Professional Documents
Culture Documents
MC SMPN 3 Kateman
MC SMPN 3 Kateman
KEGIATAN
PEKERJAAN
LOKASI
KECAMATAN KATEMAN
NO
I
URAIAN PEKERJAAN
ANALISA
VOLUME
HARGA
SATUAN (Rp.)
JUMLAH
(Rp)
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
1.00 Ls
450,000.00
450,000.00
1.00 Ls
500,000.00
500,000.00
1.00 Ls
250,000.00
SUB JUMLAH
II
250,000.00
1,200,000.00
PEKERJAAN LANTAI
1 Pek. Cor Lantai Tebal = 10 cm 1 : 2 : 3
19
7.20 M3
959,801.50
SUB JUMLAH
III
6,910,570.80
6,910,570.80
PEKERJAAN DINDING
1 Pek. Cor Tiang Kolom Praktis 10/10 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
19
0.28 M3
959,801.50
268,744.42
- Besi 8 mm
22
45.43 Kg
14,203.02
645,312.61
- Besi 6 mm
22
12.78 Kg
14,203.02
181,453.27
- Bekisting
25
5.60 M2
240,270.95
1,345,517.32
- Beton Campur 1 : 2 : 3
19
0.53 M3
959,801.50
506,775.19
- Besi 10 mm
22
5.42 Kg
14,203.02
77,016.74
- Besi 6 mm
22
22.17 Kg
14,203.02
314,897.02
- Bekisting
25
9.68 M2
240,270.95
2,325,822.80
47
81.31 M2
103,070.28
8,380,912.04
17
162.63 M2
32,352.15
SUB JUMLAH
IV
PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
11
1.06 M3
3,827,997.90
4,055,380.98
12
128.39 M2
49,808.55
6,394,919.73
41
128.39 M2
72,517.10
9,310,470.47
42
26.00 M1
81,179.40
2,110,664.40
14
52.40 M1
38,675.87
2,026,615.59
2.25 M2
321,833.45
SUB JUMLAH
V
724,125.26
24,622,176.43
PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
13
73.04 M2
63,494.10
4,637,609.06
29
73.04 M2
40,394.39
2,950,406.17
15
75.48 M2
119,855.60
SUB JUMLAH
VI
5,261,274.86
19,307,726.28
9,046,700.69
16,634,715.92
HSB
1.00 Bh
2,300,000.00
2,300,000.00
0.46 M3
4,577,483.75
2,087,332.59
33
6.00 Bh
16,821.50
100,929.00
32
2.00 Bh
20,741.50
41,483.00
6.00 M2
321,833.45
1,931,000.70
HSB
5.00 Bh
300,000.00
1,500,000.00
HSB
10.00 Bh
400,000.00
4,000,000.00
33
20.00 Bh
16,821.50
336,430.00
HSB
20.00 Bh
8,981.50
179,630.00
34
20.00 Bh
22,941.50
458,830.00
HSB
10.00 Bh
8,825.30
SUB JUMLAH
88,253.00
13,023,888.29
NO
VII
URAIAN PEKERJAAN
ANALISA
VOLUME
HARGA
SATUAN (Rp.)
(Rp)
PEKERJAAN CAT
1 Pek. Teer/ Residu
35
63.56 M2
17,086.25
1,086,070.40
36
235.67 M2
22,444.50
5,289,387.58
37
88.21 M2
42,238.50
SUB JUMLAH
VIII
JUMLAH
3,725,858.09
10,101,316.06
1.00 Ls
500,000.00
500,000.00
500,000.00
Tembilahan,
2014
Diperiksa Oleh :
PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK)
Dihitung Oleh,
CV. TAMA GRAHA CONSULINDO
(Perancana)
Diketahui Oleh :
PENGGUNA ANGGARAN
Disetujui Oleh,
PEJABAT PEMBUAT KOMITMEN (PPK)
Drs. H. HELMI. D, M. Pd
NIP. 19661231 199703 1 027
PEKERJAAN
LOKASI
KECAMATAN KATEMAN
NO
I
URAIAN PEKERJAAN
ANALISA
VOLUME
HARGA
SATUAN (Rp.)
JUMLAH
(Rp)
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
1.00 Ls
500,000.00
500,000.00
1.00 Ls
500,000.00
500,000.00
1.00 Ls
250,000.00
SUB JUMLAH
II
PEKERJAAN PONDASI
5.63 M3
27,200.00
1.41 M3
13,040.00
18,337.50
5,358.00
7,233,300.00
1,350.00 M
153,000.00
20
0.70 M3
981,305.40
689,980.36
- Beton Campur 1 : 2 : 3
19
2.81 M3
961,639.60
2,704,611.38
- Besi 10 mm
22
536.09 Kg
15,287.68
8,195,632.02
- Bekisting
23
3.75 M2
120,831.38
453,117.68
- Beton Campur 1 : 2 : 3
19
0.95 M3
961,639.60
913,557.62
- Besi 10 mm
22
101.67 Kg
15,287.68
1,554,344.00
- Besi 6 mm
22
27.17 Kg
15,287.68
415,373.83
- Bekisting
25
4.75 M2
240,279.64
1,141,328.29
SUB JUMLAH
III
PEKERJAAN LANTAI
23,472,582.68
- Beton Campur 1 : 2 : 3
19
3.00 M3
961,639.60
2,884,918.80
- Besi 10 mm
22
185.11 Kg
15,287.68
2,829,848.11
- Besi 6 mm
22
77.79 Kg
15,287.68
1,189,155.95
- Bekisting
26
15.00 M2
248,630.08
3,729,451.20
0.47 M3
4,323,124.24
2,012,414.33
6,308,966.72
10
56.00 M2
112,660.12
10
12.00 M2
112,660.12
SUB JUMLAH
IV
250,000.00
1,250,000.00
1,351,921.44
20,306,676.55
PEKERJAAN DINDING
1 Pek. Cor Tiang Kolom Praktis 10/10 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
19
0.42 M3
961,639.60
403,888.63
- Besi 10 mm
22
106.48 Kg
15,287.68
1,627,822.08
- Besi 6 mm
22
19.16 Kg
15,287.68
292,965.71
- Bekisting
25
4.20 M2
240,279.64
1,009,174.49
19
0.46 M3
961,639.60
438,507.66
- Besi 10 mm
22
93.91 Kg
15,287.68
1,435,648.64
- Besi 6 mm
22
19.15 Kg
15,287.68
292,830.08
- Bekisting
25
4.18 M2
240,279.64
1,004,368.90
47
79.31 M2
103,411.20
17
158.63 M2
32,370.96
SUB JUMLAH
V
PEKERJAAN ATAP
11
0.94 M3
3,828,030.48
3,590,692.59
12
103.50 M2
49,704.81
5,144,447.84
41
103.50 M2
70,500.92
7,296,845.22
42
9.00 M1
81,234.03
14
41.00 M1
38,635.36
731,106.27
1,584,049.92
18,347,141.84
PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
13
56.00 M2
63,425.82
3,551,845.92
29
56.00 M2
40,486.51
2,267,244.49
15
74.00 M2
119,717.72
SUB JUMLAH
VII
5,134,850.00
SUB JUMLAH
VI
8,201,811.14
19,841,867.33
8,859,111.28
14,678,201.69
HSB
1.00 Bh
2,200,000.00
2,200,000.00
0.47 M3
4,338,628.75
2,020,065.55
33
6.00 Bh
16,824.80
100,948.80
32
2.00 Bh
20,744.80
41,489.60
6.00 M2
321,744.89
1,930,469.34
HSB
5.00 Bh
300,000.00
1,500,000.00
HSB
10.00 Bh
360,000.00
3,600,000.00
33
20.00 Bh
16,824.80
336,496.00
HSB
20.00 Bh
8,984.80
179,696.00
34
20.00 Bh
22,944.80
458,896.00
HSB
10.00 Bh
8,816.50
SUB JUMLAH
VIII
PEKERJAAN CAT
1 Pek. Teer/ Residu
35
56.28 M2
17,144.00
964,864.32
36
214.63 M2
33,440.40
7,177,152.54
37
82.20 M2
42,367.20
3,482,583.84
SUB JUMLAH
IX
88,165.00
12,456,226.29
11,624,600.70
SUB JUMLAH
1.00 Ls
400,000.00
400,000.00
400,000.00
PEKERJAAN
LOKASI
KECAMATAN KATEMAN
NO
JUMLAH
URAIAN PEKERJAAN
(Rp)
PEKERJAAN PENDAHULUAN
II
PEKERJAAN PONDASI
23,472,582.68
III
PEKERJAAN LANTAI
20,306,676.55
IV
PEKERJAAN DINDING
19,841,867.33
PEKERJAAN ATAP
18,347,141.84
VI
PEKERJAAN PLAFOND
14,678,201.69
VII
12,456,226.29
VIII
PEKERJAAN CAT
11,624,600.70
IX
Terbilang :
1,250,000.00
400,000.00
JUMLAH HARGA
122,377,297.08
PPN 10 %
12,237,729.71
TOTAL JUMLAH
134,615,026.78
DIBULATKAN
134,615,000.00
Seratus Tiga Puluh Empat Juta Enam Ratus Lima Belas Ribu Rupiah.
