PUBLIC WORKS DEPARTMENT

GOVERNMENT OF KERALA

KERALA STATE TRANSPORT PROJECT - II


(UNDER WORLD BANK ASSISTANCE Loan No. 8254)

MONTHLY PROGRESS BRIEF

NOVEMBER 2015

Project Management Team


Kerala State Transport Project
T.C.11/339, JAGAD Building
Keston Road, Nanthancode,
Kawdiar P.O.
Thiruvananthapuram - 695003

MonthlyProgressBriefNovember2015

Page1

PU
UBLIC WORKS DE
EPART
TMENT
T
G
GOVE
ERNME
ENT OF
O KER
RALA

KER
RALA STAT
TE TR
RANSP
PORT PROJ
JECT - II
(UNDE
ER WORLD BANK ASSISTA
ANCE Lo
oan No. 8254)
8

MONT
THLY P
PROGR
RESS BRIEF

NO
OVEM
MBER
R 201
15

Projec
ct Mana
agemen
nt Team
m
Kerala State
S
Transport Proje
ect
T.C.11/339, JAGA
AD Buildin
ng
nthancode,,
Keston Road, Nan
hapuram - 6
695003
Kawdiarr P.O., Thirruvananth

TABLE OF CONTENTS
Kerala State Transport Project-II.................................................................................................................... 5
1.1

Project location map ............................................................................................................................................. 5

Introduction ........................................................................................................................................................... 6

1.2
Project Development Objectives....................................................................................................................... 6
1.3
Outline Project Data: ............................................................................................................................................ 6
1.4
Overall Implementation: ...................................................................................................................................... 8
1.5
Project Components ............................................................................................................................................. 9
2.1
Project Description ................................................................................................................................................ 9
2.2
Road Upgradation Under Item Rate Contract:- ......................................................................................... 9
2.3
Sub Component A1 (US$322 mn).................................................................................................................. 10
2.4
Supervision Consultancy.................................................................................................................................... 10
2.5
Sub Component A2 (US$ 91 mn) .................................................................................................................. 10
2.6
Component B Road Safety Management (US$ 22 mn) ....................................................................... 11
2.7
Component C Institutional Strengthening (US$ 10 mn) .................................................................... 11
2.8
Project Cost and Disbursement ....................................................................................................................... 12
2.9
Graphical Representation of the Progressive Expenditure and Amount Reimbursed Status as
on October 2015 ................................................................................................................................................................ 13
2.10 Physical Progress of Finished Pavement Works (km) .............................................................................. 14
3.0 Executive Summary............................................................................................................................................... 14
3.1
Upgradation Works ............................................................................................................................................. 14
3.2
Summary of Progress (works) .......................................................................................................................... 15
3.3
General Issues: ........................................................................................................................................................ 16
3.4
Stringent Actions for Breach of Contract: ................................................................................................. 17
4.1
CURRENT STATUS OF WORKS .................................................................................................................. 18
4.2
Contract Package I ................................................................................................................................................ 18
4.3
Contract Details ..................................................................................................................................................... 18
4.4
Progress of Works................................................................................................................................................ 19
4.5
Schedule of Culverts and Drainage works ................................................................................................. 20
4.6
Progress Considering the Contract price up to November 2015. ................................................... 20
4.7
Physical progress Bar Chart .............................................................................................................................. 21
4.8
S-Curve ...................................................................................................................................................................... 21
4.9
Strip map ................................................................................................................................................................. 22
4.10 Potential Issues ...................................................................................................................................................... 23
4.11
Payments to the Contractor ............................................................................................................................ 23
4.12 Implementation of EMP ..................................................................................................................................... 23
4.13 Photograph ............................................................................................................................................................ 24
4.14 Contract Package II.............................................................................................................................................. 25
4.15 Contract Details .................................................................................................................................................... 25
4.16 Progress of Works...............................................................................................................................................26
4.17 Work progress considering the contract price (end October 2015) ............................................... 27
4.18 Physical Progress .................................................................................................................................................. 28

4.19 S-Curve ........................................................................................................................................................... 28


4.20
Strip Chart............................................................................................................................................ 29

4.21
4.22
4.23
4.24
4.25

Schedule of culverts and drainage works ....................................................................................................29


Potential Issues ..................................................................................................................................................... 30
Payments to the Contractor ........................................................................................................................... 30
Implementation of EMP .................................................................................................................................... 30
Photographs ........................................................................................................................................................... 32

4.27
5.1
5.2
5.3
5.4

Contract Details .................................................................................................................................................... 33


Contract Package IVA ...................................................................................................................................... 34
Contract Details ................................................................................................................................................... 34
Utilities ..................................................................................................................................................................... 35
Mobilization of Resources ................................................................................................................................ 35

4.26

Contract Package III ..................................................................................................................... 33

MonthlyProgressBriefNovember2015

Page3

5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
6.1
6.2
6.3
6.3.1
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11

Work Progress ...................................................................................................................................................... 35


Physical Progress: .................................................................................................................................................36
S-Curve .....................................................................................................................................................................36
Potential Issues ......................................................................................................................................................36
Schedule of culverts and drainage works .................................................................................................... 37
Payment .................................................................................................................................................................... 37
Implementation of EMP ..................................................................................................................................... 37
Photographs ...........................................................................................................................................................39
Contract Package IV .......................................................................................................................................... 40
Contract details: ................................................................................................................................................... 40
Pre-Construction Activities: .............................................................................................................................. 41
Utilities ...................................................................................................................................................................... 41
Mobilization of Resources ................................................................................................................................. 41
Work Progress ....................................................................................................................................................... 41
Physical Progress ................................................................................................................................................. 43
S-Curve .................................................................................................................................................................... 43
Schedule of culverts and drainage works ................................................................................................... 44
Implementation of EMP .................................................................................................................................... 44
Payments ................................................................................................................................................................. 46
Photographs .......................................................................................................................................................... 47

7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10

Contract details: ................................................................................................................................................... 48


Utilities .................................................................................................................................................................... 49
Work Progress ..................................................................................................................................................... 49
Bar chart ................................................................................................................................................................. 50
S-Curve .................................................................................................................................................................... 50
Schedule of culverts and drainage works ..................................................................................................... 51
Key issues: ................................................................................................................................................................ 51
Payment to the contractor ................................................................................................................................ 51
Implementation of EMP ...................................................................................................................................... 51

7.11
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9

Photographs ........................................................................................................................................................... 53
Contract Package VI .......................................................................................................................................... 54
Contract details: ................................................................................................................................................... 54
Financial Progress: ................................................................................................................................................ 55
Structural Work .................................................................................................................................................... 55
Bar Chart of Physical Progress: .......................................................................................................................56
S-Curve .....................................................................................................................................................................56
Implementation of EMP ..................................................................................................................................... 57
Payment to contractor .......................................................................................................................................59
Photographs .......................................................................................................................................................... 60

10.1

Contract Package VII ........................................................................................................................................... 61

15.1
16.1
17.1
18.1
19.1

Payment to the consultants as on end September 2015:.......................................................................63


Overlay to 150 km KSTP-I Roads ..................................................................................................................63
Meetings, Site visits & Inspection ..................................................................................................................63
Land Acquisition Status .................................................................................................................................... 64
Status on Critical Actions identified by World Bank .............................................................................65

7.1 Contract Package V................................................................................................................................... 48

15.4 Compliance with Statutory Clearances .............................................................................................. 51


15.5 Traffic Management and Road Safety Measures ........................................................................... 52

9.1 Contract Package VIII................................................................................................................................ 61


11.1 Proactive actions taken by employer:.................................................................................................. 61
12.1 Road Safety Component Current Status ...................................................................................... 62
14.1 Institutional Strengthening Components Current Status ...................................................... 62

20.1Current Status of Six Point Program: ................................................................................................ 67


21.1 List of Annexure: ....................................................................................................................................... 68

MonthlyProgressBriefNovember2015

Page4

Kera
ala Sta
ate Trranspo
ort Pro
oject-III
1.1 Prroject location map
m

Introduction
Government of Kerala has decided to take up Phase-II upgradation component of KSTP
as a standalone project, the KSTP-II. The project envisages the upgradation of 363 km
of SH and MDR, Road Safety Management and Institutional Strengthening of PWD. The
total Project cost is 445 million USD out of which 216 million USD is loan assistance
from World Bank. The project loan agreement was signed on June 19, 2013 at the DEA
Office, New Delhi.

The loan effectiveness date is September 6, 2013.

The project

implementation period is five years, up to 30 November 2018.

1.2 Project Development Objectives


The Project Development objective is to improve condition, traffic flow and road safety
with a focus on vulnerable road user on Kerala State Core road networks comprising of
363 Km of state highways. The main beneficiaries of the Project will be the users living
along the Project corridors mainly the travelling public, agricultural and industrial
producers, consumers and local community. The main benefit is in the form of reduced
transport bottlenecks, lower passenger freight transport costs, reduced travel time and
improved road safety in terms of reducing severe crashes and injury. The roads
identified for improvement passes through about 87 villages covering eight districts.

1.3 Outline Project Data:


The upgrading works for six roads are included in t he KSTP-II. The major items of
works included are improvement to gradient, widening and strengthening the roads
including minor realignments wherever essential, reconstruction of narrow bridges and
culverts and improvements to drainage system. A Bypass also is proposed at Thiruvalla.
The carriageway proposed are generally 2 lane with 1.50 mt. slow lanes on either side
with hard shoulders and drains for a total width of 12 meters. The ROW is generally 15
Meters. The specification for civil works are as per MORTH & IRC standards.
The land acquisition for the project roads are almost completed except in the
Perimbilavu- Pattambi- Perinthalmanna Road.

1.3.0.1

Kasargod Kanhangad Road SH 57

Length - 27.76 km.Covers Kasargod, Pallikkara, manikoth and Kanhad areas and
Tourist destinations at Bakel Fort and Ezhimala come under this stretch.

1.3.0.2
Length

Pilathara Pappinissery Road


20.90

km.

Covers

Pilathara,

Cheruthayam,

Kunnupuram

and

Pappinissery.

MonthlyProgressBriefNovember2015

Page6

1.3.0.3

Thalassery - Valavupara Road SH 30

Length 53.12 km. It is a part of SH 30 Thalasserry Coorg Road and passes


through Koothuparambu, Mattannor, and Irutty.

1.3.0.4

Chengannur - Ettumanoor Muvattupuzha SH1

Chengannur Ettumanoor Muvattupuzha stretch of SH-1, MC (Main Central) Road, one


of the most important and oldest roads in Kerala passing through Thiruvalla,
Changanasserry, Kottayam, Ettumannor, Kuravilangad, Kuttathukulam.
Total length covered is 88 kms.
Road portion from Thiruvananthapuram (Venjaramoodu) to Chengannur was taken up
under Phase I. Bypass at Thiruvalla also forms part of this stretch. The road passes
through the plantation areas and provides access to the tourist centres Kumarakom and
Thekkady.13 bridges will be constructed in this stretch.
The improvement for this road portion is proposed in three construction packages,
Chengannor- Ettumannor(41 km), Ettumanoor-Muvattupuzha (47km) and Thiruvalla
Bypass (2.4km).

Reconstruction of three Major Bridges and Nine Minor Bridges are

included in this stretches.

1.3.0.5

Punaloor - Ponkunnam Thodupuzha SH 8

Punaloor Ponkunnam Thodupuzha stretch of SH 8 is included in this package.


Total road length is 132 kms.
Major areas covered are Punaloor, Pathanapuram, Manimala, Pala and Thodupuzha.
Five Bridges will be constructed in this stretch. The road passes through KollamPathanamthitta, Kottayam and Idukki districts. The portion from Punalur-Ponkunnam
is proposed under PPP (modified annuity) arrangement.

The bidding documents are

prepared through the Transaction Advisor and are under scrutiny.

1.3.0.6

Perumbilavu - Pattambi Perinthalmanna SH 39

Perumbilavu- Pattambi-Perinthalmanna Road Link of SH 39 is included in the package


(Starts

at

Kuttinad

Length: 41 kms.

Jn).

The

growth

centre

connected

is

Pattambi

town

The road passes through Thrissur, Palakkad and Malappuram

Districts.

The details of approval are as under:


Project appraisal

April 2013

Loan agreement signed

19 June 2013

Loan Effectiveness date

Sept 6, 2013

MonthlyProgressBriefNovember2015

Page7

Project

cost

approved

by

World -

US$445 ml

Bank
World Bank (IBRD) Loan Assistance

US$216 ml

Project implementation period

30th Oct 2013 to Dec 31, 2018

Expected closing date (Loan)

April 30, 2019

Fiscal Year
Allocation
Annual
Cumulative

1.3.0.7

FY 2014

FY 2015

FY 2016

FY 2017

FY 2018

FY 2019

22
22

43
65

45
110

54
164

32
196

20
216

The Finance plus agenda of KSTP II

1.

Upgrading Punalur Ponkunnam Road under PPP (Annuity)

2.

Development of Model Safe Corridor Kazhakuttam Adoor Section (80 km)

3.

Development of Oxbow land (left out lands)

4.

