Professional Documents
Culture Documents
Hairul Amri Project Charter PDF
Hairul Amri Project Charter PDF
TABLE OF CONTENTS
1 INTRODUCTION
1.1
EXECUTIVE SUMMARY
2.1
BUSINESS BACKGROUND
2.2
BUSINESS NEED
2.3
3 PROJECT SCOPE
3.1
OBJECTIVES
3.2
MAJOR DELIVERABLES
3.3
MILESTONE
3.4
4 RISK ANALYSIS
4.1
RISK ANALYSIS
4.2
MITAGATION
5 BUDGET ESTIMATE
5.1
MAJOR STAKEHOLDER
5.2
PROJECT ROLE
5.3
COMMUNICATION
10
7 PROJECT ORGANIZATION
11
7.1
12
13
9 REFERENCE LIST
14
Page 2 of 14
INTRODUCTION
1.1
EXECUTIVE SUMMARY
Pagoh RSA water supply in KM 34.4 North Bound Expressway, Since 2015 the
Pagoh RSA having several times of water shortage especially during peak hours &
peak season. The existing system was damaged because of the corrosion due to
ageing pipeline, panel tank & insufficient storage.
Pagoh RSA water supply upgrading is needed to fulfill the consumer usage
2.1
BACKGROUND
Rest and Service Areas or better known as the RSA or R&R are facilities that provide
traveller a stop point during their long distance trip. Located every 80 to 100 kilometers, these
facilities are to ensure every highway user is made to feel as comfortable as possible to
enjoy their journey. This facilities provide toilets, food stalls and offer more than just a pit stop
for the weary traveller. Some of the available amenities include children's playground, petrol
stations, the prayer room for Muslims, auto-teller machines (ATM), rest shelters, public
telephones and air-conditioned restaurants.
However,Pagoh RSA recently facing a several water shortage problem, this matter affecting
the reputation of this RSA & PLUS BERHAD. It also bring a huge impact to the consumer
who come & visit this area and effecting most of restaurant owner & company that running
their business there.Most of the consumer avoiding to stop by this RSA due to this matter
causing them having a difficulty to use the facilities like toilet,prayer room & the business
entrepreneur to operate their business. Its also causing a huge loss for the rental profit to
PLUS BERHAD.
As a solution to this matter after several discussion with Management of Pagoh RSA, a
proposal have been drawn out to upgrade this RSA water supply system in order to solve all
these matters.
The Existing Storage Tank only can store until 10,000 gallon per tank & the
pipeline was corroded & have leakage.
The average current usage perday are 15,000 gallon per day which is 50% higher
than the storage amount.
The existing pipeline are corroded & leaking due to ageing of the material.
The existing pressure pump are not relevant any more to support the pressure that
we need to supply the water to new & larger diameter pipeline.
Need to be replace when we replace the tank
We are proposing for the water supply system upgrade in Pagoh RSA IN KM
146.6 North South Expressway, we also propose to start the upgrading works
after the festive season (school holiday) based on previous yearly consumer
usage record its the lowest usage of the expressway, from 15th January 2016 to
Page 3 of 14
the dateline estimation, the estimation for the project duration will 60days from the
commencement date & the project budget estimation will be around RM
326,500.00.
2.2
BUSINESS NEED
The water supply is a consumer need that we have provide in order to increase the
number of consumer visiting this RSA that will contribute to restaurant & show our
responsibility to the consumer to provide a well manage facilities.
The water in the supply network need to be maintained at positive pressure to ensure that
water reaches all parts of the network, that a sufficient flow is available at every take-off
point
The water is typically pressurized by pumps that pump water in to storage tanks
constructed at the highest local point in the network. One network may have several such
supply tank & sub tank directly been supply by the service reservoirs
Water supply networks are part of the master planning of communities, counties, and
municipalities. Their planning and design requires the expertise of resident engineer
& civil engineers, who must consider many factors, such as location, current demand,
future growth, leakage, pressure, pipe size, pressure loss, fire fighting flows, etc.
using pipe network analysis and other tools.
2.3
conviction, be liable to a fine not exceeding fifty thousand ringgit or to imprisonment for a
term not exceeding six month or to both
3.1
PROJECT SCOPE
OBJECTIVES
The objectives of the water supply system upgrading in Pagoh RSA IN KM 146.6 North
South Expressway as follows:
3.2
To increase the amount of the water supply in sufficient unit 50% higher than current
storage
To supply a clean water for the needs of public health
To supply with sufficient speed (pressure)
To reserved sufficient amount due the shortage of main source of water supply
company
To reduce the maintenance cost
Increase the
MAJOR DELIVERABLES
The following table presents the major deliverables that the projects product, service or
result must meet in order for the project objectives to be satisfied.
