Professional Documents
Culture Documents
Kertas Tugasan 1 (1) 2
Kertas Tugasan 1 (1) 2
MALAYSIA (CIDB)
TINGKAT 10, MENARA DATO ONN, PUSAT
DAGANGAN DUNIA PUTRA (PWTC),
NO. 45, JLN TUN ISMAIL, 50480 KUALA LUMPUR
KERTAS TUGASAN
( ASSIGNMENT SHEET )
KOD DAN NAMA
PROGRAM /
PROGRAMS CODE &
NAME
BC-061-1:2015
BASIC SCAFFOLD ERECTION, ALTERATION AND
DISMANTLING
TAHAP / LEVEL
BC-061-1:2015-C04
INDEPENDENT WITH RETURN SCAFFOLD ERECTION,
ALTERATION AND DISMANTLING
BC-061-1:2015-C04/T(1/1)
TAJUK/TITLE:
INDEPENDENT WITH RETURN SCAFFOLD ERECTION, ALTERATION AND
DISMANTLING
TUJUAN/PURPOSE :
BC-061-1:2015-C04/T(1/1)
ARAHAN / INSTRUCTION:
Trainees are required to answer all question with reference of Information Sheet BC061-1:2015-C04/P(1/1).
This paper consistes of four (4) questions:a. Part A : Multiple Choice Question
b. Part B : True or False Question
c. Part C : Matching/Fill in the Blank Question
d. Part D : Short Answer Question
1. Time allowed: 20 minutes
2. Not impersonate or imitate opportunities to other trainees.
SOALAN/QUESTION :
PART A: MULTIPLE CHOICE QUESTION
Arahan/Direction : Circle the correct answer.
BC-061-1:2015-C04/T(1/1)
D. 1.8 m
(1 Mark)
BC-061-1:2015-C04/T(1/1)
2.
3.
4.
goods.
The maximum lift height is 3.0m.
During dismantling, no component which endangers the stability of
5.
BC-061-1:2015-C04/T(1/1)
building
putlog
1.
2.
Form two (2) side by side on the base plate. (En. Nik perlu
tukar soalan)
3.
Replace the transom using RAC and make leveling. Transom length to form
the letter .. (En. Nik perlu tukar soalan)
4.
5.
BC-061-1:2015-C04/T(1/1)
2.
(2 Marks)
BC-061-1:2015-C04/T(1/1)
Identify two (2) ways inspection of independent with return scaffold. for
standards.
i)
....................................................................................................................
...................................................................................................................
ii) ....................................................................................................................
...................................................................................................................
(4 Marks)
4.
....................................................................................................................
(1 Marks)
5.
Identify one (1) way inspection of independent with return scaffold. for
couplers
i)
....................................................................................................................
(1 Marks)
4. False
BC-061-1:2015-C04/T(1/1)
5. True
PART C: MATCHING/FILL IN THE BLANK QUESTION
1. Building
2. Standard
3. L
4. Putlog
5. Installation
BC-061-1:2015-C04/T(1/1)
3. Identify two (2) ways inspection of independent with return scaffold. for
standards.
i) Must be vertical and stable
ii) Joints should be made with sleeve couplers, or parallel couplers and
staggered.
4. Give one (1) defective mark when inspection of tube.
i) Check all tubes of splits, flattened ends and corrosion.
5. Identify one (1) way inspection of independent with return scaffold for couplers
i) Check that only correct couplers are used for right position and that
they are fully tightened