Tanggal,
Desember 2014
KEGIATAN
Pekerjaan
Lokasi
Departemen / Instansi
Kontraktor Pelaksana
NAMA PERUSAHAAN
NAMA PEMILIK
JABATAN
ALAMAT
CV. .........................
............................
Direktur
Jl. ................................
Konsultan Pengawas
NAMA PERUSAHAAN
NAMA PEMILIK
JABATAN
ALAMAT
........b/PPK-PL/FSK/DD/VIII/2014
04 Agustus 2014 s/d 02 Desember 2014
Rp 134,615,000 (Seratus Tiga Puluh Empat Juta Enam Ratus
PPHP
Tanggal
NAMA PPHP
NOMOR : ........./PPHP/DISIDIK/XII/2014
12/13/2014
IDRIS ALKASIH
NIP. 19600322 198103 1 006
ENDANG FIRTANA
SARI HARTO DIRGANTORO, A. Ma
YANTO DERI
M. ISWAN, A. Md
PPTK
PPK
KUASA PENGGUNA ANGGARAN
....../BAPKP/PPK-PL/FSK/DD/XII/2014/.......
13 Desember 2014
Nomor
Tanggal
....../BASTPP/PPK-PL/FSK/DD/XII/2014/.......
15 Desember 2014
Nomor
Tanggal
....../BAPUKP/PPK-PL/FSK/DD/XII/2014/.......
16 Desember 2014
ratus-an/puluh-an
terbilang dibulatkan
terbilang berkoma
apan - Tembilahan
0604 1 006
99103 1 002
9703 1 027
II/2014/.......
XII/2014/.......
/XII/2014/.......
INPUT DATA
TERBILANG
DIBULATKAN(Seratus Tiga Puluh Empat Juta Enam Ratus Lima
Belas Ribu Rupiah.)
TERBILANG
BERKOMA Seratus Tiga Puluh Empat Juta Enam Ratus Lima
Belas Ribu 00/100 Rupiah.
triliyun-an
milyar-an
juta-an seratus tiga puluh empat juta
ribu-an enam ratus lima belas ribu
ratus-an/puluh-an
terbilang dibulatkan seratus tiga puluh empat juta enam ratus lima belas ribu
terbilang berkoma seratus tiga puluh empat juta enam ratus lima belas ribu 00/100
615
0
0
0
134
615
0
0
0
1
6
0
134,615,000
0
0
34
0
1 satu
2 dua
3 tiga
4 empat
5 lima
6 enam
15
0
0
0
4
5
0
0
0
30
10
0
7 tujuh
8 delapan
9 sembilan
10 sepuluh
11 sebelas
12 dua belas
13 tiga belas
14 empat belas
15 lima belas
16 enam belas
17 tujuh belas
18 delapan belas
19 sembilan belas
20 dua puluh
30 tiga puluh
40 empat puluh
50 lima puluh
60 enam puluh
70 tujuh puluh
80 delapan puluh
90 sembilan puluh
OPS UPK
PENGEMBALIAN SPP
PENGEMBALIAN SPP
:
:
:
KECAMATAN KATEMAN
Dinas Pendidikan Kabupaten Indragiri Hilir
CV. .........................
Selanjutnya apabila ternyata kualitas dan kuantitas tidak sesuai dengan ketentuan spesifikasi
Teknis yang telah dipersyaratkan dalam Kontrak atau tidak sesuai dengan ketentuan peraturan
perundang-undangan yang berlaku, maka kami bertanggung jawab sepenuhnya serta bersedia
menerima sanksi administrasi dan atau sanksi hukum.
Demikian Surat Pernyataan ini dibuat dengan sesungguhnya, untuk dapat dipergunakan
sebagaimana mestinya.
Tanggal,
Desember 2014
CV. KITA FOKUS CONSULTAN
FERY IRAWAN, A. Md
Direktur Cabang
Lokasi
Departemen / Instansi
Konsultan Pengawas
No. Surat Perjanjian
6. Nilai Kontrak
:
:
:
:
KECAMATAN KATEMAN
Dinas Pendidikan Kabupaten Indragiri Hilir
CV. KITA FOKUS CONSULTAN
........b/PPK-PL/FSK/DD/VIII/2014
Tanggal : 04 Agustus 2014 s/d 02 Desember 2014
Rp
134,615,000
(Seratus Tiga Puluh Empat Juta Enam Ratus Lima Belas
Ribu Rupiah.)
Selanjutnya apabila ternyata kualitas dan kuantitas tidak sesuai dengan ketentuan spesifikasi Teknis yang
telah dipersyaratkan dalam Kontrak atau tidak sesuai dengan ketentuan peraturan perundang-undangan
yang berlaku, maka kami bertanggung jawab sepenuhnya serta bersedia menerima sanksi administrasi
dan atau sanksi hukum.
Demikian Surat Pernyataan ini dibuat dengan sesungguhnya, untuk dapat dipergunakan sebagaimana
mestinya.
Tanggal,
Desember 2014
CV. .........................
............................
Direktur
NAMA
INSTANSI
JABATAN
1.
IDRIS ALKASIH
Ketua
2.
ENDANG FIRTANA
Sekretaris
3.
Anggota
4.
YANTO DERI
Anggota
5.
M. ISWAN, A. Md
Anggota
Selaku Panitia Pemeriksa Hasil Pekerjaan di Lingkungan Dinas Pendidikan Kab. Inhil TAHUN ANGGARAN 2014.
Berdasarkan Surat Keputusan Kepala Dinas Pendidikan Kab. INHIL Nomor : 656/DISDIK/V/2014 dan Kontrak
Nomor : ........b/PPK-PL/FSK/DD/VIII/2014 Tanggal : 04 Agustus 2014 s/d 02 Desember 2014, telah melakukan
Pemeriksaan / Penelitian pada :
1.
2.
3.
4.
5.
Kegiatan
Pekerjaan
Lokasi
Pelaksana
Nilai Kontrak
:
:
:
:
:
JALAN PEMERIKSAAN :
Pemeriksaan dilalkukan melalui 3 (tiga) cara pendekatan antara lain :
1. Mengukur kembali setiap yang tercantum dalam penawaran.
2. Memperhatikan mutu/kualitas bahan yang digunakan.
Memperhatikan Teknis Pelaksanaan serta penjelasan dari pemeriksaan dan pengawasan.
