Q-5

You have been hired by EMAAR international for their ongoing project in Dubai as
Junior engineer HVAC. Solve the following load estimation problem for them and you
will be awarded a bonus.
Given:
One wall made of stone 16 thick. 5/8 inches of sand plaster on the inside. Partitions
are hollow concrete block light aggregate 8 thick with 5/8 inches of light weight plaster.
Floor is 4 sand aggregate with tile finish. The ceiling is 6 sand aggregate with
suspended insulating board plains of 1. The stone wall is exposed to the east and has a
10ft 5ft steel sash window. The window is double pane ordinary glass with white
venetian blinds on the inside.
Find:
Find actual cooling load through glass for December 3 p.m 300 South latitude, with
equipment operating for 24 hr duration during the peak load periods and a constant
temperature maintained within the room.