Monthly Progress Report April

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

RuRuJalbidhyutPariyojanaPvt.Ltd.

Kathmandu,Nepal

MonthlyProgressReportof
April2013
UpperHugdiKholaHydropowerProject(5MW)

May,2013

TableofContents:
1.

PROJECTSALIENTFEATURE ....................................................................................................................................... 1

2.

INSTITUTIONALARRANGEMENT ............................................................................................................................. 4

3.

RESOURCESATSITE.................................................................................................................................................... 4

4.

3.1

EmployerandConsultant ................................................................................................................................ 4

3.2

CivilConstructionContractor(3HC) ............................................................................................................... 4

CIVILWORKPROGRESS ............................................................................................................................................. 5
4.1

Infrastructure ..................................................................................................................................................... 5

4.1.1

MobilizationWorks .................................................................................................................................. 5

4.1.2

StaffQuarteratheadworks ................................................................................................................... 6

4.2

AccessRoad ........................................................................................................................................................ 6

4.3

Waterway ............................................................................................................................................................ 6

4.3.1

HeadracePipe ........................................................................................................................................... 6

4.3.2

PenstockPipe ............................................................................................................................................ 7

5.

VISITORSOFTHEMONTH ......................................................................................................................................... 8

6.

ACCIDENTSATSITE..................................................................................................................................................... 8

7.

MAJORACTIVITIES ...................................................................................................................................................... 8

8.

PHOTOGRAPHS ........................................................................................................................................................... 9

ListofTables:
Table 4-1Quantity Record of Access Road ................................................................................................................... 6
Table 4-2Quantity Record of Headrace Pipe................................................................................................................ 6
Table 4-3Quantity Record of Civil works Penstock Pipe .......................................................................................... 7

ListofFigures:
Figure 4-1 Surveying waterway ........................................................................................................................................ 5
Figure 4-2 Erection of rock crusher................................................................................................................................ 5
Figure 4-3 Excavation at Headrace pipe alignment ...................................................................................................... 7
Figure 4-4 Excavation at penstock alignment ................................................................................................................ 8

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

1.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

PROJECTSALIENTFEATURE

General
NameoftheProject

UpperHugdiKholaHydropowerProject

District

Gulmi

LocationoftheProjectSite

RupakotandHarewaVDCs

Nameoftheriver

HugdiKhola

TypeofScheme

RunofRiver

InstalledCapacity

5000kW

CatchmentArea(atintake)

120km2

Designdischarge

3.75m3/s

Designflooddischarge(atintake)

495m3/s

CompensationFlow

0.08m3/s

DesignFloodDischarge(1in100years)atweir :

495m3/s

DesignDiversionDischarge(1in5years)

13m3/s

Hydrology

DiversionWeir
Typeofweir

Concretefreeflow

Weirlength

18m

WeirCrestlevel

El1028.50m

Typeandnumbersofintake

Sideintake,orificetype,2Nos.

OpeningDimension

2.0mx2.0m(WxH)

Invertlevelofintake

1027.5masl

LengthxWidthxHeight

10.75mx2.6mx2.138m

Graveltrapgates

1No,0.40m(H)x0.4m(W)

LengthandType

30mOpenCanal

Size/Shape

2.0mx1.63m/Rectangular

Intakestructure

GravelTrap

ApproachCanal

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

SettlingBasin
Type

Surfacedoublebasinrectangulartype

two

Dimension(LengthxwidthXoveralldepth)

43.0mX5.0m3.60m(each)

Particlesizetobesettled

0.2mm

Trappingefficiency

90%

LengthoftheFlushingChannel

35m

Settlingbasininletgates

2Nos,each1.5m(W)X1.35m(H)

Settlingbasinoutletgates

2Nos,each1.5m(W)X1.45m(H)

Settlingbasinflushinggates

2Noseach0.6m(W)X0.6m(H)