Construction of Head Quarter Building for PWD / KSTP under green building

concept

1.4 Overall Implementation:


Project Staffing: KSTP is managed by a Project Director, in the Rank of a senior level Chief
Engineer assisted by one Chief Engineer, a Superintending Engineer and other engineers
and officers.

The Technical Wing headed by the Chief Engineer is responsible for

activities related to engineering, environment, social and contract management. Further,


the legal contract management cell is headed by a legal professional. KSTP has qualified
and experienced Social and Environmental Experts and a Project Management Advisor.
The Finance Wing headed by a Finance Controller (deputed from the Secretariat) has a
qualified Finance Manager with support staff. On the field, the KSTP has Two
Superintending Engineers, Five Divisions located at Kottarakkara, Muvattupuzha,
Kuttippuram, Kannur, Ponkunnam each headed by an Executive Engineer to monitor
project progress.
Project co-ordination: Govt. of Kerala has established two committees to monitor, coordinate,
and expedite project activities. The Project Steering Committee chaired by the Chief Secretary, has
its main functions to review and approval of recommendations regarding acceptance of
tenders and taking the final decisions on all matters concerning procurement and
monitoring of project activities.

The members of the committee are Additional Chief

Secretary (Finance), Secretaries to Government, PWD, Law Department, Revenue, Chief


Engineer, R&B, Project Director, KSTP, Chief Engineer (Projects) KSTP.

There is an

Evaluation Committee headed by the PWD Secretary and comprising the Project
MonthlyProgressBriefNovember2015

Page8

Director, KSTP and Chief Engineer (Projects), to make recommendations on any issues
on procurement as may require approval of the Steering Committee.

1.5 Project Components


1.5.0.1

Road Upgrading Works:

This component will include upgrading 363 kms of strategically important State
Highways to complete network connectivity in the state with the objective of reducing
travel time between key socio-economic centers.

1.5.0.2

Road Safety Management:

This component will support the strengthening of the road safety management systems
in Kerala with the objective of arresting the increase of crash fatalities in the state. This
component will finance various initiatives building on the work already undertaken
during the first project including a safe corridor demonstration project, implementation of
local level programs utilizing the challenge fund and advisory support for road safety
activities. The road section improved under KSTP-I from Kazhakuttom - VenjaramooduAdoor is proposed to be developed as Safe Corridor Demonstration Project (80 km)

1.5.0.3

Institutional Strengthening:

The objective of this component is to improve the sustainability of Keralas state road
network with respect to its functional adequacy, financial viability and capacity of key
state road sector institutions to deliver road infrastructure and services that are
responsive to road user needs.
Sector.

The major initiatives include Modernization of Road

The development and Management of a Strategic Road Network is proposed

under the Road Sector Modernization Program.

2.1 Project Description


2.2 Road Upgradation Under Item Rate Contract:This component will include upgrading of 240 km of State Highways through FIDIC
based input contracts and conventional item rate contracts as noted below.
1.

Pilathara - Pappinissery Road

20.90 km

2.

Kasaragod Kanhangad Road

27.76 km

3.

Thalassery Valavupara Road

53.10 km

4.

Ponkunnam Thodupuzha Road

50.30 km

5.

Chenganur Ettumanoor Road

41.00 km

6.

Ettumanoor Muvattupuzha Road

47.00 km

MonthlyProgressBriefNovember2015

Page9

2.2.0.1

Road upgradation under PPP (Hybrid Modified Annuity)

mode:Punalur - Ponkunnam stretch (82 km) of Punalur Thodupuzha Road

Road upgradation under Engineering Procurement


Construction (EPC) mode:-

2.2.0.2

Perimbilavu Pattambi- Perinthalmanna Road 41 km

2.3 Sub Component A1 (US$322 mn)


Consists of the following civil contracts:
SI.
NO.

CONTRACT PACKAGE

NAME OF WORK

LENGTH (KM)

1.

KSTP-II/UG-1

Kasargod Kanhangad

27.78

2.

KSTP-II/UG-2

Pilathara Pappinisery

20.90

3.

KSTP-II/UG-3

Thalassery Valavupara

54.00

4.

KSTP-II/UG-4

Chengannoor - Ettumannoor

45.40

5.

KSTP-II/UG-5

Ettumannoor- Muvattupuzha

40.96

6.

KSTP-II/UG-4A

Thiruvalla Bypass along Chengannoor Ettumannoor

2.3

7.

KSTP-II/UG-6

Ponkunnam - Thodupuzha

50

8.

KSTP-II/UG-

Punalur-Ponkunnam

82

9.

KSTP-II/UG-7

Perumbilavu - Perinthalmanna

41

2.4 Supervision Consultancy


Under this component, 2 supervision consultancies CSC1 and CSC 2, 2 Independent
engineering services, Transaction Advisory Service for PPP are included. Contract
Agreement for Consultancy for CSC 1 for 190 Km of upgradation road has been executed
with M/s Egis International in JV with Egis India Consulting Engineers Pvt. Ltd on
28.02.2013 and mobilized and in place.

Egis has established rented office for Team

Leader at Thiruvananthapuram near to Clients Office and started functioning from April
2013. Also RE offices at Kanhangad in Kasargod District for package - 1, Pazhyangadi in
Kannur District for package II and at Uliyil near Mattannur in Kannur District for
package III, Pallam in Kottayam for Package IV, for Package V atKoothattukulam.
M/s MSV International USA is the selected consultant for Construction Supervision for
the Ponkunnam Thodupuzha stretch (50 km) CSC-2.

They have established their

Resident Engineer cum Team Leader office at Ponkunnam. The length of road covered is
50 km and the assignment commenced on 15 May 2014.

2.5 Sub Component A2 (US$ 91 mn)


DPR for this sub component (Punalur Ponkunnam 82 Km under PPP) completed and
schedule prepared by the consultants. M/s L&T Ramboll, Chennai in association with
M/s Fortress has been selected for the Transaction Advisory Services and activities in
MonthlyProgressBriefNovember2015

Page10

progress. The Investor Meet was held on March 2015 at Kochi. The bidding process for
pre-qualifying bidder is expected to commence by end December 2015.

2.6 Component B Road Safety Management (US$ 22 mn)


The baseline survey for the proposed safe demonstration corridor has been completed by
NATPAC and report shared with Bank. M/s VicRoads, Australia has been selected as
consultant for Road Safety Capacity Building and program management and activities in
progress. The design activities on the Safe Corridor Demonstration Project (SCDP) are in
progress.

2.7 Component C Institutional Strengthening (US$ 10 mn)


2.7.0.1 Consultancy Services
Procurement for the following Consultancy services was initiated. Some are completed
and others are at different stages of progress
1. Consultancy for Road User Perception Survey has been completed for 363 Km of
Project Roads through M/s Sherwood Consultants and report shared with Bank.
2. Consultancy for Prioritization and DPR Preparation for 1000 Km of Improvement
of State roads was entrusted with M/s Egis India Consulting Engineers Pvt. Ltd
and final report submitted. DPR for 439 km roads has been completed.

The

preliminary project report was submitted to Government for posing for External
Financial Assistance.
3. Consultancy for Strategic Option Study (SOS) for 8570 Km newly declared MDR
was completed by M/s CDM Smith Associates Pvt. Ltd. Study report has been
handed over to PWD and further action to improve these roads will be taken by
them using their own funds.
4. Consultancy service for Developing Multi Model Integrated Transport Hub at 3
cities, Trivandrum, Kozhikode and Kochi was completed and report forwarded to
Government. This report was also shared with NATPAC for consideration while
preparing Comprehensive City Development Projects.
5. The ToR on Strategic Road Network in Package II, III and IV has been sent to
Bank for review. The Client Executive Program Sponsor has been identified and
contract signed and functioning. The EoIs for the Packages have been received
and evaluated. The RFP is being submitted to Bank.
6. Rebidding for the selection of consultant for Development of Integrated
Information management System is in progress.

The Technical and Financial

proposals have been received and is under evaluation.

MonthlyProgressBriefNovember2015

Page11

7. The Project Management Software has been installed and training given to CSC
and KSTP Engineers. The PMS is operationalized.
8. The assignment for Community Participatory Road Safety and Asset Management
is now proposed for re-bidding.
9. The ToR for PMC with Post Construction Audit functions has been prepared and
89th Steering Committee has not taken any decision as it has to be discussed at
the next mission of World Bank.

2.8 Project Cost and Disbursement

Sl
No

Claim

DISBURSED
AMOUNT
CLAIMED
USDin
inLakh

EXPENDITURE
inLakh

Date

millions

TOTAL

1
2
3
4
5

Frontend
fee
Retroactive
1stQuarter
2nd
Quarter
3rdquarter
4thquarter

1stQuarter
201415

2nd
Quarter

3rdQuarter

9.

4thQuarter

10.

4thQuarter

11.

1stQuarter
201516

12
13.

BALANCEFUNDS
AVAILABLEFOR
CLAIM(MUSD)

MonthlyProgressBriefNovember2015

TOTAL

15.06.12to
1,863.95
15.06.13

01.07.13to
1,355.79
30.9.13
01.10.13to
1,906.01
31.12.13
01.01.14to
2,696.00
20.03.14
21.03.14to
53.79
31.03.14
01.04.14to
1,826.41
18.06.14
19.06.14to
14.69
30.06.14
01.07.14to
1,405.61
30.09.14
30.09.14to
3,790.21
31.12.14
01.01.2015to
3,706.35
28.02.2015
01.03.2015to
31.03.2015
01.04.2015to
3,704.89
06.06.2015
3534.13
and
30.06.2015
154.40

2nd Quarter
30.09.2015
201516
01.10.2015to
3rdQuarter
30.11.2015

Total

TOTAL

TOTAL

1,043.00

764.00
1,071.00
1,510.00
30.00
1,023.00
8.23
787.00
2,124.00
2,076.00

216.00
0.54

1.69

1.23

1.71

2.50

0.05

1.70

0.01

1.27

3.44
3.32

215.46
213.77
213.77
212.54
210.82
208.32
208.27
206.57
206.56
205.29
201.85
201.85

2,075.00

3.32

195.21

1991.00
86.00

3.13
0.14

192.08

3527.06

1977.00

3.04

188.90

4695

188.90

30707

16,565.23

27.10

Page12

Estimated Actual loan allocation and disbursement received


(Banks Financial Year (January to December) (US$ million)
Fiscal Year
Allocation
Annual
Cumulative
Disbursement
Received so far
Cumulative

FY 2014
(Jan-Dec)

FY 2015
(Jan-Dec)

FY 2016
(Jan-Dec)

FY 2017
(Jan-Dec)

FY 2018
(Jan-Dec)

FY 2019
(Jan-Dec)

22
22

43
65

45
110

54
164

32
196

20
216

14.15

12.95

14.15

27.10

2.9 Graphical Representation of the Progressive Expenditure and Amount


Reimbursed Status as on October 2015
Year
2013-14
2014-15
2015-16
(upto end November 2015)
2016-17
2017-18
2018-19

Cumulative Expenditure
(INR Crores)
78.75
223.23

Progressive Amount
Reimbursed (INR Crores)
44.42
125.40

307.07

165.91

350

300

250

200

CumulativeExpenditure(INR
Crores)

150

ProgressiveAmount
Reimbursed(INRCrores)

100

50

0
1

MonthlyProgressBriefNovember2015

Page13

2.10 Ph
hysical Proogress of Finished
F
P
Pavement Works
W
(km
m)

BC

15.35

DBM

44
4.08

K
KM
WMM

4
44.85

GSB

47.45

10

1
15

20

25

30
0

35

40

45

50

3.0 Ex
xecutiv
ve Sum
mmary
3.1 Up
pgradation Work
ks
The worrk for Pack
kages 1,2,4,4A,5 and 6 are in progress.
p
T
The work in
n Package 3 was
terminatted due to poor perfo
ormance off the contrractor, and
d under arrrangement as 3A
and 3B. The work
k for Packag
ge 8 is und
der PPP (Hy
ybrid Annuity) and bid
dding is ex
xpected
to comm
mence by end
e
Novem
mber 2015.

The worrk for Pack


kage 8 is not
n
taken up as

upgrada
ation due to non av
vailability of land.

This is b
being take
en up as Heavy

Mainten
nance within
n the availa
able land.
363 Km of upgrada
ation civil works
w
are d
divided into 9 Contractt packages..
SI.
CONTRAC
CT
NAM
ME OF WOR
RK
CO
ONTRACTOR
R
NO.
PACKAG
GE
1.

KSTP-II/UG-1

Kasarg
god Kanhangad

RDS Projects, Ko
ochi

2.

KSTP-II/UG-2

Pilatha
ara Pappinisery

RDS Projects, Ko
ochi

3.

KSTP-II/UG-3

Thalass
sery Valav
vupara

T
Terminated

4.

KSTP-II/UG-4

Chengann
noor - Ettumannoor

Delm
ma-Sreedhan
nya
JV

5.

KSTP-II/UG-5

Ettumann
noor- Muva
attupuzha

NAPC
C Ltd, Chenn
nai

6.

K
KSTP-II/UG
G-4A

Thiruva
alla Bypass
s along
(Chengann
noor Ettu
umannoor)

EKK
K & Co, Koch
hi.

7.

KSTP-II/UG-6

Ponkunnam - Thodupuzha

GHV EKK JV

8.