Dengan melalui 3 (tiga) cara pendekatan tersebut, maka diperoleh hasil pemeriksaan :
NO
I
URAIAN PEKERJAAN
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
VOLUME
KETERANGAN
1.00 Ls
1.00 Ls
1.00 Ls
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
5.63
1.41
1,350
0.70
M3
M3
M
M3
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
2.81 M3
536.09 Kg
3.75 M2
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
0.95
101.67
27.17
4.75
Telah
Telah
Telah
Telah
M3
Kg
Kg
M2
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
3.00
185.11
77.79
15.00
0.47
56.00
12.00
M3
Kg
Kg
M2
M3
M2
M2
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
0.42
106.48
19.16
4.20
M3
Kg
Kg
M2
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
0.46
93.91
19.15
4.18
79.31
158.63
M3
Kg
Kg
M2
M2
M2
Telah
Telah
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
0.94
103.50
103.50
9.00
41.00
M3
M2
M2
M1
M1
Telah
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
56.00 M2
56.00 M2
74.00 M2
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Bh
M3
Bh
Bh
M2
Bh
Bh
Bh
Bh
Bh
Bh
56.28 M2
214.63 M2
82.20 M2
1.00 Ls
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Pasal 1
Masa Pemeliharaan adalah 6 (Enam) bulan terhitung sejak tanggal Serah Terima Pertama Pekerjaan.
Pasal 2
Penyedia barang/jasa wajib memelihara hasil pekerjaan selama masa pemeliharaan sehingga kondisi tetap
seperti saat penyerahan pertama pekerjaan.
Pasal 3
Apabila Penyedia barang/jasa tidak melaksanakan kewajiban pemeliharaan sebagaimana mestinya maka
pengguna barang/jasa berhak menggunakan uang retensi untuk membiayai perbaikan/pemeliharaan atau
mencairkan jaminan pemeliharaan dan jika dana yang tersedia tidak mencukupi menjadi tanggung jawab
penyedia barang/jasa (kontraktor).
Demikian Berita Acara Pemeriksaan Kegiatan ini dibuat dengan sebenarnya berdasarkan Pemeriksaan /
Penelitian yang seksama terhadap Proyek dimaksud, untuk dapat dipergunakan sebagai mestinya.
PANITIA PEMERIKSA HASIL PEKERJAAN YANG MELAKUKAN PEMERIKSAAN/PENELITIAN
PEKERJAAN GEDUNG SEKOLAH SMPN 003 KATEMAN
KECAMATAN KATEMAN
1.
IDRIS ALKASIH
1. ................................
2.
ENDANG FIRTANA
3.
4.
YANTO DERI
5.
M. ISWAN, A. Md
2. ................................
3. ................................
4. ................................
5. ................................
1.
1. ................................
2.
FERY IRAWAN, A. Md
CV. KITA FOKUS CONSULTAN (PENGAWAS)
3.
............................
CV. ......................... (PELAKSANA)
2. ................................
3. ................................
Diketahui Oleh :
Pejabat Pembuat Komitmen
(PPK)
(PPHP)
JABATAN
Ketua
Sekretaris
Anggota
Anggota
Anggota
Ribu Rupiah.)
KETERANGAN
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah
Telah
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Telah
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
Telah Dilaksanakan
ma Pekerjaan.
dasarkan Pemeriksaan /
ai mestinya.
AN/PENELITIAN
..........................
..........................
AN
..........................
KEGIATAN :
PENAMBAHAN GEDUNG SEKOLAH
TAHUN ANGGARAN 2014
PEKERJAAN :
GEDUNG SEKOLAH SMPN 003 KATEMAN
KECAMATAN KATEMAN
BERITA ACARA
PEMERIKSAAN KEMAJUAN PEKERJAAN
Nomor
:
Tanggal :
Lampiran :
....../BAPKP/PPK-PL/FSK/DD/XII/2014/.......
13 Desember 2014
1 (Satu) Berkas
Pada hari ini Jumat Tanggal Lima Bulan Desember Tahun Dua Ribu Empat Belas, Kami yang bertandatangan
dibawah ini :
1. Nama
Jabatan
Alamat
:
:
:
FERY IRAWAN, A. Md
Direktur Cabang CV. KITA FOKUS CONSULTAN
Jl. Tanjung Emas - Tj. Harapan - Tembilahan
2. Nama
Jabatan
Alamat
:
:
:
............................
Direktur CV. .........................
Jl. ................................
Disetujui Oleh,
PELAKSANA
CV. .........................
Diperiksa Oleh,
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
............................
Direktur
FERY IRAWAN, A. Md
Direktur Cabang
ERITA ACARA
N KEMAJUAN PEKERJAAN
PKP/PPK-PL/FSK/DD/XII/2014/.......
TAN PENGAWAS
OKUS CONSULTAN
KEGIATAN :
PENAMBAHAN GEDUNG SEKOLAH
TAHUN ANGGARAN 2014
PEKERJAAN :
GEDUNG SEKOLAH SMPN 003 KATEMAN
KECAMATAN KATEMAN
BERITA ACARA
SERAH TERIMA PERTAMA PEKERJAAN
Nomor
:
Tanggal :
Lampiran :
....../BASTPP/PPK-PL/FSK/DD/XII/2014/.......
15 Desember 2014
1 (Satu) Berkas
:
:
IDRIS ALKASIH
Ketua Panitia Penerima Hasil Pekerjaan KEGIATAN PENAMBAHAN GEDUNG SEKOLAH di
KABUPATEN INDRAGIRI HILIR TAHUN ANGGARAN 2014.
Alamat
2. Nama
Jabatan
Alamat
:
:
:
............................
Direktur CV. .........................
Jl. ................................
Diperiksa Oleh,
PELAKSANA
CV. .........................
IDRIS ALKASIH
NIP. 19600322 198103 1 006
............................
Direktur
ERITA ACARA
MA PERTAMA PEKERJAAN
STPP/PPK-PL/FSK/DD/XII/2014/.......
APKP/PPK-PL/FSK/DD/XII/2014/.......
erima
akan seperlunya.
KEGIATAN :
PENAMBAHAN GEDUNG SEKOLAH
TAHUN ANGGARAN 2014
PEKERJAAN :
GEDUNG SEKOLAH SMPN 003 KATEMAN
KECAMATAN KATEMAN
BERITA ACARA
PEMBAYARAN UNTUK KEMAJUAN PEKERJAAN
Nomor
:
Tanggal :
Lampiran :
....../BAPUKP/PPK-PL/FSK/DD/XII/2014/.......
16 Desember 2014
1 (Satu) Berkas
Pada hari ini Selasa Tanggal Sembilan Bulan Desember Tahun Dua Ribu Empat Belas, Kami yang
bertandatangan dibawah ini :
1. Nama
Jabatan
:
:
GEDUNG
SEKOLAH
di
Alamat
: Jl. Veteran No. 09 Tembilahan, Kabupaten Indragiri Hilir.
Yang berwenang dalam bertindak untuk dan atas nama Pemerintah yang selanjutnya disebut PIHAK PERTAMA.
2. Nama
: ............................
Jabatan
: Direktur CV. .........................
Alamat
: Jl. ................................
Yang berwenang dalam bertindak untuk dan atas nama CV. ......................... yang selanjutnya disebut PIHAK KED
1. Telah mengadakan Penelitian atas Pekerjaan Pengawasan dan Kebenaran Laporan Kemajuan Pekerjaan pada
Minggu VII (Tujuh) seperti terlampir yang ternyata kemudian sesuai dengan kebenaran :
a.
b.
c.
d.
