and bus laybyes
for trucks, buses and light
vehicles
Pricing of parking areas may be
done for the quantities of various
items based on the approved
dimensions and pavement design
for a particular terrain and soil.
Rates for items may be from
respective chapters.
53
Hour
0.02
0.50
68.00
0.10
C. Lawn
Providing a lawn planted with grass
and its maintenance.
Pricing of lawn may be done as
rates given in the chapter
horticulture for the quantities as
approved
dimensions
in
drawings.
8.38. Suggestive
per
on
per
the
Rumble Strips
Provision of 15 nos. rumble strips
covered with premix bituminous
carpet, 15-20 mm high at center,
250 mm wide placed at 1 m center
to center at approved locations to
control speed, marked with white
strips of road marking paint.
Unit = sqm
Taking output = 100 sqm (including
gaps)
The rate per sqm of premix carpet
and road marking may be adopted
from Chapters 5 & 8 respectively
for the quantities calculated from
approved drawings.
8.39. Suggestive
Policeman Umbrella
Provision ofa2m high (floor to roof)
umbrella for traffic policeman at
road crossings, where necessary,
installed on a raised platform, built
on a central support of a steel pipe
100 mm dia, roof made of 25 mm
dia steel pipe to provide covered
area of 3 sqm, roofed with CGI
sheets, all steel parts to be given 2
coats of paint.
Unit = each
Taking output = one number
54
Quantities of these
items to be
calculated as per
approved design
and cost added as
per rates of these
items given in
Chapters 3 and 13
Earthwork
cement
concrete/brick
or stone
masonry
Painting
a) Labour
Mate
Mazdoor
Blacksmith
Welder
b) Material
Steel pipe 100 mm dia
Steel pipe 25 mm dia
CGI sheets
Sqm
2.5
Day
Day
Day
Day
0.09
1.00
1.00
0.25
M
M
Kg
3.50
10.00
8.00
Hour
0.50
Painting
Add 25 per cent of dost of material
for fabrication
Add 2 per cent of cost of material
for welding consumables, J-hooks,
washers etc.
c) Machinery
Tractor-trolley
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Rate per policeman umbrella =
a+b+c+d+e
55
8.40. Suggestive
at
56
8.41. Suggestive
Toll Plaza
The construction, operation and
maintenance of Toll Plaza can be
broken into separate items of work
as under based on the approved
design and drawings:
a) Provision of toll collection
service
lane
to
separate
different categories of vehicles
for purpose of toll collection.
This
involves
considerable
increase in carriageway width.
b) Provision of 2.5 m wide
separators for different toll
collection service lanes for
safety.
c) Toll booths with integrated roof
cover
d) Barrier gates for individual lanes
e) Provision of building to provide
facility to toll plaza personnel
f) Toll plaza office equipment and
furniture
g) Water
supply,
electricity,
sanitation, septictank system
and drainage
h) Telephone, intercomes, wireless
communication system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above
mentioned items may be calculated
from the approved design and
drawings and their rates adopted
from respective Chapters of the
Standard Data Book.
57
8.42. Suggestive
Signs
in
58
m)
n)
o)
p)
q)
r)
s)
t)
u)
v)
w)
x)
y)
z)
aa)Speed limit
bb)Weight limit
cc) Height and length limit
dd)No stopping or standing
ee)Any other warning or regulatory
safety
sign
as
per
site
requirement and consistent with
IRC: SP: 55-2001 and IRC: 67
The rates for traffic signs are
already worked out and given
elsewhere in this chapter. The
same may be adopted.
8.43. Suggestive
59
a) Labour
Mate
Mazdoor
Painter
Welder
Day
Day
Day
Day
b) Material
Angle iron 45 x 45 x 5 mm
Kg
MS sheet 300 mm wide, 2.5 m Kg
long and 2.6 mm thick
Paint
Litre
Add 2 per cent of cost of steel
forwelding consumables, nuts
and bolts and drilling holes
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Rate per barricade = a+b+c+d
8.44. Suggestive
Permanent Type
Construction Zone
Barricade
in
60
0.02
0.25
0.50
0.25
25.00
15.00
0.50
a) Labour
Mate
Mazdoor
Painter
Welder
Day
Day
Day
Day
b) Material
Angle iron 50 x 50 x 5 mm, 2 m Kg
long,
2Nos.
MS sheet of 12 SWG, 3 Nos. of Kg
200 mm width and 4 m length
Paint
Litre
Add 1 per cent of cost of steel for
welding consumables, nuts and
bolts and drilling holes
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Rate per barricade = a+b+c+d
B. With wooden components
Construction of a permanent type
barricade
made
of
wooden
components, 1.5m high from road
level, fitted with 3 horizontal planks
200 mm wide and 3.66 m long on
100 x 100 mm wooden vertical
post, painted with yellow and white
strips, 150 mm in width at an angle
of 45, complete as per IRC: SP:
55-2001.
Unit = each
Taking output = one barricade
61
0.05
0.30
0.60
0.30
15.00
50.00
1.00
a) Labour
Mate
Mazdoor
Painter
Carpenter
Day
Day
Day
Day
0.05
0.30
0.60
0.60
b) Material
Timber
Cum
0.18
a) Labour
Mate
Mazdoor
Painter
Mason
Day
Day
Day
Day
0.24
3.00
1.00
2.00
b) Material
Brick
Cement
Sand
Paint
Nos.
Kg
Cum
Litre
1800.00
22.00
0.09
1.25
c) Overheads % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
62
one
drum
a) Labour
Mate
Mazdoor
Painter
Day
Day
Day
b) Material
Steel drum 300 mm dia 1.2 m Nos.
high/empty bitumen drum
Paint
Litre
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Rate per
a+b+c+d
8.46. Suggestive
drum
delineator
Flagman
Positioning of a smart flagman with
a yellow vest and a yellow cap and
a red flag 600 x 600 mm securely
fastened to a staff 1 m in length for
guiding the traffic.
Unit = each
Taking output = one flagman
63
0.02
0.25
0.25
1.00
0.50
a) Labour
Mate
Mazdoor
Day
Day
b) Material
Flag of red colour cloth 600 x Each
600 mm
Wooden staff for fastening of Each
flag 25 mm dia, one m long
c) Overheads @ % on (a+b)
e) Contractor's profit @ % on
(a+b+c)
Rate per flagman = a+b+c+d
64
0.04
1.00
1.00
1.00
Chapter-9
Pipe Culverts
Preamble:
1.
Pipe culverts of size 1000 mm and 1200 mm dia in single row and double row
which are generally used on roads, have been included. Only laying of pipe has
been included in the rate. Auxiliary works such as excavation, backfilling,
concrete and masonry shall be paid for separately, as provided under the
respective clauses.
2.
In case of RCC culverts, rates for various items of work involved such as
excavation, backfilling, masonry, cement concrete etc. have been provided under
respective clauses in the chapters on foundations, sub-structures, superstructures and river training and protection works in bridge section of this book.
3.
Any river training and protection work like stone pitching, apron, rivetment, curtain
wall etc. may be provided under the respective clauses included in Chapter 16 of
bridge section.
4.
The choice between first class bedding and cement cradle bedding will depend
on particular situations and the approved design.
5.
6.
Backfilling upto 300 mm above top of the pipe shall be carefully done and the soil
thoroughly rammed, tamped or vibrated in layers not exceeding 150 mm.
7.
Head walls and other ancillary works shall be costed under respective clauses.
8.
The height of filling above the top of pipe shall not be less than 600 mm.
Sr.
No.
9.1.
Reference to
MoRT&H
Specifications
408
Description
PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix
with crushed stone aggregate 40
mm nominal size mechanically
mixed, placed in foundation and
compacted by vibration including
curing for 14 days.
Unit = cum
Taking output =15 cum
Unit
Quantity
Rate
Rs.
a) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.64
1.00
15.00
b) Material
Aggregate at site
Sand at site
Cement at site
Cost of water
Cum
Cum
Tonne
KL
13.80
6.90
3.30
18.00
c) Machinery
Concrete mixer 0.47 0.28 cum Hour
Generator set 33 kVA
Hour
Water tanker 6 KL capacity
Hour
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d )
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
9.2.
Note:
2900
Laying
Reinforced
Cement
Concrete Pipe NP4/Presteressed
Concrete Pipe on First Class
Bedding in Single Row
Laying reinforced cement concrete
pipe NP4/ prestressed concrete
pipe for culverts on first class
bedding of granular material in
single row including fixing collar
with cement mortar 1:2 but
excluding excavation, protection
works, backfilling, concrete and
masonry works in head walls and
parapets.
Unit = metre
Taking output = 12.5 metre (5 pipes
of 2.5 m length each)
6.00
6.00
3.00
a) A. 1000 mm dia
a) Labour
Mate
Mason
Mazdoor
Day
Day
Day
b) Material
Sand at site
Cement at site
RCC pipe NP-4 /prestressed
concrete pipe including collar at
site
Granular material passing 5.6
mm sieve for bedding
c) Overheads @ % (a+b)
d) Contractor's
(a+b+c)
profit
1.
2.
0.18
0.50
4.00
Cum 0.07
Tonne 0.05
Mtr
12.50
Cum
4.50
B) 1200 mm dia
a) Labour
Mate
Mason
Mazdoor
Day
Day
Day
b) Material
Sand at site
Cement at site
RCC pipe NP-4/prestressed
concrete pipe including collar at
site
Granular material passing 5-6
mm sieve for class bedding
c) Overheads @ % on (a+b)
d) Contractor's profit @
(a+b+c)
% on
1.
2.
0.28
1.00
6.00
Cum 0.09
Tonne 0.07
Metre 12.50
Cum
5.00
Day
Day
Day
b) Material
Sand at site
Cement at site
RCC pipe NP-4/prestressed
concrete pipe including collar at
site
Granular material passing 5.6
mm sieve for bedding
c) Overheads @ %(a+b)
e) Contractor's profit @ % (a+b+c)
Cost for 12.5 metre = a+b+c+d
Rate per metre = (a+b+c+d)/12.5
0.36
1.00
8.00
Cum 0.14
Tonne 0.10
Metre 25.00
Cum
12.50
Note:
Day
Day
Day
b) Material
Sand at site
Cement at site
RCC pipe NP-4 /prestressed
concrete pipe including collar at
site
Granular material passing 5-6
mm sieve for class bedding
c) Overheads @ % on (a+b)
d) Contractor's profit @
(a+b+c)
% on
0.56
2.00
12.00
Cum 0.18
Tonne 0.14
Metre 25.00
Cum
13.75
Note:
Chapter-10
Maintenance of Roads
Preamble:
1.
In the case of rain cuts, it has been assumed that some material cut by rain,
approximately 25 per cent will be available at site which can be retrieved and
re-used and the balance 75 per cent is required to be provided as fresh
material.
2.
3.
In the case of chocking of drain, it has been assumed that half the depth of
drain has been filled with earth/debris, which requires clearance.
4.
During the process of landslide clearance on hill roads, it has been assumed
that earth will be disposed off by the dozer on the valley side. In case there is
any objection to this arrangement due to particular site conditions, resources
like loader and tipper will have to be provided for disposal of earth/debris for
the lead involved.
5.
6.
The items like slurry seal, fog spray, crack prevention courses, surface
dressing for maintenance works have already been included in Chapter-5 and
are not being repeated in this chapter.
7.
The cost of other items like repair of ruts and undulation maintenance of
earthen shoulders, cross drainage works, minor and major bridges and
miscellaneous items like turfing and arboriculture, painting and lettering on km
stones, repair to signage, repair to footpath, street lighting, railing, dividers,
separators and under passes for pedestrians has been given in the "Report of
the Committee on Norms for Maintenance of Roads in India" published by IRC
in January 2001 which may be referred for guidance.
8.
Sr.
No.
10.1
Reference to
MoRT&H
Specifications
3002
Description
Restoration of Rain Cuts
Unit
Quantity
Rate
Rs.
Day
Day
b) Machinery
Excavator 1.0 cum bucket Hour
capacity @ 60
cum per hour
Tipper (L is average lead in km t.Km
for borrow
earth)
Add 10 per cent of cost of
carriage towards loading and
unloading charges
Plate compactor
Hour
c) Overheads @ % on (a+b)
d) Contractor's profit @
(a+b+c)
% on
0.08
2.00
0.13
12xL
0.50
10.2.
3003
Day
Day
b) Machinery
Excavator 1.0 cum bucket Hour
capacity @ 60 cum per hour
Tipper (L is average lead in km t.Km
for borrow earth)
0.18
4.50
0.25
24xL
12.00
10.3.
3003
Day
Day
b) Machinery
Plate compactor @ 25 sqm per Hour
hour
c) Overheads @ % on (a+b)
d) Contractor's profit @
(a+b+c)
% on
0.10
2.50
4.00
10.4.
3004.2
Day
Day
Day
3.76
90
4
Hour
Hour
Hour
Hour
6
6
45
12
Cum
184.5
Cum
92.25
Tonne 14.97
Tonne 2.46
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
10.5.