KSTP-II/UG-7

Perumbilavu Perinthalmanna (EPC)

LA initiated

KSTP-II/UG-8

Punalur Ponkunnam (PPP)

TA consultancy in
progress

The works are being executed under FIDIC (5th edition) Conditions of Contract.

The

work involves improvement of State Highways including geometric improvements and


realignments to standard 2 lane of 7 m carriageway, 1.5 m paved shoulders. The
Construction Works include:

Widening the existing pavement where it is less than design width;

Scarification, clearance, earthworks,

granular sub-base, wet mix macadam base course, bituminous mix surfacing,

Construction of overlays to the existing pavement, inclusive of regulating course


to a designed vertical profile;

Geometric realignments at specific locations;

Construction of paved shoulders;

Construction and maintenance of diversion roads

Construction of lined and unlined longitudinal drains, covered drains and


footpaths in urban areas;

New culverts, new bridges and rehabilitation of existing bridges/culverts and


protective works

Provision of road signs and markings;

Provision of traffic safety features - road furniture and other road safety
appurtenances,

Routine maintenance and maintenance during Defects Notification Period.

Environmental protection measures and Social enhancement works/ landscaping


works etc.

3.2 Summary of Progress (works)


The following tables present the summary of progress in each contract package during
the month under report (November 2015).

Contract packages

Contract value
(Rs. Crore)

Cumulative

Achieved

target in

cumulative

percentage up to

percentage upto

end of September

end of the

2015

September 2015

Balance period
(months)

KSTP/PMT/UG-I

1,33,05

77.51%

32.78%

7 (extended)

KSTP/PMT/UG-II

118.20

86.35%

30.50%

KSTP/PMT/UG-III

234.99

MonthlyProgressBriefNovember2015

Work terminated
and being
Page15

rearranged
KSTP/PMT/UG-V

171.49

45.43%

13.38%

31.80

77.80%

33.40%

KSTP/PMT/UG-VI

227.13

51.86%

56.54%

12

KSTP/PMT/UG-IV

293.58

21.85%

13.32%

23

KSTP/PMT/
UG-IVA

3.2.0.1
Name of
consultant
CSC-1 M/s Egis
International in
JV with M/s Egis
India Pvt. Ltd.
CSC-2 M/s MSV
International USA

Details of Supervision Consultancy Assignments:


Contract
signed

Contract
Period

Commence
ment Date

Contract
Amount (Rs.)

28.02.201
3

42
months

04.04.2013

18,36,04,600

14.05.201
4

30
months

14.05.2014

4,41,88200

Work Package
I, II, III, IV,
IVA & V
(190 km)
VI
(50 km)

3.3 General Issues:


The progress is not as per programme. The major factors that hindered the progress of
works were:
1. Delay in obtaining statutory clearances for erection of plants and crushers from
the State Pollution Control Board, Mining and Geology Department and local
bodies.
2. Unprecedented unseasonal rains affected adversely works in all the contract
Packages.
3. Resistance in identifying, erecting and operating crushers and quarry from the
local people.
4. Poor cashflow problems with the contractors.
5. Shortage of machinery, labour force in most of the contracts.
6. Frequent changes made in key personnel in some of the contracts by the
contractor
7. Migrant labours working in all packages and labourers not available during
festival season for long duration.
8. Lack of planning and managerial issues in contracts I, II & V
9. Work Contract-III terminated. Balance works procured under two contract (3A &
3B)
10. Delay in getting Environmental Clearance from Government Agency for excavation
and conveyance of earth from borrow area.

MonthlyProgressBriefNovember2015

Page16

All these issues are now sorted out and the works are in progress now. The contractors
were instructed to speed up the works to show better results.

Contract Package-III

terminated due to poor performance of the contractor.

3.4 Stringent Actions for Breach of Contract:


The contract for Package-III has been terminated due to non performance and
emergency work arranged to make the road motorable and complete. The balance works
are under arrangement in two packages 3A & 3B

For Package V the contractor

responded to the notice under clause 15.1 and improved performance.

The work is

being closely monitored on daily basis by CSC and PMT. For Package 1 and 2 notice
under Clause 15.1 was issued and the contractor has mobilized additional resources
and opened additional work fronts and the work has gained momentum now.

MonthlyProgressBriefNovember2015

Page17

The following sections describe Civil Works Contract packages in


detail:

4.1 CURRENT STATUS OF WORKS


4.2 Contract Package I

Upgradation of Road from Kasargod to Kanhangad of SH 57

Scope of Works
Viaduct
Major Bridge
Minor Bridge
Widening Bridge
New culverts
Widening Slab culverts
Reconstruction
Foot path
Drain
Solar Lights

_
_

1
2
2
2
16
16
9
6.7 Km
22.20 Km

4.3 Contract Details


Letter of Acceptance Date

06.03.2013

Agreement Date

01.04.2013

Name of Contractor

M/s RDS Projects Ltd, Kochi

Contract Price

Rs.133,05,79,485/-

Notice to Commence

24.04.2013

Total Length

27.78 Km

Contract Period

24 months

Completion Date

23-04-2015 extended to

Defect Liability Period

365 days

1st Milestone
2nd Milestone
3rd Milestone

Km. 0+000 Km. 10+000 - 22nd February 2014 revised


to 22 March 2015
Km. 0+000 Km. 20+000 - 23 Oct 2014 revised to 23
Feb 2016
Km. 0+000 Km. 27+780 - 26th April 2015 and revised to
30 June 2016

MonthlyProgressBriefNovember2015

Page18

4.4 Progress of Works


4.4.0.1 Structures
Viaduct at Km.3+392 All 54 Piles completed. Also all 8 Pile Caps, Pier caps and 07nos Deck
slab completed. The Miscellaneous works and approaches retaining wall with PCC/RCC are in
progress.
Chithari Bridge at Km.18+400 Total piles completed. 04nos Pile caps and 04nos Deck Slab
Completed. The Miscellaneous works are in progress.
MS- I Box Culverts All culverts are completed out of 16nos Box Culvert at Km.1+076,
Km.1+750, Km.1+974, Km. 2+215, Km. 2+454, Km. 2+704, Km. 4+970, Km. 5+500, Km. 5+737,
Km. 6+630, Km. 8+894, Km. 11+620 and Km.11+820 have been substantially completed.
Pipe Culvert 01 no. Km.4+320 is completed.
Slab Culverts 05 nos. Km. 7+015, Km. 7+463, Km. 8+093, Km. 8+679 and 9+921 are completed.
MS- II Box Culverts Km. 13+830, Km.15+490, Km.16+427, km.17+816 and km.18+011 are
completed. km.19+364, km.20+365 and km.21+065 are in Progress and remaining 2 nos. of
culverts are yet to be started.
MS- III Box Culverts 07nos culverts are yet to be started.
Box cell Minor Bridges
Km. 2+600 Slab completed at BHS.
Km. 6+510 Slab completed at LHS and RHS retained.
Considering the overall value of estimate of Rs. 133.05 crores, Progress up to 25th Nov2015 in
comparison with revised programme based on EOT- 2
III

I
(Km. 1+000 to Km.
2+800 and Km.
3+800 to Km.
12+000)

(Km. 12+000 to
Km. 22+000)

(Km. 0+000 to Km.


1+000, Km. 2+800 to
Km. 3+800 and Km.
22+000 to Km.
27+780)

Length in km

10

20

27.78

Length handed over to


contractor in km

10

Unencumbered land
available to the
contractor in km

10

20

27.78

Stretch completed in
all respects in km

Milestone

II

20

27.78

FW

HW

FW

HW

FW

HW

GSB completed in km

9.300

0.445

0.990

0.380

0.340

0.110

WMM completed in

9.170

0.430

0.960

0.040

0.210

0.240

MonthlyProgressBriefNovember2015

Page19

III

II

(Km. 1+000 to Km.


2+800 and Km.
3+800 to Km.
12+000)

Milestone

(Km. 0+000 to Km.


1+000, Km. 2+800 to
Km. 3+800 and Km.
22+000 to Km.
27+780)

(Km. 12+000 to
Km. 22+000)

km
DBM completed in km

8.960

0.600

0.930

0.030

0.270

0.100

BC completed in km

5.775

0.620

0.895

0.000

0.000

CD completed in Nos.

22

05

Culverts

MilestoneI
(1to2.8Kmand3.80to12.0Km)

MilestoneII(12to22Km.)

Numberremaining

Numberinprogress

Numbercompleted

No.dwgsapproved

Totalnumber

Numberremaining

Numberinprogress

Numbercompleted

No.dwgsapproved

TotalNumber

Numberremaining

Numberinprogress

Numbercompleted

No.dwgsapproved

Natureofwork

Totalnumber

4.5 Schedule of Culverts and Drainage works

MilestoneIII
(0to1.0Km,2.80to3.80Kmand22to27.78Km.)

WideningSlab/BoxCulverts 9 9 9 1 1
ReconstructionSlab/Box

7 7 7 7 7 4 2 1 2 2

NewBoxCulvert/Pipe
culvert

6 6 6 3 1 1 2 4 4

Totalculverts

22 22 22 10 8 5 2 3 7 7

Bridges/ROBRetained**

2 2

BridgesWidening***

2 2 2

NewBridges/Viaduct*

1 1 1 1 1 1

4.6 Progress Considering the Contract price up to November 2015.


Up to previous
Month (October)
Target
Achieved
70.87%

31.82%

This Month
Target

Achieved

6.64%

0.96%

MonthlyProgressBriefNovember2015

Cumulative to end of this


Month
Target
Achieved
77.51%

32.78%

Page20

4.7 Physical progress Bar Chart

14334
18029
10046

Concreting (cum)

14823
10411
3710

BC (cum)

26990

DBM (cum)

13232
5773

Estimated BOQ Quantity


Cumulative target to end of this Month

79468

WMM (cum)

60747
27697

Cumulative Achieved to end of this Month

63492

GSB (cum)

49177
29717
94397

Subgrade (cum)

71902
13087
56510

Embankment (cum)

44138
28509
184052

Excavation (cum)

160657
94662

50000

100000

150000

200000

Revised Programme (R-5)

Achieved Progress

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

4.8 S-Curve

MonthlyProgressBriefNovember2015

Page21

4.9 Strip map

Chainage (Km)

0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
2100
2200
2300
2400
2500
2600
2700
2800
2900
3000
3100
3200
3300
3400
3500
3600
3700
3800
3900
4000
4100
4200
4300
4400
4500
4600
4700
4800
4900
5000
5100
5200
5300

Culverts & Bridges

On
Cum.
Complet going
ed Work Work
(No/Km (No./K
m)
)

Miscellaneous Works
Bridges Nos

LEFT SIDE

Culverts Nos
Drains and Walls

## ## ##

Bituminous Concrete

##

1070.00

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3340.00

## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3340.00

## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3575.00

## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3590.00

## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3590.00

## ## ## ## ## ##

## ## ## ##

Dense Bituminous Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ##

Granular Sub base

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Subgrade

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

EW - Embankment

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ## ##

Pothole repair & patching

RIGHT SIDE

Pothole repair & patching


EW - Embankment

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3420.00

Subgrade

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3420.00

Granular Sub base

## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3380.00

Wet Mix Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3290.00

Dense Bituminous Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

3290.00

## ## ##

## ## ## ## ##

1225.00

Bituminous Concrete

## ## ## ## ## ##

Drains and Walls

##

## ## ##

## ## ##

## ## ##

##

Culverts Nos
Bridges Nos
Miscellaneous Works

Chainage (Km)

5400
5500
5600
5700
5800
5900
6000
6100
6200
6300
6400
6500
6600
6700
6800
6900
7000
7100
7200
7300
7400
7500
7600
7700
7800
7900
8000
8100
8200
8300
8400
8500
8600
8700
8800
8900
9000
9100
9200
9300
9400
9500
9600
9700
9800
9900
10000
10100
10200
10300
10400
10500
10600
10700

Culverts & Bridges

On
Cum.
Complet going
ed Work Work
(No/Km (No./K
m)
)

Miscellaneous Works
Bridges Nos

LEFT SIDE

Culverts Nos

##

Drains and Walls

##

##

##

##

## ## ## ##

##

## ## ##

## ## ## ## ## ## ##

## ##

Bituminous Concrete

## ## ## ## ## ## ## ## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

4780.00

Dense Bituminous Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Wet Mix Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Granular Sub base

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Subgrade

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

EW - Embankment

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

EW - Embankment

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Subgrade

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Granular Sub base

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Wet Mix Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Dense Bituminous Macadam

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

5400.00

Bituminous Concrete

## ## ## ## ## ## ## ## ## ##

4405.00

Drains and Walls

##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

Pothole repair & patching

RIGHT SIDE

Pothole repair & patching

Culverts Nos

## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ##
##

## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ## ##

## ## ##

##

## ## ##

##

## ##

##

Bridges Nos
Miscellaneous Works

16100

16000

15900

15800

15700

15600

15500

15400

15300

15200

15100

15000

14900

14800

14700

14600

14500

14400

14300

14200

14100

14000

13900

13800

13700

13600

13500

13400

13300

13200

13100

13000

12900

12800

12700

12600

12500

12400

12300

12200

12100

12000

11900

11800

11700

11600

11500

11400

11300

11200

11100

11000

10900

Chainage (Km)

10800

Culverts & Bridges

On
Cum.
Complet going
ed Work Work
(No/Km (No./K
m)
)

Miscellaneous Works
Bridges Nos

LEFTSIDE

Culverts Nos

##

##

##

Drains and Walls


1275.00

Bituminous Concrete

## ## ## ##

Dense Bituminous Macadam

## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ##

Wet Mix Macadam

## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ## ##

Granular Sub base

## ## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ## ##

## ## ## ##

2150.00

Subgrade

## ## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ## ##

## ## ## ##

2150.00

EW - Embankment

## ## ## ## ##

## ## ##

## ## ## ## ## ## ## ## ## ##

## ## ## ##

2050.00

## ## ## ## ## ## ## ## ##

1750.00
1750.00

Pothole repair & patching

RIGHTSIDE

Pothole repair & patching


EW - Embankment

## ## ## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ##

1950.00

Subgrade

## ## ## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ##

1950.00

Granular Sub base

## ## ## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ##

1940.00

Wet Mix Macadam

## ## ## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ##

1940.00

Dense Bituminous Macadam

## ## ## ## ## ##

## ## ## ## ## ## ## ## ## ## ## ##

1840.00

Bituminous Concrete

## ## ## ##

Drains and Walls


Culverts Nos

1205.00

## ## ## ## ## ## ## ## ##
## ## ##

##

##

##

Bridges Nos
Miscellaneous Works

MonthlyProgressBriefNovember2015

Page22

4.10 Potential Issues

Lack of resources at site which reflected in planning of works at site, delay in


preparing mix designs, delay in submission of working cross sections, in
preparation of survey data etc.