Noofbays

HeadracePipe
Type

Exposedonsurface

Material

MildSteel

Thickness

6mm

Internaldiameter

1.35m

Length

1242.66muptoheadracecanal

HeadraceCanal
Type

RCCrectangular

Size

1.72mX1.7m

Length

468.428muptoforebay

RCCrectangular

Forebay
Type
LengthXWidthXDepth

22X5X2.05m

FullSupplyLevel

El1013.425m

Exposedonsurface

Material

MildSteel

Thickness

Variesfrom8mmto16mm

Internaldiameter

1300mm

Length

1604.132m

PenstockPipe
Type

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

Powerhouse
Type

Surface

Size

24.6mx17.6m

Height

11.0m

RectangularRCC

Length

36maftertailracejunction

Size

2.5mX2.5mrectangular

TypeofTurbine

2700kWx2nos,Pelton

Ratedefficiency

90%

Axis

Horizontal

Type/layout/unit

Brushlesssynchronous/horizontal/2nos

RatedCapacity

3125kVAeach,50Hz,Threephase

96%

StepupTransformer

3Phase,ONANCooled

Capacity/Rating

3150kVA,6.3/33kV,50Hz/2nos

RatedEfficiency

99%

TailraceCanal
Type

Turbine

Generator

RatedEfficiency

Transformer

TransmissionLine&GridConnection
Transmissionline

33kV,

Length

15km(PHto33/11kVBirbasSubstation)

171.42m

Ratednethead

161.59m

DesignDischarge

3.75m3/sec

Installedcapacity

5000kW

DryseasonEnergy

5.49GWh

WetSeasonEnergy

22.77GWh

TotalEnergy

28.26GWh

PowerandEnergy
Grosshead

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

2.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

INSTITUTIONALARRANGEMENT

FollowingentitiesconstitutethewholeinstitutionalarrangementofUpperHugdiKholaHydropower
ProjecthavingInstalledCapacity5MW

Employer:RuRuJalbidhyutPariyojanaPvt.Ltd.(RuRu).
Engineer:CEPADHydroConsultantPvt.Ltd.(CEPAD).
Contractor(CivilConstruction):HighHimalayaHydroConstructionPvt.Ltd.(3HC).
Contractor(HydroMechanical):Biddocumenthasbeenfloat,lastsubmissiondate13May2013
Contractor(ElectroMechanical):Tenderingisinprocess
Contractor(Transmissionline):Tenderingisinprocess
FinancingInstitution:CleanEnergyDevelopmentBankLimited(LeadBank)

3.

RESOURCESATSITE

3.1

EMPLOYERANDCONSULTANT

HumanResources:(10)
ResidentEngineer1,ProjectEngineer1,DesignEngineer1,AdminAccount1,SiteSupervisor3,
Driver1,Cook1,Helper1

3.2

CIVILCONSTRUCTIONCONTRACTOR(3HC)

HumanResources:(20)
Projectmanager
Engineer/Surveyer/Overseer
Supervisor/Forman
Skilledworker
Unskilledlabours
Operators/Drivers
Helpers

1
5
1
3
2
3
2

Mechanical/Electricalstaff
Office/Store
Cook/peon/SG
SubTotal
Otherworkers(Unskilled)

Total

0
2
1
20
0

20

PlantandEquipments:
Generator30KVA
Generator45KVA
Generator5KVA
Excavator
WheelLoader
DumpTrucks
BackHoe(JCB)
Tractor
Truckformaterialstransportation
LightVehicle
Motorbike
ConcreteMixture

1
2

RockDrillmachine
Levelmachinewithset
TotalStation
Vibrators
DewateringPump
GrindingMachineLSD64
Weighingbalance
Seiveanalysisset
Compactor
Concretecompressivetestingmachine

1
1
1

1
1
1

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

4.

CIVILWORKPROGRESS

4.1

INFRASTRUCTURE

4.1.1

MOBILIZATIONWORKS

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

Jointsurveyforquantityverificationofwaterwayiscompleted.

Figure41Surveyingwaterway

Establishmentofsurveycontrolpointsforwholeprojectareaiscompleted.
SumitomoSH210Excavatorisworkingonpipealignment(waterway)andKomatsuPC200
Excavatorhasarrivedatsiteon2ndApril2013andisalsocontinuingworkatwaterway
alignment.
Constructionofcontractorcamp80%workcompleted.
Establishmentoflaboratoryatsiteiscompletedandmixdesignhasbeenstarted.
RockcrushermachinehasbeenarrivedatsiteandconstructionofRockcrushermachine
foundationhasbeencompleted.

Figure42 Erectionofrockcrusher
5

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

4.1.2

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

STAFFQUARTERATHEADWORKS

BadmintoncourthasbeenconstructednearbystaffquarterfortherefreshmentoftheEngineerand
Employersstaff.

4.2

ACCESSROAD

Trackopeningworkthroughoutthepipealignmentiscompletedhoweverfewretainingstructureneedto
beconstructedandhasbeenplannedforcomingmonth..
Table41QuantityRecordofAccessRoad
S.
No.

