Lead Chart

Lead in
Km.

Total Cost
per trip

1
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
6.00
7.00
8.00
9.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
45.00
50.00
60.00
70.00
80.00
90.00
100.00
125.00
150.00
175.00
200.00

Task per
trip
Unit Per
2
374.36
412.37
449.51
485.48
522.37
557.80
593.34
628.54
663.14
697.74
767.11
835.62
904.23
970.21
1033.88
1282.63
1598.75
1914.50
2236.11
2395.09
2691.24
2983.84
3271.34
3866.97
4461.64
5057.71
5646.97
6242.70
7019.06
8342.23
9670.09
10957.30

Lime
Sand,
Aggregate Rubble Excavated
murum aggregate 40 mm and
stone
rock
earth,
below 40
above
rubbish mm size,
manure brickbat,
concrete
timber
blocks
6.00 Cum 5.00 Cum 4.25 Cum 4.25 Cum 3.00 Cum

Tar
Steel,
bitumen
Cement
roofing
R.C.C.
and
block, A.C.
flooring, pipe, G.I.
asphalt
Sheet
4.60 MT.

Per Cum
3
62.39
68.73
74.92
80.91
87.06
92.97
98.89
104.76
110.52
116.29
127.85
139.27
150.70
161.70
172.31
213.77
266.46
319.08
372.68
399.18
448.54
497.31
545.22
644.49
743.61
842.95
941.16
1040.45
1169.84
1390.37
1611.68
1826.22

Per MT.
8
81.38
89.64
97.72
105.54
113.56
121.26
128.99
136.64
144.16
151.68
166.76
181.66
196.57
210.91
224.76
278.83
347.55
416.19
486.11
520.67
585.05
648.66
711.16
840.65
969.92
1099.50
1227.60
1357.11
1525.88
1813.53
2102.19
2382.02

Per Cum
4
74.87
82.47
89.90
97.10
104.47
111.56
118.67
125.71
132.63
139.55
153.42
167.12
180.85
194.04
206.78
256.53
319.75
382.90
447.22
479.02
538.25
596.77
654.27
773.39
892.33
1011.54
1129.39
1248.54
1403.81
1668.45
1934.02
2191.46

Per Cum
5
88.08
97.03
105.77
114.23
122.91
131.25
139.61
147.89
156.03
164.17
180.50
196.62
212.76
228.28
243.27
301.80
376.18
450.47
526.14
563.55
633.23
702.08
769.73
909.87
1049.80
1190.05
1328.70
1468.87
1651.54
1962.88
2275.32
2578.19

Per Cum
6
88.08
97.03
105.77
114.23
122.91
131.25
139.61
147.89
156.03
164.17
180.50
196.62
212.76
228.28
243.27
301.80
376.18
450.47
526.14
563.55
633.23
702.08
769.73
909.87
1049.80
1190.05
1328.70
1468.87
1651.54
1962.88
2275.32
2578.19

Per Cum
7
124.79
137.46
149.84
161.83
174.12
185.93
197.78
209.51
221.05
232.58
255.70
278.54
301.41
323.40
344.63
427.54
532.92
638.17
745.37
798.36
897.08
994.61
1090.45
1288.99
1487.21
1685.90
1882.32
2080.90
2339.69
2780.74
3223.36
3652.43

Bricks
empty
cement
bags

Tiles not
round roof
tiles

Steam
Coal

Matting
bamboos,
ballies,
cielling
rubber,
P.V.C. pipe

7.00 MT.

200 Nos.

3200 Nos.

5.50 MT.

3.00 MT.

Per MT.
9
53.48
58.91
64.22
69.35
74.62
79.69
84.76
89.79
94.73
99.68
109.59
119.37
129.18
138.60
147.70
183.23
228.39
273.50
319.44
342.16
384.46
426.26
467.33
552.42
637.38
722.53
806.71
891.81
1002.72
1191.75
1381.44
1565.33

1000 Nos. 1000 Nos.


10
11
187.18
116.99
206.18
128.86
224.75
140.47
242.74
151.71
261.18
163.24
278.90
174.31
296.67
185.42
314.27
196.42
331.57
207.23
348.87
218.04
383.55
239.72
417.81
261.13
452.11
282.57
485.10
303.19
516.94
323.09
641.32
400.82
799.37
499.61
957.25
598.28
1118.05
698.78
1197.54
748.46
1345.62
841.01
1491.92
932.45
1635.67
1022.29
1933.48
1208.43
2230.82
1394.26
2528.85
1580.53
2823.48
1764.68
3121.35
1950.84
3509.53
2193.46
4171.11
2606.95
4835.05
3021.90
5478.65
3424.16

Per MT.
12
68.07
74.98
81.73
88.27
94.98
101.42
107.88
114.28
120.57
126.86
139.47
151.93
164.40
176.40
187.98
233.21
290.68
348.09
406.56
435.47
489.32
542.52
594.79
703.09
811.21
919.58
1026.72
1135.04
1276.19
1516.77
1758.20
1992.24

Per MT.
13
124.79
137.46
149.84
161.83
174.12
185.93
197.78
209.51
221.05
232.58
255.70
278.54
301.41
323.40
344.63
427.54
532.92
638.17
745.37
798.36
897.08
994.61
1090.45
1288.99
1487.21
1685.90
1882.32
2080.90
2339.69
2780.74
3223.36
3652.43