Monthly Progress Report April
Monthly Progress Report April
Monthly Progress Report April
Kathmandu,Nepal
MonthlyProgressReportof
April2013
UpperHugdiKholaHydropowerProject(5MW)
May,2013
TableofContents:
1.
PROJECTSALIENTFEATURE ....................................................................................................................................... 1
2.
INSTITUTIONALARRANGEMENT ............................................................................................................................. 4
3.
RESOURCESATSITE.................................................................................................................................................... 4
4.
3.1
EmployerandConsultant ................................................................................................................................ 4
3.2
CivilConstructionContractor(3HC) ............................................................................................................... 4
CIVILWORKPROGRESS ............................................................................................................................................. 5
4.1
Infrastructure ..................................................................................................................................................... 5
4.1.1
MobilizationWorks .................................................................................................................................. 5
4.1.2
StaffQuarteratheadworks ................................................................................................................... 6
4.2
AccessRoad ........................................................................................................................................................ 6
4.3
Waterway ............................................................................................................................................................ 6
4.3.1
HeadracePipe ........................................................................................................................................... 6
4.3.2
PenstockPipe ............................................................................................................................................ 7
5.
VISITORSOFTHEMONTH ......................................................................................................................................... 8
6.
ACCIDENTSATSITE..................................................................................................................................................... 8
7.
MAJORACTIVITIES ...................................................................................................................................................... 8
8.
PHOTOGRAPHS ........................................................................................................................................................... 9
ListofTables:
Table 4-1Quantity Record of Access Road ................................................................................................................... 6
Table 4-2Quantity Record of Headrace Pipe................................................................................................................ 6
Table 4-3Quantity Record of Civil works Penstock Pipe .......................................................................................... 7
ListofFigures:
Figure 4-1 Surveying waterway ........................................................................................................................................ 5
Figure 4-2 Erection of rock crusher................................................................................................................................ 5
Figure 4-3 Excavation at Headrace pipe alignment ...................................................................................................... 7
Figure 4-4 Excavation at penstock alignment ................................................................................................................ 8
1.
PROJECTSALIENTFEATURE
General
NameoftheProject
UpperHugdiKholaHydropowerProject
District
Gulmi
LocationoftheProjectSite
RupakotandHarewaVDCs
Nameoftheriver
HugdiKhola
TypeofScheme
RunofRiver
InstalledCapacity
5000kW
CatchmentArea(atintake)
120km2
Designdischarge
3.75m3/s
Designflooddischarge(atintake)
495m3/s
CompensationFlow
0.08m3/s
DesignFloodDischarge(1in100years)atweir :
495m3/s
DesignDiversionDischarge(1in5years)
13m3/s
Hydrology
DiversionWeir
Typeofweir
Concretefreeflow
Weirlength
18m
WeirCrestlevel
El1028.50m
Typeandnumbersofintake
Sideintake,orificetype,2Nos.
OpeningDimension
2.0mx2.0m(WxH)
Invertlevelofintake
1027.5masl
LengthxWidthxHeight
10.75mx2.6mx2.138m
Graveltrapgates
1No,0.40m(H)x0.4m(W)
LengthandType
30mOpenCanal
Size/Shape
2.0mx1.63m/Rectangular
Intakestructure
GravelTrap
ApproachCanal
SettlingBasin
Type
Surfacedoublebasinrectangulartype
two
Dimension(LengthxwidthXoveralldepth)
43.0mX5.0m3.60m(each)
Particlesizetobesettled
0.2mm
Trappingefficiency
90%
LengthoftheFlushingChannel
35m
Settlingbasininletgates
2Nos,each1.5m(W)X1.35m(H)
Settlingbasinoutletgates
2Nos,each1.5m(W)X1.45m(H)
Settlingbasinflushinggates
2Noseach0.6m(W)X0.6m(H)
Noofbays
HeadracePipe
Type
Exposedonsurface
Material
MildSteel
Thickness
6mm
Internaldiameter
1.35m
Length
1242.66muptoheadracecanal
HeadraceCanal
Type
RCCrectangular
Size
1.72mX1.7m
Length
468.428muptoforebay
RCCrectangular
Forebay
Type
LengthXWidthXDepth
22X5X2.05m
FullSupplyLevel
El1013.425m
Exposedonsurface
Material
MildSteel
Thickness
Variesfrom8mmto16mm
Internaldiameter
1300mm
Length
1604.132m
PenstockPipe
Type
Powerhouse
Type
Surface
Size
24.6mx17.6m
Height
11.0m
RectangularRCC
Length
36maftertailracejunction
Size
2.5mX2.5mrectangular
TypeofTurbine
2700kWx2nos,Pelton
Ratedefficiency
90%
Axis
Horizontal
Type/layout/unit
Brushlesssynchronous/horizontal/2nos
RatedCapacity
3125kVAeach,50Hz,Threephase
96%
StepupTransformer
3Phase,ONANCooled
Capacity/Rating
3150kVA,6.3/33kV,50Hz/2nos
RatedEfficiency
99%
TailraceCanal
Type
Turbine
Generator
RatedEfficiency
Transformer
TransmissionLine&GridConnection
Transmissionline
33kV,
Length
15km(PHto33/11kVBirbasSubstation)
171.42m
Ratednethead
161.59m
DesignDischarge
3.75m3/sec
Installedcapacity
5000kW
DryseasonEnergy
5.49GWh
WetSeasonEnergy
22.77GWh
TotalEnergy
28.26GWh
PowerandEnergy
Grosshead
2.