1.1
1.2
1.3
2
3
4

WorkDescription
Earthworkinexcavation

Unit

Previous

Earthexcavationinnormalsoil
Earthexcavationinboulder/gravel
mixedsoil
Earthexcavationinrock/boulder
Earthfillingwithoutcompaction
Gabionwork
Stonemasonry1:4

480.00

2,000.00

m3

320.00

Quantity
upto
Present
date

1,870.00
2,350.00

2,350.00 100.00%

3,650.00

5,650.00

5,650.00 100.00%

430.00

750.00

m
m
m

BOQ

Progress
%

750.00 100.00%
700.00

120.00

45.00

4.3

WATERWAY

4.3.1

HEADRACEPIPE

Excavationworksthroughoutthepipelinealignmentisinprogressalongwithtrackopening.

Table42QuantityRecordofHeadracePipe
S.
No.
1
1.1
1.2
1.3
2
3
4

5
6
7

WorkDescription
EarthworkinExcavation
Earthexcavationinnormalsoil
Earthexcavationinboulder/gravel
mixedsoil
Earthexcavationinrock/boulder
Earthfillingwithoutcompaction
Surfacepreparation,Levelingand
compaction
ConcreteWorks
C15with40%plum
C15
C25
Reinforcementwork(Intotalwithall
necessary)
Formwork
Gabionwork

Unit

Previous

500.00

m
3

Quantity
Upto
Present
date

850.00

BoQ

1,350.00

3,500.00 1,000.00

4,500.00

7,733.44
15,066.88

Progress
%

17.46%
29.87%

300.00

250.00

550.00

2,577.81

21.34%

23,474.00

900.39

m3
3

m
2

786.31

67.53

232.35

tonns

28.50

m2

2,067.34

m
m

1,245.00

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

Figure43ExcavationatHeadracepipealignment

4.3.2

PENSTOCKPIPE

Excavationworksthroughoutthepenstockalignmentisstartedalongwithtrackopening.

Table43QuantityRecordofCivilworksPenstockPipe
Quantity
SN
1
1.1
1.2
1.3
2
3
4

5
6
7

WorkDescription
EarthworkinExcavation
Earthexcavationinnormalsoil
Earthexcavationinboulder/gravel
mixedsoil
Earthexcavationinrock/boulder
Earthfillingwithoutcompaction
Surfacepreparation,Levelingand
compaction
ConcreteWorks
C15with40%plum
C15
C25
Reinforcementwork(Intotalwithall
necessary)
Formwork
Gabionwork

Unit

Previous

Present

Upto
Date

m3

220

1,500

1,720.00

m3

2,000

8,500

10,500.00

m3

180

600

780.00

Progress
%

BOQ


11,685.33
21,220.67
4,195.11

14.72%
49.48%
18.59%

30,463.04

m
3

m
3

m
tonns
2

m
3

1,501.14

1,209.57

112.59

577.88

70.09

2,578.37

1,085.00

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

Figure44Excavationatpenstockalignment

5.

VISITORSOFTHEMONTH
ManagingDirectorandProjectManagerhasvisitthesiteon8th10thApril2013.

6.

ACCIDENTSATSITE

Therehasnotbeenanysortofmajorinjuriesorcausalitiessustainedresultedintheprojectsofar.

7.

MAJORACTIVITIES

CivilContractormobilizationisinprogress
Accessroadtrackopeninghasbeencompleted
Excavationworksofheadraceandpenstockpipeisinprogress
Jointsurveyforquantityverificationofwaterwayiscompleted.
Establishmentofsurveycontrolpointsforwholeprojectareaiscompleted.

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

8.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

PHOTOGRAPHS

CivilContractorunloadingDieselGeneratorat HWsite

CivilLabestablishedatHWsite

Concretecubesfordesignmixconcrete

Cubecuringpond

Cubetestisinprogress

Cursherinstallationisinprogress

RuRu Jalbidhyut Pariyojana Pvt. Ltd.

Upper Hugdi Khola Hydropower Project


Progress Report, April 2013

Excavationatwaterwayisinprogress

PenstockAlignmentatchainage2200m

BadmintoncourtnearstaffquarteratHWsite

Technicalteamisdiscussionatpowerhousesite

CivilContractor'sCamp

Powerhouse area along withCivilCamp

10

You might also like