The poor cash flow of Contractor has seriously hampered the progress of works.

There were delays in shifting of utilities. However Employer and the Contractors
are coordinating with various Service Providers like KSEB, KWA, BSNL, Forest
and other departments for shifting of utilities and tree cutting along the project.

Monthly Achieved Progress is not improving and progress of works is not at all at
par with the targeted progress. Instructions are issued to the Contractor for
taking stringent measures to enhance the progress of works. Clause 15.1 Notice
to Correct issued on 23rd June 2015 and works speeded up.

4.11 Payments to the Contractor

Mobilization advance, Equipment advance and Interim payment Certificate for works up
to (IPC-13) was paid to the Contractor amounting to Rs. 442082448/-. Timely payments
are released to the contractor. The Steering Committee held on 28.06.2014 lowered the
threshold limit of minimum IPC amount for Rs. 1.5 crores from Rs. 3.00 crores to
facilitate the cash flow of contractor. There is no pending payment to contractor.

4.12 Implementation of EMP


4.12.0.1 Environment Management at work sites
The CSC is closely watching the implementation of EMP and instructing the contractor
to improve the measures adopted by them. The Environmental Engineer of CSC
conducting regular site visits to project site and base camps. Measures taken by the
Contractor for implementing the mitigation measures proposed in the EMP are reviewed.
The progress of the work was not satisfactory. The construction of via duct and other
ancillary works was stopped by locals demanding that a weir to be constructed instead
of a culvert removed by KSTP for viaduct construction .A dispute raised by WRD
demanding that they will construct the weir at accost of 90 lakhs and the amount to be
remitted by KSTP in advance. Considering the delay in arranging the works by WRD
KSTP informed that the work can be entrusted to the contractor under the supervision of
WRD. This arrangement was not accepting by them, There for a high level meeting is to
be convened to resolve the issue. . The debris and cofferdam from the viaduct and
Chithari bridge site is partially removed. Contractor was asked to develop oxbow land
along the corridor wherever enough land is available. Contractor will prepare site specific
plans for approval of the Engineer. This was pending with the contractor. Contractor

MonthlyProgressBriefNovember2015

Page23

procured 1500 saplings for planting but it was not started .The environmental
enhancement works proposed in front of thrikanad temple was not started so far.

4.13 Photograph

Approach slab at A1 of Chithari Bridge at km.18+400

BC laying from km.4+400 to km.4+600 LHS

MonthlyProgressBriefNovember2015

Approach slab at A2 of Chithari Bridge at


km.18+400

Deck slab in progress at km.20+365 Box culvert

Page24

4.14

Contract Package II

Upgradation of Road from Pilathara to Pappinissery of SH 67

Scope of Works
New ROB
Repair of Bridge
New Box culverts
Widening Slab culverts
Reconstruction
Drain
Foot path
Solar Lights

_
-

2
2
9
20
8
26.04 Km
12.6 Km

4.15 Contract Details


Letter of Acceptance Date

05.03.2013

Agreement Date

01.04.2013

Name of Contractor

M/s RDS Projects Ltd, Kochi

Contract Price

Rs.118,29,77,833/-

Notice to Commence

23.04.2013

Total Length

20.90 Km

Contract Period

24 months

Completion Date

22nd April 2015 extended to 20 June 2016

Defect Liability Period

365 days
Km. 0+000 Km. 08+000 - 22nd February 2014
Revised to 30 September 2015
Km. 0+000 Km. 14+000 - 13 February 2016

1st Milestone
2nd Milestone
3rd Milestone

Km. 0+000 Km. 20+900 - 22 April 2015 revised to 20


June 2016

MonthlyProgressBriefNovember2015

Page25

4.16 Progress of Works


4.16.0.1

Structure

Railway Department has approved GAD of ROB @KM 7+420(Thavam) in July-2014.


Now tree cutting work in the Railway land completed and Railway gate shifting works
is to be carried out by the Railway department so that the diversion road work for
diverting traffic can be commenced by the road Contractor.

Test piling work started for Ramapuram Bridge @ Km.4+260 on 24th June -2015 and
completed on 08th July 2015.
Ramapuram Bridge @ Km.4+260, Piling Work 9 Nos out of 16 completed. Piles P1/D,
P1/A, P1/C, P2/A, P1/B, P2/B, P2/C, A1/C & P2/D completed.

Test pile casting has been done for ROB @KM7+420 and initial load test on pile is
completed. Routine Pile load test for A2/B and P1/D completed and results are
awaited.

ROB at Km. 7+420 Piling Work started on 18/12/14, Piling Work 24 Nos out of 24
Nos completed. Pile cap for A1, P4 completed and breaking of piles for A2 & P1 are in
progress. Abutment A1 completed up to abutment cap bottom level.

Test pile casting has been done for ROB @KM19+950 and initial load test on pile
completed.
9 Pile Cap for A1, P1, P2, P3, P4, P5, P9, P10, P21 & P22 (10Nos) Completed
& Abutment and Pier Wall P1 to P5 Completed.
9 Pier Cap P1, P2, P3, P4, P5 & P22 (6Nos) Completed.
9 Girder and deck slab for P3- P4 and P4-P5 completed.
9 Girder concrete for P2-P3 completed and shuttering & steel reinforcement
work for deck slab P2-P3 is in progress

There are 4Nos of widening

slab culverts in Milestone I and contractor has

completed 2 Slab Culverts @Km.2+139.50 and Slab Culvert @Km.5+142.

Widening works of Slab Culverts in Milestone-II and Contractor has completed 2 Slab
Culvert @Km.10+064.71 RHS, Slab Culvert @Km11+582 RHS and Work in Progress
@Km.10+885.61 LHS, @Km.12+374 LHS and @Km.12+688 LHS. Box Culverts in
Milestone-II is also in progress for 1No culverts i.e. @ Km.9+600 BHS Slab completed
and Return wall balance.

Construction of Box Culverts in Milestone-III is in progress for one culvert at @


Km.14+741

There are 12 Nos. of Box Culverts in Milestone-I out of which 10Nos Culvert @Km0+118.60,

@Km.0+530.290,

MonthlyProgressBriefNovember2015

@Km.0+813.610,

@Km.1+122.390,

Page26

@Km.1+420.620, @Km.1+721.220, @Km.6+102.70, @Km.7+120, @Km.7+778.42 and


@Km2+675 have been completed and works are in progress on 2Nos. of culverts.
Box Culvert @ Km.3+280 RHS completed, LHS and Wing wall work balance.
Widening works of Slab Culverts in Milestone-II and Contractor has completed 3 Slab
Culvert @ Km.10+064.71, @ Km.10+885.61 and @Km11+582. Box Culverts in
Milestone-II is also in progress for 1No culverts i.e. @ Km.9+600.

Construction of Box Culverts in Milestone-III is in progress for one culvert at @


Km.14+741

Considering the overall value of work 118.30 crores, Progress up to 30th November 2015
is as follows in comparison with revised programme based on EOT-2
For previous month
(October)
Target
Achieved
78.06%

28.99%

This month
(November)
Target
Achieved
8.28%

Cumulative to end of this month


(November)
Target
Achieved

1.58%

86.35%

30.50%

4.17 Work progress considering the contract price (end October


2015)

Milestone

II

III

Length in km

8.000

14

20.9

Length handed over to contractor in km

8.000

14

Unencumbered land available to the contractor


in km

8.000

14

Stretch completed in all respects in km

FW

HW

FW

HW

GSB completed in km

7.81

0.00

1.31

0.35

WMM completed in km

7.81

0.00

1.23

0.23

DBM completed in km

7.81

0.00

1.17

0.23

BC completed in km

7.56

0.00

0.75

0.12

CD completed in Nos.

MonthlyProgressBriefNovember2015

13

Page27

4.18 Physical Progress

5656

Bored Pile (Lm)

5657

4847
21139

Concreting (cum)

19703

3291
10442

BC (cum)

8426

3935
19202

DBM (cum)

11043
BOQ Quantity

5070

Cumulative target to end of this month (R5)

57501

WMM (cum)

50480

Cumulative Achieved to end of this month

25039
42722

GSB (cum)

37709

23533
93145

Subgrade (cum)

81536

9269
13583

Embankment (cum)

39253

11217
180833

Excavation (cum)

147299

54431

50000

100000

150000

200000

Original Programme
(R-0)

60%

70%

80%

90%

100%

4.19 S-Curve

50%

Revised Programme
(R-5)

30%

40%

Target-86.35%
Achieved-30.51%

0%

10%

20%

Achieved Progress

MonthlyProgressBriefNovember2015

Page28

4.20 Strip Chart

4700

4800

4900

5000

5100

Wet Mix Macadam 1st

Granular Sub base

Subgrade

EW - Embankment

5300

4600

5200

4500

4400

4000

4300

3900

4200

3800

1
1

4100

3700

3600

3500

3400

3300

3200

3100

3000

2900

2800

2700

2600

2500

2400

2300

2200

2100

1200

2000

1100

1900

900

1800

800

1000

1700

700

1600

600

1500

500

1400

400

1300

300

200

Chainage (Km)

100

Culverts & Bridges

Miscellaneous Works
Bridges Nos

LEFTSIDE

Culverts Nos
Drains and Walls
Bituminous Concrete

##

Dense Bituminous Macadam

Wet Mix Macadam 2nd

EW - Embankment

##

Wet Mix Macadam 2nd

## 1

Dense Bituminous Macadam

## 1

Bituminous Concrete

## 1

Drains and Walls

## ##

1
1

9400

9300

9200

9100

9000

1 1 1 1 1 1 1 1 1 ##

8900

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

10700

##

Wet Mix Macadam 1st

10600

Granular Sub base

8800

RIGHTSIDE

Subgrade

Culverts Nos
Bridges Nos
Miscellaneous Works

9500

9600

9700

9800

9900

10000

10100

10200

10300

10400

10500

8700

8600

8500

8400

8300

8200

8100

8000

7900

7800

7700

7600

7500

7400

7300

7200

7100

7000

6900

6800

6700

6600

6500

6400

6300

6200

6100

6000

5900

5800

5700

5600

Chainage (Km)

5500

5400

Culverts & Bridges

Miscellaneous Works
Bridges Nos

LEFTSIDE

Culverts Nos
Drains and Walls
Bituminous Concrete

## ## ## ## ## ## ## ## ## ## ## ##

Dense Bituminous Macadam

## ## ## ## ## ## ## ## ## ## ## ##

Wet Mix Macadam 2nd

Wet Mix Macadam 1st

Granular Sub base

Subgrade

EW - Embankment

EW - Embankment
Subgrade

RIGHTSIDE

Granular Sub base


Wet Mix Macadam 1st
Wet Mix Macadam 2nd
Dense Bituminous Macadam

## ## ## ## ## ##

Bituminous Concrete

## ## ## ## ## ## ## ## ##

Drains and Walls

##

##

## ## ## ## ##

## ##

##

Culverts Nos
Bridges Nos
Miscellaneous Works

Milestone - I(0-8km)

Culverts

Milestone - II(8-14km)

Number remaining

Number in progress

Number completed

No. dwgs approved

Original number

Number remaining

Number in progress

Number completed

No. dwgs approved

Original number

Number remaining

Number completed

No. dwgs approved

Original number

Nature of work

Number in progress

4.21 Schedule of culverts and drainage works

Milestone - III(14-20.9km)

Widening Slab Culverts

(1)

Slab Culvert retained

11

11

16

15

13

14

13

Bridges Retained*

New Bridges/ROB**

Reconstruction
New Box Culvert
Total culverts

MonthlyProgressBriefNovember2015

Page29

4.22 Potential Issues

Lack of experienced staff at site which reflected in planning of works at site, delay in
preparing Mix designs, delay in submission of working cross sections, in preparation
of survey data etc.

