Labour (For Taking Out Doors)
Labour (For Taking Out Doors)
and
refixing the same after cutting from the bottom portion as per requirement all complete as per direction of Engineer-inCharge.
Details of cost for (2.20 sqm) each
Ref : DAR2007/ P702/Item 15.13.1 7 P322 /item 9.21.1
Labour (For taking out doors)
Carpenter IInd class
0.05 No.
Beldar
0.08 No.
Sundries
0.52 LS
Labour (For refixing doors & windows) assume 75% labours
Carpenter (average)
0.41 No.
Beldar
0.41 No.
480.00
350.00
1.97
each
each
LS
24.00
28.00
1.02
480.00
350.00
each
each
196.80
143.50
393.32
3.93
397.26
59.59
456.85