RAILWAY ELECTRIFICATION AND DOUBLE-DOUBLE TRACKING OF JAVA MAIN LINE PROJECT

PACKAGE B1: RAILWAY FACILITY CONSTRUCTION FOR BEKASI TO CIKARANG

Table of Interface Issues

No. Item Description Interfacing


Party

Proposed Action

Coordination with
Civil Works
Civil Works for access
to Station area and
arrangement of works

1. Coordination shall be required for delivery/access routes


based on access dates and work progress.
2. Coordination of traffic regulation among the Contractors
shall be necessary especially for adjacent major roads and
entrance gates.
3. Minimum impact on works of interfacing parties shall be
considered to avoid any significant delay.
4.Mutual understanding and keep good communication and
coorporation in work schedule.
5. Coordination shall be required for arrangement Stockpiled
area in order to do not disturb other work section.

Coordination with
PT.KAI for Work
Permission

1.

PT.KAI

2.
3.

Turnouts
Installation,Rail
Replacement

Signal

Track Alignment,
Track Center

OHC

1.
2.
3.

1.
2.
3.

Perform Presentation to describe work method. Obtaining


Approval for Telegram ( Day work and Night Work,
Windows Time, Open and Closure Track )
Minimum impact on works of interfacing parties shall be
considered In order to avoid accident, minimize Train trip
traffic delay
Coordination shall be required for using wagon
Coordination shall be required for installation of Turnout
Includes : point machines, IRJ, Install Rail bonding
Tongue Clamp for necessary temporary lock
Mutual understanding and keep good communication and
coorporation in work schedule
Coordination shall be required to determine for track
alignment and Overhead Feeder wire
Coordination shall be required to Determine Clearence
gauge for Concrete Pole
Mutual understanding and keep good communication and
coorporation in work schedule

Att-7-Page 1 of 1