Pekerjaan
Lokasi
Departemen / Instansi
Surat Perintah Kerja
:
:
:
:
e.
Nilai Kontrak
Dan terbukti pula bahwa Kemajuan Pekerjaan telah mencapai prosentase sebesar : 100% (Seratus Persen)
Berdasarkan Surat Perintah Kerja dan menyerahkan jaminan pemeliharaan, maka kontraktor yang bersangkutan
dapat menerima Pembayaran sebesar 100% (Seratus Persen) dari Nilai Kontrak yaitu :
Sebesar Rp
134,615,000
100.00%
.................................................................
(Seratus Tiga Puluh Empat Juta Enam Ratus Lima Belas Ribu Rupiah.)
Demikian Berita Acara ini dibuat dalam rangkap 6 (enam) untuk dapat dipergunakan seperlunya.
PIHAK PERTAMA
PEJABAT PEMBUAT KOMITMEN
(PPK)
PIHAK KEDUA
PELAKSANA
CV. .........................
............................
Direktur
BERITA ACARA
UNTUK KEMAJUAN PEKERJAAN
/BAPUKP/PPK-PL/FSK/DD/XII/2014/.......
NAMBAHAN
2014.
GEDUNG
SEKOLAH
di
2 Desember 2014
Rp
-Rp 134,615,000
unakan seperlunya.
PIHAK KEDUA
PELAKSANA
CV. .........................
............................
DINAS PENDIDIKAN
Jl. Veteran No. 09 Telp. (0768) 21179 Fax. (0768) 21179 Tembilahan
KEGIATAN
PENAMBAHAN GEDUNG SEKOLAH
TAHUN ANGGARAN 2014
: NOPEMBER 2014
TANGGAL
PEKERJAAN
GEDUNG SEKOLAH SMPN 003 KATEMAN
KECAMATAN KATEMAN
NOMOR KONTRAK
TANGGAL
NILAI KONTRAK
: ........b/PPK-PL/FSK/DD/VIII/2014
: 04 Agustus 2014 s/d 02 Desember 2014
: Rp
134,615,000
PELAKSANA
CV. .........................
Jl. ................................
PEKERJAAN
DINAS PENDIDIKAN
NO
1
URAIAN PEKERJAAN
2
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
LAPORAN MINGGUAN
MINGGU KE :
VOLUME
KONTRAK
3
20 Oktober 2014
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
I (PERTAMA)
BOBOT
%
26 Oktober 2014
MINGGU INI
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
536.09
3.75
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
6,308,966.72
1,351,921.44
20,306,676.55
BOBOT
%
MINGGU INI
5.16%
1.10%
16.59%
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
0.46 M3
93.91 Kg
19.15 Kg
961,639.60
15,287.68
15,287.68
438,507.66
1,435,648.64
292,830.08
0.36%
1.17%
0.24%
NO
URAIAN PEKERJAAN
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
IX PEKERJAAN LAIN - LAIN
1 Pek. Pembersihan Akhir Proyek
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
BOBOT
%
MINGGU INI
4.18 M2
240,279.64
79.31 M2
103,411.20
158.63 M2
32,370.96
Sub Total
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
0.82%
6.70%
4.20%
16.21%
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
400,000.00
0.33%
1.00 Ls
400,000.00
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
Sub Total
JUMLAH
PPN 10%
TOTAL
DIBULATKAN
BOBOT
%
400,000.00
0.33%
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
100%
MINGGU INI
BO
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiks
KONTRAKTOR
CV. ..........
RIKI KARDO, ST
Inspector
(.................
Pelaksana
PEKERJAAN
KONSULTAN PENGAWAS
PORAN MINGGUAN
KONTRAK PELAKSANA
CV. .........................
26 Oktober 2014
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
1.00
1.00
1.00
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
5.63
1.41
1,350.00
0.70
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
536.09
3.75
0.00%
100.00%
100.00%
0.00%
6.70%
0.37%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
BOBOT REALISASI :
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
14.70%
PEKERJAAN
DINAS PENDIDIKAN
NO
1
URAIAN PEKERJAAN
2
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
LAPORAN MINGGUAN
MINGGU KE :
VOLUME
KONTRAK
3
27 Oktober 2014
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
II (DUA)
BOBOT
%
02 November 201
MINGGU INI
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
536.09
3.75
2.81
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
6,308,966.72
1,351,921.44
20,306,676.55
BOBOT
%
MINGGU INI
5.16%
1.10%
16.59%
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
0.46 M3
93.91 Kg
19.15 Kg
961,639.60
15,287.68
15,287.68
438,507.66
1,435,648.64
292,830.08
0.36%
1.17%
0.24%
NO
URAIAN PEKERJAAN
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
IX PEKERJAAN LAIN - LAIN
1 Pek. Pembersihan Akhir Proyek
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
BOBOT
%
MINGGU INI
4.18 M2
240,279.64
79.31 M2
103,411.20
158.63 M2
32,370.96
Sub Total
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
0.82%
6.70%
4.20%
16.21%
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
400,000.00
0.33%
1.00 Ls
400,000.00
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
Sub Total
JUMLAH
PPN 10%
TOTAL
DIBULATKAN
BOBOT
%
400,000.00
0.33%
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
100%
MINGGU INI
BO
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiks
KONTRAKTOR
CV. ..........
RIKI KARDO, ST
Inspector
(.................
Pelaksana
PEKERJAAN
KONSULTAN PENGAWAS
PORAN MINGGUAN
KONTRAK PELAKSANA
CV. .........................
02 November 2014
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
1.00
1.00
1.00
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
5.63
1.41
1,350.00
0.70
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
2.81
536.09
3.75
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
0.95
101.67
27.17
4.75
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
BOBOT REALISASI :
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
20.20%
PEKERJAAN
DINAS PENDIDIKAN
NO
1
URAIAN PEKERJAAN
2
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
LAPORAN MINGGUAN
MINGGU KE :
VOLUME
KONTRAK
3
03 November 2014
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
III (TIGA)
BOBOT
%
09 November 201
MINGGU INI
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
2.81
536.09
3.75
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
2.36%
2.31%
0.97%
3.05%
1.64%
3.00
185.11
77.79
15.00
0.47
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
6,308,966.72
1,351,921.44
20,306,676.55
BOBOT
%
MINGGU INI
5.16%
1.10%
16.59%
56.00
12.00
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
106.48
19.16
4.20
0.46 M3
93.91 Kg
19.15 Kg
961,639.60
15,287.68
15,287.68
438,507.66
1,435,648.64
292,830.08
0.36%
1.17%
0.24%
NO
URAIAN PEKERJAAN
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
IX PEKERJAAN LAIN - LAIN
1 Pek. Pembersihan Akhir Proyek
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
BOBOT
%
MINGGU INI
4.18 M2
240,279.64
79.31 M2
103,411.20
158.63 M2
32,370.96
Sub Total
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
0.82%
6.70%
4.20%
16.21%
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
400,000.00
0.33%
1.00 Ls
400,000.00
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
Sub Total
JUMLAH
PPN 10%
TOTAL
DIBULATKAN
BOBOT
%
400,000.00
0.33%
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
100%
MINGGU INI
BO
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiks
KONTRAKTOR
CV. ..........
RIKI KARDO, ST
Inspector
(.................