The contractor has established one quarry, crusher and HM Plant for contract I and
II.

The aggregate production is not sufficient to meet the requirement of both

packages.

Now, tree cutting work in the Railway land is in progress for construction of RoB at
Thavam and Railway gate shifting works is to be carried out by the Railway
department so that the diversion road work for diverting traffic can be commenced by
the road Contractor.

4.23 Payments to the Contractor


Mobilization advance and Equipment advance and all IPCs was paid to the Contractor
amounting to Rs. 374832554/-. The Steering Committee held on 28.06.2014 lowered the
threshold limit of minimum IPC amount for Rs. 1.5 crores from Rs. 3.00 crores to
facilitate the cash flow of contractor. There is no pending payment to the contractor.

4.24 Implementation of EMP


4.24.0.1

Environment Management at Work Sites

Major activities during the current month are ROB works ,piling for Ramapuram bridge
and some road works. Reviewed the measures taken by the Contractor for implementing
the mitigation measures proposed in the EMP. Instructions were given to avoid
accumulation of debris along the project site and at ROB location and to remove the
debris from the site periodically. Regular sprinkling of water at active work phase are to
be continued. The Environmental management for Pappinissery ROB at Ch.19+950 to be
improved. The waste management systems in the Camp are being followed properly but
the new labour accommodation at the camp requires additional measures for improved
ventilation. . General housekeeping at Camp site is satisfactory. The surrounding of the
camp to be cleared and waste collection system to be continued. The dust accumulated
around the batching plant site is to be removed and sprinkling of water to be
continued.Direction to improve the management measures was given during the visit.
Even the measures adopted by the Contractor for implementing EMP is satisfactory,
some improvement is required in ROB sites and Road.

Contractor has to provide

required measures to stop spills in future. The cut earth available is minimum and
borrow materials has to be brought from contract 1 site. This was delayed due to
restrictions imposed by government but no action taken by the contractor in this regard
MonthlyProgressBriefNovember2015

Page30

so far. Contractor has to produce documentary evidences that the contractor borrow
materials cannot be brought due to the restrictions by govt . The environmental
enhancement measures such as construction of parking bus bays noise barriers ox bow
land development, tree planting etc are to be taken along with the pavement works. The
access to the houses at flood prone areas to be verified and existing access to be reinstated after raising of the road. Contractor .The debris stocked at camp site is to be
removed and the same can be used for maintaining the access road to the camp which is
in a bad shape. The temporary camp established is not removed. The RE issued notices
to the contractor. Contractor informed that this will be immediately removed.

4.24.0.2

Traffic Management and Road Safety Measures

The contractor is required to provide safety precautions such as barricading, flags,


safety signboards and traffic cones at all work zones to ensure safety for all road users.
Personal safety equipment such as jackets, safety shoes, face shields and hand gloves
are to be provided to all workers as necessary. Instructions were given to provide
adequate safety sign boards and fencing all along the active work sites. The safety
arrangements at ROB locations are very poor and to be improved. The traffic at these
locations has been fully diverted. The deviation road repaired to divert traffic to be
maintained till completion of the ROB works.
The safety measures adopted by the contractor are not satisfactory in ROB locations and
to be improved. Direction were also issued to the contractor to implement safety
requirements in Rob location. The railway has started construction of the railway span
and expected to completed within 4 months. Contractor activity to be speeded up to
complete the approaches along with railway work, in order to open the restricted traffic
movements to the houses and shops. The construction signs provided at site to be
maintained throughout the construction period and any damaged one to be replaced.
Notices were also issued to the contractor for their lapses by RE and if not improved
penalty will be imposed from their payments. The site visit observation of the
environmental expert is also attached as annexure.

MonthlyProgressBriefNovember2015

Page31

4.25 Photographs

GSB Laying from km 15+650 to km16+100

Deck slab Concreting P2-P3 @ ROB km 19+950

Pile cap P19 reinforcement work @ ROB km 19+950

MonthlyProgressBriefNovember2015

Precast drain cover slab erection @ km 13+250 RHS

Page32

4.26

Con
ntract Packa
age III

Up
pgradatio
on of Road from T
Thalasseryy to Valavvupara off SH 30

Scope of
o Works
Constru
uction of Ma
ajor Bridges
Constru
uction of Miinor Bridge
e
New Box
x culverts
Widenin
ng Slab culv
verts
Reconsttruction of C
Culverts
Drain
Footpath
h
Solar lig
ghts

3
4
21
88
50
65.30 Km
44Km

C
Details
4.27 Contract
Contractt with M/s
s SACYR-ESSAR JV, Mumbai was
w
Termin
nated on 22
2.04.2015 due to
non perfformance. The work in this Pac
ckage is sp
plit into tw
wo Packages
s 3A and 3B
3 and
bid for 3A has been
b
appro
oved by th
he Steerin
ng Committee bids for
f
3B is under
finalizatiion.

5.1 Contract Package IVA


Construction of Thiruvalla Bypass along Chengannoor Ettumannoor Road (SH-1) from chainage 7+390 to 9+400

Scope of Works
Major Bridges

- Nil

Minor Bridge

- 1 no.

Flyovers

- 1 no.

Culverts

- 8 nos.

Pipe Culverts

- 2 nos.

Solar lights

- 1380 nos.

5.2 Contract Details


Letter of Acceptance Date

29.10.2013

Agreement Date

29.11.2013

Name of Contractor
Contract Price
Notice to Commence
Total Length

M/s EKK & Co, Kochi


Rs. 31,80,45,071/19.12.2013
2.3 Km

Contract Period

24 months

Completion Date

06 August 2014 revised to 31 Dec 2014

Defect Liability Period

MonthlyProgressBriefNovember2015

365 days

Page34

5.3 Utilities
Utilities such as water lines, telephone cables and associated accessories, electrical lines
and associated accessories and trees are remaining to be removed / shifted. Contractor
has submitted item rates required for relocation of electrical utilities from the project
road in the absence of specific provision in the BOQ.

5.4 Mobilization of Resources


Contractor has not established any equipment like WMM Plant, HM Plant and Crusher.
The Concrete Batching plant has been established. On restarting the work, the
contractor has started to mobilize the required plants and machinery.

5.5 Work Progress


All Survey works and confirmatory boring required have been completed except for the
minor bridge location.
PVD installation drainage blanket have been completed. Embankment stage 1 loading
completed.
Culvert at KM 0+980 completed.
Culvert work at Km 1+150 completed.
Culvert at KM 0+885 completed except for return wall.
2nos of culverts are in progress
Minor Bridge at Km.0+380:23 Nos Pile completed out of 24 Nos.
Flyover at Km.1+350:9 All GFC Drawings Issued
9 Test Pile Completed, 40 Nos of Working Pile Completed out of 42 Nos.
9 4 Nos pile cap completed.
9 4 Nos of Piers and 1 Nos of Abutment and 3 nos piers Completed.
9 A1-P1 girder works in progress
9 Pre-casting of RE Wall panels completed.

Progress up to end November 2015 is as following:


Up to previous month
(October)
Target
Achieved
68.35%

27.43%

This month (November)


Target

Achieved

9.41%

5.90%

MonthlyProgressBriefNovember2015

Cumulative to end of this


November
Target
Achieved
77.8%

33.40%

Page35

5.6 Physical Progress:

526
686
1451

Piling

6215
5401
1184

Concrete total

BC

1452
0
0

DBM

1815
0
0

BOQ Quantity
Cumulative target to end of this month

9275

WMM

0
0

Cumulative Achieved to end of this month

8750
2500
85

GSB

20109
19600

Subgrade

0
148258

Embankment

130710
53077
21960
25490

Excavation

4444
154500

PVD

232000
227229

50000

100000

150000

200000

250000

100%

5.7 S-Curve

70%

80%

90%

S Curve ThiruvallaBypass

60%

68.4%

40%

50%

Original
Programme (R-0)

0%

10%

20%

30%

Achieved
Progress as on
Sept 2015

5.8 Potential Issues


The following issues are very critical which may have adverse impact on the timely
completion of the Project.

Handover of unencumbered land at Km 1+450 to 1+750 pending and action taken


to acquire.

MonthlyProgressBriefNovember2015

Page36

Slow Progress of work due to Court order for 9 Months initially

Delay in mobilization of Crusher, WMM Plant and HM Plant due to above.

Delay in shifting Water utilities of the project

No. dwgs approved

Number completed

Pipe culvert

New Box Culvert

Total culverts

10

Fly over

Minor bridge

Nature of work

Number remaining

Total number

Number in progress

5.9 Schedule of culverts and drainage works

Culverts

5.10 Payment
Upto IPC-7 has been paid to the contractor Rs. 78215582/-

5.11 Implementation of EMP


5.11.0.1 General
The construction activities for Contract IV-A is in progress Contractor completed two
piers and the super structure work for deck in progress. Construction of piers, pile for
flyover is also in progress .The piling work for the bridge has started. The PVD for the
embankment is completed and the settlement is observing .Contractor has completed
casting of precast panels for RE wall. Contractor has established a batching plant and
the required consents have been also obtained. Considering the space constrains
additional management measures are required for the camp site at Thiruvalla. Proper
site drainage system to be planned for collecting the waste water from the batching plant
and curing of concrete panels and this was not completed.. Direction issued to the
contractor to collect the pile muck and keep it for some time for settling the clear water
can be allowed to flow into the adjacent land and the waste material has to be dumped
for forming the bunds. Now it is noticed that the waste material is directly dumping into
the water body. The contractor has rented houses for accommodating staff and labour in
Thiruvalla town area. Clearing and grubbing on the other end of the bypass started. The
site was visited by the environmental expert on 30th October and report attached. Notice
issued to the contractor for the major lapse and penalty clause will be imposed.
MonthlyProgressBriefNovember2015

Page37

5.11.0.2

Environment Management at Project Ancillary Facilities

The contractor has establishing a base camps at the locations detailed in Table below.
Details of Construction Camps
Camp identity
Location
Village
Camp 1 Batching Pant about 50 cents of land owned Thiruvalla Town.
Muncipality,
,precast
yard
,Labour by Thiruvalla
and it is beside the project
camp, store, laboratory
site.
Debris Disposal site
Thiruvalla
municipal area Thuruvalla
approved by municipality.
Labour Camp
Thiruvalla Town
rented At Thiruvalla Town.
building.
Environment management facilities adopted at these ancillary facilities are detailed in
Environment Management Facilities at Ancillary facilities
Sl.No.
1

Details of
Camp/Plant
Construction
Camp

Environment Management Facilities Provided


Provided with sanitation facilities, drinking water supply,
and solid waste collection facilities.
Internal roads
developed partially by utilising the
construction debris.
Generators are provided , vertical stack of adequate height
provided ,but no enclosure for DG set used by the subcontractor.
The site drainage to be improved by construction of
collection tanks.
Fencing only partially done, Complete fencing around the
camp is required.

Contractor has mobilized the environmental cum safety engineer but CV of the person
was not submitted. The contractor was directed to submit monthly EMP reports. The
contractor is bringing borrow material from contract 6 .Site visit conducted by the
environmental Expert on 30th November 2015 and observation attached as annexure
to this report.Action taken for the lapses and notice issued.

MonthlyProgressBriefNovember2015

Page38

5.12 Photographs

Steel Reinforcement for girder work in progress at A1-P1 of


Flyover.

Piezometer

Staging for girder Concrete

Steel Reinforcement for girder work in progress at A1-P1 of


Flyover.

MonthlyProgressBriefNovember2015

Page39

6.1 Contract Package IV


Upgradation of Road from Chengannoor to Ettumannoor of
SH-1
Scope of Works (45.40 Km):
Construction of Major Bridges
Construction of Minor Bridge

New Box culverts


Widening Slab culverts

Reconstruction of Culverts
Foot path, Solar lights

3
5
9
8
59

6.2 Contract details:


Letter of Acceptance

21.08.2014

Agreement date

15.09.2014

Name of contractor

M/s Delma-Sreedhanya JV

Contract amount

Rs. 293,58,17987

Notice to commence

November 25, 2014

Total length

45-80

Contract period

36 months

Completion date

24.11.2017

Defect liability period

365 days

I milestone

10 km upto BC level 18 months from


commencement date

II milestone

25 km upto BC level 25 months from


commencement date

III milestone

MonthlyProgressBriefNovember2015

47.80 km upto BC level 36 months from


commencement date

Page40

6.3 Pre-Construction Activities:


6.3.1 Utilities

Utilities such as water lines, telephone cables and associated accessories,


electrical lines and associated accessories and trees are being removed /
shifted.

Removal of stumps of trees cut by agencies engaged by KSTP is also the


responsibility of the Contractor.

Relocation of Electrical lines and Waterlines are included in the Contract.

2915 lm of 700mm, 560 lm of 200mm & 200 lm of 300mm DI pipe laid. 8700 lm
of 160mm PVC pipe laid. Work in progress.

Electrical Utility shifted for approximately 10 km. Work in progress.