3004.2
Day
Day
Day
b) Machinery
Air compressor 250 cfm
MP100-110TPH capacity
Tipper 10 tonnes capacity
Smooth wheeled roller
tonne
c) Material
i) Bitumen
ii) Bitumen emulsion
coat
iii) Aggregates
for
Hour
Hour
Hour
8-10 Hour
2.92
70
3
6
6
45
12
Tonne 22.5
tack Tonne 1.18
Cum
Cum
Cum
Tonne
99.75
65.55
114
8.62
Cum
Cum
Cum
Tonne
85.5
71.25
122.55
8.62
% on
10.6.
Note:
3004.3.
Crack Filling
Filling of crack using slow - curing
bitumen emulsion and applying
crusher dust in case cracks are
wider than 3 mm.
Unit= Running metre
Taking out put = 500 m
a) Labour
Mate
Mazdoor
Day
Day
b) Material
Slow-curing bitumen emulsion Kg
Stone crusher dust
Cum
0.04
1
33
0.02
c) Overheads @ % on (a+b)
d) Contractor's profit @
(a+b+c)
% on
3004.4
Dusting
Applying crusher dust to areas of
road where bleeding of excess
bitumen has occurred
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
Day
Day
b) Material
Stone crusher dust finer than 3 Cum
mm with not more than 10 per
cent passing 0.075 sieve
c) Overheads @ % on (a+b)
d) Contractor's profit @
(a+b+c)
% on
0.08
2
6.25
10.8.
3004.3.2
3004.3.4
3004.5
3004.6
Fog Seal
Crack Prevention Courses
Slurry Seal
Surface Dressing for Maintenance
Works
The above-mentioned items have
already been included in Chapter 5.
10.9.
3005.1
Day
Day
Day
b) Material
Epoxy primer
Kg
Epoxy
compound
with Kg
accessories for preparing epoxy
mortar
c) Machinery
Air compressor 250 cfm for Hour
cleaning
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 10 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10
Note:
The
constituents
of
epoxy
mortary/epoxy concrete will be as
per the instruction and manual of
the manufacturer.
0.04
0.50
0.50
2.50
10.00
0.05
10.10. 3005.2
Day
Day
0.04
0.50
b) Material
Primer
Sealant
Kg
Kg
0.25
1.00
c) Machinery
Air compressor 250 cfm for Hour
cleaning
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 10,metre =a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10
10.11. 3000
10
0.05
a) Labour
Mate
Mazdoor
Day
Day
0.08
1.00
Day
Day
0.04
1.00
b) Overheads @ % on (a)
c) Contractor's profit @
(a+b)
% on
b) Machinery
Dozer 180 HP @ 60 cum per Hour
hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 100 cum = a+b+c+d
Rate per cum = (a+b+c+d)/100
11
1.67
Note:
10.13. 3000
Day
Day
Day
Day
b) Machinery
Dozer D 80 A-12, 180 HP @ 60 Hour
cum per hour
Air compressor 250 cfm with Hour
two jack hammer
c) Materials
Gelatine 80 per cent @ 35 kg Kg
per 100 cum
Electric
Detonators
@
1 Nos.
Detonator for 2 Gelatine sticks
of 125 gms each
d) Overheads @ % on (a+b+c)
12
0.09
1.50
0.75
0.07
1.67
2.50
17.50
70.00
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Note:
10.14. 3000
Day
Day
b) Macninery
Dozer D 80 A-12, 180 HP @ Hour
850 cum per hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 5000 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5000
Note:
13
0.08
2.0
5.88
10.15. 3000
Day
Day
b) Machinery
Snow blower equipment 140 HP Hour
@ 600 cum per hour
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Cost for 3600 cum (a+b+c+d)
Rate per cum = (a+b+c+d)/3600
14
0.08
2.00
6.00
Chapter-11
Horticulture
Preamble:
1. The items of turfing with sods and seeding and mulching have been included in the
chapter of earthwork.
2. The analysis of rates for grassing of lawns and hedges has been included, as the
same may be needed for resting places on highways.
3. Five types of tree guards as under have been provided:
a)
b)
c)
d)
e)
Selection from above may be made as per actual situation and design.
4. Analysis of rates for wrought ron and mild steel welded work has been included to
cater for any miscellaneous work in connection with horticulture, fencing and traffic
sign.
5. Though the estimate for compensatory afforestation is made by the forest
department, the rate for this item has been analysed and included for the purpose of
estimation.
6. In the rate analysis of some items, the quantities of sub-items involved in that
analysis, like, excavation for foundation, foundation concrete, painting, lettering, etc.
have been given. The rates for such items may be taken from relevant chapters
where the same have already been analysed.
7. As grass and plantation need more care, one mate has been provided for every 10
mazdoors in case of horticulture.
Sr.
No.
11.1.
Reference to
MoRT&H
Specifications
307
Description
Spreading of Sludge Farm Yard
Manure or/and Good Earth
Unit
Quantit
y
Rate
Rs.
Day
Day
b) Overheads @
% on (a)
307
0.04
1.00
0.17
0.75
1.00
b) Machinery
Water tanker 6 KL capacity
Hour
0.50
c) Material
Doob grass
Kg
100.00
d) Overheads @
% on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
ii) In rows 7.5 cm apart in either
direction
a) Labour
Mate
Day
Mazdoor for grassing
Day
Mazdoor for maintenance for 30 Day
days
b) Machinery
Water tanker 6 KL capacity
Hour
0.75
c) Material
Doob grass
Kg
200.00
d) Overheads @
% on (a+b+c)
e) Contractor's profit @
(a+b+c+d)
% on
0.22
1.25
1.00
11.3.
307
11.4.
307
0.15
0.50
1.00
0.50
0.01
0.18
100.00
a) Labour
Mali
Day
b) Machinery
Water tanker 6 KL capacity
Hours 15.00
c) Material
Cost of water
KL
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
11.5.
307
10.00
90.00
a) Labour
Mate
Day
Mazdoor for preparation of Day
ground
Mali for fetching doob grass Day
roots hedges and grassing at 10
cm apart
b) Machinery
Water tanker 6 KL capacity Hour
Tractor with filler
Hour
c) Material
Supply of farmyard manure at Cum
site of work @ 0.6 cumper 100
sqm
Fine grass
Kg
0.25
1.00
1.50
0.50
0.01
0.60
100.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ %
(a+b+c+d)
on
307
Day
10.00
b) Machinery
Water tanker 6 KL capacity
Hour
20.00
c) Material
Cost of water
KL
60.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
11.7.
307
Planting
and
Maintaining
Permanent Hedges
A)
of
Planting
permanent
hedges
including digging of trenches, 60
cm wide and 45 cm deep, refilling
the excavated earth mixed with
farmyard manure, supplied at the
rate of 4.65 cum per 100 metre and
supplying and planting hedge
plants at 30 cm apart.
Unit = Running metre
Taking output = 100 metre
a) Labour
Mate
Day
Mazdoor for digging of trench 60 Day
cm wide and 45 cm deep
Mazdoor
for
refilling
the Day
excavated earth mixed with cow
dung, preparation of ground and
digging of plant, from the
nursery carriage to site and
planting in position
b) Machinery
Water tanker 6 KL capacity
Hour
1.4
10.00
4.00
0.50
c) Material
Cost of hedge plants 2 rows at Each
30 cm apart
Supply of farmyard manure at Cum
site of work
Pesticide
Kg
Cost of water
KL
d) Overheads @
2x340
4.67
0.25
3.00
% on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 100 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/100
B) Maintenance of hedge for one
year
Unit = Running metre Taking output
= 100 m
a) Labour
Mats
Mazdoor
Day
Day
3.00
30.00
b) Machinery
Water tanker 6 KL capacity
Hour
5.00
c) Material
Manure sludge / farmyard Cum
manure
Pesticide
Kg
Cost of water
KL
Cost of hedge plants @ 10% Each
casualty
d) Overheads @ % on (a+b+c+d)
e) Contractor's profit @
(a+b+c+d)
% on
2.00
0.50
30.00
68.00
11.8.
307
Planting
and
Maintaining
Flowering Plants and Shrubs
of
Day
Day
1.20
12.00
b) Machinery
Water tanker 6 KL capacity
Hour
6.00
c) Material
Plants
Shrubs
Manure sludge
manure
Pesticide
Cost of water
Each
Each
farmyard Cum
Kg
KL
d) Overheads @ % on (a+b+c)
Contractor's
(a+b+c+d)
profit
on
200.00
800.00
63.64
0.50
36.00
a)
Labour
Mate
Mazdoor
b) Machinery
Water tanker 6 KL capacity
c) Material
Manure
Sludge/farmyard
manure at site
Cost of water
Replacement of casualties @
10 percent
Plants
Shrubs
Pesticides
Day
Day
36.00
365.00
Hour
90.00
Cum
10.00
KL
180.00
Each
Each
Kg
20.00
80.00
1.50
d) Overheads @ % on (a+b+c)
Contractor's
(a+b+c+d)
profit
on
Maintenance/year/km = (a+b+c+d+e)
11.9.
307
their
10
1.70
2.00
15.00
b) Machinery
Water tanker 6 KL capacity
Hour
c) Material
Sapling 2 m high 25 mm dia Each
Farmyard manure
Cum
Presticide
Kg
Cost of water
KL
d) Overheads @
2.00
10.00
0.94
0.50
12.00
% on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Cost for 10 trees = a+b+c+d+e
Rate per tree = (a+b+c+d+e)/10
11.10
308
Day
Day
0.12
3.00
b) Machinery
Water tanker 6 KL capacity
Hour
0.50
11
c) Material
Cost of water
KL
d) Overheads @ % on (a+b+c)
e) Contractor's profit @
(a+b+c+d)
% on
Supply at Site
Farmyard Manure
Well
Decayed
b) Overheads @
% on (a)
c) Contractor's profit @
% on
(a+b) Rate per cum = (a+b+c)
11.12. 308.2
Supply at Site of
Deoiled Neem Cake
Work/Store-
12
3.00
a)
Cost,
carriage,
loading, Quintal 1.00
unloading and stacking in
store/site
b)
Overheads @
c)
Contractor's profit
(a+b)
% on (a)
% on
Supplying Sludge
Supplying sludge duly stacked at
site/store
Unit = cum
Taking output = one cum
a)
b)
Overheads @
c)
Contractor's profit @
(a+b)
% on (a)
% on
13
1.00
a) Labour
Mate
Mason
Mazdoor
Day
Day
Day
b) Material
Brick 2nd class
carriage
Cement mortar 1:6
d)
e)
including Nos.
0.05
0.25
0.25
230.00
Cum
0.025
Day
Day
Day
0.002
0.05
0.05
Overheads @ % on (a+b)
Contractor's profit @
(a+b+c)
% on
class
including Nos.
c) Overheads @ % on (a+b)
d) Contractor's profit @
(a+b+c)
% on
14
50.00
11.16. New
Day
Day
Day
b) Material
Empty bitumen drum
Each
MS sheet 50 x 0.5 mm
Kg
Rivets 6 mm dia and 10 mm in Each
length
c) Overheads @
% on (a+b)
d) Contractor's profit @
(a+b+c)
% on
15
0.02
0.15
0.07
1.00
0.65
22.00
11.17. New
Day
Day
Day
b) Material
Empty bitumen drum
Each
MS sheet 50 x 0.5 mm
Kg
Rivets 6 mm dia and 10 mm in Each
length
MS plate 30 x 3 mm
Kg
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on
(a+b+c)
Rate for each tree guard = a+b+c+d
16
0.04
0.20
0.20
1.50
0.65
50.00
1.30
11.18. New
Wrought Iron
Welded Work
and
Mild
Steel
c) Overheads @ % on (a+b)
d) Contractor's profit %on (a+b+c)
17
2.50
0.45
2.00
11.19. New
Day
Day
Day
0.05
0.25
0.25
b) Material
MS iron 25 x 6 mm
MS iron 25 x 3 mm
Kg
Kg
19.20
9.60
Hour
0.04
including Sqm
1.77
coats
e) Overheads % on (a+b+c)
f) Contractor's profit @
(a+b+c+e)
% on
18
Note:
11.20. New
Day
Day
Day
Day
0.05
0.25
0.25
0.25
b) Material
MS angle 30 x 30 x 3 mm
MS iron 25 x 3 mm
Steel wire 3 mm dia
Kg
Kg
Kg
13.50
18.00
6.00
Hour
0.04
including Sqm
1.50
coats
e) Overheads @ % on (a+b+c)
f) Contractor's profit @ % on
(a+b+c+e)
Rate per tree guard = a+b+c+d+e+f
19
11.21
New
Compensatory Afforestation
Planting trees as compensatory
afforestation at the rate of 290 trees
per hectare at a spacing of 6 m by
grubbing and levelling the ground
upto a deth of 150 mm, digging
holes 0.9 m dia, 1 m deep, mixing
farm yard/sludge manure with soil,
planting of sapling 2 m high with 25
cm dia stem, backfilling the hole
and watering.
Unit = hectare
Taking output = one hectare
a) Labour
i) Planting
Mate
Day
Mazdoor
Day
ii) For Maintenance for one
year
Mate
Day
Mazdoor
Day
b) Machinery
Dozer 80 HP @ 1000 sqm/hour Hour
Water tanker 6 KL capacity (for Hour
planting)
Water tanker 6 KL capacity (for Hour
maintenance)
c) Material
Sapling 1 to 1.5 m high 2 cm dia
stem
Add 10 per cent of sapling
Decayed
farmyard/sludge
manure (planting)
Decayed
farm
yard/sludge
manure (maintenance)
Pesticides for planting
Pesticides for maintenance
Cost of water
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on
(a+b+c+d)
Rate per hectare = a+b+c+d+e
20
2.50
25.00
5.00
50.00
10
3.00
25.00
Nos.