Major Deliverable
Deliverable Description
Project Charter
Project Schedule
Requirements Review
Design Review
Deployment Plan
Page 5 of 14
3.3
EXECUTIVE MILESTONES
For Pagoh water supply upgrading projects, these milestones could be used to complete
the Funding Plan/Cost and Schedule.
Executive Milestones
Pre commissioning
Demolishing of Existing
Existing Panel Tank
Existing Pipeline
Pressure Pump
17th January
Duration : 15days
Duration : 15days
Duration : 1 day
TIMELINE
Summary for project duration
Project Plan &
Inspection by Plus
Start work
Replacement
Expertise
Page 6 of 14
Completed
3.4
CONSTRAINTS
The will be a time constraints to developing a water supply system. The time estimation
for daily storage that we could supply to RSA area.
This section identifies any limitation that must be taken into consideration prior to the
initiation of the project.
The time estimation is needed to monitor a storage record for each day (so we could
know the real-time usage for data collection purposed)
This data collection will be useful for any next upgrading works, example like toilet or
extension of RSA area.
Example : if the next upgrading need extra 2,000 gallon of water per day,
In advanced we already know that our storage are sufficient supply or not.
Legal The Service must meet The Local authority requirement
Resources - End-user will not be available for testing during December 2016 and
January 2017.
Dependencies
This project delivers a service,& result that will be released with another new
improved, water supply that will effect the tenant in this RSA for their production or
Operation.
Page 7 of 14
RISK ANALYSIS
4.1
INTERNAL RISK
The risk of several major water shortage due to installation of the replacement item, may
effect the supply rate during the project. This is List the risks that the project sponsor
should be aware of before making a decision on funding the project, including risks of not
funding the project
Risk
Details
Water shortage
-Risk for not doing the
Project
Water shortage
-Risk for not doing the
Project
4.2
MITIGATION PLAN
In order to mitigate this risk we will prepare a mobile supply tank that equivalent the
current supply amount.
Safety briefing & safety monitoring will be held by the Safety Officer.
Page 8 of 14
BUDGET ESTIMATE
No. Item
Budget
Preliminary
RM
Demolishing
RM 10,000.00
Replacement
RM 150,000.00
FRP tank
Pipe line
Pressure pump
5.1
2,500.00
RM 162,500.00
MAJOR STAKEHOLDER
i)
5.2
COMMUNICATION
OBJECTIVE OF COMMUNICATIONS:
To Update sponsor on status of the project, issue, risk & expectation management
communication to the team & stakeholder.
Primary communication methods :
Meeting
Status Reports
.
LINE OF COMMUNICATION :
No. NAME
ROLE
HAIRUL AMRI
PROJECT MANAGER
NIZAM ABU
PROJECT EXECUTIVE
YUSAINI ALI
PROJECT MONITOR
SHAMUGAN
SAFETY OFFICER
Page 9 of 14
140
120
100
storage
80
Maintainance
60
Shortage
40
20
0
1st Qtr
st
2nd Qtr
3rd Qtr
th
4th Qtr
From 1 qtr to 4 qtr this chart show that the shortage when higher drastically & the main
concern is on the storage & maintenance issue that cost a lot budget loss. The priority to
proceed on this proposal is high level.
Page 10 of 14
PROJECT ROLE
ROLES AND RESPONSIBILITIES
This section describes the key roles & line of communication supporting the project.
Name &
Organization
Project Role
Project Responsibilities
Project Sponsor
YUSAINI ALI
PLUS BERHAD
Project
Monitor/PLUS
Monitor
HISHAM AHMAD
Contracting Officer
Project Executive
HAIRUL AMRI
PLUS BERHAD
Project Manager
STEVEN ROGER
Business Steward
Technical Steward
Person who is responsible for the technical dayto-day aspects of the system including the details
PLUS BERHAD
PLUS BERHAD
NIZAM ABU
PLUS BERHAD
PLUS BERHAD
WONG AIK
CHONG
Page 11 of 14
Name &
Organization
PROPEL BERHAD
Project Role
SHAMUGAN
Safety Officer
PROPEL BERHAD
Project Responsibilities
of system development. The Technical Steward
is responsible for providing technical direction to
the project.
Person who is responsible for playing the lead
role for maintaining the projects information
security.
Page 12 of 14
The undersigned acknowledge they have reviewed the project charter and authorize and
fund the Water Supply System Upgrading in Pagoh in KM 146.6,North South
Expressway project. Changes to this project charter will be coordinated with and
approved by the undersigned or their designated representatives.
Business Steward,
Signature:
Date:
Print Name:
Title:
Role:
Project
Sponsor
Date:
Signature:
Print Name:
Title:
Role:
Project
Manager
Signature:
Date:
Print Name:
Title:
Role:
Page 13 of 14
IN TEXT REFERENCE
Page 14 of 14