LEMBAGA PEMBANGUNAN INDUSTRI PEMBINAAN

MALAYSIA (CIDB)
TINGKAT 10, MENARA DATO ONN, PUSAT
DAGANGAN DUNIA PUTRA (PWTC),
NO. 45, JLN TUN ISMAIL, 50480 KUALA LUMPUR

KERTAS TUGASAN
( ASSIGNMENT SHEET )
KOD DAN NAMA
PROGRAM /
PROGRAMS CODE &
NAME

BC-061-1:2015
BASIC SCAFFOLD ERECTION, ALTERATION AND
DISMANTLING

TAHAP / LEVEL

NO. DAN TAJUK UNIT


KOMPETENSI /
COMPETENCY UNIT NO.
AND TITLE

BC-061-1:2015-C04
INDEPENDENT WITH RETURN SCAFFOLD ERECTION,
ALTERATION AND DISMANTLING

NO. DAN PENYATAAN


AKTIVITI KERJA / WORK
ACTIVITIES NO. AND
STATEMENT

1. COMPLY WITH SAFETY, HEALTH AND


ENVIRONMENT REQUIREMENTS
2. PERFORM SCAFFOLD DESIGN SKETCHING
3. PREPARE SCAFFOLD SITE
4. ERECT FRAME SCAFFOLD
5. ERECT TUBULAR SCAFFOLD
6. ERECT MODULAR SCAFFOLD
7. PERFORM HOUSEKEEPING

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 1


Drp / of
: 8

TAJUK/TITLE:
INDEPENDENT WITH RETURN SCAFFOLD ERECTION, ALTERATION AND
DISMANTLING
TUJUAN/PURPOSE :

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 2


Drpd/of : 8

This Assignment Sheet is intended to assess understanding and knowledge of


trainees in the on tubular, modular and frame scaffold for Independent with Return
Scaffold erected, altered and dismantled.

ARAHAN / INSTRUCTION:
Trainees are required to answer all question with reference of Information Sheet BC061-1:2015-C04/P(1/1).
This paper consistes of four (4) questions:a. Part A : Multiple Choice Question
b. Part B : True or False Question
c. Part C : Matching/Fill in the Blank Question
d. Part D : Short Answer Question
1. Time allowed: 20 minutes
2. Not impersonate or imitate opportunities to other trainees.
SOALAN/QUESTION :
PART A: MULTIPLE CHOICE QUESTION
Arahan/Direction : Circle the correct answer.

1. What is the opening distance ledger for light duty scaffold?


A. 3 m
B. 2.4 m
C. 1.5 m
D. 1.8 m
(1 Mark)
2. What is the opening distance ledger for medium duty scaffold?
A. 3 m
B. 2,4 m
C. 1.5 m

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 3


Drpd/of : 8

D. 1.8 m
(1 Mark)

3. What is the opening distance ledger for heavy duty scaffold?


A. 3 m
B. 2.4 m
C. 1.5 m
D. 1.8 m
(1 Mark)
4. What is the opening distance transom for heavy duty scaffold?
A. 3 m
B. 2.4 m
C. 1.5 m
D. 1.8 m
(1 Mark)

5. What is the opening distance transom for medium duty scaffold?


A. 3 m
B. 2.4 m
C. 1.5 m
D. 1.8 m
(1 Mark)

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 4


Drpd/of : 8

PART B: TRUE OR FALSE QUESTION


Arahan / Direction : Tick () if TRUE and mark (X) if FALSE.
1.

All alteration to existing scaffoldings should be carried out in such a

2.

way that the stability of the scaffold is not impaired.


Open guardrail and toe board if it prevent entry process or material

3.
4.

goods.
The maximum lift height is 3.0m.
During dismantling, no component which endangers the stability of

5.

the remaining structure will not be removed.


Materials should be lowered to the ground as the scaffold is
dismantled progressively.
(5 Marks)

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 5


Drpd/of : 8

PART C: MATCHING/FILL IN THE BLANK QUESTION


Arahan / Direction : Please fill in the blank with the appropriate answer.
installation

building

putlog

1.

The inner row is set as close to the .. as is practicable.

2.

Form two (2) side by side on the base plate. (En. Nik perlu
tukar soalan)

3.

Replace the transom using RAC and make leveling. Transom length to form
the letter .. (En. Nik perlu tukar soalan)

4.

Install ledger, transom, bracing and .. on the second lift.

5.

Planning erection with the of sole board and


adjustable baseplate on each standard.
(5 Marks)

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 6


Drpd/of : 8

PART D : SHORT ANSWER QUESTION


Arahan / Direction : Please fill in the blank with the appropriate answer.
1.

Define independent with return scaffold.


............................................................................................................................
............................................................................................................................
(2 Marks)

2.

Illustrate independent with return scaffold..

(2 Marks)

NO. KOD / CODE NO.


3.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 7


Drpd/of : 8

Identify two (2) ways inspection of independent with return scaffold. for
standards.
i)

....................................................................................................................
...................................................................................................................

ii) ....................................................................................................................
...................................................................................................................
(4 Marks)
4.

Give one (1) defective mark when inspection of tube.


i)

....................................................................................................................
(1 Marks)

5.

Identify one (1) way inspection of independent with return scaffold. for
couplers
i)

....................................................................................................................
(1 Marks)

MARKING SCHEME (disimpan oleh Tenaga Pengajar)


PART A: MULTIPLE CHOICE QUESTION
1. A
2. B
3. B
4. D
5. D
BAHAGIAN B: TRUE AND FALSE QUESTION
1. True
2. True
3. False

4. False

The maximum lift height is 2.0m

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 8


Drpd/of : 8

During dismantling, no component which endangers the stability of the


remaining structure should be removed

5. True
PART C: MATCHING/FILL IN THE BLANK QUESTION
1. Building
2. Standard
3. L
4. Putlog
5. Installation

BAHAGIAN D: SOALAN JAWAPAN PENDEK


1. Define independent with return scaffold.
An independent scaffold consists of a double row of standards, with each row
parallel to the building
2. Illustrate independent with return scaffold..

NO. KOD / CODE NO.

BC-061-1:2015-C04/T(1/1)

Muka Surat / Page : 9


Drpd/of : 8

3. Identify two (2) ways inspection of independent with return scaffold. for
standards.
i) Must be vertical and stable
ii) Joints should be made with sleeve couplers, or parallel couplers and
staggered.
4. Give one (1) defective mark when inspection of tube.
i) Check all tubes of splits, flattened ends and corrosion.
5. Identify one (1) way inspection of independent with return scaffold for couplers
i) Check that only correct couplers are used for right position and that
they are fully tightened