290.00
Nos.
Cum
29.00
60.90
Cum
4.00
Kg
Kg
KL
0.50
1.50
18.00
Note:
21
Chapter-12
Foundation
Preamble:
1.
Excavation for structures has been provided both by manual and mechanical means.
The rate relevant to a particular situation may be adopted.
2.
The earth excavated from foundation has been proposed to be backfilled and balance
quantity utilized for road work locally except for marshy soil where disposal has been
provided.
3.
The rock foundations are required to be prepared which has been analysed.
4.
5.
Embedment of foundation in soft and hard rocks has been provided as required by
the specifications.
6.
Dewatering has been provided in excavation for foundation. In case dewatering is not
required for a particular site condition, the same may be omitted.
7.
Mixing of cement concrete has been considered both by using concrete mixer and
batching plant. The rate can be adopted depending upon availability of equipment
and as approved by the Engineer.
8.
Concrete batching plant is generally placed within one km of the bridge site. In case
of longer lead, transportation cost may be worked out based on tonne km.
9.
The coarse and fine aggregate for cement concrete shall be as per IS: 383.
10. Description of items has been given very briefly. Relevant clauses of MoRT&H
Specifications may be referred for detailed specification.
11. The rate analysis for well foundation has been included for diameter varying from 6m
to 12 m. Well for twin D type has also been included.
12. Pneumatic sinking is a specialised job. All safety precaution as per 13:4138 are
required to be taken. Medical supervision for such works is considered very essential.
Depth of pneumatic sinking has been restricted to 30 m below normal water level.
13. Rate analysis for various types of piles like bored cast-in-situ, driven precast RCC pile
and driven steel piles of H section have been included. If the steel casing in case of
driven pile is required to be retained, the same is required to be priced separately.
14. Pile driving rigs including vibratory hammers are assumed to be self-contained with
power units and necessary accessories required for driving.
15. The quantity of concrete, which is required to be stripped off upto a minimum height
of 600 mm above the designed top level of the pile, has been taken into account in
the rate analysis.
16. The amount indicated for testing of piles are for the base year 2001 -2002. For
1
Reference to
MoRT&H
Description
specifications
304
Excavation for Structures
Unit
Quantity
Day
Day
0.14
3.50
Rate
Rs.
Day
Day
0.18
4.50
Day
Day
0.24
6.00
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note:
Note:
Mate
Mazdoor
Day
Day
b) Machinery
Hydraulic excavator 1.0 cum bucket Hour
capacity
0.32
8
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Note:
Day
Day
0.32
8
b) Machinery
Hydraulic excavator 1.0 cum bucket
Hour
Day
Day
0.4
10
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 210 cum =a+b+c+d
Rate per cum = (a+b+c+d)/210
Note:
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Note:
Day
Day
0.20
5.00
Day
Day
0.24
6
b) Overheads @ % on (a)
c) Contractor's profit @ % on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note:
b) Machinery
Hydraulic excavator 1.0 cum bucket Hour
capacity
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 180 cum =a+b+c+d
Rate per cum = (a+b+c+d)/180
Note:
Note:
Day
Day
Day
Day
0.35
0.5
0.25
8.00
Hour
Kg
Nos.
3.50
14
Day
Day
b) Machinery
Air Compressor 250 cfm with 2 leads Hour
of pneumatic breaker
0.2
5
c) Overheads @ % on (a+b)
e) Contractor's profit @ % on (a+b+c)
Cost for 10 cum =a+b+c+d
Rate per cum = (a+b+c+d)/10
Note:
Day
Day
0.4
10
b) Machinery
Tractor-trolley for removal
Hour
2.67
d) Overheads @ % on (a+b)
e) Contractor's profit @ % on (a+b+c)
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
8
Note:
Note:
0.08
2
0.17
0.45
Mate
Day
Mazdoor for dressing sides, bottom Day
and backfilling
b) Machinery
Tractor-trolley for transportation
0.12
3.00
Hour
2.00
a) Labour
Mate
Mazdoor
Day
Day
0.01
0.3
b) Material
Sand (assuming 20 per cent voids)
Cum
1.2
c) Overheads @ % on (a+b)
e) Contractor's profit @ % on (a+b+c)
Cost for 6 cum = a+b+c+d
Rate per cum = (a+b+c+d)/6
12.2.
304
12.3.
304
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per cum = a+b+c+d
12.4.
2100
10
Day
Day
Day
0.64
1
15
b) Material
Aggregate 40 mm
Coarse sand
Cement
Cost of water
Cum
Cum
Tonne
KL
13.50
6.75
3.45
18.00
c) Machinery
Concrete mixer 0.4/0.28 cum
33 KVA generator set
Water tanker 6 KL capacity
Hour
Hour
Hour
6.00
6.00
2.00
a) Material
Bricks 1st class
Cement Mortar 1:3
Nos.
Cum
2500
1.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.48
4
8.00
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Note:
c) Overheads @
% on (a+b)
12.6.
Sub-analysis
12.7.
1400
MT
Cum
0.51
1.05
Day
Day
0.04
0.90
1405.4
Rubble
Cum
stone Nos.
= 0.79
b) Labour
Mate
Mason
Mazdoor
c) Overheads @
5.50
35.00
Cum
1.50
Day
Day
Day
0.66
7.50
9
% on (a+b)
B. Random
Rubble
(coursed/uncoursed)
Masonry
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through
and
12
bond
Cum
stone Nos.
5.50
35.00
(35nos.x0.24mx0.24mx0.39m = 0.79
cum)
Cement mortar 1:3
Cum
b) Labour
Mate
Mason
Mazdoor
1.55
Day
Day
Day
0.62
6
9
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
Cum
4.13
6.75
8.1
4.05
1.35
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.5
20
c) Overheads @
% on (a+b)
12.8.
c) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour
Generator 63 KVA
Hour
d) Formwork @ 4 per cent on cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
13
on
6.00
6.00
MT
Cum
Cum
Cum
Cum
5.16
6.75
5.4
5.4
2.7
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.5
20
c) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour
Generator 33 KVA
Hour
6.00
6.00
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
on
MT
Cum
Cum
5.21
6.75
8.1
10 mm aggregate
b) Labour
Mate
Mason
Mazdoor
Cum
5.4
Day
Day
Day
0.86
1.5
20
c) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour
Generator 33 KVA
Hour
6.00
6.00
MT
Cum
Cum
Cum
41.66
54.00
64.80
43.20
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18.00
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t-km.
Hour
300L
6.00
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity
Transit mixer 4.0 cum capacity lead
upto 1 km
Lead beyond 1 km, L-lead in km
Concrete pump
d) Formwork @ 4 per cent on cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
% on (a+b+c+d)
f) Contractor's
profit
15
on
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
D. PCC Grade M 25
Case-l: Using Concrete Mixer
Unit = cum
Taking output =15 cum
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
Cum
5.99
6.75
5.4
5.4
2.7
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.5
20
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Generator 33 KVA
Hour
d) Formwork@ 3.75 per cent of (a+b+c)
e) Overheads @
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
on
16
MT
Cum
Cum
Cum
Cum
47.95
54
43.2
43.2
21.6
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3
18
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300L
Hour
6.00
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
6.05
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.50
20.00
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity
Transit mixer 4 cum capacity lead upto
1 km
Transit mixer 4 cum capacity lead
beyond 1 km, L-lead in kilometre
Concrete pump
d) Formwork @ 3.75 per cent of cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
on
c) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour
Generator 33 KVA
Hour
d) Formwork @ 3.75 per cent of (a+b+c)
e) Overheads @
% on (a+b+c+d)
17
6.00
6.00
f) Contractor's
(a+b+c+d+e)
profit
on
MT
Cum
Cum
Cum
48.38
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300L
Hour
6.00
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit mixer 4 cum capacity lead upto
1 km
Transit mixer 4 cum capacity lead
beyond 1 km, L-lead in kilometre
Concrete pump
d) Formwork @ 3.75 per cent on cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
18
on
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
Cum
6.08
6.75
5.4
5.4
2.7
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.50
20.00
c) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour
Generator 33 KVA
Hour
6.00
6.00
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
on
MT
Cum
Cum
Cum
Cum
48.60
54
43.2
43.2
21.6
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300L
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity
Transit mixer 4 cum capacity lead upto
1 km
Transit mixer 4 cum capacity lead
19
Hour
6.00
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
6.10
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.50
20.00
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
on
c) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour
Generator 33 KVA
Hour
d) Formwork @ 3.5 per cent on cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
20
on
6.00
6.00
MT
Cum
Cum
Cum
48.80
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15
t.km
300L
Hour
6.00
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
6.33
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.50
20.00
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity
Transit mixer 4 cum capacity lead upto
1 km
Transit mixer 4 cum capacity lead
beyond 1 km, L-lead in kilometre
Concrete pump
d) Formwork @ 3.5 per cent of cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
on
21
c) Machinery
Concrete mixer 0.40/0.28 cum capacity Hour
Generator 33 KVA
Hour
6.00
6.00
% on (a+b+c+d)
f) Contractor's
profit
@
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f
on
MT
Cum
Cum
Cum
50.64
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
30L
Hour
6.00
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity
Transit mixer 4 cum capacity lead upto
1 km
Transit mixer 4 cum capacity lead
beyond 1 km, L-lead in kilometre
Concrete pump
d) Formwork @ 3 per cent on cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
% on (a+b+c+d)
f) Contractor's
(a+b+c+d+e)
profit
22
on
Note:
12.9.
1200
Cum
Nos.
b) Labour
Mate
Day
Mazdoor for filling sand bags, stitching Day
and placing
c) Machinery
Crane with grab 1 cum capacity Hour
Consumables @ 2.5 per cent of (c)
above
d) Overheads @
251.20
750.00
0.40
15.00
20.00
% on (a+b+c)
23
Cum
Nos.
Nos.
Rm
904.32
6000
95
190
Mate
Mazdoor for piling 8" dia ballies
Mazdoor for bracing with 2" dia ballies
Mazdoor for filling sand bags, stitching
and placing
`
c) Machinery
Crane with grab 1 cum capacity
Day
Day
Day
Day
5.60
18.00
12.00
110.00
Hour
50.00
Cum
Nos.
450.00
300.00
% on (a+b+c)
b) Labour
Mate
Day
Mazdoor for filling sand bags, stitching Day
and placing
c) Machinery
Front end Loader 1 cum capacity
Tipper 5.5 cum capacity
d) Overheads @
% on (a+b+c)
Hour
Hour
0.24
6.00
27.00
28.00
RCCM 20 Grade
Same as for 12.8 (C) except for
formwork which shall be @ 20 per
cent of the cost of concrete instead of
4 per cent.
Day
Day
Day
Day
Day
1.05
20.00
1.32
5.50
5.50
5.50
16.50
MT
Cum
Cum
Cum
Kg
51.60
54.00
64.80
43.20
206.00
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18.00
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300.L
Hour
6.00
c) Machinery
Batching Plant
Generator 100 KVa
Loader 1 cum capacity
Transit mixer 4 cum capacity for lead
upto 1 km
Transit mixer 4 cum capacity for lead
beyond 1 km
Concrete pump
d) Formwork @ 10 per cent on cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
f) Contractor's
(a+b+c+d+e)
% on (a+b+c+d)
profit
on
involved)
Case-l: Using Concrete Mixer
(i) PCC Grade M 20
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
Admixture
MT
Cum
Cum
Cum
Cum
Kg
5.55
6.75
5.4
5.4
2.7
18.60
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.9
1.50
20.00
c) Machinery
Concrete
mixer
0.40/0.28
cum Hour
capacity
Generator 33 KVA
Hour
Light crane 3 tonnes capacity for Hour
handling tremie pipe
6.00
6.00
6.00
% on (a+b+c)
MT
Cum
Cum
Cum
44.4
54
64.8
43.2
Admixture
Kg
148.80
Day
Day
Day
0.88
3.00
18
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300.L
Hour
6.00
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
Admixture
MT
Cum
Cum
Cum
Cum
Kg
5.99
6.75
5.4
5.4
2.7
21.60
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.9
1.50
20.00
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KW
Loader 1 cum capacity
Transit mixer 4 cum capacity, lead
upto 1 km
Transit mixer 4 cum capacity, lead
beyond 1 km, L - lead in kilometre
Concrete pump
Add 5 per cent of cost of material and
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe.
d) Overheads @
% on (a+b+c)
c) Machinery
Concrete
mixer
capacity
29
0.40/0.28
cum Hour
6.00
Generator 33 KVA
Hour
Light crane of 3 tonnes capacity for Hour
handling tremie pipe
6.00
6.00
% on (a+b+c)
MT
Cum
Cum
Cum
Kg
47.88
54
64.8
43.2
172.80
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.88
3.00
18
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300.L
Hour
6.00
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity
Transit mixer 4 cum capacity, lead
upto 1 km
Transit mixer 4 cum capacity, lead
beyond 1 km, L-lead in kilometre
Concrete pump
Add 5-pre cent of cost of material and
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for underwater concreting
with tremie pipe.