Pelaksana
PEKERJAAN
KONSULTAN PENGAWAS
PORAN MINGGUAN
KONTRAK PELAKSANA
CV. .........................
09 November 2014
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
1.00
1.00
1.00
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
5.63
1.41
1,350.00
0.70
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
2.81
536.09
3.75
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
0.95
101.67
27.17
4.75
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
3.00
185.11
77.79
15.00
0.47
100.00%
100.00%
100.00%
100.00%
100.00%
2.36%
2.31%
0.97%
3.05%
1.64%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
56.00
12.00
100.00%
100.00%
5.16%
1.10%
106.48
19.16
4.20
0.00%
100.00%
100.00%
100.00%
0.00%
1.33%
0.24%
0.82%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
BOBOT REALISASI :
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
39.19%
PEKERJAAN
DINAS PENDIDIKAN
NO
1
URAIAN PEKERJAAN
2
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
LAPORAN MINGGUAN
MINGGU KE :
VOLUME
KONTRAK
3
10 November 2014
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
IV (EMPAT)
BOBOT
%
MINGGU
LALU
MINGGU INI
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
2.81
536.09
3.75
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
3.00
185.11
77.79
15.00
0.47
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
16 November 201
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
6,308,966.72
1,351,921.44
20,306,676.55
BOBOT
%
5.16%
1.10%
16.59%
MINGGU INI
56.00
12.00
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
106.48
19.16
4.20
0.42
0.46 M3
93.91 Kg
19.15 Kg
961,639.60
15,287.68
15,287.68
438,507.66
1,435,648.64
292,830.08
0.36%
1.17%
0.24%
0.46
93.91
19.15
NO
URAIAN PEKERJAAN
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
IX PEKERJAAN LAIN - LAIN
1 Pek. Pembersihan Akhir Proyek
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
BOBOT
%
MINGGU INI
4.18 M2
240,279.64
79.31 M2
103,411.20
158.63 M2
32,370.96
Sub Total
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
0.82%
6.70%
4.20%
16.21%
4.18
79.31
158.63
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
400,000.00
0.33%
1.00 Ls
400,000.00
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
Sub Total
JUMLAH
PPN 10%
TOTAL
DIBULATKAN
BOBOT
%
400,000.00
0.33%
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
100%
MINGGU INI
BO
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiks
KONTRAKTOR
CV. ..........
RIKI KARDO, ST
Inspector
(.................
Pelaksana
PEKERJAAN
KONSULTAN PENGAWAS
PORAN MINGGUAN
KONTRAK PELAKSANA
CV. .........................
16 November 2014
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
1.00
1.00
1.00
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
5.63
1.41
1,350.00
0.70
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
2.81
536.09
3.75
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
0.95
101.67
27.17
4.75
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
3.00
185.11
77.79
15.00
0.47
100.00%
100.00%
100.00%
100.00%
100.00%
2.36%
2.31%
0.97%
3.05%
1.64%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
56.00
12.00
100.00%
100.00%
5.16%
1.10%
0.42
106.48
19.16
4.20
100.00%
100.00%
100.00%
100.00%
0.33%
1.33%
0.24%
0.82%
0.46
93.91
19.15
100.00%
100.00%
100.00%
0.36%
1.17%
0.24%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
100.00%
100.00%
100.00%
0.82%
6.70%
4.20%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
4.18
79.31
158.63
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
BOBOT REALISASI :
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
53.01%
PEKERJAAN
DINAS PENDIDIKAN
NO
1
URAIAN PEKERJAAN
2
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
LAPORAN MINGGUAN
MINGGU KE :
VOLUME
KONTRAK
3
17 November 2014
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
V (LIMA)
BOBOT
%
MINGGU
LALU
MINGGU INI
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
2.81
536.09
3.75
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
3.00
185.11
77.79
15.00
0.47
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
23 November 201
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
6,308,966.72
1,351,921.44
20,306,676.55
BOBOT
%
5.16%
1.10%
16.59%
MINGGU INI
56.00
12.00
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
0.42
106.48
19.16
4.20
0.46 M3
93.91 Kg
19.15 Kg
961,639.60
15,287.68
15,287.68
438,507.66
1,435,648.64
292,830.08
0.36%
1.17%
0.24%
0.46
93.91
19.15
NO
URAIAN PEKERJAAN
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
IX PEKERJAAN LAIN - LAIN
1 Pek. Pembersihan Akhir Proyek
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
BOBOT
%
MINGGU INI
4.18 M2
240,279.64
79.31 M2
103,411.20
158.63 M2
32,370.96
Sub Total
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
0.82%
6.70%
4.20%
16.21%
4.18
79.31
158.63
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
0.94
103.50
103.50
9.00
41.00
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
400,000.00
0.33%
1.00 Ls
400,000.00
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
Sub Total
JUMLAH
PPN 10%
TOTAL
DIBULATKAN
BOBOT
%
400,000.00
0.33%
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
100%
MINGGU INI
BO
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiks
KONTRAKTOR
CV. ..........
RIKI KARDO, ST
Inspector
(.................
Pelaksana
PEKERJAAN
KONSULTAN PENGAWAS
PORAN MINGGUAN
KONTRAK PELAKSANA
CV. .........................
23 November 2014
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
1.00
1.00
1.00
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
5.63
1.41
1,350.00
0.70
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
2.81
536.09
3.75
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
0.95
101.67
27.17
4.75
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
3.00
185.11
77.79
15.00
0.47
100.00%
100.00%
100.00%
100.00%
100.00%
2.36%
2.31%
0.97%
3.05%
1.64%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
56.00
12.00
100.00%
100.00%
5.16%
1.10%
0.42
106.48
19.16
4.20
100.00%
100.00%
100.00%
100.00%
0.33%
1.33%
0.24%
0.82%
0.46
93.91
19.15
100.00%
100.00%
100.00%
0.36%
1.17%
0.24%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
4.18
79.31
158.63
100.00%
100.00%
100.00%
0.82%
6.70%
4.20%
0.94
103.50
103.50
9.00
41.00
100.00%
100.00%
100.00%
100.00%
100.00%
2.93%
4.20%
5.96%
0.60%
1.29%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
BOBOT REALISASI :
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
68.00%
PEKERJAAN
DINAS PENDIDIKAN
NO
1
URAIAN PEKERJAAN
2
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
LAPORAN MINGGUAN
MINGGU KE :
VOLUME
KONTRAK
3
24 November 2014
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
VI (ENAM)
BOBOT
%
MINGGU
LALU
MINGGU INI
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
2.81
536.09
3.75
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
3.00
185.11
77.79
15.00
0.47
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
30 November 201
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
6,308,966.72
1,351,921.44
20,306,676.55
BOBOT
%
5.16%
1.10%
16.59%
MINGGU INI
56.00
12.00
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
0.42
106.48
19.16
4.20
0.46 M3
93.91 Kg
19.15 Kg
961,639.60
15,287.68
15,287.68
438,507.66
1,435,648.64
292,830.08
0.36%
1.17%
0.24%
0.46
93.91
19.15
NO
URAIAN PEKERJAAN
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
IX PEKERJAAN LAIN - LAIN
1 Pek. Pembersihan Akhir Proyek
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
BOBOT
%
MINGGU INI
4.18 M2
240,279.64
79.31 M2
103,411.20
158.63 M2
32,370.96
Sub Total
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
0.82%
6.70%
4.20%
16.21%
4.18
79.31
158.63
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
0.94
103.50
103.50
9.00
41.00
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
56.00
56.00
74.00
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
1.00
0.47
6.00
2.00
-
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
400,000.00
0.33%
1.00 Ls
400,000.00
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
Sub Total
JUMLAH
PPN 10%
TOTAL
DIBULATKAN
BOBOT
%
400,000.00
0.33%
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
100%
MINGGU INI
BO
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiks
KONTRAKTOR
CV. ..........
RIKI KARDO, ST
Inspector
(.................
