Professional Documents
Culture Documents
1 SATIP-W-011-01 Welding of On-Plot Piping - Rev1 PDF
1 SATIP-W-011-01 Welding of On-Plot Piping - Rev1 PDF
1 SATIP-W-011-01 Welding of On-Plot Piping - Rev1 PDF
SATIP No.
APPROVED DATE
SATIP-W-011-01
PROJECT TITLE:
ITEM
NO.
1.0
PROJECT PHASE
25-May-05
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
TASK / ACTIVITY
CHECKLIST
and/or
TEST RECORD
QUALITY
RECORD
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
SAUDI
ARAMCO
REMARKS
DOCUMENT REVIEW
1.1
Welding Procedure
Specifications/Welding Procedure
Qualification Record (WPS/WPQR)
SAIC-W-2001
RH1
RH1
1.2
SAIC-W-2035
RH1
R1
1.3
SAIC-W-2002
RH1
RH1
1.4
SAIC-W-2008
RH1
RH1
SAIC-W-2003
RH1
RH1
SAIC-W-2012
RH1
RH1
SAIC-L-2004
RH1
RH1
1.5
1.6
1.7
Refer to the respective SATIP for NDE (SATIP-NDEUT-01, LPT-01, MPT-01, RT-01)
1.8
1.9
SAIC-W-2009
2.1
SAIC-W-2010
2.2
SAIC-W-2011
2.0
DISCIPLINE:
RH1
R1
SAIC-W-2010
SATR-W-2009
H1
W2
SAIC-W-2011
SATR-W-2011
H1
W2
MATERIAL RECEIVING
Page 1 of 4
SATIP No.
SATIP-W-011-01
PROJECT TITLE:
ITEM
NO.
PROJECT PHASE
3.0
3.1
3.2
TASK / ACTIVITY
3.4
3.7
CHECKLIST
and/or
TEST RECORD
QUALITY
RECORD
SAIC-L-2010
SAIC-L-2010
SATR-A-2012
SATR-A-2013
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
SAUDI
ARAMCO
H1
W1
3.6
MECHANICAL
REMARKS
INSTALLATION
3.3
3.5
25-May-05
CONTRACTOR/SUBCONTRACTOR
2.3
DISCIPLINE:
SAIC-W-2032
SAIC-W-2033
SAIC-W-2005
SAIC-W-2006
SAIC-W-2032
SATR-W-2010
SAIC-W-2033
SATR-W-2006
SAIC-W-2005
SATR-W-2006
SAIC-W-2006
SATR-W-2007
Page 2 of 4
H1
H1
H1
W1
W1/H1
W2/H1
(See
remarks)
S/W2
(See
remarks)
SATIP No.
SATIP-W-011-01
PROJECT TITLE:
ITEM
NO.
PROJECT PHASE
25-May-05
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
TASK / ACTIVITY
CHECKLIST
and/or
TEST RECORD
QUALITY
RECORD
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
SAUDI
ARAMCO
3.8
SAIC-W-2037
SAIC-W-2037
H1
W1
3.9
SAIC-W-2007
SAIC-W-2007
SATR-W-2007
H1
W1
3.10
SAIC-W-2013
SAIC-W-2013
W1
3.11
DISCIPLINE:
SAIC-W-2015
SATR-W-2007
H1
REMARKS
W1/W2
3.12
Verification of Non-Destructive
Examination Method Application and
Evaluation of Results
See Remarks
See Remarks
W1/RH1
W1/R1
3.13
SAIC-W-2016
SAIC-W-2016
SATR-W-2013
SATR-W-2018
SATR-W-2019
H1
R1
3.14
SAIC-W-2004
SAIC-W-2004
SATR-W-2005
H1
W1& R1
3.15
SAIC-W-2014
SAIC-W-2014
SATR-W-2012
H1
W1 & R1
Page 3 of 4
SATIP No.
SATIP-W-011-01
PROJECT TITLE:
ITEM
NO.
25-May-05
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
PROJECT PHASE
TASK / ACTIVITY
CHECKLIST
and/or
TEST RECORD
QUALITY
RECORD
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
SAUDI
ARAMCO
3.16
SAIC-L-2010
SAIC-L-2010
SATR-A-2012
SATR-A-2013
H1
W\1 & R1
3.17
SAIC-W-2036
SAIC-W-2036
H1
H1
SATR-W-2008
H1
R1
4.0
DISCIPLINE:
REMARKS
PRE-COMMISSIONING
Final Welding Inspection &
Documentation (Welding Summary
Report / Record & Weld Map)
4.1
GENERAL NOTES
1
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
of Saudi Aramco participation based upon the Contractors performance.
Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
is not present.
Hold:
If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
LEGEND
W1
H2
RH1
W2
R1
RH2
H1
R2
Page 4 of 4
Surveillance