d) Overheads @
% on (a+b+c)
30
MT
Cum
Cum
Cum
Cum
Kg
6.08
6.75
5.4
5.4
2.7
21.60
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.9
1.50
20.00
c) Machinery
Concrete
mixer
0.40/0.28
cum Hour
capacity
Generator 33 KVA
Hour
Light crane of 3 tonne capacity for Hour
handling tremie pipe
Add 5 per cent of cost of material and
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe.
d) Overheads @
% on (a+b+c)
31
6.00
6.00
6.00
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
Admixture
Mt
Cum
Cum
Cum
Kg
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
c) Machinery
Batching plant @ 20 cum/hr
Generator 100 KVA
Loader 1 cum capacity
Transit mixer 4 cum capacity, lead upto
1 km
Transit mixer 4 cum capacity, lead
beyond 1 km, L-lead in kilometre
Concrete pump
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300.L
Hour
6.00
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
Admixture
MT
Cum
Cum
Cum
Cum
Kg
6.29
6.75
5.4
5.4
2.7
21.60
b) Labour
Mate
Mason
Day
Day
0.9
1.50
% on (a+b+c)
32
Mazdoor
Day
c) Machinery
Concrete
mixer
0.40/0.28
cum Hour
capacity Generator 33 KVA
Hour
Light crane of 3 tonne capacity for Hour
handling tremie pipe
20.00
6.00
6.00
6.00
% on (a+b+c)
MT
Cum
Cum
Cum
Kg
50.28
54
64.8
43.2
172.80
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.88
3.00
18
c) Machinery
Batching plant @ 20 cum/hr
Hour
Generator 100 KVA
Hour
Loader 1 cum capacity
Hour
Transit mixer 4 cum capacity, lead Hour
upto 1 km
Transit mixer 4 cum capacity, lead t.km
beyond 1 km, L-lead in kilometre
Concrete pump
Hour
Add 5 per cent of cost of material and
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
33
6.00
6.00
6.00
15.00
300.L
6.00
% on (a+b+c)
Grade M 20 PCC
Same as in bottom plug concrete,
excluding cost of forming sump,
protective bunds, chiselling etc.
Grade M 15 PCC
Same as item 12.8(A)
formwork
excluding
excluding
34
excluding
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
5.12
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.5
20
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Generator 33 KVA
Hour
Formwork @ 4 per cent of a+b+c
d) Overheads @
6
6
% on (a+b+c)
MT
Cum
Cum
Cum
40.92
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3
18
Hour
Hour
Hour
6.00
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
c) Machinery
Batching plant (output 20 cum/hr)
Generator 100 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
Formwork @ 4 per cent of (a+b+c)
35
d) Overheads @
% on (a+b+c)
RCC Grade M 25
MT
Cum
Cum
Cum
6.05
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.5
20
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Generator 33 KVA
Hour
Formwork @ 3.75 per cent of a+b+c
d) Overheads @
e) Contractor's
(a+b+c+d)
% on (a+b+c+d)
profit
36
on
6
6
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
48.40
54
64.8
43.2
Day
Day
Day
0.84
3
18
Hour
Hour
Hour
6.00
6.00
6
Hour
t.km
Hour
15.00
300.L
6.00
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
6.10
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.5
20
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching plant (output 20 cum/hr)
Generator 100 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km L-lead in kilometre
Concrete pump
Formwork @ 4 per cent of (a+b+c)
d) Overheads @
% on (a+b+c)
c) Machinery
Concrete mixer (capacity 0.40/0.28
cum)
Generator 33 KVA
Formwork @ 3.5 per cent of (a+b+c)
37
d) Overheads @
% on (a+b+c)
MT
Cum
Cum
Cum
48.79
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
6
18
Hour
Hour
Hour
6.00
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
MT
Cum
6.33
6.75
c) Machinery
Batching plant (output 20 cum/hr)
Generator 100 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
Formwork @ 3.5 per cent of (a+b+c)
d) Overheads @
% on (a+b+c+d)
RCC Grade M 35
Case-l: Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
38
20 mm aggregate
10 mm aggregate
b) Labour
Mate
Mason
Mazdoor
Cum
Cum
8.1
5.4
Day
Day
Day
0.86
1.5
20
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Generator 33 KVA
Hour
6
6
% on (a+b+c)
MT
Cum
Cum
Cum
50.64
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3
18
Hour
Hour
Hour
6.00
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
c) Machinery
Batching plant (output 20 cum/hr)
Generator 100 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
Formwork @ 3 per cent of (a+b+c)
d) Overheads @
% on (a+b+c)
MT
Cum
Cum
Cum
Kg
52.20
54.00
64.80
43.20
206.00
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18.00
Hour
Hour
Hour
Hour
6.00
6.00
6.00
15.00
t.km
300.L
Hour
6.00
c) Machinery
Batching Plant
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead
upto 1 km
Transit mixer 4 cum capacity for lead
beyond 1 km
Concrete pump
d) Formwork @ 3 per cent on cost of
concrete i.e. cost of material, labour
and machinery
e) Overheads @
f) Contractor's
(a+b+c+d+e)
% on (a+b+c+d)
profit
40
on
12.12
Section 1200
Day
Day
Day
0.12
4
2
b) Machinery
Hire & running charges of crane with Hours 2
grab bucket of 0.75 cum capacity and
accessories
Day
Day
Day
0.15
1.25
2.5
b) Machinery
Hire & running charges of crane with Hours 3
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
41
(b)
c) Overheads @
% on (a+b)
Beyond 10 m upto 20 m
Add 5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
iv
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for Kentledge
including
supports,
loading
arrangement and labour
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
B. Clayey Soil (6 m dia Well)
Unit = Running metre
Taking output = 1 metre
i.
Day
Day
Day
0.15
1.50
2.25
b) Machinery
Hire & running charges of crane with Hours 3.00
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
42
(b)
c) Overheads @
% on (a+b)
Day
Day
Day
0.30
3.00
4.50
b) Machinery
Hire & running charges of crane with Hours 6.00
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hours 2.00
attachment for cutting hard clay
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
Beyond 10 m upto 20 m
Add 5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add for dewatering @ 5 per cent of
cost, if required
iv
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 5 per cent of cost for dewatering
of the cost, if required
Add 25 per cent of cost for kentledge
including
supports,
loading
43
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 5 per cent of cost for dewatering,
if required
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
C. Soft Rock (6 m dia Well)
Unit = Running metre
Taking output = 1 m
Depth in soft rock strata upto 3 m
Rate of sinking = 0.25 m per Hour
a) Labour
Mate
Sinker (skilled)
Sinking helper (semi-skilled)
Diver
Day
Day
Day
Day
0.92
3.00
20.00
0.50
b) Machinery
Hire & running charges of crane with Hours 4.00
grab bucket of 0.75 cum capacity and
accessories
Air compressor
breakers
with
Kg.
Nos.
4.00
18.00
b) Labour
Mate
Driller
Blaster
Mazdoor
Mazdoor (skilled)
Day
Day
Day
Day
Day
1.56
2
0.25
12
4
c) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Hire & running charges of compressor Hour
with pneumatic breaker/Jack hammer
for drilling
Dewatering @ 5 per cent of cost of (b+c),
if required
Consumables in sinking @ 10 per cent of
cost of (b).
d) Overheads @
% on (a+b+c)
45
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
0.15
1.25
2.5
3.25
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
iv
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
46
0.18
1.5
3
4.5
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement, and labour etc.
B. Clayey Soil (7 m dia Well)
Unit = Running metre
Taking output = 1 cum
Day
Day
Day
0.18
1.50
3.00
b) Machinery
Hire & running charges of crane with Hours 4.50
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
Day
Day
Day
b) Machinery
47
0.26
2.00
4.00
6.00
3.25
% on (a+b)
iv
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 5 per cent of cost for dewatering
on the cost, if required
Add 25 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 5 per cent of cost for dewatering,
if required
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
C. Soft Rock (7 m dia Well)
Unit= Running metre
48
Taking output = 1 m
Depth in soft rock strata upto 3 m
Rate of sinking = 0.22 m per Hour
a) Labour
Mate
Sinker (skilled)
Sinking helper (semi-skilled)
Diver
Day
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic Hour
breakers
0.58
4.00
10.00
0.75
4.50
3.75
% on (a+b)
Kg.
No.
7.00
30.00
b) Labour
Mate
Driller
Blaster
Mazdoor
Mazdoor (skilled)
Diver
Day
Day
Day
Day
Day
Day
1.6
2
0.25
18
4
0.5
c) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
49
d) Overheads @
% on (a+b+c)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @ of
% on (a+b)
50
0.18
1.5
3
a) Labour
Mate
Sinker
Sinking helper
Day
Day
Day
0.25
1.75
3.5
b) Machinery
Hire & running charges of crane with Hours 5
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overhead @
% on (a+b)
iv
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour etc.
B. Clayey Soil (8 m dia well)
Unit = Running metre
Taking output = 1 metre
51
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
0.22
2.00
3.50
5.50
% on (a+b)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hour
attachment for cutting hard clay
Consumables in sinking @ 10 per cent of
(b).
c) Overhead @
% on (a+b)
52
0.32
2.50
4.50
6.00
3.50
Day
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic Hour
breakers
Consumables in sinking @ 10 per cent of
(b)
53
0.68
4.00
12.00
1.00
5.00
3.75
% on (a+b)
Kg.
No.
8.00
32.00
b) Labour
Mate
Driller
Blaster
Mazdoor
Mazdoor (Skilled)
Day
Day
Day
Day
Day
1.09
2
0.25
20
4
c) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Hire & running charges of compressor Hour
with pneumatic breaker/jack hammer
for drilling
Dewatering @ 5 per cent of cost of (b+c),
if required.
Consumables in sinking @ 10 per cent of
cost of (b)
d) Overheads @
% on (a+b+c)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
0.19
1.5
3.25
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
0.27
1.75
4
5.5
iv
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour etc.
B. Clayey Soil (9 m dia well)
Unit= Running metre
Taking output = 1 cum
(i) Depth below bed level upto 3.0 m
Rate of sinking 0.17 m/Hour
a) Labour
Mate
Sinker (skilled)
Sinking helper (semi-skilled)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
0.24
2.25
3.75
5.75
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hour
attachment for cutting hard clay
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
iv
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 5 per cent of cost for dewatering
on the cost, if required
Add 25 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
57
0.34
2.50
5.00
6.50
3.75
Day
Day
Day
Day
0.76
4.00
14.00
1.2
b) Machinery
Hire & running charges of crane with Hours 6.50
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic breakers
Hours 4.00
Kg
10.00
Electric detonators
b) Labour
Mate
Driller
Blaster
Mazdoor
Mazdoor (skilled)
Diver
Nos.
40.00
Day
Day
Day
Day
Day
Day
1.17
2
0.25
22
4
1
c) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Hire & running charges of compressor Hour
with pneumatic breaker/jack hammer
for drilling
2.5
% on (a+b+c)
Day
Day
Day
0.2
1.5
3.5
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
% on (a+b)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
60
0.31
2
4.25
5.75
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
0.25
2.50
5.50
6.00
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hour
attachment for cutting hard clay
61
0.40
3.00
5.50
6.00
4.00
% on (a+b)
62
Mate
Sinker (skilled)
Sinking helper (semi-skilled)
Diver
Day
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic Hour
breakers
0.86
4.00
16.00
1.4
7.00
4.25
Kg
Nos.
11
44.00
b) Labour
Mate
Driller
Blaster
Mazdoor
Mazdoor (skilled)
Day
Day
Day
Day
Day
1.27
2.00
0.25
24.00
4.00
c) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Hire & running charges of compressor Hour
with pneumatic breaker/jack hammer
or drill
Dewatering @ 5 per cent of cost (c), if
required
63
8.5
% on (a+b+c)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
64
0.21
1.5
3.3
a) Labour
Mate
Sinker
Sinking helper
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
65
0.32
5
4.5
4.00
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
0.26
2.50
4.00
5.00
% on (a+b)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hour
attachment for cutting hard clay
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
0.43
3.50
5.75
6.00
4.25
Day
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic Hour
breakers
Consumables in sinking @ 10 per cent of
(b)
67
0.95
4.25
18.00
1.50
8.00
4.50
Kg.
Nos.
12
48.00
b) Labour
Mate
Driller
Blaster
Mazdoor
Mazdoor (skilled)
Day
Day
Day
Day
Day
1.35
2.00
0.25
26.00
4.00
c) Machinery
Hire & running charges of crane with grab Hour
bucket of 0.75 cum capacity and
accessories
Hire & running charges of compressor Hour
with pneumatic breaker/jack hammer or
drill
Dewatering @ 5 per cent of cost (c), if
required
Consumables in sinking @ 10 per cent of
cost of (b+c)
d) Overheads @
% on (a+b+c)
10
3.5
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
0.22
1.75
4
c) Overheads @ of % on (a+b)
d) Contractor's profit @
% on (a+b+c)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @ 10 per cent of
(b)
69
0.37
2.5
4.75
6.5
c) Overheads @
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
kentledge
loading
kentledge
loading
Day
Day
Day
b) Machinery
Hire and running charges of crane Hour
with grab bucket of 0.75 cum capacity
and accessories
70
0.30
3.00
4.50
6.25
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hour
attachment for cutting hard clay
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
0.48
3.75
6.00
8.33
4.50
cost, if required
Add 25 per cent for
including
supports,
arrangement and labour
kentledge
loading
Day
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hour
attachment for cutting hard clay.
