1.a Trace the evolution of the modern production management thought
b. Explain the tools and techniques of production Management that helps
in improving productivity
2.a What is product life cycle? What are the different product strategies
adopted during the different stages of the product life cycle.
b. Bring out the differences between process focused organizations and
product focussed organization, Give suitable examples
3.a List the different qualitative and quantitative methods of forecasting
used in industry. Also write a note on Delphi Technique
b. Alpha company has the following sales pattern during 2003 to 2011. Compute the sales
10
10
10
10
10
200
3
200
4
200
5
200
6
200
7
200
8
200
9
201
0
201
1
Sales (in
6
8
11
23
29
34
40
45
56
lakhs)
4.a What are the factors affecting plant location? Explain
b. Distinguish between product and process layout with suitable example
c. List the various techniques available for solving plant location problems.
Explain rank positional weight method of solving the same
PART - B
5.a Explain the different types of production plans
b. What is aggregate planning? Bring out the different aggregate planning
strategies
6.a What is Master schedule? Bring out the steps in developing a Master
schedule
b. The processing times (hours) for 6 jobs on three machines are given in the following table
JOB
M1
M2
M3
The jobs are processed on the
1
2
3
4
3
12
5
2
8
6
4
6
13 14
9
12
three machines according
5
6
9
11
3
1
8
13
to the order M 1, M2, M3. Obtain
10
6
6
8
10
10
10
10
the optimal sequence using Johnsons Rule. Also determine the total elapsed time.
Contd.
7.a Ten jobs are to be assigned to four machines. The processing times of jobs on the
16
.2 four
Page No... 2
P08ME74
machines are as shown below:
JOB
M/C A
M/C B
M/C C
M/C D
1
10
15
14
12
2
18
20
22
27
3
17
21
25
28
4
16
17
24
25
5
12
20
17
NP
6
16
22
19
28
7
12
NP
18
22
8
15
18
16
20
9
25
30
27
35
10
18
25
29
32
NP Not Possible
Assuming the total number of hours available on each machine is 65 hours, solve the
machine loading problem using indexing method.
b. List at least four commonly used commercial loading and scheduling
8.
a.
devices
Discuss the advantages and limitation of centralized and decentralized
dispatching system
b. List and explain the basic methods of progress reporting
*****
4
10