6.4 Mobilization of Resources


6.4.1.1

Plant and machinery

The Contractor has started the process of mobilizing Plant and Equipment. They have
identified their base camp at Ettumannur. WMM plant has been set up at Pattithanam
and Hot mix plant is being installed at Chingavanam. Another camp is functional at
Thirumoolapuram where Batching plant, Pre casting yard is functional.
The Chingavanam QC Lab is established at Chingavanam.
Hot Mix Plant has been established and operational at Chingavanam
Construction Equipments are being brought to site.

6.4.1.2

Human resources

The Contractor has started mobilizing the required manpower. Most of the Key persons
are in place. Planning Engineer has to be placed immediately.

6.4.1.3

Materials

Material sources are being identified and materials being tested for suitability before
approval.

6.5 Work Progress

Preparatory works & mobilization has been in progress since the handing over of
site on 24th September 2014.

Survey work has been completed. FRLs have been re-designed and approved for
the entire stretch.

Test piles have been cast at the A1 side of the Kallissery Bridge at Km 1+558 & A1
side of the Varattar Bridge at Km4+008.

Bridge at Km.0+750:9 Bridge work completed.


9 Approach road works completed up to DBM.
MonthlyProgressBriefNovember2015

Page41

Bridge at Km.1+558:Confirmatory Boring completed for Abutment & Pier locations.


Out of 40 nos, 38 Nos of Piling completed.
Pile cap A1 & A2 completed and abutment works are in progress.
1no. each of vertical load test and lateral load test done
Bridge at Km.4+008:Confirmatory Boring completed and initial Load Test for Test pile at A1 completed.
Out of 20 Nos, 15 nos of Piling completed. Work on 1 no of pile is in progress. 2
nos of pile cap and 2 nos of pier completed. 1 no. Lateral load test done.
Bridge at Km.5+213:9 Confirmatory Boring Completed. Piling works commenced. Out of 36 Nos, 7
Nos of piling completed.
Bridge at Km.11+235:9 Bridge work completed.
9 Approach road works are in progress.
Bridge at Km.39+740:Confirmatory Boring at Abutment and Pier locations completed.
Existing bridge demolished.
Total piling completed (24 Nos) and 4 Nos pile cap completed.
Abutment A1 and Piers P1&P2 completed.
A1-P1 deck slab completed.
Bridges at Km. 2+500, km 20+118 & km 24+695
9 Confirmatory bore for soil investigation completed. Only widening is proposed
for these bridges
Culverts:9 Culvert works at 11 locations have been completed. 10 culverts in progress
Drain & Retaining Wall:9 Retaining wall at various locations have been commenced.1392 lm completed
and work for 400 lm is in progress.
9 Precast Drain concrete casting stated on 17/1/2015. Installation of about
5200m completed.
Utility shifting works:9 Electrical Utility shifting and water line relocation are in progress
Hot mix plant has been commissioned in October 2015. DBM works has been
commenced.
Progress up to end November 2015 is as following:
Upto previous Month

This Month

Cumulative to end of this Month

Target

Achieved

Target

Achieved

Target

Achieved

18.48%

11.33%

3.37%

1.99%

21.85%

13.32%

MonthlyProgressBriefNovember2015

Page42

6.6 Physical Progress

60500

Precast Drains

14000
7811
37055

Concrete total

6581
5307
21000

BC

0
0
BOQ Quantity

30000

DBM

2813
1808

Cumulative target to end of this month

122071

WMM

Cumulative Achieved to end of this month

11444
6343
96000

GSB

9000
7304
71921

Subgrade

10610
2970
67504

Embankment

42922
2644
375826

Excavation

148038
18622

50000

100000

150000

200000

250000

300000

350000

400000

18.48%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

6.7 S-Curve

MonthlyProgressBriefNovember2015

Page43

Total number

No. dwgs approved

Number completed

Number in progress

Number remaining

6.8 Schedule of culverts and drainage works

Pipe culvert

New Box Culvert

81

47

13

10

58

Total culverts

82

48

14

10

58

Minor bridge

Major Bridge

Widening Bridge

Nature of work

Culverts

1
3

6.9 Implementation of EMP


6.9.1.1

General

The Environment Management Plan (EMP) prepared for Package IV describes the
environmental issues anticipated during the execution of the project and suggests
mitigation measures to be carried out during the implementation to minimize the impact
on the environment. The EMP has been made an integral part of the construction
contract and is being implemented along with the execution of the project. The progress
of implementation of EMP during the execution of Package IV as October 2015 is
summarized below
The batching plant commissioned and the works for other facilities continuing.
Contractor has submitted the HSE plan and was also approved. Site specific
management plan was also submitted for each facility. The contractor has mobilized
Engineers for Environment and Safety but the Environmental engineer resigned.
Contractor has to appoint another person immediately. This was not done so far. The
bride work at Puthenveettilpady completed and will be open shortly. The vent way
clearance of the bridge is not completed fully. The waste disposal at batching plant site
is to be improved. Contractor has promised to establish a small plant to treat kitchen
waste. This was also not done. Ponding os water noticed at this camp site. The waste
dispoasal at this camp is not satisfactory. The contractor obtained consent to operate
the batching plant.
Culvert and Bridge works are in progress. Contractor has taken land for HM plant at
Chingavanam and the HM plant erecting completed and other works such as
construction of ramp, Generator and diesel bulk storage facility works are progressing..
WMM plant at Vembally installed and initial works started. The PCB clearance status
shown on the following table. Contractor informed that the consent for operate the HM
and WMM plant will be obtained shortly.
Staff engaged by the Contractor for EMP implementation.
MonthlyProgressBriefNovember2015

Page44

Name

Designation

Mobilisation Date

Rajan Piallai

Environmental Engineer

May2015,resigned on
Sept.2015

Ajo Abraham

Safety Officer

December 2014

6.9.1.2

Environment Management at Project Ancillary Facilities

The contractor has establishing 3 base camps at the locations


Details of Construction Camps
Camp identity
Location
Camp 1 Batching Pant, precast About 1 acres of land,
yard, Labour camp, Store
500
m
away
from
project road
Camp-2 HM plant, Office, Store, 3 acres of Land at Ch.
Labour camp,
RHS 500 m from project
road)
Camp-3 WMM Plant, labour 3
acres,
RHS
on
camp.
contract 5

detailed in Table 10.2.


Village
Thirummoolapuram.
Consent to establish
obtained from PCB.
Chigavanam. Consent
application submitted.

Vembally 3km from


project road. Consent
to establish obtained.
Environment management facilities adopted at these ancillary facilities are detailed in.
Environment Management Facilities at Ancillary facilities
Sl. No. Details
of Environment Management Facilities Provided
Camp/Plant
1
Construction
Provided with sanitation facilities, drinking water supply,
camp
and solid waste collection facilities. Waste disposal system
to be improved.
Internal roads are developed partially by utilising the
construction debris obtained during the tarred surface
cutting, banana plants were planted in the free space
Generators are provided with vertical stack of adequate
height.
The solid waste disposal facility like compost pit is
provided. Roof for the collection centre was not provided.
The waste oil collection trench to be provided to avoid
mixing with rain water.
Housekeeping to be improved.
2
Labour Camps Water supply and toilet facilities provided.
Toilets with septic tanks and soak pit provided
Dust bins provided for collection of solid wastes.
For disposal of solid wastes compost pits provided
LPG connections are provided for cooking.
Mixing of wastes noticed. Housekeeping to be
improved.kitchen waste to be treated by installing bio gas
plant.
The access to the labour camp to be clearly marked with
sign boards
First Aid and Fire extinguisher to be provided.
General house keeping to be improved
3
Quarry,
NO Quarry or Borrow operating .materials procured from
Crusher,
other crushers.
4
Borrow area
Identified at kaviyoor village , 6km from project road
MonthlyProgressBriefNovember2015

Page45

Obtained permission to take 1340 cum eatth. Additional


borrow areas to be identified.
5
Debris
Identified, Abandoned quarry is proposed as disposal area.
Disposal sites
Existing Puramboke land is being used for storage.
6
Water Sources Bore well
No clearance required
Contractor has obtained the consent for establishment for the batching plant and WMM
plant. The consent application for HM plant submitted .Contractor was advised to
expedite action to obtain the clearances from the PCB urgently.IT is noticed that the
contractor commissioned the HM plant and WMM plant. The consent to operate is not
yet submitted .This will be a major lapse and action as per contract is required. The
operation of the plant will be possible after getting the clearances. The scarified
materials and concrete waste materials are using for developing the HM and Batching
plant site. Contractor was also directed to improve the Road safety during construction
along the road .Wearing of PPE by the workers at bridge site is also insisted to avoid any
accident . Contractor is also proposing to bring borrow materials from contract V as
extra materials is available in contract V. Employer may initiate action in obtaining
clearances for operation of borrow areas, otherwise extra expenditure has to be incurred
as conveyance charges for bringing materials from contract V. The contractor was also
advised to produce documentary evidence that borrow operation was not possible due to
the delay in getting the required clearance. This was not submitted. Considering the
restricted space constrains, additional safety measures are required and the movement
of trucks inside the camp is to be regulated properly.
The environment expert of EGIS visited the site on 30thOctober 2015and site visit
observation communicated to the contractor for action and report

6.10 Payments
The contractor has been paid IPC-5 Rs. 443604048/-

MonthlyProgressBriefNovember2015

Page46

6.11 Photographs

GSB & Retaining wall work in progress at Pannikuzhy


Bridge approaches (Ch. 11+235)

GSB work in progress at 21+270 to 21+600 (RHS)

MonthlyProgressBriefNovember2015

Earth work in progress at Pannikuzhy Bridge approaches


(Ch. 11+235)

Top slab (A1-P1) & Pile cap P2 reinforcement work in


progress at Neelimangalam Bridge (Ch. 39+709)

Page47

7.1 Contrac
ct Pack
kage V
Upgradati
U
on of Roa
ad from E
Ettumann
noor to M
Muvattupu
uzha of SH
S 1

Scope off Works (400.96 Km):


Constru
uction of Major Bridge
es

Constru
uction of Minor Bridge
e

New Bo
ox culverts

Widenin
ng Slab culveerts

14

Reconsttruction of Culverts

75

Foot pa
ath, Solar L
Lights

7.2 Coontract deetails:


Letter off Acceptanc
ce Date

29.11.2
2013

Agreeme
ent Date

30.12.2
2013

Name off Contractorr

M/s NAPC
C Ltd.,

Contractt Price

Rs. 171
1.49

Notice to
o Commenc
ce

04.02.2
2014

Total Len
ngth

40.60 km

Contractt Period

30 mon
nths

Complettion Date

03.08.2
2016

Defect Liability
L
Perriod

365 da
ays

1st Miles
stone

10 km
m BC leve
el 02.05.2015

2nd Miles
stone

30 km
m BC leve
el 03.02.2016

3rd Miles
stone

40.960 km
m whole worrks by 03.0
08.2016

7.3 Utilities
Relocation of electrical utilities and water supply line using materials issued by KSTP is
the responsibility of Contractor. Removal of stumps of trees cut by agencies engaged by
KSTP is also the responsibility of Contractor. KSTP/PMT has made arrangements with
BSNL and other private agencies for relocation of cables, telephone posts and telephone
pillars. KSTP has issued most of the items required for relocation of Electric and Water
utilities and relocation work is under progress. Non procurement of complete items
required for utility shifting is a constraint in carrying out utility shifting.

7.4 Work Progress


Widening of slab culvert

4 Nos.

Construction of Box culvert

29 Nos full width

Survey work Completed

Full project road

OGL recorded

Full project road except OGLs on all existing

branch roads between km. 7.50 and km. 40+960.


Construction of drain

14950 m (Total precast drain segments casted

are 14214 Nos, each 1.5 m length)


GSB

7210 m (Average)

WMM top layer

6785 m (Average)

DBM

5405 m (Average)

Milestone

II

III

10000

20000

10960

GSB completed in km

7210

WMM completed in km

6785

DBM completed in km

6585

29

Length in km
Stretch completed in all respects in km

BC completed in km
CD completed in Nos.

Up to previous month
(October)

This month (November)

Target

Achieved

Target

Achieved

Target

Achieved

39.48%

11.93%

5.95%

1.35%

45.43%

13.38%

MonthlyProgressBriefNovember2015

Cumulative to end of this month (November)

Page49

7.5 Bar chart

26691
7433
2462

Concreting (cum)

19095
5400
0

BC (cum)

35840
20000
4865

DBM (cum)

BOQ Quantity
Cumulative Target to end of this month

134110

WMM (cum)

75882
16963

Cumulative Achieved to end of this Month


68921
72254

GSB (cum)
16143

64000
50515

Subgrade (cum)
9862

135501

Embankment (cum)

52980
7884
483045

Excavation (cum)

258327
82557

50000

100000

150000

200000

250000

300000

350000

400000

450000

500000

550000

30%

40%

50%

60%

70%

80%

90%

100%

7.6 S-Curve

Achieved
Progress

0%

10%

20%

As per R4 programme
on 06.01.15

MonthlyProgressBriefNovember2015

Page50

Milestone - I

Culverts
Widening Slab Culverts

Slab Culvert retained

Reconstruction Slab/Box

24

24

23

New Box Culvert

31

32

New Pipe Culvert

Total culverts

34

Bridges Retained

Milestone - II

5
1

28
1

3
5

49

27

Number remaining

Number in progress

Milestone - III

21

Number completed

No. dwgs approved

Original number

Number remaining

Number in progress

Number completed

No. dwgs approved

Original number

Number remaining

Number in progress

Number completed

No. dwgs approved

Nature of work

Original number

7.7 Schedule of culverts and drainage works

22

11

11

43

27

5
0

27
1

Widening Bridges

Reconstruction Bridges

Total Bridges

7.8 Key issues:


The following issues are very critical which may have adverse impact on the timely
completion of the Project.
Delay in Identification and procurement of adequate construction materials.

