Professional Documents
Culture Documents
23 Crashing PDF
23 Crashing PDF
Class 5
Multiple-shift work
Extended workdays
Using larger or more productive equipment
Increasing the number of craftspeople
Using materials with faster installation methods
E.g. Doka formwork
Cost-Resource Trade-off
Realistic
Assumption
Simplistic
Assumption
2000
1000
10
20
No. of Resources
Number of Resources
Resource-Duration trade-off
Simplistic Assumption
8
Actual
Crash Point
Crash Cost
1,300
Normal Point
Normal Cost
1,000
12
13
14
15
CC - NC
ND - CD
Where,
S Cost-Per-Day Slope
CC Crash Cost
NC Normal Cost
ND Normal Duration
CD Crash Duration
Crash Point
Crash Cost
1,300
Poor Assumption
1,150
1,050
Normal Point
Normal Cost
1,000
12
13
14
15
0
A 120
B 20
Start
0
C 40
0
D 30
0
0
F 60
0
E 50
0
0
Finish
Cost trade-offs
Activity
NC (Normal
CC (Crash
Cost) Rs.
Cost) Rs.
Duration (Days)
Normal
Crash
120
100
12000
14000
20
15
1800
2800
40
30
16000
22000
30
20
1400
2000
50
40
3600
4800
60
45
13500
18000
Crashing Algorithm
1. Choose task(s) to crash only from the critical
path(s)
2. When choosing tasks, ensure that all critical
paths will be affected and reduced equally
3. At any point, choose tasks with the least costper-day slope that can be crashed
1. When crashing tasks simultaneously choose tasks
such that the sum of their slopes is the least
Crashing Limits
Physical Limit
The number of days an activity can be
reduced without making it impossible to
construct
E.g: Concrete pouring cannot be faster than
curing time
Logical Limit
The number of days a critical activity can be
crashed without a new critical path being
created.
120
20
A 120
20
20
B 20
Start
0
20
60
60
C 40
20
40
140
20
90
D 30
60
20
60
10
80
F 60
30
10
90
140
90
140
E 50
90
90
140
Fi nish
140
140
140
ND
CD
NC
CC
(000)
(000)
C/D D C
DA
CA
120
100 12
14
100
12
20
15
1.8
2.8
200
1.8
40
30
16
22
600
16
30
20
1.4
60
1.4
50
40
3.6
4.8
120
3.6
60
45
13.5 18
300
13.5
D
Left
ND
CD
NC
CC
(000)
(000)
C/D D C
DA
CA
120
100 12
14
100
12
20
15
1.8
2.8
200
1.8
40
30
16
22
600
16
30
20
1.4
60
50
40
3.6
4.8
120
3.6
60
45
13.5 18
300
13.5
10 600
20
D
Left
Update Network
0
120
10
A 120
10
20
B 20
Start
0
20
60
60
C 40
20
40
130
10
80
80
D 20
60
20
60
80
F 60
20
80
130
130
E 50
80
80
130
130
Finish
130
130
ND
CD
NC
CC
(000)
(000)
C/D D C
DA
(000)
CA
(000)
D
Left
120
100 12
14
100
12
20
15
1.8
2.8
200
1.8
40
30
16
22
600
16
30
20
1.4
60
10 0.6
20
50
40
3.6
4.8
120
10 1.2
40
4.8
60
45
13.5 18
300
13.5
Update Network
120
0
A 120
120
20
B 20
Start
0
20
60
60
C 40
20
40
80
D 20
60
60
20
0
80
F 60
20
80
12
0
80
120
E 40
80
80
120
Finish
12
0
120
120
ND
CD
NC
CC
(000)
(000)
C/D D C
DA
(000)
CA
(000)
D
Left
120
100 12
14
100
0.5
115
12.5 15
20
15
1.8
2.8
200
15
2.8
40
30
16
22
600
30
20
1.4
60
10 0.6
20
50
40
3.6
4.8
120
10 1.2
40
4.8
60
45
13.5 18
300
16
13.5
Update Network
115
0
A 115
115
15
B 15
Start
0
15
55
55
C 40
15
15
75
D 20
55
55
15
0
75
F 60
15
75
11
5
75
115
E 40
75
75
115
Finish
11
5
115
115
ND
CD
NC
CC
(000)
(000)
C/D D C
DA
(000)
CA
(000)
D
Left
120
100 12
14
100
15 1.5
105
13.5 5
20
15
1.8
2.8
200
15
2.8
40
30
16
22
600
10 6
30
22
30
20
1.4
60
10 0.6
20
50
40
3.6
4.8
120
10 1.2
40
4.8
60
45
13.5 18
300
10 3
50
16.5
Final Network
105
0
A 105
105
15
B 15
Start
0
15
45
45
C 30
15
15
65
D 20
45
45
15
0
65
F 50
15
65
10
5
65
105
E 40
65
65
105
Finish
10
5
105
105
Cost-Profile
Direct Cost
(Rs.)
48,300
Project
Duration
(days)
140
Duration
Reduction
(days)
0
48,900
130
10
50,100
120
20
51,600
115
25
61,600
105
35
Cost (Rs)
40000
Series1
30000
20000
10000
0
105
115
120
130
140
Duration (days)
Construction Costs
Direct Costs
Indirect Costs
Direct Costs
Labor, Material, Equipment, Subcontracts
Shortening durations normally increase
direct costs
overtime or extra shifts are more costly
more crews mean more supervision
more equipment might be needed
early delivery of resources might cost more
Indirect Costs
Costs incurred in direct support of field work, but
cannot be associated with any particular
physical portion of the job.
Two types
costs that are part of the contract like trailer
overheads
General costs to the company such as home office
overheads, paying marketing and secretarial staff
Cost (Rs.)
1,00,000
50,000
10,000
25,000
15,000
3,000
10,000
40,000
1,000
Set-up Cost
Minimum Project
Cost
Total Direct
Cost
Total Project
Cost
Minimum Direct
Cost
Project Indirect
Cost
Minimum
Duration
Project
Duration
(days)
140
Duration
Reduction
(days)
0
48,900
130
10
50,100
120
20
51,600
115
25
61,600
105
35
Direct
Cost
(Rs.)
Overheads
(Rs.)
Bonus
(Rs.)
Total
Cost (Rs.)
140
48,300
70,000
1,18,300
130
48,900
65,000
-3,000
1,10,900
120
50,100
60,000
-6,000
1,04,100
115
51,600
57,500
-7,500
1,01,600
105
61,600
52,500
-10,500 1,03,600
120000
115000
110000
105000
100000
95000
90000
105
115
120
130
140
Duration (Days)
Summarizing Crashing:
Step 1 Attempt Crashing at no cost
Reevaluate activity times. See if you can shift
resources from critical to non-critical activities.
Restudy job logic and come up with ingenious
solutions
Parallelize or overlap critical activities strip
forms and painting can be overlapped for a
bridge
Subcontract so that you are not constrained by
your own resources
Thank You