Consumables in sinking @ 10 per cent of
(b)
Add for dewatering @ 5 per cent, if
required
c) Overheads @
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
1.06
4.50
20.00
1.75
10.00
4.75
Kg
Nos.
14
56.00
b) Labour
Mate
Driller
Blaster
Mazdoor
Mazdoor (skilled)
Day
Day
Day
Day
Day
1.44
2.00
0.25
28
4.5
c) Machinery
Hire and running charges of crane Hour
with grab bucket of 0.75 cum capacity
and accessories
Hire and running charges of
compressor
with
pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 percent, if required
Consumables in sinking @ 10 per cent of
(c)
d) Overheads @
% on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 0.25 m = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/0.25
12.19. 1200
73
12.5
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
0.2
1.25
3.75
5.50
% on (a+b)
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
0.3
1.5
4
5.88
Beyond 20 m upto 30 m
Add 7.5 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
Beyond 30 m upto 40 m
Add 10 per cent for every additional
metre depth of sinking over the rate of
sinking for the previous metre
Add 20 per cent of cost for kentledge
including
supports,
loading
arrangement and labour
B. Clayey Soil (Twin D Type Well)
Unit = Running metre
Taking output = 1 metre
(i) Depth below bed level upto 3.0 m
Rate of sinking @ 0.16 m/Hour
a) Labour
Mate
Sinker (skilled)
Sinking helper (semi-skilled)
Day
Day
Day
0.26
2.50
4.00
b) Machinery
Hire & running charges of crane with Hours 6.25
grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
75
a) Labour
Mate
Sinker
Sinking helper
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic chisel Hour
attachment for cutting hard clay
Consumables in sinking @ 10 per cent of
(b)
c) Overheads @
% on (a+b)
per
cent for
supports,
76
kentledge
loading
0.45
3.25
6.00
6.67
4.50
Day
Day
Day
Day
b) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Air compressor with pneumatic Hour
breakers
0.86
4.50
15.00
1.5
8.33
6.00
% on (a+b)
Kg.
Nos.
10
40.00
b) Labour
Mate
Driller
Blaster
Mazdoor
Day
Day
Day
Day
1.34
2.00
0.25
25.00
77
Mazdoor (skilled)
Day
c) Machinery
Hire & running charges of crane with Hour
grab bucket of 0.75 cum capacity and
accessories
Hire & running charges of compressor Hour
with pneumatic breaker/jack hammer
or drill
4.25
10
% on (a+b+c)
78
MT
0.480
Blasting material
Gelatine 80 percent
Electric detonators
Kg
Each
1.50
6.00
Day
Day
Day
Day
Day
Day
0.50
1.00
1.86
1.00
0.50
30.00
Day
10.00
Day
4.00
b) Labour
Medical Officer
Para medical personnel
Mate
Drillers
Blaster
Mazdoor
(for
cutting,
blasting,
cleaning, removal of material, etc.)
Mazdoor skilled (for fixation and
removal of adopter for air lock,
carrying out mechanical and electrical
operations and repairs and other
skilled jobs)
Diver
c) Machinery
i. Induction, deinduction and erection of Hour
plant and equipment including all
components and accessories for
pneumatic method of well sinking
Induction and deinduction
L.S
Erection at site and commissioning
L.S
Usage of plant and equipment for Hour
pneumatic method of well sinking
Air compressor 250 cfm, 2 nos.
Hour
Hire and running charges of crane of 15 Hour
tonne capacity
Rs. 1,00,000
Rs. 1,50,000
6.00
6.00
6.00
6.00
6.00
d) Overheads @
% on (a+b+c)
6.00
2x6
6.00
% on (a+b)
Cum
1.2
Day
Day
0.01
0.3
1.05
Day
Day
Day
Day
Day
1.24
6.00
5.00
5.00
10.00
Cum
6.62
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
6.00
Hour
0.50
Hour
6.00
Hour
Hour
0.30
0.30
Kg
300
Day
Day
0.14
3.50
Cum
7.85
Hour
6.00
Hour
0.50
Hour
6.00
Hour
0.40
% on (b+c)
0.4
350
Day
Day
0.16
4.00
Cum
10.17
Hour
6.00
Hour
0.50
Hour
6.00
Hour
Hour
0.50
0.5
Kg
385
Day
0.18
% on (b+c)
Mazdoor
d) Overheads @
Day
4.50
Cum
17.66
% on (b+c)
Day
Day
% on (b+c+d)
84
160
70
50
0.5
0.12
3
Cum
23.55
160
70
50
0.5
0.5
Day
Day
0.16
4
Cum
22.61
% on (b+c+d)
86
160
70
50
0.5
Day
Day
0.18
4.5
Cum
11.78
% on (b+c+d)
87
a) C.I Shoes
Kg
b) M.S.shoes
Kg
c) Steel helmet and cushion block on Kg
top of pile head during driving
c) Machinery
Crane 201 capacity
Hour
Vibrating
pile
driving
hammer Hour
complete with power unit and
accessories
d) Labour
Mate/Supervisor
Mazdoor
240
105
30
6.00
6.00
Day
Day
0.12
3
Cum
22.08
% on (b+c+d)
160
70
40
c) Machinery
Crane 40 T capacity
Hour
Vibrating
Pile
driving
hammer Hour
complete with power unit and
accessories
d) Labour
Mate/Supervisor
Mazdoor
Day
Day
6.00
6.00
0.16
% on (b+c+d)
profit
on
12.31
Note:
Hour
hammer Our
31.40
160
70
50
6.00
6.00
complete with
accessories
power
unit
and
d) Labour
Mate/Supervisor
Mazdoor
Day
Day
0.2
5
Cum
5.40
% on (b+c+d)
90
240
105
30
6.00
6.00
Mate/Supervisor
Mazdoor
Day
Day
0.12
3
% on (b+c+d)
Day
Day
12.50
160
70
30
6.00
6.00
0.16
4
% on (b+c+d)
Day
Day
22.50
160
70
30
6.00
6.00
0.18
4.5
e) Overheads @
% on (b+c+d)
Day
Day
% on (a+b+c)
6
6.00
0.12
3
6.00
6.00
Day
Day
0.14
3.5
MT
MT
1
1
% on (a+b+c)
Note:
300
5000
Technical Specifications
A. RCC Grade M 20
Unit = cum
Taking output =15 cum
Case-l: Using Concrete Mixer
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mate
Mason
Mazdoor for concreting
Mazdoor for breaking pile
bending bars, cleaning, etc.
MT
Cum
Cum
Cum
Day
Day
Day
head, Day
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Generator (capacity 33 KVA)
Hour
5.12
6.75
8.1
5.4
0.9
1.5
20
1
6
6
MT
Cum
Cum
Cum
Day
Day
Day
head, Day
c) Machinery
Batching plant (output 20 cum/hr)
Generator 100 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete Pump
Formwork @ 4 per cent on cost of
concrete, i.e., cost of a) Material, b)
95
5.12
6.75
8.1
5.4
0.16
0.38
2.5
1
Hour
Hour
Hour
0.75
0.75
0.75
Hour
t.km
Hour
2.00
37.5L
0.75
% on (a+b+c)
MT
Cum
Cum
Cum
Day
Day
Day
head, Day
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Generator (capacity 33 KVA)
Hour
5.99
6.75
8.1
5.4
0.9
1.5
20
1
6
6
MT
Cum
Cum
Cum
Day
Day
Day
head, Day
5.99
6.75
8.1
5.4
0.16
0.38
2.5
1
c) Machinery
Batching plant (output 20 cum/hr)
Generator 125 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
Hour
Hour
Hour
0.75
0.75
0.75
Hour
t.km
Hour
2.00
37.5L
0.75
MT
Cum
Cum
Cum
6.10
6.75
8.1
5.4
% on (a+b+c)
Day
Day
Day
head, Day
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Hour
Generator (capacity 33 KVA)
0.9
1.5
20
1
6
6
MT
97
6.10
Coarse sand
20 mm aggregate
10 mm aggregate
Cum
Cum
Cum
b) Labour
Mate
Mason
Mazdoor for concreting
Mazdoor for breaking pile
bending bars, cleaning, etc.
Day
Day
Day
head, Day
c) Machinery
Batching plant (output 20 cum/hr)
Generator 100 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
6.75
8.1
5.4
0.16
0.38
2.5
1
Hour
Hour
Hour
0.75
0.75
0.75
Hour
t.km
Hour
2.00
37.5L
0.75
MT
Cum
Cum
Cum
6.33
6.75
8.1
5.4
% on (a+b+c)
profit
on
Day
Day
Day
head, Day
0.9
1.5
20
1
c) Machinery
Concrete mixer (capacity 0.40/0.28 Hour
cum)
Generator (capacity 33 KVA)
Hour
6
6
MT
Cum
Cum
Cum
Day
Day
Day
head, Day
c) Machinery
Batching plant (output 20 cum/hr)
Generator 125 KVA
Loader (capacity 1 cum)
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
6.33
6.75
8.1
5.4
0.16
0.38
2.5
1
Hour
Hour
Hour
0.75
0.75
0.75
Hour
t.km
Hour
2.00
37.5L
0.75
MT
4.13
% on (a+b+c)
99
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
b) Labour
Mate
Mason
Mazdoor
Cum
Cum
Cum
Cum
6.75
8.1
4.05
1.35
Day
Day
Day
0.86
1.5
20
c) Machinery
Concrete mixer 0.40/0.28 capacity Hour
Generator 33 KVA
Hour
d) Overheads @
6
6
% on (a+b+c)
1.05
6.00
Day
Day
Day
% on (a+b)
100
0.40
2.00
6.00
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps MT
and wastage
Binding wire
Kg
1.05
6.00
Day
Day
Day
% on (a+b)
d) Contractor's profit @
Rate per MT = (a+b+c+d)
101
% on (a+b+c)
0.43
2.25
6.50
Chapter-13
Substructure
Preamble:
1. Although, Substructures are generally constructed in cement concrete, the rate analysis
for brick and stone masonry in CM 1:3 have also been included which can be adopted if
permitted by design.
2. The cost of formwork will vary with the height of the substructure. Provision has
accordingly been made.
3. As the higher grade of concrete is constlier, the provision made for formwork on
percentage basis has been suitably adjusted to make it comparable with other grades.
4. Bridge bearing, being commercial items produced by specialized firms with imported
technology and parts, the rates for the same are required to be ascertained from the
market for the approved design and technical specifications.
5. Filter media and backfilling behind abutments are required to be provided as per
guidelines given in IRC: 78-2000.
6. Weep holes shall be provided as per Clause 2706 of MoRT&H Specifications.
7. In case of roller-cum-rocker bearings, only full circular rollers are to be provided.
8. All bearings shall be set truly level so as to have full and even seating.
9. For elastomeric bearing pads, the concrete surface shall be levelled such that the
variation is not more than 1.5 mm from a straight edge placed in any direction across
the area.
10. The bearing should be procured only from those manufacturers who have been prequalified by the Ministry of Road Transport and Highways.
11. The bottoms of girders resting on the bearing shall be plane and truly horizontal.
12. For spans in grade, the bearing shall be placed horizontal by using sole plates for
suitably designed RCC pedestals.
Sr.
No.
13.1.
Reference to
MoRT&H
Description
specifications
1300 & 2200 Brick masonry work in 1:3 in substructure
complete excluding pointing and plastering,
as per drawing and Technical Specification
Unit
Quantity
Unit = cum
Taking output = 1 cum
a) Material
Bricks 1st class
Nos
500.00
Rate
Rs.
Day
Day
Day
0.24
0.06
0.8
0.80
Day
Day
Day
0.03
0.04
0.50
0.50
% on (a+b)
13.3.
Note:
0.144
Mate
Mason
Mazdoor
c) Overheads @
Day
Day
Day
0.04
0.50
0.50
% on (a+b)
13.4.
Day
Day
Day
% on (a+b+c)
1.00
7.00
0.33
0.1
1.2
1.2
Day
Day
Day
1.10
7.00
0.30
0.12
1.50
1.50
% on (a+b)
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
Day
Day
Day
1.11
7.00
0.33
0.2
2.5
2.5
d) PCC Grade M 30
Same as item 12.8 (F) upto 5 m height
with the only change that the provision
of formwork shall be 10 per cent
instead of 3.50 per cent of cost of
material, labour and machinery.
For height above 5 m and upto 10m.
Same as item 12.8 (F) with the
following changes: (i) Add 2 per cent
of cost of material, labour and
machinery excluding formwork to cater
for extra lift. (ii) The provision of
formwork shall be 12 percent instead
of 3.50 per cent of cost of material,
labour and machinery.
For height above 10m.
Same as item 12.8 (F) with the
following changes: (i) Add 4 per cent
of cost of material, labour and
machinery excluding formwork to cater
for extra lift. (ii) The provision of
formwork shall be 15 per cent instead
of 3.50 per cent of cost ofmaterial,
labour and machinery.
e) RCC Grade M 20
Same as item 12.8 (C) upto 5 m
height, except for formwork which
shall be 10 per cent instead of 4 per
cent of cost of material, labour and
machinery.
