A progressing cavity pump overhaul can be handled on a professional basis with clearly understood expectations and communications, regardless of whether the repair is to be done at
the pump manufacturer's facility, in-house, or by a third party
(on- or off-site).
Having the pump manufacturer (original equipment manufacturer) perform the overhaul has some obvious advantages,
not least of which is their access to original component design,
dimensional, and tolerance data, material specifications, and
their experience with the pump. They also usually have complete testing facilities. New pump warranties are sometimes
available from the original pump manufacturer, as well as upgrades and modernizations.
Third-party repair is frequently less costly, at least on a firstcost basis, but rarely includes a warranty, almost never includes
any meaningful testing, and can sacrifice reliability for expediency.
Owner
Serial No.
Recevied Condtion
Part
I,D. Qty Part No.
Part Name
By
Date
Comments
Subtotal
AssembtyfTest
Other
Other
Total.
Price
6. A written inspection report relating the above component condition/disposition recommendations should
be produced- The report should include pricing for the
recommended overhaul, noting what is or is not included (painting, testing, special preservation, etc.).
If a warranty claim or troubleshooting effort is to be made,
be sure to keep all parts, regardless of condition, so a more
complete evaluation can be made.
A comparison to the cost of a new pump may be appropriate if such is still manufactured. Many off-the-shelf pumps
are manufactured in large lot sizes and sell for about the same
price as an overhaul handled on a one-time basis.
The party paying for the overhaul should review these
recommendations and, depending on cost, time, criticality,
etc., either challenge the observations if any appear questionable or authorize the overhaul to commence. Note that time
will frequently determine the reuse of questionable or worn
parts. The overhaul should specifically state that new pump
performance will be achieved (or something less) due to economics or time. A loading or unloading pump flow rate may
not be very critical to day-to-day operations, while pump
capacity may be critical for gas sealing, machinery lubrication,
or process applications. If something less than new pump performance is expected, then the minimum flow rate should be
agreed upon before the overhaul proceeds.
If weld buildup or repair is to be conducted, be sure that
the weld procedures and welders have been adequately quali-
fied. Plating and spray buildup processes are frequently technique-sensitive and may need some nondestructive testing
after application to confirm whether the objectives were met.
Not all pumps are tested after repair. If this is a requirement, specify so in the ordering document Testing ranges from
turning the pump shaft by hand, to hydrostatic and spin tests,
to full qualification testing as would be conducted on a new
pump. If new pump flow rate is expected after the repair, again,
so specify. If the overhauled pump will be installed and operated
upon its return, no special preservation or packaging may be
needed. On the other hand, if the pump will go into storage,
internal preservation and sturdy crating should be specified.
Application of a paint should be included if the pump exterior is
of cast iron, steel, or other material susceptible to rusting.