to the control account level to allow for identification of a responsible party for WBS for
EVM purposes.
3. Dedicated project/program organization: A project or program manager is assigned to a
large project or program and is given a budget, scope, and schedule. The manager hires and
manages the human resources required for the project or program.
4. Matrix organization: In this type of an organization, the project team member remains a
member of their functional organization, but is assigned to a specific project, and is given
assignments by the project manager rather than by the functional manager. Control account
managers (CAMs) on a project can also fulfill a role as functional managers.
Organisational Breakdown Structures are a good way of organising and communicating the
overall structure of the Project Team.
When coded effectively, the OBS can be combined with the WBS to communicate who is
responsible for which work package or group of deliverables.
A combination of WBS code and OBS code can also be used to identify project budget areas
(cost centres) which then get fully costed once resources are assigned from the Resource
Breakdown Structure.
This then, can become the basis for controlling project cost as well.
References:
http://www.aacei.org/toc/toc_83R-13.pdf
http://www.thecourse-pm.com/Library/OBS.htm
http://www2.lbl.gov/Ops/assets/docs/PMO/PMO%20Procedures/PMO-1.3%20Project
%20Organizational%20Breakdown%20Structure.pdf
http://www.free-management-ebooks.com/dldtem/dltmpm-obs.htm