For height, upto 10 m, add 2 per cent
of cost as above excluding formwok.
For cost of formwork add 12 per cent
of cost of material, labour and
machinery instead of 4 per cent.
For height above 10m.
Same as item 12.8 (C) with the
following changes: (i) Add 4 per cent
of cost of material, labour and
machinery excluding formwork to cater
for extra lift. (ii) The provision of
formwork shall be 15 per cent instead
of 4 per cent of cost of material, labour
and machinery.
f) RCC Grade M 25
Same as item 12.8 (E) upto 5m height,
excluding formwork. For cost of
Note:
13.6.
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
1.05
6.00
0.34
2.00
6.50
a) Material
MS bars including 5 per cent overlaps MT
and wastage
Binding wire
Kg
b) Labour for straightening, cutting,
bending, shifting to site, tying and
placing in position
Mate
Day
Blacksmith
Day
Mazdoor
Day
1.05
6.00
0.34
2.00
6.50
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per MT = (a+b+c+d)
13.8.
31.5
Day
Day
Day
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
30
10
0.05
0.03
0.5
0.25
Note:
13.9.
710.1.4. of
IRC:78 &
2200
Day
Day
0.28
7.00
b) Material
Granular material
Cum
12.00
c) Machinery
Plate compactor/power rammer
Water Tanker
Hour
Hour
2.50
0.05
d) Overheads @ % on (a+b+c)
e) Contractor's
(a+b+c+d)
profit
on
0.28
7.00
b) Material
Sand
Cum
12.00
c) Machinery
Plate compactor/power rammer
Water tanker
Hour
Hour
2.50
0.06
10
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 10 cum of sandy backfill =
a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
13.10.
710.1.4. of
IRC:78 and
2200
Hour
0.32
7.00
1.00
12.00
0.06
Specifications
Unit: one tonne capacity
Considering a 250 tonne capacity bearing
for this analysis
a) Labour
Mate
Mazdoor skilled
Mazdoor
Day
Day
Day
b) Material
Cast steel rocker bearing assembly of Nos.
250 tonne design load capacity duly
painted complete with all its
components as per drawing and
specifications
0.06
0.50
1.00
1.00
Day
Day
Day
b) Material
Forged steel roller bearing of 250 Nos.
tonne design load capacity duly
painted complete with all its
components as per drawing and
specifications
12
0.06
1.00
0.50
1.00
Day
Day
Day
b) Material
PTFE sliding plate bearing assembly Nos.
of 80 tonne design load capacity duly
painted complete with all its
components as per drawing and
technical specification
Add 1 per cent for foundation anchorage
bolts and consumables
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 80 tonne capacity bearing =
a+b+c+d
Rate per tonne capacity = (a+b+c+d)/80
13.14. 2000 & 2200
0.006
1.00
0.50
1.00
0.06
1.00
0.50
1.00
a) Labour
Mate
Mazdoor
Mazdoor skilled
Day
Day
Day
b) Material
Supply of sliding plate bearing of 80 Nos.
tonne design capacity complete as per
drawings and technical specifications
0.04
0.75
0.35
1.00
Day
Day
Day
b) Material
Pot type bearing assembly consisting Nos.
of a metal piston supported by a disc,
PTFE pads providing sliding surfaces
15
0.08
1.50
0.50
1.00
16
Chapter-14
Superstructure
Preamble:
1. The rate for the wearing coat has been analysed as under:
a) Cement concrete wearing coat
b) Ashphaltic concrete wearing coat
c) Bitumen mastic wearing coat
The item may be selected as per approved design. In case the thickness of wearing
coat is different from that analysed, the rate for the desired thickness may be worked
out on pro-rata basis.
2. The rate analysis has been done both for RCC Railing and M.S. Railing, which can be
adopted as per approved design.
3. The length of drainage spout has been provided in such a way that it is connected to
the drainage system on the ground in case of flyovers and there is no splashing of
water on the structure in case of bridges.
4. The rate for anti-corrosive treatment is required to be ascertained from firms
specialised in this work. In this connection Circular No. RW/NH-34041/44/91 -S&R
dated 21.3.2000 of Ministry of Road Transport and Highways may be referred for
further details,
5. Expansion joints involving movements exceeding 40 mm are specialised readymade
items commercially produced by reputed firms with imported technology and parts. The
rates for such joints are required to be ascertained from the firms pre-qualified by the
Ministry.
6. The rate analysis for pre-cast and pre-tensioned girders has also been included.
7. The rate analysis for prestressed cement concrete of M 60 grade has also been
included which can be adopted for bridges with innovative design/construction.
8. MoRT&H letter No. RW/NH-34059/1/96 S&R dated 30.11.2000 and subsequent
corrigendum dated 25.1.2001 may be referred for detailed specifications and provisions
for various types of expansion joints.
9. Supply of new type of expansion joint may be obtained on the basis of competitive
bidding form amongst the suppliers pre-qualified by the Ministry of Road Transport and
Highways. Further, a warranty of 10 years of trouble free performance may be insisted
from the suppliers.
10. For bridges having wide deck/span length of more than 120 m or/and involving complex
movements/ rotations in different directions/planes, provision of special type of modular
expansion joints such as swivel joists joints are required for which firms specialised in
this field may be consulted. Such cases will require prior approval of Ministry.
Sr.
No.
14.1.
Reference to
Description
Unit
MoRT&H
specifications
1500, 1600 & Furnishing and placing reinforced/
1700
prestressed
cement
concrete
in
superstructure as per drawing and
Technical Specifications
Quantity
A. RCC Grade M 20
Case-1: Using Concrete Mixer
Unit = 1 cum
Taking output =15 cum
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
5.12
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.50
20.00
c) Machinery
Concrete mixer (cap.0.40/0.28 cum) Hour
Generator 33 KVA
Hour
d) For formwork and staging add the
following:
i) For solid slab superstructure, 20-30
per cent of (a+b+c)
Height upto 5m
- 20 per cent
Height 5 m to 10 m
- 25 per cent
Height above 10m
- 30 per cent
ii) For T-beam & slab, 25-35 per cent of
(a+b+c)
Height upto 5m
- 25 per cent
Height 5 m to 10 m
- 30 per cent
Height above 10m
- 35 per cent
6.00
6.00
Rate
Rs.
e) Overheads @
% on (a+b+c+d)
f) Contractor's profit @
(a+b+c+d+e)
% on
MT
Cum
Cum
Cum
40.92
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
c) Machinery
Batching plant (assuming output
20 cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
d) For formwork and staging add the
following:
i) For solid slab superstructure, 20-30
per cent of (a+b+c)
Height upto 5m
- 20 per cent
Height 5 m to 10 m
- 25 per cent
Height above 10m
- 30 per cent
ii) For T-beam & slab, 25-35 per cent of
(a+b+c)
Height upto 5m
- 25 per cent
Height 5 m to 10 m
- 30 per cent
Height above 10m
- 35 per cent
e) Overheads @ % on (a+b+c+d)
f) Contractor's profit @
3
% on
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
B. RCC Grade M 25
Case-l: Using Concrete Mixer
Unit = 1 cum
Taking output =15 cum
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
5.99
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.86
1.50
20.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) Hour
Generator 33 KVA
Hour
d) For formwork and staging add the
following:
i) For solid slab superstructure, 20-30
per cent of (a+b+c)
Height upto 5m
- 20 per cent
Height 5 m to 10 m
- 25 per cent
Height above 10m
- 30 per cent
ii) For T-beam & slab, 25-35 per cent of
(a+b+c)
Height upto 5m
- 25 per cent
Height 5 m to 10 m
- 30 per cent
Height above 10m
- 35 per cent
e) Overheads @
% on (a+b+c+d)
f) Contractor's profit
(a+b+c+d+e)
on
6.00
6.00
Unit = cum
Taking output =120 cum
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
47.95
54.2
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.84
3.00
18
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km
Hour
15.00
30.L
6.00
c) Machinery
Batching plant (assuming output 20
cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
d) For formwork and staging add the
following:
I) For solid slab superstructure, 20-30
per cent of cost of concrete
Height upto 5 m
- 20 per cent
Height 5 m to 10 m
- 25 per cent
Height above 10m
- 30 percent
ii. For T-beam & slab, 25-35 per cent of
(a+b+c)
Height upto 5m
- 25 per cent
Height 5 m to 10 m
- 30 per cent
Height above 10m
- 35 per cent
e) Overheads @
% on (a+b+c+d)
f) Contractor's profit @
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
C. RCC Grade M 30
Case-1: Using Concrete Mixer
Unit = 1 cum
% on
MT
Cum
Cum
Cum
6.10
6.75
8.1
5.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.9
1.50
21.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) Hour
Generator 33 KVA
Hour
6.00
6.00
% on (a+b+c+d)
f) Contractor's profit @
(a+b+c+d+e)
% on
MT
Cum
Cum
Cum
48.79
54.6
64.8
43.2
Mate
Mason
Mazdoor
Day
Day
Day
0.88
3.00
19
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km.
Hour
15.00
300.L
6.00
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
MT
Cum
Cum
Cum
6.33
6.75
8.1
5.4
b) Labour
Mate
Day
0.9
c) Machinery
Batching plant (assuming output 20
cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
d) For formwork and staging add the
following:
i) For solid slab superstructure, 20-30
per cent of cost of concrete
Height upto 5m
- 20 per cent
Height 5 m to 10 m
Height above 10m
- 25 per cent
- 30 per cent
% on
Mason
Mazdoor
Day
Day
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) Hour
Generator 33 KVA
Hour
1.50
21.00
6.00
6.00
MT
Cum
Cum
Cum
50.64
54
64.8
43.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.88
3.00
19
c) Machinery
Batching plant (assuming output 20
cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
MT
Cum
Cum
Cum
Kg
6.45
6.75
8.1
5.4
25.8
% on
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) Hour
Generator 33 KVA
Hour
0.96
2.00
22.00
6.00
6.00
% on (a+b+c+d)
f) Contractor's profit
(a+b+c+d+e)
on
MT
Cum
Cum
Cum
Kg
51.6
54
64.8
43.2
206.4
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.94
3.50
20
c) Machinery
Batching plant (assuming output 20 Hour
10
6.00
cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
Hour
6.00
Hour
t.km.
Hour
15.00
300.L
6.00
MT
Cum
Cum
Cum
Kg
55.80
54
64.8
43.2
223.2
% on
11
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching plant (assuming output 20
cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 km
Lead beyond 1 km, L-lead in kilometre
Concrete pump
d) For formwork and staging add the
following:
i) For
solid
slab/voided
slab
superstructure, 16-26 per cent of cost
of concrete
Height upto 5m
- 16 per cent
Height 5 m to 10m
- 21 percent
Height above 10m
- 26 per cent
ii) For I-beam and slab including
launching of precast girders by
launching truss upto 40m span, 21-31
per cent of cost of concrete
Height upto 5m
- 21 per cent
Height 5 m to 10 m
- 26 per cent
Height above 10m
- 31 per cent
iii) For cast-in-situ box girder, segmental
construction and balanced cantilever,
36-56 per cent of cost of concrete
Height upto 5m
- 36 per cent
Height 5 m to 10 m
- 46 per cent
Height above 10m
- 56 per cent
e) Overheads @
% on (a+b+c+d)
f) Contractor's profit @
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
G. PSC Grade M 50
Unit = 1 cum
Taking output =120 cum
12
% on
Day
Day
Day
0.94
3.50
20
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
Admixture @ 0.4 per cent of cement
MT
Cum
Cum
Cum
Kg
58.80
54
64.8
43.2
235.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.94
3.50
20
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
MT
Cum
Cum
Cum
Kg
63.50
54.00
64.80
43.20
254.00
c) Machinery
Batching plant (assuming output 20
cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 km.
Lead beyond 1 km, L-lead in kilometre
Concrete pump
d) For formwork and staging add the
following:
i) For cast-in-situ box girder, segmental
construction and balanced cantilever,
35-55 per cent of cost of concrete
Height upto 5m
- 35 per cent
Height 5 m to 10 m
- 45 per cent
Height above 10m
- 55 per cent
e) Overheads @
% on (a+b+c+d)
f) Contractor's profit @
(a+b+c+d+e)
% on
13
Mate
Mason
Mazdoor
c) Machinery
Batching plant (assuming output 20
cum/hr)
Generator 100 KVA
Loader
Transit mixer (capacity 4.0 cum)
Lead upto 1 mm
Lead beyond 1 km, L-lead in kilometre
Concrete pump
d) For formwork and staging add the
following:
i) For cast-in-situ box girder, segmental
construction and balanced cantilever,
35-55 per cent of cost of concrete
Height upto 5m
- 35 per cent
Height 5 m to 10 m
- 45 per cent
Height above 10m
- 55 per cent
e) Overheads @ % on (a+b+c+d)
f) Contractor's profit @
(a+b+c+d+e)
% on
Day
Day
Day
0.94
3.50
20
Hour
6.00
Hour
Hour
6.00
6.00
Hour
t.km
Hour
15.00
300.L
6.00
1600
1.05
8.00
0.44
3.00
8.00
% on (a+b)
1800
MT
0.385
42.00
Nos.