Pelaksana
PEKERJAAN
KONSULTAN PENGAWAS
PORAN MINGGUAN
KONTRAK PELAKSANA
CV. .........................
30 November 2014
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
1.00
1.00
1.00
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
5.63
1.41
1,350.00
0.70
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
2.81
536.09
3.75
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
0.95
101.67
27.17
4.75
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
3.00
185.11
77.79
15.00
0.47
100.00%
100.00%
100.00%
100.00%
100.00%
2.36%
2.31%
0.97%
3.05%
1.64%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
56.00
12.00
100.00%
100.00%
5.16%
1.10%
0.42
106.48
19.16
4.20
100.00%
100.00%
100.00%
100.00%
0.33%
1.33%
0.24%
0.82%
0.46
93.91
19.15
100.00%
100.00%
100.00%
0.36%
1.17%
0.24%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
4.18
79.31
158.63
100.00%
100.00%
100.00%
0.82%
6.70%
4.20%
0.94
103.50
103.50
9.00
41.00
100.00%
100.00%
100.00%
100.00%
100.00%
2.93%
4.20%
5.96%
0.60%
1.29%
56.00
56.00
74.00
100.00%
100.00%
100.00%
2.90%
1.85%
7.24%
1.00
0.47
6.00
2.00
-
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1.80%
1.65%
0.08%
0.03%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
BOBOT REALISASI :
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
83.56%
PEKERJAAN
DINAS PENDIDIKAN
NO
1
URAIAN PEKERJAAN
2
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
LAPORAN MINGGUAN
MINGGU KE :
VOLUME
KONTRAK
3
01 Desember 2014
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
VII (TUJUH)
BOBOT
%
MINGGU
LALU
MINGGU INI
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
2.81
536.09
3.75
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
3.00
185.11
77.79
15.00
0.47
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
07 Desember 201
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
6,308,966.72
1,351,921.44
20,306,676.55
BOBOT
%
5.16%
1.10%
16.59%
MINGGU INI
56.00
12.00
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
0.42
106.48
19.16
4.20
0.46 M3
93.91 Kg
19.15 Kg
961,639.60
15,287.68
15,287.68
438,507.66
1,435,648.64
292,830.08
0.36%
1.17%
0.24%
0.46
93.91
19.15
NO
URAIAN PEKERJAAN
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
IX PEKERJAAN LAIN - LAIN
1 Pek. Pembersihan Akhir Proyek
VOLUME
KONTRAK
3
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
BOBOT
%
MINGGU INI
4.18 M2
240,279.64
79.31 M2
103,411.20
158.63 M2
32,370.96
Sub Total
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
0.82%
6.70%
4.20%
16.21%
4.18
79.31
158.63
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
0.94
103.50
103.50
9.00
41.00
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
56.00
56.00
74.00
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
1.00
0.47
6.00
2.00
-
6.00
5.00
10.00
20.00
20.00
20.00
10.00
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
56.28
214.63
82.20
400,000.00
0.33%
1.00
1.00 Ls
400,000.00
NO
1
URAIAN PEKERJAAN
2
VOLUME
KONTRAK
KONTRAK ASLI
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
Sub Total
JUMLAH
PPN 10%
TOTAL
DIBULATKAN
BOBOT
%
400,000.00
0.33%
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
100%
MINGGU INI
BO
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiks
KONTRAKTOR
CV. ..........
RIKI KARDO, ST
Inspector
(.................
Pelaksana
PEKERJAAN
KONSULTAN PENGAWAS
PORAN MINGGUAN
KONTRAK PELAKSANA
CV. .........................
07 Desember 2014
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
1.00
1.00
1.00
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
5.63
1.41
1,350.00
0.70
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
2.81
536.09
3.75
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
0.95
101.67
27.17
4.75
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
3.00
185.11
77.79
15.00
0.47
100.00%
100.00%
100.00%
100.00%
100.00%
2.36%
2.31%
0.97%
3.05%
1.64%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
56.00
12.00
100.00%
100.00%
5.16%
1.10%
0.42
106.48
19.16
4.20
100.00%
100.00%
100.00%
100.00%
0.33%
1.33%
0.24%
0.82%
0.46
93.91
19.15
100.00%
100.00%
100.00%
0.36%
1.17%
0.24%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
4.18
79.31
158.63
100.00%
100.00%
100.00%
0.82%
6.70%
4.20%
0.94
103.50
103.50
9.00
41.00
100.00%
100.00%
100.00%
100.00%
100.00%
2.93%
4.20%
5.96%
0.60%
1.29%
56.00
56.00
74.00
100.00%
100.00%
100.00%
2.90%
1.85%
7.24%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
56.28
214.63
82.20
100.00%
100.00%
100.00%
0.79%
5.86%
2.85%
1.00
100.00%
0.33%
PROSENTASE
TERHADAP
PEKERJAAN (%)
BOBOT REALISASI
(%)
10
11
BOBOT REALISASI :
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
100.00%
PEKERJAAN
DINAS PENDIDIKAN
LAPORAN BULANAN
BULAN KE :
I (PERTAMA)
20 Oktober 2014
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
16 November 2014
REALISASI PEKERJAAN
BOBOT
%
6
S/D BULAN
REALISASI HARGA
INI
7
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
500,000.00
500,000.00
250,000.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
153,000.00
18,337.50
7,233,300.00
689,980.36
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
2.81
536.09
3.75
2,704,611.38
8,195,632.02
453,117.68
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
913,557.62
1,554,344.00
415,373.83
1,141,328.29
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
3.00
185.11
77.79
15.00
0.47
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
REALISASI PEKERJAAN
BOBOT
%
6,308,966.72
1,351,921.44
20,306,676.55
5.16%
1.10%
16.59%
S/D BULAN
REALISASI HARGA
INI
7
56.00
12.00
6,308,966.72
1,351,921.44
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
0.42
106.48
19.16
4.20
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.46 M3
961,639.60
438,507.66
0.36%
0.46
438,507.66
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
- Besi 10 mm
- Besi 6 mm
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
REALISASI PEKERJAAN
BOBOT
%
S/D BULAN
REALISASI HARGA
INI
7
93.91
19.15
4.18
79.31
158.63
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
M2
103,411.20
M2
32,370.96
Sub Total
1,435,648.64
292,830.08
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
1.17%
0.24%
0.82%
6.70%
4.20%
16.21%
93.91
19.15
4.18
79.31
158.63
1,435,648.64
292,830.08
1,004,368.90
8,201,811.14
5,134,850.00
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
400,000.00
Sub Total
JUMLAH
PPN 10%
HARGA DI KONTRAK :
TOTAL
DIBULATKAN
400,000.00
400,000.00
###
12,237,729.71
###
###
REALISASI PEKERJAAN
BOBOT
%
6
0.33%
0.33%
100%
S/D BULAN
REALISASI HARGA
INI
7
HARGA
REALISASI :
64,871,126.56
6,487,112.66
71,358,239.22
71,358,000.00
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiksa Oleh :
KONTRAKTOR PELAKSAN
CV. .........................
RIKI KARDO, ST
Inspector
(................................
