Work Method Track Shifting 5 CM 20 CM
Work Method Track Shifting 5 CM 20 CM
Work Method Track Shifting 5 CM 20 CM
Preparation work
1.1. Verify contract and specification
1.2. Confirmation drawing and submit to engineer.
1.3. Subgrade preparation already finish
1.4. Material already approved by Engineer
1.5. Material already Stocking
2.
Site Survey
2.1. Survey and Stackingout every 10 m
2.2. Coordination with Civil section, Signal section, and OHC section
3.
Safety
3.1. Safety for manpower Train watcher standby on working time.
3.2. Safety for train operation Accordance with PT.KAI regulation.
3.3. Safety for transportation material and equipment Coordination with PT. KAI ( Train Dispatcher ).
4.
Excecution work
4.1. Preparation track shifting day time
4.1.1.
4.1.2.
Measure and marking on the bottom rail by paint marker for shifting.
4.1.3.
5.
4.2.1.
4.2.2.
Figg.4.3.1
Att-4-Page 1 of 4
Att-4-Page 2 of 4
Att-4-Page 3 of 4
Att-4-Page 4 of 4