2.00
MT
0.125
spacers,
insulation
miscellaneous items
tape
and
b) Labour
i) For making
anchorages
Mate
Blacksmith
Mazdoor
and
fixing
cables,
Day
Day
Day
0.16
1.00
3.00
Day
Day
Day
0.05
0.25
1.00
Day
Day
Day
0.05
0.25
1.00
c) Machinery
Stressing jack with pump
Grouting pump with agitator
Generator 33 KVA
Hour
Hour
Hour
2.50
1.00
3.50
1.00
0.075
d) Overheads @
% on (a+b+c)
14.4.
Note:
2702
MT
deck
slab Day
0.15
c) Overheads @ % on (b)
Mastic Asphalt
Providing and laying 12 mm thick mastic
asphalt wearing course on top of deck
slab excluding prime coat with paving
grade bitumen meeting the requirements
given in Table 500-29, prepared by using
mastic cooker and laid to required level
and slope after cleaning the surface,
including providing anti-skid surface with
bitumen precoated fine grained hard
stone chipping of 9.5 mm nominal size at
the rate of 0.005 cum per 10 sqm and at
an approximate spacing of 10 cm center
to center in both directions, pressed into
surface when the temperature of surfaces
not less than 100C, protruding 1 mm to 4
mm over mastic surface, all complete as
per Clause 515.
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)
(0.869 cum) assuming a density of 2.3
tonnes/cum
a) Labour
Mate
Mazdoor
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm per
hour
Air compressor 250 cfm
Mastic cooker 1 tonne capacity
Bitumen boiler 1500 litres capacity
Tractor for towing and positioning of
mastic cooker and bitumen boiler
c) Material
Base
mastic
(without
coarse
aggregates) = 60 per cent
Coarse aggregate (3.35 mm to 9.5
mm) = 40 per cent
17
Day
Day
Day
0.49
11.00
1.25
Hour
0.06
Hour
Hour
Hour
Hour
0.06
6.00
6.00
1.00
0.39
0.36
0.55
0.036
1.05
18
2703, 1500,
1600 & 1700
Reinforced
Cement
19
0.865
14.7.
2703, 1500,
1600 & 1700
Reinforced
Cement Cum
4.092
MoRT&HSD/202
Cost for 48 m = a
Rate per metre = (a)/48
Note:
14.8.
2703.2
1900
&
MT
MT
MT
MT
2.946
1.012
0.18
0.15
Day
Day
Day
2.80
30.00
40.00
% on (a+b)
21
2705
welder
0.02
0.02
0.02
Day
Day
Day
0.01
0.01
0.20
% on (a+b)
14.10. 2700
22
6.00
6.00
2.00
Day
etc.) Day
Day
c)
4.00
1.00
14.12
Note:
1600
Note:
23
1.00
0.05
Precast-pretensioned Girders
Providing, precasting, transporting and
placing in position precast-pretensioned
concrete girders as per drawing and
Technical Specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M 40
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
Admixture @ 0.4 per cent of cement
HYSD steel.
HT strand with 5 per cent as wastage
and extra length for anchoring
LDO for steam curing
MT
Cum
Cum
Cum
Kg
MT
MT
0.47
0.45
0.54
0.36
1.88
0.1
0.06
Litre
37.00
0.06
0.35
1.40
0.02
0.14
0.50
Day
Day
Day
0.12
1.00
2.00
0.03
0.05
0.60
Day
Day
0.01
0.35
0.01
0.25
0.01
0.06
0.24
c) Machinery
i) At casting yard
Generator 100 KVA
Batching plant @ 20 cum/hour
Transit mixer 4 cum capacity
Concrete pump stationary
Crane 35 tonne capacity
Trailer 30 tonne capacity
Loader
Hour
Hour
Hour
Hour
Hour
Hour
Hour
% on (a+b+c)
25
0.05
0.05
0.10
0.05
0.10
0.10
0.05
0.15
2.5L
0.15
1.00
1.00
Day
Day
Day
0.01
0.05
0.20
Day
Day
Day
0.01
0.25
0.25
% on (a+b)
Crash Barriers
The rate analysis for rigid crash barrier in
reinforced cement concrete, semi-rigid
crash barrier with metal beam and flexible
crash barrier with wire ropes have been
made and included in Chapter-8 on Traffic
and Transportation
14.16. 800
b) Material
Water based paint of approved quality Litres
for cement concrete surface
c) Overheads @
% on (a+b)
26
5.00
Burried joint
Providing and laying a hurried expansion
joint, expansion gap being 20 mm,
covered with 12 mm thick, 200 mm wide
galvanised weldable structural steel plate
as per IS: 2062, placed symmetrical to
centre line of the joint, resting freely over
the top surface of the deck concrete,
welding of 8 mm dia. 100 mm long
galvanised nails spaced 300 mm c/c
along the centre line of the plate, all as
specified in Clause 2604.
Unit = Running metre
Taking output = 12m
a) Labour
Mate
Mazdoor
Mazdoor (skilled)
Day
Day
Day
b) Material
Galvanised M.S. plate 200 mm wide, Kg
12 mm thick @ 94.20 kg/sqm
including 5 per cent wastage
Add 1 per cent of cost of steel plate
cutting, welding consumables and
galvanised nails
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 12m = a+b+c+d
Rate per metre = (a+b+c+d)/12
Note:
14.18. 2605
0.02
0.40
0.20
237.50
Day
Day
Day
b) Material
Copper plate -12m long x 250 mm Kg
wide Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage
@
2.5
percent=1.33
kg/54.73 kg say = 55 kg.
0.04
0.50
0.50
55.00
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 12 m = a+b+c+d
Rate per metre = (a+b+c+d)/12
(ii) Providing and fixing 20 mm thick
compressible fibre board in expansion
joint complete as per drawing and
Technical Specifications
Unit = Running metre
Taking output = 12 m
a) Labour
For carrying, placing & fixing
Mate
Mazdoor
Mazdoor (skilled)
Day
Day
Day
b) Material
20 mm thick compressible fibre board Sqm
12m long x 25 cm deep
Area = 12x0.25 =3 sqm
c) Overheads @
% on (a+b)
0.01
0.10
0.10
3.00
Day
Day
Day
b) Material
Premoulded joint filler 12m long, 20 Sqm
mm thick and 300 mm deep
c) Overheads @
0.01
0.20
0.10
3.60
% on (a+b)
% on (a+b)
Day
Day
Day
0.01
0.10
0.10
Cum
0.012
Tonne 0.001
14.19. 2600
Day
Day
Day
0.052
1.00
0.30
Cum
0.75
Kg
Kg
77.50
113.00
Hour
Hour
0.50
0.50
30
14.20. 2606
Day
Day
Day
b) Material
Supply of elastomeric slab seal M
expansion
joint
assembly
manufactured by using chloroprene,
elastomer for elastomeric slab unit
conforming to Clause 915.1 of IRC: 83
(Part II), complete as per approved
drawings and standard specification
conforming to Clause 2606 of
MoRT&H Specifications
Add 5 per cent of cost of material for
anchorage reinforcement, welding and
other incidentals
c) Overheads @
% on (a+b)
31
0.06
1.0
0.50
12.00
Day
Day
Day
b) Material
Galvanised angle sections 100 mm x Kg
100 mm of 12 mm thickness weldable
structural steel as per IS: 2062, 2 Nos.
of 24 m length each @ 17.7 kg/m and
5 per cent wastage
Add 5 per cent of cost of above for
structural steel for anchorage, welding
and other incidentals
Preformed continuous chloroprene
elastomer or closed cell foam sealing
element with high tear strength,
vulcanised in a single operation for the
full length of a joint to ensure water
tightness
Add 1 per cent of cost of sealing element
for lubricant-cum-adhesive and other
consumables
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 12m = a+b+c+d
Rate per metre = (a+b+c+d)/12
Note:
0.036
0.60
0.30
446.00
Day
Day
Day
b) Material
Supply of complete assembly of strip RM
seal expansion joint comprising of
edge beams, anchorage, strip seal
element and complete accessories as
per approved specifications and
drawings
Add 5 per cent of cost of material for
anchorage reinforcement, welding and
other incidentals
c) Overheads @
% on (a+b)
33
0.05
1.00
0.25
12.00
Note:
14.23. 2600
Day
Day
Day
b) Material
Supply of a modular strip/box seal RM
joint assembly comprising of edge
beams, central beam, 2 modules
chloroprene
seal,
anchorage
elements, support and control system,
all steel sections protected against
corrosion and installed by the
manufacturer or his authorised
representative.
c) Overheads @
% on (a+b)
0.056
1.00
0.40
12.00
Day
Day
Day
b) Material
Supply of a modular strip/box seal RM
joint
assembly
containing
3
modules/cells and comprising of edge
beams,
two
central
beams,
chloroprene
seal,
anchorage
elements, support and control system,
all steel sections protected against
corrosion and installed by the
manufacturer or his authorised
representative.
c) Overheads @
% on (a+b)
35
0.07
1.25
0.50
12.00
Note:
36
Chapter-15
River Training and Protection Works
Preamble:
1. Three types of aprons on riverbed as under have been catered.
a) Boulder apron laid dry
b) Boulder apron laid in wire crates
c) Apron laid in cement concrete blocks on M 15
2. A toe wall for toe protection of pitching can be either in dry rubble masonry (uncoursed)
or in nominal mix cement concrete M 15. Depending upon the design, the rates may be
adopted under respective clauses.
3. Flooring has been proposed in dry rubble stone, rubble stone laid in C M 1:3 and with
cement concrete blocks M 15.
4. Curtain walls proposed are of following two types:
a) Course rubble stone masonry (1st sort) in C M 1:3.
b) Cement concrete M 15 grade.
5. The rate analysis for gabion structures comprising of stone boulders laid in wire crates
have been included. Such structures are suited as retaining structures and for erosion
control in river training works especially for situations where some settlement of
foundation in anticipated. These structures can adjust in minor settlements, being
flexible structures, without losing their functional requirement.
Sr.
No.
15.1.
Reference to
MoRT&H
Description
specifications
2503
Providing and laying boulders apron on
river bed for protection against scourwith
stone boulders weighing not less than 40
kg each complete as per drawing and
Technical Specifications
Unit
Quantity
Cum
Cum
1.00
0.20
Rate
Rs.
Mate
Mason
Mazdoor
c) Overheads @
Day
Day
Day
0.04
0.35
0.75*
Sqm
22
Cum
Cum
5.63
1.13
Day
Day
Day
0.18
1.50
*3.00
% (a+b)
d) Contractor's profit @
% (a+b+c)
15.2.
Note:
2503
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
15.3.
Note:
2503
Cum
1.00
Cum
Cum
1.00
0.20
2504
Mate
Mason
Mazdoor for laying stones, filling of
quarry spalls
Day
Day
Day
0.04
0.35
0.75
Cum
1.00
Cum
1.20
Day
Day
Day
0.05
0.25
1*
c) Overheads @
% on (a+b)
d) Contractor's profit @ % on (a+b+c)
Rate per cum = (a+b+c+d)
B. Cement Concrete Blocks of size 0.3 x
0.3 x 0.3 m cast in cement concrete of
grade M 15
Unit = cum
Taking output = 1 cum
a) Concrete grade M 15
Rate as per item No. 12.8 (A)
Add 2 per cent of cost to account for
nominal surface reinforcement and filling
of granular material in recesses between
blocks
Rate per cum = (a)
15.5.
2504
% on (a+b)
Geotextile Filter
Laying of a geotextile filter between
pitching and embankment slopes on
which pitching is laid to prevent escape of
the embankment material through the
voids of the stone pitching/ cement
concrete blocks as well as to allow free
movement of water without creating any
uplift head on the pitching.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate
Mazdoor
Mazdoor (skilled)
b) Material
Permeable synthetic geotextile
including 5 per cent for overlap and
wastage
c) Overheads @
% on (a+b)
2504.4
Toe Protection
A toe wall for toe protection can either be
in dry rubble masonry in case of dry
rubble pitching or pitching with stones in
wire crates or it can be in PCC M 15
nominal mix if cement concrete block
have been used for pitching. Rates for toe
wall can be adopted from respective
Clauses depending upon approved
design. The rate for excavation for
foundation, dry rubble masonry and PCC
M 15 have been analysed and given in
5
Day
Day
Day
0.02
0.3
0.10
Sqm
11.00
respective chapters.
15.8.
2505
Cum
0.33
Cum
Cum
Cum
1.00
0.20
Day
Day
Day
0.08
0.50
1.50
Cum
1.00
% on (b+c)
Cum
a) Material
Stone
Stone spalls
Cum
Cum
1
0.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.1
0.5
1.5
2506
% on (a+b)
2507.2
15.11. 2507.2
Cum
Cum
1
0.2
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
0.05
0.25
1.00
% on (a+b)
d) Contractor's profit @
% on (a+b+c)
Day
Day
Day
b) Material
Galvanised steel wire crates of mesh Sqm
size 100 mm x 100 mm woven with 4
mm dia. Gl wire in rolls of required
size.
Stone boulders with least dimension of Cum
200 mm
Stone spalls of minimum size 25 mm
Cum
c) Overheads @
% on (a+b)
15.13. 2503.3
0.28
5.00
2.00
61.00
12.6
2.52
Day
Day
Day
b) Material
Galvanised steel wire crates of mesh Sqm
size 100 mm x 100 mm woven with 4
mm dia
Gl wire in rolls of required size to
cover 6.00 cum
Stone boulders with least dimension of Sqm
200mm
Stone spalls of minimum size 25 mm
Cum
c) Overheads @
% on (a+b)
10
0.14
2.50
1.00
65.00
6.00
1.2
Chapter-16
Repair and Rehabilitation
Preamble:
1. Removal of cement concrete wearing coat and asphaltic wearing coat has been
proposed with pneumatic breakers.