Pelaksana Lapangan
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
KONTRAK PELAKSANA
CV. .........................
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
100.00%
100.00%
100.00%
100.00%
100.00%
2.36%
2.31%
0.97%
3.05%
1.64%
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
100.00%
100.00%
5.16%
1.10%
100.00%
100.00%
100.00%
100.00%
0.33%
1.33%
0.24%
0.82%
100.00%
0.36%
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
100.00%
100.00%
100.00%
100.00%
100.00%
1.17%
0.24%
0.82%
6.70%
4.20%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
0.00%
0.00%
BOBOT
REALISASI :
53.01%
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
PEKERJAAN
DINAS PENDIDIKAN
LAPORAN BULANAN
BULAN KE :
II (DUA)
17 November 2014
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
PEKERJAAN PENDAHULUAN
1 Pek. Pembersihan Lokasi
2 Pek. Pas. Bouwplank/ Pengukuran
3 Pek. Papan Nama Proyek
II PEKERJAAN PONDASI
1 Pek. Galian Tanah
2 Pek. Timbunan Kembali
3 Pek. Cerocok Kayu Bulat 10-12 x 6 M1
4 Pek. Cor Lantai Kerja 1 : 3 : 5
5 Pek. Cor Tapak Pondasi 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Bekisting
6 Pek. Cor Tiang Umpak 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
III PEKERJAAN LANTAI
1 Pek. Balok Lantai Beton 20/20 cm 1 : 2 : 3
- Beton Campur 1 : 2 : 3
- Besi 10 mm
- Besi 6 mm
- Bekisting
2 Pek. Gelegar Kayu 5/7 Kelas III
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
500,000.00
1.00 Ls
500,000.00
1.00 Ls
250,000.00
Sub Total
5.63
1.41
1,350.00
0.70
07 Desember 2014
REALISASI PEKERJAAN
BOBOT
%
6
S/D BULAN
REALISASI HARGA
INI
7
500,000.00
500,000.00
250,000.00
1,250,000.00
0.41%
0.41%
0.20%
1.02%
1.00
1.00
1.00
500,000.00
500,000.00
250,000.00
M3
M3
M
M3
27,200.00
13,040.00
5,358.00
981,305.40
153,000.00
18,337.50
7,233,300.00
689,980.36
0.13%
0.01%
5.91%
0.56%
5.63
1.41
1,350.00
0.70
153,000.00
18,337.50
7,233,300.00
689,980.36
2.81 M3
536.09 Kg
3.75 M2
961,639.60
15,287.68
120,831.38
2,704,611.38
8,195,632.02
453,117.68
2.21%
6.70%
0.37%
2.81
536.09
3.75
2,704,611.38
8,195,632.02
453,117.68
0.95
101.67
27.17
4.75
M3
961,639.60
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
Sub Total
913,557.62
1,554,344.00
415,373.83
1,141,328.29
23,472,582.68
0.75%
1.27%
0.34%
0.93%
19.18%
0.95
101.67
27.17
4.75
913,557.62
1,554,344.00
415,373.83
1,141,328.29
3.00
185.11
77.79
15.00
0.47
M3
Kg
Kg
M2
M3
2.36%
2.31%
0.97%
3.05%
1.64%
3.00
185.11
77.79
15.00
0.47
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
961,639.60
15,287.68
15,287.68
248,630.08
4,323,124.24
2,884,918.80
2,829,848.11
1,189,155.95
3,729,451.20
2,012,414.33
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
56.00 M2
112,660.12
12.00 M2
112,660.12
Sub Total
0.42
106.48
19.16
4.20
REALISASI PEKERJAAN
BOBOT
%
6,308,966.72
1,351,921.44
20,306,676.55
5.16%
1.10%
16.59%
S/D BULAN
REALISASI HARGA
INI
7
56.00
12.00
6,308,966.72
1,351,921.44
M3
Kg
Kg
M2
961,639.60
15,287.68
15,287.68
240,279.64
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.33%
1.33%
0.24%
0.82%
0.42
106.48
19.16
4.20
403,888.63
1,627,822.08
292,965.71
1,009,174.49
0.46 M3
961,639.60
438,507.66
0.36%
0.46
438,507.66
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
- Besi 10 mm
- Besi 6 mm
- Bekisting
3 Pek. Pasangan Batako 5 x 15 x 30 cm
4 Pek. Plasteran Pas. Batako
V PEKERJAAN ATAP
1 Pek. Kuda Kuda Kayu Klas III
2 Pek. Reng Kayu Klas III
3 Pek. Atap Genteng Metal
4 Pek. Perabung Genteng Metal
5 Pek. Lysplank Papan Kls III
VI PEKERJAAN PLAFOND
1 Pek. Rangka Plafond Kayu Kls III
2 Pek. Plafond Triplek 4 mm
3 Pek. Peri-Peri Papan Kls III
VII PEKERJAAN PINTU /JENDELA
1 Pek. Pintu Panel 2 (Dua) Daun
2 Pek. Kunsen Pintu & Jendela Kayu Kls III
3 Pek. Engsel Pintu
4 Pek. Kunci Tanam
5 Pek. Pasang Ventilasi Jalusi Kayu Kelas III
6 Pek. Jendela Kaca Mati 5 mm
7 Pek. Jendela Kaca Bingkai 5 mm
8 Pek. Engsel Jendela
9 Pek. Grendel Jendela
10 Pek. Kait Angin Jendela
11 Pek. Tarikan Jendela
VIII PEKERJAAN CAT
1 Pek. Teer/ Residu
2 Pek. Cat Air Dinding
3 Pek. Cat Minyak
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
REALISASI PEKERJAAN
BOBOT
%
S/D BULAN
REALISASI HARGA
INI
7
93.91
19.15
4.18
79.31
158.63
Kg
15,287.68
Kg
15,287.68
M2
240,279.64
M2
103,411.20
M2
32,370.96
Sub Total
1,435,648.64
292,830.08
1,004,368.90
8,201,811.14
5,134,850.00
19,841,867.33
1.17%
0.24%
0.82%
6.70%
4.20%
16.21%
93.91
19.15
4.18
79.31
158.63
1,435,648.64
292,830.08
1,004,368.90
8,201,811.14
5,134,850.00
0.94
103.50
103.50
9.00
41.00
M3
3,828,030.48
M2
49,704.81
M2
70,500.92
M1
81,234.03
M1
38,635.36
Sub Total
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
18,347,141.84
2.93%
4.20%
5.96%
0.60%
1.29%
14.99%
0.94
103.50
103.50
9.00
41.00
3,590,692.59
5,144,447.84
7,296,845.22
731,106.27
1,584,049.92
56.00 M2
63,425.82
56.00 M2
40,486.51
74.00 M2
119,717.72
Sub Total
3,551,845.92
2,267,244.49
8,859,111.28
14,678,201.69
2.90%
1.85%
7.24%
11.99%
56.00
56.00
74.00
3,551,845.92
2,267,244.49
8,859,111.28
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
Bh
2,200,000.00
M3
4,338,628.75
Bh
16,824.80
Bh
20,744.80
M2
321,744.89
Bh
300,000.00
Bh
360,000.00
Bh
16,824.80
Bh
8,984.80
Bh
22,944.80
Bh
8,816.50
Sub Total
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
12,456,226.29
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
10.18%
1.00
0.47
6.00
2.00
6.00
5.00
10.00
20.00
20.00
20.00
10.00
2,200,000.00
2,020,065.55
100,948.80
41,489.60
1,930,469.34
1,500,000.00
3,600,000.00
336,496.00
179,696.00
458,896.00
88,165.00
56.28 M2
17,144.00
214.63 M2
33,440.40
82.20 M2
42,367.20
Sub Total
964,864.32
7,177,152.54
3,482,583.84
11,624,600.70
0.79%
5.86%
2.85%
9.50%
56.28
214.63
82.20
964,864.32
7,177,152.54
3,482,583.84
KONTRAK ASLI
NO
URAIAN PEKERJAAN
VOLUME
KONTRAK
HARGA
JUMLAH HARGA
SATUAN (Rp)
(Rp)
4
1.00 Ls
400,000.00
Sub Total
JUMLAH
PPN 10%
HARGA DI KONTRAK :
TOTAL
DIBULATKAN
400,000.00
400,000.00
###
12,237,729.71
###
###
REALISASI PEKERJAAN
BOBOT
%
6
0.33%
0.33%
100%
S/D BULAN
REALISASI HARGA
INI
7
1.00
HARGA
REALISASI :
400,000.00
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
Diperiksa Oleh :
KONTRAKTOR PELAKSAN
CV. .........................
RIKI KARDO, ST
Inspector
(................................