INSTITUTIONALARRANGEMENT
FollowingentitiesconstitutethewholeinstitutionalarrangementofUpperHugdiKholaHydropower
ProjecthavingInstalledCapacity5MW
Employer:RuRuJalbidhyutPariyojanaPvt.Ltd.(RuRu).
Engineer:CEPADHydroConsultantPvt.Ltd.(CEPAD).
Contractor(CivilConstruction):HighHimalayaHydroConstructionPvt.Ltd.(3HC).
Contractor(HydroMechanical):Biddocumenthasbeenfloat,lastsubmissiondate13May2013
Contractor(ElectroMechanical):Tenderingisinprocess
Contractor(Transmissionline):Tenderingisinprocess
FinancingInstitution:CleanEnergyDevelopmentBankLimited(LeadBank)
3.
RESOURCESATSITE
3.1
EMPLOYERANDCONSULTANT
HumanResources:(10)
ResidentEngineer1,ProjectEngineer1,DesignEngineer1,AdminAccount1,SiteSupervisor3,
Driver1,Cook1,Helper1
3.2
CIVILCONSTRUCTIONCONTRACTOR(3HC)
HumanResources:(20)
Projectmanager
Engineer/Surveyer/Overseer
Supervisor/Forman
Skilledworker
Unskilledlabours
Operators/Drivers
Helpers
1
5
1
3
2
3
2
Mechanical/Electricalstaff
Office/Store
Cook/peon/SG
SubTotal
Otherworkers(Unskilled)
Total
0
2
1
20
0
20
PlantandEquipments:
Generator30KVA
Generator45KVA
Generator5KVA
Excavator
WheelLoader
DumpTrucks
BackHoe(JCB)
Tractor
Truckformaterialstransportation
LightVehicle
Motorbike
ConcreteMixture
1
2
RockDrillmachine
Levelmachinewithset
TotalStation
Vibrators
DewateringPump
GrindingMachineLSD64
Weighingbalance
Seiveanalysisset
Compactor
Concretecompressivetestingmachine
1
1
1
1
1
1
4.
CIVILWORKPROGRESS
4.1
INFRASTRUCTURE
4.1.1
MOBILIZATIONWORKS
Jointsurveyforquantityverificationofwaterwayiscompleted.
Figure41Surveyingwaterway
Establishmentofsurveycontrolpointsforwholeprojectareaiscompleted.
SumitomoSH210Excavatorisworkingonpipealignment(waterway)andKomatsuPC200
Excavatorhasarrivedatsiteon2ndApril2013andisalsocontinuingworkatwaterway
alignment.
Constructionofcontractorcamp80%workcompleted.
Establishmentoflaboratoryatsiteiscompletedandmixdesignhasbeenstarted.
RockcrushermachinehasbeenarrivedatsiteandconstructionofRockcrushermachine
foundationhasbeencompleted.
Figure42 Erectionofrockcrusher
5
4.1.2
STAFFQUARTERATHEADWORKS
BadmintoncourthasbeenconstructednearbystaffquarterfortherefreshmentoftheEngineerand
Employersstaff.