Delay in mobilization of adequate labour and machineries.

Inadequate planning

Change in management of company and frequent change of key personnel of


contractor

Being very slow progress of work notice to improve has been given as per the contract
provisions and contractor has improved the performance

7.9 Payment to the contractor


The contractor has been paid Rs. 230885929/-

7.10 Implementation of EMP


15.4 Compliance with Statutory Clearances
The action taken by Contractor for complying with statutory requirements is
summarized below:
Compliance with Statutory Requirements
Unit

Status of Compliance

Remarks

Quarry

Planning to take on lease. Two Quarry-1. Owned by Sabu


quarries are identified which have all Varghesse.
statutory clearances.
Quarry-1. Owned by Babu
Kuriakose.

Crusher

Obtained Consent to Establish from Date of Issue of Consent to

MonthlyProgressBriefNovember2015

Page51

Kerala State Pollution Control Board

Hot
Plant

Mix Obtained Consent to Establish from


Kerala State Pollution Control Board

Base camp Obtained Consent to Establish and


and
operate from Kerala State Pollution
batching
Control Board
plant
WMM Plant

Obtained Consent to Establish from


Kerala State Pollution Control Board

Contractor has obtained consent to operate for

Establish-02.05.2014
and
Valid Upto 28.02.2017. No
major activities at crusher
site.
Date of Issue of Consent to
Establish-01.04.2014
and
Valid Upto 28.02.2017
Date of Issue of Consent to
Establish-01.04.2014
and
Valid Upto 28.02.2017.
Consent
to
operate
02.05.2014 and valid Upto
28.02.2017
Date of Issue of Consent to
Establish-01.04.2014
and
Valid Upto 28.02.2017
all the plants except crusher..

Considering the lapses on the part of the contractor on EMP management, Penalty
clauses invoked and recommended payment deductions. Tree planting air quality water
quality monitoring was also to be done. . The remaining works of parking area , bus
bays, noise receptors are to be taken along with the pavement works. Contactor has
taken full width of the road for construction This was created traffic management issues
.No traffic worthy road for the movement of traffic in construction zones provided. The
disposal of excavated earth is an issue, as large quantities of cut earth is available
.Disposal site has to be provided to the contractor by the employer Contractor has
identified two private temporary disposal site. At ch 0+500 the side of the abandoned
quarry to be protected urgently with retaining walls or crash barriers. At present the
safety engineer is entrusted the responsibility of safety and environment management.
Considering the works are spread over 40km, additional support staff is to be provided
to assist him.

15.5 Traffic Management and Road Safety Measures


Contractor has submitted the Health, Environmental and Safety management plan
which was approved.. Traffic safety management at site has to be improved urgently.
Contractor performance was not satisfactory on safety management and notice was also
issued for their poor performance, The construction safety signage at construction zone
are not maintained .Contractor was directed to improve this .Site visit observation
forwarded to the contractor for action and report.

MonthlyProgressBriefNovember2015

Page52

7.11 Photographs

DBM laid from 0+060 to 0+500 Both Sides

Gabion wall at 5+600 LHS

Precast Drain from 0+150 to 0+300 RHS

Roadway Excavation at 9+400 LHS

MonthlyProgressBriefNovember2015

Page53

8.1 Contract Package VI

Upgradation of Road from Ponkunnam to Thodupuzha


Scope of work (46.363 km)
Minor Bridge reconstruction - 1 no.
Culvert:
Reconstruction

109 nos.

Widening

44nos.

New Construction

7 nos.

Drain

65 km

Foot Path

Solar Street Light

8.2 Contract details:


Letter of Acceptance date

04.02.2014

Agreement date

05.05.2014

Name of Contractor

M/s GHV-EKK (JV)

Contract price

Rs. 227,13,73,548

Notice to Commence

10.06.2014

Total Length

46.363 km

Contract Period

30 months

Completion date

09.12.2016

Defect Liability Period

365 days

1st Milestone

10 km

2nd Milestone

25 km

3rd Milestone

Completion of full stretch & Thodupuzha


Bypass

MonthlyProgressBriefNovember2015

Page54

8.3 Financial Progress:


Summary of progress for major items is as follows:

I
(85+000 to 95+000)
Milestone

Length in km

II
(84+000 to 85+000)
Bypass 2.57 km
(95+000 to 106+400)

10.000

III
(106+400 to 117+430)
(117+430 to 131+015)

14.970

24.615

Side

LHS

RHS

LHS

RHS

LHS

RHS

GSB completed in km

10.20

9.85

3.65

3.94

4.91

5.35

WMM completed in km

9.55

9.07

3.55

3.60

4.15

4.75

DBM completed in km

7.88

8.18

3.41

3.57

3.54

4.25

BC completed in km
CD works completed in
No.s
CD works in progress in
No.s

20 / 20

42 / 43

39 / 83

15

Work progress considering the contract price:


Upto previous month
(October)

This month
(November)

Cumulative (till end of this


month) (November)

Target

Achieved

Target

Achieved

Target

Achieved

47.12%

51.53%

4.74%

5.01%

51.86%

56.54%

8.4 Structural Work


During the month precast box culvert work has been commenced in 1 location in
Milestone-II, 17 locations in Milestone-III. Box culvert Cast-in-situ work has been
commenced in 2 locations in Milestone-III. During the month, in total 801 No.s Drain
segments cast have been done of 125mm thick wall thickness. In total 56.4 km drain
work has been completed. Precast Drain segments 9609 No.s as on date has been
completed. In total 10258 Nos Precast drain cover slabs have been completed in
Kidangoor Casting yard.
Precast Box Culvert work has been commenced in following chainages:

S.
No.
1.
2.
3.
4.
5.

Work Description

Side

Chainage

Precast Box Culvert


Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert

RHS
LHS
RHS
LHS
LHS

129.022
119.760
129.470
123.692
119.750

MonthlyProgressBriefNovember2015

Page55

6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.

Precast Box Culvert


Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert
Precast Box Culvert

RHS
LHS
RHS
RHS
LHS
LHS
LHS
RHS
RHS
RHS
LHS
RHS

119.820
102.435
126.990
128.200
107.139
124.080
124.386
126.043
127.906
129.810
124.632
129.497

8.5 Bar Chart of Physical Progress:


BOQQuantity

ConcretingM40(cum)
ConcretingM35(cum)
ConcretingM30(cum)
ConcretingM25(cum)

BC(cum)
DBM(cum)

8925
7950

42045

26862
15784
13100
14874
5750
730
28616
11600
9494

Looseningandrecompacting

67000
45438

Subgrade(cum)

76823

Embankment (cum)
0

145542

76350

42398

GSB(cum)

255685

156000

61452

WMM(cum)

Excavation(cum) inhardrock

CumulativeAchievedto endofthis month

29
0
0
102
102
0
3050
1555
1519
5092
2850
985

ConcretingM20(cum)
ConcretingM15(cum)

Cumulativetarget to endof thismonth

124075
140000

222161

41194
30500
25389
25000
68992

Excavation(cum)

212732

267600

397929

60%

70%

80%

90%

100%

8.6 S-Curve

30%

40%

50%

Original Programme
(R-0)m

0%

10%

20%

Achieved
Progress

MonthlyProgressBriefNovember2015

Page56

8.7 Implementation of EMP


8.7.0.1

General

Consultants supervision initiatives for compliance of environment management plan


and to strengthen mitigation efforts at construction site were in progress in various
areas during month September 2015. Planning, monitoring and supervision for
environment mitigation work was been done for compliance of EMP along with upgradation of road from Ponkunnam (KM 84+000) to Thodupuzha (130+000) and
Thodupuzha bypass of SH-08.
During the work progress the statutory compliance under environment regulations,
Waste (Management and Handling) Act 1989 and PUC (Central Motor and Vehicle) Act
1988 was emphasized. The traffic management and safety has been practiced
throughout. PAPs grievance has been rectified by implementing the suggested action
plans by KSTP.

8.7.0.2

EMP Monthly Progress Report:

S.
No.

Enhancement Measure

1.
2.
3.

Noise Barrier
Hand pumps
Bus Shelter

4.

Sign Boards

5.
6.
7.
8.
9.
10.
11.
12.

Physical
target
(Nos.)

19
6
41
Quantity
not
estimated

Preserving
and
landscaping the cultural
7
properties like shrines
and hyundi
Constructing new well
3
Providing new water taps 33
Quantity
Parking space for auto
not
rickshaws, cars and jeep
estimated
Landscaping of type C
17
oxbow lands
Planting trees along road
864
side
Planting trees on inner
side of sound insulating 440
wall
Providing 1.2 m high Quantity

MonthlyProgressBriefNovember2015

Units
carried
over
from
previous
month
(a)
1
1
0

Units
Units
completed
started in
in
reporting
reporting
month
month

Units
carried
over to
next
month

(b)
2
0
0

(c)
0
1
0

(d)
3
0
0

0
0

0
0

0
0

0
0

0
Page57

fencing under via duct

13.

not
estimated

Concrete flooring with


slope drains and oil 3
interceptors

C.
S. No.

Details of Sites for Project Ancillary Facilities


Cumulative
No of sites Cumulative
Type of Camp/Site Cumulative
No of sites operational No of sites No of sites
redeveloped Closed*
opened
1.
Construction Camp
2
2
0
0
2.
Labour Camp
2
2
0
0
3.
Quarry & Stone
1
1
0
0
crusher unit
4.
Borrow Area
0
0
0
0
5.
Debris Disposal Site
0
0
0
0
6.
Water Sources
3
3
0
0
*A site will be considered closed after redeveloping and obtaining closure certificate from CSC.
D.
S. No.
1.
2.
3.
4.

Reporting/Monitoring formats to be annexed with this monthly report by the CSC


Reporting/Monitoring format
Yes/No
Format for Register of sites opened and closed and its reporting
Format for Register of complaints and its reporting
Reporting format for Work Force Management
Yes
Reporting Format for Occupational Health and Safety Measures
Yes

5.

Reporting Format for Top Soil Conservation

6.

Reporting Format for water sprinkling for Dust Suppression

Yes

7.

Reporting format for Road Safety Measures during construction

Yes

8.

Reporting Format for Register if Accidents and its Reporting

9.

Reporting Format for Enhancement and Mitigation of Cultural Properties

10.

Reporting Format for Noise barrier construction

11.

Reporting Format for Enhancement Measures Other than Cultural


Properties

12.

Reporting Format for Tree Plantation

13.

Reporting Format for Environmental Pollution Monitoring

14.

Checklist for Monitoring of Construction Camp Management

15.

Checklist for Monitoring of Labour Camp Management

16.

Checklist for Monitoring of Quarry and Stone Crusher Management

17.

Checklist for Monitoring of Borrow Area Management

18.

Checklist for Monitoring of Debris Disposal Site Management

19.

Checklist for Monitoring of Redevelopment of Construction Camp Site

20.

Checklist for Monitoring of Redevelopment of Labour Camp Site

MonthlyProgressBriefNovember2015

Yes

Page58

21.
22.

Checklist for Monitoring of Redevelopment of Quarry and Stone Crusher


Site
Checklist for Monitoring of Redevelopment of Borrow Areas

23.

Checklist for Monitoring of Redevelopment of Debris Disposal Site

I Submission Details

Submitted By
(Environmental Officer of CSC

Approved By
(Environmental Officer of PMT)

Signature & date


Remarks by PMT

8.8 Payment to contractor


Payment up to November 2015 is IPC-18 Rs. 1111805824/-

MonthlyProgressBriefNovember2015

Page59

8.9 Photographs

GSB Work in progress at CH:108+600 in


LHS

Hard rock excavation work in progress


at 121+900 in RHS

MonthlyProgressBriefNovember2015

GSB Work in progress at CH:109+100 in


LHS.

Construction of drainage in the school


premises at Ch:89+460(RHS)

Page60

9.1 Contract Package VIII

Upgradation of Road from Punalur to Ponkunnam


Work has to be arranged under PPP mode (Modified Annuity). DPR submitted by
M/s CDM Smith Associates is under review.

The Transaction Advisory has been

selected and assignment commenced. The Transaction Advisory is M/s L&T Ramboll in
JV with M/s Fortress.
completed.
endorsed.

The review of DPR and RFQ, RFP and Financial modal are

Bidding documents were placed before the Steering Committee and


The Government had expressed willingness to include the project in the

Infrastructure fund being mobilized.

The Government has now been requested for

permission for including provision for revolving LC towards payment of semi annuity.
The notification calling attention prospective bidders is being published.