Pelaksana Lapangan
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
KONTRAK PELAKSANA
CV. .........................
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
100.00%
100.00%
100.00%
0.41%
0.41%
0.20%
100.00%
100.00%
100.00%
100.00%
0.13%
0.01%
5.91%
0.56%
100.00%
100.00%
100.00%
2.21%
6.70%
0.37%
100.00%
100.00%
100.00%
100.00%
0.75%
1.27%
0.34%
0.93%
100.00%
100.00%
100.00%
100.00%
100.00%
2.36%
2.31%
0.97%
3.05%
1.64%
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
100.00%
100.00%
5.16%
1.10%
100.00%
100.00%
100.00%
100.00%
0.33%
1.33%
0.24%
0.82%
100.00%
0.36%
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
100.00%
100.00%
100.00%
100.00%
100.00%
1.17%
0.24%
0.82%
6.70%
4.20%
100.00%
100.00%
100.00%
100.00%
100.00%
2.93%
4.20%
5.96%
0.60%
1.29%
100.00%
100.00%
100.00%
2.90%
1.85%
7.24%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
1.80%
1.65%
0.08%
0.03%
1.58%
1.23%
2.94%
0.27%
0.15%
0.37%
0.07%
100.00%
100.00%
100.00%
0.79%
5.86%
2.85%
PROSENTASE
TERHADAP
PEKERJAAN
(%)
BOBOT REALISASI
(%)
10
100.00%
0.33%
BOBOT
REALISASI :
100.00%
Diperiksa Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
(.................................)
Pelaksana Lapangan
REKAPITULASI BULANAN
KEGIATAN
PEKERJAAN
LOKASI
WAKTU PELAKSANAAN
:
:
:
:
KONTRAKTOR PELAKSANA
KONSULTAN PENGAWAS
SERTIFIKAT
TANGGAL
KONTRAK
NO
I
II
III
IV
V
VI
VII
VIII
IX
1
2
3
4
URAIAN PEKERJAAN
NILAI (Rp)
BOBOT
PENDAHULUAN
1,250,000.00
1.02%
PONDASI
23,472,582.68
19.18%
LANTAI
20,306,676.55
16.59%
DINDING
19,841,867.33
16.21%
ATAP
18,347,141.84
14.99%
PLAFOND
14,678,201.69
11.99%
PINTU /JENDELA
12,456,226.29
10.18%
CAT
11,624,600.70
9.50%
LAIN - LAIN
400,000.00
0.33%
JUMLAH HARGA
122,377,297.08
PPN 10 %
12,237,729.71
100.00%
TOTAL JUMLAH
134,615,026.78
DIBULATKAN
134,615,000.00
Nilai Bruto dari Sertifikat ini
Pengurangan :
a. Pengembalian Uang Muka
0.00%
x
b. Lain - lain
Nilai Pekerjaan yang disyahkan untuk dibayarkan pada sertifikat ini
Pembulatan
CV. .........................
CV. KITA FOKUS CONSULTAN
BULAN OKTOBER & NOPEMBER
16 Nopember 2014
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
Terbilang :
:
:
:
:
S/D BULAN
LALU
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
1.02%
19.18%
16.59%
16.21%
0.00%
0.00%
0.00%
0.00%
0.00%
S/D BULAN
INI
1.02%
19.18%
16.59%
16.21%
0.00%
0.00%
0.00%
0.00%
0.00%
53.01%
53.01%
BULAN INI
53.01%
134,615,000.00
(Tujuh Puluh Satu Juta Tiga Ratus Lima Puluh Delapan Ribu Rupiah)
Diketahui Oleh :
PEJABAT PELAKSANA TEKNIS KEGIATAN
(PPTK)
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
FERY IRAWAN, A. Md
Direktur Cabang
KAPITULASI BULANAN
:
:
:
:
CV. .........................
CV. KITA FOKUS CONSULTAN
BULAN OKTOBER & NOPEMBER 2014
16 Nopember 2014
NILAI PEKERJAAN YANG
DIBAYAR
(Rp)
1,250,000.00
23,472,582.68
20,306,676.55
19,841,867.33
64,871,126.56
6,487,112.66
71,358,239.22
71,358,000.00
71,358,000.00
71,358,000.00
71,358,000.00
Satu Juta Tiga Ratus Lima Puluh Delapan Ribu Rupiah)
Dibuat Oleh :
KONTRAKTOR PELAKSANA
CV. .........................
............................
Direktur
REKAPITULASI BULANAN
KEGIATAN
PEKERJAAN
LOKASI
WAKTU PELAKSANAAN
:
:
:
:
KONTRAKTOR PELAKSANA
KONSULTAN PENGAWAS
SERTIFIKAT
TANGGAL
KONTRAK
NO
I
II
III
IV
V
VI
VII
VIII
IX
1
2
3
4
URAIAN PEKERJAAN
NILAI (Rp)
BOBOT
PENDAHULUAN
1,250,000.00
1.02%
PONDASI
23,472,582.68
19.18%
LANTAI
20,306,676.55
16.59%
DINDING
19,841,867.33
16.21%
ATAP
18,347,141.84
14.99%
PLAFOND
14,678,201.69
11.99%
PINTU /JENDELA
12,456,226.29
10.18%
CAT
11,624,600.70
9.50%
LAIN - LAIN
400,000.00
0.33%
JUMLAH HARGA
122,377,297.08
PPN 10 %
12,237,729.71
100.00%
TOTAL JUMLAH
134,615,026.78
DIBULATKAN
134,615,000.00
Nilai Bruto dari Sertifikat ini
Pengurangan :
a. Pengembalian Uang Muka
0.00%
x
b. Lain - lain
Nilai Pekerjaan yang disyahkan untuk dibayarkan pada sertifikat ini
Pembulatan
CV. .........................
CV. KITA FOKUS CONSULTAN
BULAN NOPEMBER & DESEMBE
7 Desember 2014
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
PEKERJAAN
Terbilang :
:
:
:
:
S/D BULAN
LALU
1.02%
19.18%
16.59%
16.21%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
14.99%
11.99%
10.18%
9.50%
0.33%
S/D BULAN
INI
1.02%
19.18%
16.59%
16.21%
14.99%
11.99%
10.18%
9.50%
0.33%
46.99%
100.00%
BULAN INI
53.01%
100.00%
Rp 134,615,000
Rp
Rp
(Seratus Tiga Puluh Empat Juta Enam Ratus Lima Belas Ribu Rupiah)
Diketahui Oleh :
PEJABAT PELAKSANA TEKNIS KEGIATAN
(PPTK)
Diperiksa Oleh :
KONSULTAN PENGAWAS
CV. KITA FOKUS CONSULTAN
FERY IRAWAN, A. Md
Direktur Cabang
KAPITULASI BULANAN
:
:
:
:
CV. .........................
CV. KITA FOKUS CONSULTAN
BULAN NOPEMBER & DESEMBER 2014
7 Desember 2014
NILAI PEKERJAAN YANG
DIBAYAR
(Rp)
Rp
1,250,000.00
23,472,582.68
20,306,676.55
19,841,867.33
18,347,141.84
14,678,201.69
12,456,226.29
11,624,600.70
400,000.00
122,377,297.08
12,237,729.71
134,615,026.78
134,615,000.00
134,615,000.00
Rp
Rp
134,615,000.00
134,615,000.00
............................
Direktur