2. The rate for external prestressing has been analysed for three different spans of 25,50
and 100 m.
3. Sealing of cracks has been proposed with cement grout, cement mortar (1:1) grout and
epoxy grout by injecting with grout pump through nipples..
4. Bonding of new concrete with old concrete is proposed with epoxy resin.
5. The repair and replacement of following structures has been included:
a)
b)
c)
d)
e)
Sr.
No.
16.1.
Bridge bearings
Expansion Joints
Concrete Railing
Mild steel railing
Crash barrier
Reference to
MoRT&H
Description
Unit
specifications
2809
Removal of existing cement concrete
wearing coat including its disposal
complete as per technical specification
without causing any detrimental effect to
any part of the bridge structure and
removal of dismantled material with all lifts
and lead upto 1000 m
Quantity
Day
Day
b) Machinery
Air Compressor 250 cfm with Hour
pneumatic breaker/jack hammer along
with accessories
Tractor-trolley
Hour
c) Overheads @
% on (a+b)
0.06
1.00
1.00
0.50
Rate
Rs.
2809
Day
Day
b) Machinery
Air compressor 250
pneumatic breaker
Tractor-trolley
cfm
0.03
0.75
with Hour
0.75
Hour
0.40
Kg
Cum
Kg
16.00
0.04
2.00
Kg
Kg
0.67
0.64
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
16.3.
2807
b) Labour
Mate
Mason
Mazdoor
Day
Day
Day
c) Machinery
Compressor with guniting equipment Hour
along with accessories
d) Overheads @
0.01
0.04
0.14
0.10
% on (a+b+c)
2800
% on (a+b)
2806
1.00
Day
Day
Day
0.01
0.08
0.08
Day
0.04
A. Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage Kg
Admixtures (anti shrinkage compound)
@ 20 per cent of cost of cement
b) Labour
Mate
Mazdoor Skilled
Mazdoor
c) Machinery
Grout pump
accessories
d) Overheads @
Day
Day
Day
with
agitator
and Hour
1.10
0.08
0.10
0.10
0.1
% on (a+b+c)
Day
Day
Day
c) Machinery
Grout pump
accessories
with
d) Overheads @
% on (a+b+c)
agitator
and Hour
2800
0.55
0.55
0.08
0.10
0.10
0.10
Day
Day
Day
b) Material
Pre-packed polymer concrete based Kg
on
epoxy system complete with
curing
compound,
initiator
and
promoter including 5 per cent wastage
c) Machinery
Grout pump
accessories
with
d) Overheads @
% on (a+b+c)
agitator
and Hour
0.06
0.75
0.75
315.00
2.00
16.7.
Note:
2803
Kg
1.10
b) Labour
Mate
Mazdoor (skilled)
Mazdoor
Day
Day
Day
0.08
0.10
0.10
c) Machinery
Epoxy Injection gun
d) Overheads @
Hour
0.10
% on (a+b+c)
2804
2.50
2.20
2.00
Day
Day
Day
% on (a+b)
2807
0.04
0.50
0.50
Day
Day
Day
0.04
0.50
0.50
b) Machinery
Air compressor 250 cfm
Shotcreting equipment
Water tanker 6 KL capacity
Hour
Hour
Hour
1.00
1.00
0.02
c) Material
Cement
Sand
Coarse aggregate of size 4.75 mm
Quick setting compound
Water
Kg
Cum
Cum
Kg
KL
120.00
0.15
0.15
2.50
0.10
d) Overheads @
% on (a+b+c)
1.4
12.00
Day
7
0.04
Skilled labour
Unskilled labour
c) Overheads @
Day
Day
0.50
0.50
% on (a+b)
Day
Day
Day
% on (a+b)
: 25 m
: 4 no.
: 8 no.
Unit=MT
Taking output = 1 MT
Assume 12.7 mm dia. Strand in 12T13
system. Weight 9.42 kg/m of cable.
8
0.04
0.50
0.50
a) Material
HTS strand including 5 per cent
wastage and extra length for jacking
HDPE pipes 75mm dia including 5 per
cent wastage
Cement for grouting
Tube anchorage set complete with
bearing plate, permanent wedges, etc.
Epoxy
MS plates for deviator (where deviator
blocks are not provided)
MT
1.05
RM
112
Kg
Nos.
400.00
8.00
Kg
MT
6.00
2.10
Day
Day
Day
0.24
3.00
3.00
0.44
3
8.00
Day
Day
Day
0.13
0.70
2.65
Day
Day
Day
0.13
0.70
2.65
c) Machinery
Stressing jack with pump
Grouting pump with agitator
Hour
Hour
4.00
1.35
d) Overheads @
% on (a+b+c)
: 50 m
: 4 no.
: 8 no.
Unit=MT
Taking output = 3.10MT
Assume 12.7 mm dia Strand in 19T13
system.
Weight 14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent
wastage and extra length for jacking
HDPE pipes 90 mm dia including 5
per cent wastage
Cement for grouting
Tube anchorage set complete with
bearing plate, permanent wedges, etc
MT
3.1
RM
224
Tonne 1.01
Nos.
8.00
Epoxy
Kg
MS plates for deviator (where deviator MT
blocks are not provided)
10.00
7.00
Day
Day
Day
0.08
8.00
8.00
1.28
7
25.00
0.2
1.50
5
Day
Day
Day
10
Day
Day
Day
0.26
1.50
5
c) Machinery
Stressing jack with pump
Grouting pump with agitator
Hour
Hour
7.00
3
MT
9.28
RM
672
d) Overheads @ % on (a+b+c)
e) Contractor's profit @ % on (a+b+c+d)
Cost for 3.10 MT = a+b+c+d+e
Rate per MT = (a+b+c+d+e)/3.10
16.14. 2810
: 100 m
: 6 no.
: 12 no.
Unit=MT
Taking output = 9.28 MT
Assume 12.7 mm dia. Strand in 19T13
system. Weight 14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent
wastage and extra length for jacking
HDPE pipes 90 mm dia including 5
per cent wastage
Cement for grouting
Tube anchorage set complete with
bearing plate, permanent wedges, etc
Epoxy
MS plates for deviator (where deviator
blocks are not provided)
Add 20 per cent cost of material for other
materials, like, lead sheet, sleeves,
deviator fixtures, etc.
b) Labour
i)
Tonne 3.04
12.00
Nos.
Kg
MT
14.00
20.00
Mate
Semi-skilled
Mazdoor
Day
Day
Day
1.72
18.00
25.00
4
20
80.00
iii) Forprestressing
Mate/Supervisor
Fitter
Mazdoor
Day
Day
Day
0.0
1.50
6
Day
Day
Day
1
5.00
20
c) Machinery
Stressing jack with pump
Grouting pump with agitator
Hour
Hour
10.00
10
d) Overheads @
% on (a+b+c)
3.00
0.64
4.00
12.00
0.15
Cost of bearing
c) Overheads @ % on (a+b)
Nos.
16.16. 2808
Overheads @
% on (a+b)
16.17.
Replacement
of
Expansion
complete as per drawings
Unit= 1 Running metre
Taking output = 12 Running metre
a) Material
13
joints
3.00
0.64
4.00
12.00
0.15
As
per
actuals
9.6
3.6
0.26
6.00
0.50
% on (a+b)
16.18.
of
Damaged
Concrete
disposal
of Hour
% on (a+b)
0.20
5.00
1.00
superstructure
16.19.
disposal
of Hour
0.40
10.00
1.00
% on (a+b)
16.20.
disposal
% on (a+b)
15
of Hour
0.16
4.00
1.00
16.21.
Day
Day
0.04
1
b) Material
M 30 grade concrete
Cum
This may be priced based on the rate
given
in
the
Chapter
on
Superstructure.
c) Overheads @
0.3
% on (a)
Cum
0.1
HYSD reinforcement
Rate as per items 14.2
b) Labour *
Mate
Mazdoor
*
MT
0.013
Day
Day
0.016
0.2
c) Overheads @
% on (b)
Day
Day
Day
c) Overheads @ % on (a+b)
d) Contractor's profit @ % on (a+b+c)
Cost of repair for 10 m = a+b+c+d
Cost of metres (a+b+c+d)/10
17
29
10
1
0.016
0.2
0.2
Chapter-17
Usage Rates of Plant and Machinery
Sr.
No.
Description of
Machine
Output of Machine
Activity
Unit
Output
Unit
Rates
1.
Dozer D-50-A 15
Spreading
Cutting
Clearing
cum/hour
cum/hour
cum/hour
200
100
150
per hour
1423
2.
Dozer D-80-A 12
Spreading
Cutting
Clearing
cum/hour
cum/hour
cum/hour
300
150
250
per hour
2400
3.
Clearing
Motor Grader 3.35 metre Spreading
blade
GSB
WMM
cum/hour
cum/hour
cum/hour
cum/hour
200
200
50
50
per hour
1545
4.
Soil Ordinary
Hydraulic Excavator of 1
Soil Marshy
cum bucket
Soil Unsuitable
cum/hour
cum/hour
cum/hour
60
60
60
per hour
840
5.
Soil loading
Front end loader 1 cum
Aggregate
bucket capacity
loading
cum/hour
cum/hour
60
25
per hour
520
per km
15.6
per tonne,
km
1.74
per hour
200
6.
Tipper-5 cum
Transportation of Capacity in
soil, GSB, WMM,
cum
Hotmix etc.
Earth/Soil
GSB
WMM
7.
8.
9.
Water Tanker
Water Transport
5.5
cum/hour
cum/hour
cum/hour
100
60
60
per hour
cum/hour
cum/hour
70
25
per hour
297
Capacity in
KL
per km
15.6
994
Description of
Sr.
No.
Machine
Output of Machine
Activity
Unit
Output
Unit
Rates
Capacity in
HP
50
per hour
234
10. Tractor
Pulling
11. Rotavator
Scarifying
cum/hour
25
per hour
11
12. Ripper
Scarifying
cum/hour
60
per hour
18
General Purpose
capacity in
cfm
170/
250
per hour
206
Wet Mix
cum/hour
25
per hour
111
Surface Cleaning
sqm/hour
1250
per hour
230
Applying bitumen
sqm/hour
tack coat
1750
per hour
692
Applying emulsion
sqm/hour
tack coat
1750
per hour
516
18.
Hotmix Plant
capacity
-120
TPH DBM/BM/SDC/
Premix
cum/hour
40
per hour
15100
19.
Hotmix Plant-1
capacity
00
TPH DBM/BM/SDC/
Premix
cum/hour
30
per hour
11167
20.
cum/hour
25
per hour
8930
21.
cum/hour
17
per hour
7150
22.
40
per hour
1725
23.
Paver Finisher
100 TPH
40
30
per hour
per hour
629
629
1500
per hour
1700
Surface Dressing
sqm/hour
Sr.
No.
Description of
Machine
Unit
Output
Unit
Rates
Rolling of Aspalt
cum/hour
Surface
30
per hour
738
Rolling of Asphalt
cum/hour
Surface
25
per hour
802
Repair
holes
cum/hour
per hour
585
Bitumen Spraying
capacity
in litre
1500
per hour
128
Producing GSB
cum/hour
40
per hour
670
Mastic
Coat
Wearing capacity
in tonne
per hour
40
20
13
per hour
per hour
1440
1200
Transportation of
cum/hour
Concrete Mix to
cum/hour
Site
4.5
3
per hour
per hour
600
550
33
22
per hour
165
per hour
per hour
per hour
825
550
230
33.
of
pot-
of cum/hour
cum/hour
Cranes
a) 80 tonnes
34.
b) 35 tonnes
c) 3 tonnes
Lifting Purpose
Lifting Purpose
Lifting Purpose
For
Pouring capacity
Concrete
in cum
per hour
10
Kerb Making
Rm/hour
80
per hour
200
Concrete Mixer
37. a) 0.4/0.28 cum
b) 01 cum
2.5
7.5
per hour
per hour
150
150
Sr.
No.
Description of
Machine
Output of Machine
Activity
Unit
38.
39.
Concrete Paver
with 40 HP Motor
41.
Prestressing Jack
Pump & Access
Crushing of Spalls
Crushing of Spalls
with Stressing of
Wires/Stands
TPH
TPH
Output
Unit
2 to 3
per hour
3525
20
per hour
1850
100
200
per hour
per hour
5590
11760
per hour
83
Steel
Rates
Generator
42. a) 100KVA
b) 33 KVA
Generation
Electric Energy
of
KVA
KVA
100
50
per hour
per hour
450
240
Pneumatic Sinking of
Wells
cum/
hour
1.5 to
2.00
per hour
2690
14.5
1.6
capacity/
cum
4.5
per km
per tonne
knr
Sqm/hour
100
per hour
60
Sqm/hour
2700
per hour
650
46.
Mobile
Slurry
Equipment
Road Marking
laying
Note : The usage rates given above are for the base year 2001-2002. For subsequent
years, escalation is required to be added depending upon the market situation.