4.2
ACCESSROAD
Trackopeningworkthroughoutthepipealignmentiscompletedhoweverfewretainingstructureneedto
beconstructedandhasbeenplannedforcomingmonth..
Table41QuantityRecordofAccessRoad
S.
No.
1.1
1.2
1.3
2
3
4
WorkDescription
Earthworkinexcavation
Unit
Previous
Earthexcavationinnormalsoil
Earthexcavationinboulder/gravel
mixedsoil
Earthexcavationinrock/boulder
Earthfillingwithoutcompaction
Gabionwork
Stonemasonry1:4
480.00
2,000.00
m3
320.00
Quantity
upto
Present
date
1,870.00
2,350.00
2,350.00 100.00%
3,650.00
5,650.00
5,650.00 100.00%
430.00
750.00
m
m
m
BOQ
Progress
%
750.00 100.00%
700.00
120.00
45.00
4.3
WATERWAY
4.3.1
HEADRACEPIPE
Excavationworksthroughoutthepipelinealignmentisinprogressalongwithtrackopening.
Table42QuantityRecordofHeadracePipe
S.
No.
1
1.1
1.2
1.3
2
3
4
5
6
7
WorkDescription
EarthworkinExcavation
Earthexcavationinnormalsoil
Earthexcavationinboulder/gravel
mixedsoil
Earthexcavationinrock/boulder
Earthfillingwithoutcompaction
Surfacepreparation,Levelingand
compaction
ConcreteWorks
C15with40%plum
C15
C25
Reinforcementwork(Intotalwithall
necessary)
Formwork
Gabionwork
Unit
Previous
500.00
m
3
Quantity
Upto
Present
date
850.00
BoQ
1,350.00
3,500.00 1,000.00
4,500.00
7,733.44
15,066.88
Progress
%
17.46%
29.87%
300.00
250.00
550.00
2,577.81
21.34%
23,474.00
900.39
m3
3
m
2
786.31
67.53
232.35
tonns
28.50
m2
2,067.34
m
m
1,245.00
Figure43ExcavationatHeadracepipealignment
4.3.2
PENSTOCKPIPE
Excavationworksthroughoutthepenstockalignmentisstartedalongwithtrackopening.
Table43QuantityRecordofCivilworksPenstockPipe
Quantity
SN
1
1.1
1.2
1.3
2
3
4
5
6
7
WorkDescription
EarthworkinExcavation
Earthexcavationinnormalsoil
Earthexcavationinboulder/gravel
mixedsoil
Earthexcavationinrock/boulder
Earthfillingwithoutcompaction
Surfacepreparation,Levelingand
compaction
ConcreteWorks
C15with40%plum
C15
C25
Reinforcementwork(Intotalwithall
necessary)
Formwork
Gabionwork
Unit
Previous
Present
Upto
Date
m3
220
1,500
1,720.00
m3
2,000
8,500
10,500.00
m3
180
600
780.00
Progress
%
BOQ
11,685.33
21,220.67
4,195.11
14.72%
49.48%
18.59%
30,463.04
m
3
m
3
m
tonns
2
m
3
1,501.14
1,209.57
112.59
577.88
70.09
2,578.37
1,085.00
Figure44Excavationatpenstockalignment
5.
VISITORSOFTHEMONTH
ManagingDirectorandProjectManagerhasvisitthesiteon8th10thApril2013.
6.
ACCIDENTSATSITE
Therehasnotbeenanysortofmajorinjuriesorcausalitiessustainedresultedintheprojectsofar.
7.
MAJORACTIVITIES
CivilContractormobilizationisinprogress
Accessroadtrackopeninghasbeencompleted
Excavationworksofheadraceandpenstockpipeisinprogress
Jointsurveyforquantityverificationofwaterwayiscompleted.
Establishmentofsurveycontrolpointsforwholeprojectareaiscompleted.
8.
PHOTOGRAPHS
CivilContractorunloadingDieselGeneratorat HWsite
CivilLabestablishedatHWsite
Concretecubesfordesignmixconcrete
Cubecuringpond
Cubetestisinprogress
Cursherinstallationisinprogress
Excavationatwaterwayisinprogress
PenstockAlignmentatchainage2200m
BadmintoncourtnearstaffquarteratHWsite
Technicalteamisdiscussionatpowerhousesite
CivilContractor'sCamp
10