9.1.0.1

Investor Meet:

On March 7, 2015 investor meet was conducted at Kochi in which more than 20
prospective concessionaires participated. They have shown good interest in the project.
Mr. Arnab, Task Team Leader, Mr. Bernard, Senior Transport Specialist and Ms. Carla
Gonzalez, of World Bank participated.

10.1
Contract Package VII
Upgradation of Road from Perumbilavu Pattambi Perintalmanna
Horizontal alignment finalized and boundary stone planted for land acquisition.

The

original proposal was to upgrade the project under EPC mode. But due to the delay
anticipated in acquiring the land invoking the provision of the new LA Act for which
rules are being finalized by the Government, it has been decided to provide a modest
level of improvement to the surface. It is also proposed to make use of the savings due
to the change in the improvement proposals for providing overlay to the KSTP-I roads.
Accordingly proposals have been submitted to the Government and to the Bank after
obtaining approval of the Steering Committee on 28th July 2014.

The bid has been

awarded.

11.1 Proactive actions taken by employer:


1. The threshold limit of minimum IPC has been lowered to Rs. 1.50 crores from
Rs. 3.00 crores to facilitate cash flow of the contractors.
2. Extension of time limit for completion of Milestone-I has been granted for Package
I, II and III to compensate the delay caused due to reasons beyond the control of
MonthlyProgressBriefNovember2015

Page61

the contractors. But contractor for Package III could not speed up the work and
hence terminated for non performance.

12.1 Road Safety Component Current Status


Road Safety Capacity Building and Program
Project
i.

Management

Base Line Road Safety Survey for Safe Corridor Demonstration Project
Kazhakkoottam Adoor Study completed

ii. Road Safety Capacity Building and program management


M/s Vick Roads, Australia is identified as consultant and assignment commenced.
The inception Report submitted and workshop to finalise the report was held 30
January 2015. The consultations for strengthening of the institutions responsible
for Management of Road Safety in the State is in progress.

The project also

includes assistance in developing Safe Corridor Demonstration Projects and Local


Level Road Safety Programs and Implementation. The consultant has submitted
proposal for strengthening KRSA and trained the KSTP Engineers to design the
Road Safety interactions in SCDP.

The DPR for developing SCDP was also

prepared along with bid documents has been finalized as advised by the Bank.
The bidding for procuring traffic counters completed and the approval of Steering
Committee is being obtained.

The bidding for marketing agency are also in

progress.

14.1 Institutional Strengthening Components Current Status


1

Road User Perception Survey

::

Completed, report submitted

Prioritization and DPR preparation for 1000


km

::

Work completed. Draft DPR presented.


The project was processed to Govt. and
posing for JICA assistance.

::

Work completed and Report forwarded


to Chief Engineer (R&B) for preparing
DPRs of individual road packages with
PWD funds.

::

Final report received and submitted to


Government. This was also shared
with NATPAC

::

EOI notification for work packages 2,3


& 4 invited. The Client Executive
Program Sponsor joined and
functioning. The Technical and
Financial Advisors are being placed.

::

The ToR was revised and EoI invited


and EoI from Six Firms received and 5

SOS for 8750 km MDR

Development of Multi Model (Hub)


Prefeasibility study

Appointment of client Executive Program


Sponsor and work packages

Integrated Information Management System

MonthlyProgressBriefNovember2015

Page62

firms short listed. Two bids received


and under evaluation.
7

::

Architectural and Structural Design


completed under KSTP II and proposal
submitted to Government for
Administrative Sanction for the
construction. Now World Bank has
suggested to revise the AR Drawing, for
the newly proposed Road Agency. The
design will be finalized in consultation
with the Client Executive Programme
Sponsor

::

Seven EoIs received and Five Firms


short listed and pre-bid completed.
Only 2 firms have submitted their offer
and one firm is qualified. The Steering
Committee has rejected the proposal
being single offer and higher rate.

::

Review of existing IT systems in PWD


completed.

Construction of Head of Quarters Building


under Green building concept

Community Participatory Road Safety and


Asset Management Program

Review and updating information systems in


PWD.

15.1 Payment to the consultants as on end September 2015:


M/s Egis India JV

Rs. 167157697

M/s MSV International

Rs. 22296112

16.1

Overlay to 150 km KSTP-I Roads

It has been proposed to provide overlay to 150 km of KSTP-I improved roads from the
savings anticipated from the Perumpilavu Perintalmanna road.

The Steering

Committee at its meeting held on 28 June 2014 approved the proposal and intimated to
the Bank. The DPR has been completed by the KHRI and economic evaluation was got
done through a specialist. The bidding documents completed and forwarded to Bank.
The documentation under review by Bank. The Bank has now informed to defer the
project.

17.1

Meetings, Site visits & Inspection

Package-I

The Project Director KSTP inspected the Project on 30th Oct 2015.

Progress Review Meeting convened at REs site office on 06th Nov 2015, RE with
CSC Staffs and Contractors representative attended.

MonthlyProgressBriefNovember2015

Page63

The DB conducted meeting at the Office of the Executive Engineer, KSTP Divn.
Kannur on 13th Nov 2015 and visited the Project site on 14th Nov 2015

The Environmental Engineer, CSC Visited the Project site on 18th Nov 2015.

Team Leader Visited the Project Site on 23rd Nov 2015 to 26th Nov 2015.

Revenue Divisional Officer (RDO), Kanhangad conducted meeting on 25th


Nov.2015 to understand the plan upgradation works with in the Kanhagad
Municipality limits.

Package-II

Dispute Board meeting conducted on 13th November 2015 at the office of the
Executive Engineer, Kannur. The chairman & board members visited the site on
14th November 2015.

Progress Review Meeting was held at CSC Office, Pazhayangadi

on 07th

November 2015.

Utility Coordination meeting convened at Vyduthi Bhavan, KSEB, Kannur on 06th


November 2015.

Team Leader, CSC visited the site on 26th November 2015.

Environmental expert, CSC visited the site on 19th November 2015.

Package-IV
The Chief Engineer has visited the project site twice during the month.
Leader inspected the works in the project site on 18.11.2015.

The Team

Package-IVA
The Chief Engineer has visited the project site twice during the month.
Package-V
No progress review meeting was convened in the month of November 2015. Chief
Engineer KSTP inspected the site on 10th November and 14th November 2015. Team
Leader of CSC inspected the site on 18th November 2015.

18.1
Sl.
No

Land Acquisition Status


Name of Road

Total Required
Land (Hectare)

Extent
pending

LA stage

acquisition

Kasaragod-Kanhangad

2.9830

NA

Pilathara-Pappinissery

6.2340

NA

Thalassery-Valavupara

25.3200

0.4505

MonthlyProgressBriefNovember2015

Negotiated
purchase (NP)
Page64

in progress
4

Chengannur-Ettumanoor

Thiruvalla Bypass

EttumanoorMuvattupuzha

15.3680

0.0964

NP in progress

2.7801

0.4701

NP stalemate

17.8660

1.3189

NP in progress

Ponkunnam-Thodupuzha

35.7330

NA

Punalur-Ponkunnam

17.7050

0.0260

NP in Progress

9.7332

9.7332

Being initiated

PerumbilavuPerinthalmanna

Direct purchase proposal of land was approved by the Steering Committee on 28 June
2014

19.1

Bank

Status on Critical Actions identified by World

Component A - Road Network Upgrading and Safety Improvement

1.

Award of Contract Package 3A

The bid has already been called for


under National Competitive Bidding
::
(NCB) and are approved by the Steering
Committee and sent to Bank for review.

2.

Award of Package-3B

The bids invited under National


:: Competitive Bidding (NCB) and are
under finalization.

3.

The contractor has speeded up the


works and since the rainy season is
almost over, it would be possible to
Achieve consistent Monthly Progress
::
achieve a monthly progress of 2.50%
of 2.5% for Contract-5
for this contract in the upcoming
months

4.

The contractor has speeded up the


Achieve
a
consistent
Monthly
works and it is expected that 5%
::
Progress of 5% for Contract-1 & 2
progress per month could be achieved
from November onwards.

5.

Initiate an independent assessment


The Value Engineer and IIT Experts
for approving the Variation Orders in :: and CESS experts visited the sites and
Contract 4 & 6
reports submitted and acted on it

6.

The RFQ with Project Structuring and


viability report was submitted to the
Finance Department for review through
:: the Secretary to Government, PWD, as
decided by the Steering Committee.
The endorsement from Government
received and document submitted to

Issue of RFQ for PPP Road

MonthlyProgressBriefNovember2015

Page65

the Bank for review.

7.

The ToR was reviewed by the Bank.


This has been deferred by Steering
Finalize ToR for PMC Consultants
:: Committee for detailed discussion with
and submit to Bank
the Mission on necessity at this stage.

Component - B - Road Safety Management

8.

The consolidated DPR incorporating


Submit Draft Bid Document for the
the Road Safety and Overlay Works are
Road Safety Demonstration Corridor :: under
preparation
and
will
be
Civil Works
submitted to the World Bank for review
by mid November.

9.

Complete
Specialized
Recruitment in KRSA

Staff

Four search agencies have been


identified by M/s VicRoads on success
::
fee basis, as earlier attempts by KRSA
was futile.

Component - C - Institutional Strengthening


Advertisement has been issued with
Appoint Technical and Financial
due date as November 6, 2015.
10. Advisor for the Client Executive ::
Program Sponsor
Complete Review and Validation of
This has been done and ToRs sent to
11. task inputs and man months for :: Bank for all three consultancies.
Consultancy Activities
Issue of RFP for the Sector Strategic
12.
Option Study Work Packages

EoI received:
Package-2 Thirteen numbers
Package-3 Eleven numbers
Package-4 Twelve numbers
Short listing commenced

Issue RFP for Integrated OmniChannel IT and Communication


Five firms shortlisted and RFP sent to
for
improved
Public :: them with due date as November 12,
13. System
Communication
and
User
2015.
Engagement
Engage
Agency
for
Stakeholder Engagement in
Safety
Enhancement and
17.
preservation.
(Community Participatory and
Safeguard Program)

One consultant was qualified in the


technical proposal Evaluation and the
financial proposal was opened on
This was not
:: August 7, 2015.
approved by the Steering Committee
Asset
being single offer at high rate. Revision
of ToR is in progress

direct
Road
asset

General Issue
Engage
Agency
for
direct
20. Stakeholder Engagement in Road :: This is same as item 17 above.
Safety
Enhancement and asset
MonthlyProgressBriefNovember2015

Page66

preservation
Start
using
the
e-project
KSTP has started using PMS software.
management system for improving
21.
:: The Finance Management is through
overall project management
Tally Software, now
Finance Management
22.

Submit IUFR for period ended 20th


June 2015

23. Internal audit


24.

Submit approved final accounts to


external audit for FY 14-15

:: Submitted
:: For 14-15 completed.
::

This has been approved by Steering


Committee and minutes awaited.

Can be undertaken on completion of


the above two activities (date of
Submit external audit report for FY
25.
:: submission of accounts with audit
2014-15
report has been extended by World
Bank till 31.12.2015)
26.

Submit internal audit report for first


half of FY 2015-16

:: To be done

27.

Obtain required funding from State


Treasury on a timely basis

:: Noted. Action being taken

20.1 Current Status of Six Point Program:


1. Achieve a consistent 5% :: As the performance of contractor is not up to
financial progress per month
the expected level, notice under Clause 15.1 of
from December 2014 onward
contract issued to improve the performance was
for contract Package-1 and 2
served. The contractor has now brought in
more labourers and other resources and
speeded up the works. It is expected that 5%
financial progress could be achieved from
November 2015 onwards.
2. Achieve a consistent 2.5% :: Package-3: The work has been terminated due
financial progress per month
to poor performance. This package has since
from
December
2014
been split into two smaller packages and
onwards
for
Contract
bidding completed and Package 3A awarded.
Package 3 and 5
Award of 3B is being finalized.
Package-5: The contractor has arranged to
speed up the work by engaging more labourers
and pumping additional resources. It would be
possible to achieve 2.50% progress in the
coming months.
3. Keep the Project Account :: There is no interruption to the fund flow to the
project now.
adequately funded at all time
MonthlyProgressBriefNovember2015

Page67

to meet the requirement for


next 45 days
4. Roll out the new rules for the :: The rules have been cleared by the State
Right to Fair Compensation
Cabinet and actions for direct purchase of land
and Transparency in Land
are in progress.
Acquisition Bill, 2013 to
enable
resumption
of
remaining land acquisition
by February 2015
5. Engage the Client Executive :: Shri. Babu Jacob IAS (Retd.) former Chief
Program Sponsor, set up the
Secretary, Kerala has taken over the position of
client Sponsors office and
Client Executive Program Sponsor.
The
initiate procurement of Work
advisors are also being mobilized. The ToR for
Packages WP1 through 4
work Packages 2,3 and 4 sent to World Bank for
review. Meanwhile EoIs have been received for
short listing
6. Pace
of
project :: As the works are speeded up by the contractors
disbursements accelerate to
it would be possible to accelerate the pace of
at least three times the
project disbursement.
current level

21.1 List of Annexure:


Annex 1

Important correspondence with the contractors and minutes of the meeting

MonthlyProgressBriefNovember2015

Page68