1 SATIP-W-011-01 Welding of On-Plot Piping - Rev1 PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


WELDING OF ON-PLOT PIPING

APPROVED DATE

SATIP-W-011-01

PROJECT TITLE:

ITEM
NO.

1.0

PROJECT PHASE

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

TASK / ACTIVITY

CHECKLIST
and/or
TEST RECORD

QUALITY
RECORD

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

REMARKS

DOCUMENT REVIEW

1.1

Welding Procedure
Specifications/Welding Procedure
Qualification Record (WPS/WPQR)

SAIC-W-2001

RH1

RH1

1.2

Welder & Welding Operator


Certifications (and Issuance of JCC)

SAIC-W-2035

RH1

R1

1.3

Method Statement & WPS for Weld


Repair, ie:
a) Crack and other weld defects
b) Weld mis-alignments

SAIC-W-2002

RH1

RH1

1.4

Procedure for Weld Identification and


Weld Traceability (Original Welds and
modified/repaired welds)

SAIC-W-2008

RH1

RH1

SAIC-W-2003

RH1

RH1

SAIC-W-2012

RH1

RH1

SAIC-L-2004

RH1

RH1

Post Weld Heat Treatment (PWHT)


Procedure
Production Weld Hardness Testing
Procedure
Positive Material Identification Procedure
(Alloy Verification)

1.5
1.6
1.7

Refer to the respective SATIP for NDE (SATIP-NDEUT-01, LPT-01, MPT-01, RT-01)

1.8

Non-Destructive Testing Procedures

1.9

Procedure for Control of Welding


Consumables

SAIC-W-2009

2.1

Receiving Inspection and Verification of


Welding Consumables-(Properties, Type,
approve source, storage, etc.)

SAIC-W-2010

2.2

Welding Equipment Calibration


Verification

SAIC-W-2011

2.0

DISCIPLINE:

RH1

R1

SAIC-W-2010
SATR-W-2009

H1

W2

S. Aramco shall verify and inspect the first batch of


delivered consumables, then random inspection
thereafter.

SAIC-W-2011
SATR-W-2011

H1

W2

Random witnessing by S. Aramco at each calibration


cycle.

MATERIAL RECEIVING

Page 1 of 4

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)


APPROVED DATE

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


WELDING OF ON-PLOT PIPING

SATIP-W-011-01

PROJECT TITLE:

ITEM
NO.

PROJECT PHASE

3.0
3.1
3.2

TASK / ACTIVITY

3.4

Control of Welding ConsumablesStorage, Handling, Issuance &


Conditioning

3.7

CHECKLIST
and/or
TEST RECORD

QUALITY
RECORD

SAIC-L-2010

SAIC-L-2010
SATR-A-2012
SATR-A-2013

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

H1

W1

Welding of Overlays & Clad Materials


(If Required)
Welding of Strip Linings
(If Required)
Welding of Special Corrosion-Resistant
Materials
(If Required)

3.6

MECHANICAL

REMARKS

Refer to Note 1 of the General Notes for S.Aramco


Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.

INSTALLATION

3.3

3.5

25-May-05
CONTRACTOR/SUBCONTRACTOR

Positive Material Identification of Low


Alloy, Stainless Steel, Nickel & Copper
Based Materials (If Required)

2.3

DISCIPLINE:

Buttering or Weld Build-Up of Joints

Pre-Welding & Weld Joint Fit-Up


Inspection

In-Process Weld Inspection

See SATIP No: W-014-01


See SATIP N0: W-016-01 and other applicable SATIPW series (if required)
See SATIP No: W-016-01

SAIC-W-2032

SAIC-W-2033

SAIC-W-2005

SAIC-W-2006

SAIC-W-2032
SATR-W-2010

SAIC-W-2033
SATR-W-2006

SAIC-W-2005
SATR-W-2006

SAIC-W-2006
SATR-W-2007

Page 2 of 4

H1

H1

H1

W1

W1/H1

Saudi Aramco inspection responsibility varies from H1


to W1:
a) "W1" -for build-up thickness not exceeding 1/3 of
the metal thickness or 10mm whicever is less.
b) "H1" - for build-up thickness exceeding the above
and requiring CSD's approval.

W2/H1
(See
remarks)

S. Aramco's responsibilities varies as follows :


a) "W2" - for Welding on normal services at normal
conditions, refer to Note 1 of the General Notes.
b) "H1" - for critical welds, ie.; Tie-Ins, buttering, Hot
Taps, NDE-In-Lieu of Hydro & others as determined by
project requirements.

S/W2
(See
remarks)

S. Aramco's responsibilities varies as follows:


a) "S" - Generally is a surveillance activity for Saudi
Aramco, except in welding of stainless steel piping and
piping in low temp service.
b) "W2" - S. Aramco inspects and verifies Heat Input at
random or on routine basis for low temp service and
for stainless steel welding.

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)


APPROVED DATE

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


WELDING OF ON-PLOT PIPING

SATIP-W-011-01

PROJECT TITLE:

ITEM
NO.

PROJECT PHASE

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

TASK / ACTIVITY

CHECKLIST
and/or
TEST RECORD

QUALITY
RECORD

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

3.8

Inspect Welding of Socket Joint and Seal


Welding Threaded Jts.

SAIC-W-2037

SAIC-W-2037

H1

W1

3.9

Post-Welding Visual Inspection

SAIC-W-2007

SAIC-W-2007
SATR-W-2007

H1

W1

3.10

Repair of Weld Joints or Base Metal by


Welding (Prior to Weld Acceptance)

SAIC-W-2013

SAIC-W-2013

W1

3.11

DISCIPLINE:

Selection of Weld Joints for NDE

SAIC-W-2015

SATR-W-2007

H1

REMARKS

W1/W2

For Saudi Aramco Responsibility:


a) "W1" -PID Inspectors shall participate in the
seletion of weld to be radiographed.
b) "W2" - will be in effect once the level of
confidence to the QC is established.
* Use the applicable SATIPS:
a) SATIP-NDE-LT-01
b) SATIP-NDE-LPT-01
c) SATIP-NDE-MPT-01
d) SATIP-NDE-RT-01
e) SATIP-NDE-UT-01
**Refer to Note 1 of the General Notes for S.Aramco
Inspection responsibility, afterwhich
pre-arranged or random Witnessing shall be
agreed upon.

3.12

Verification of Non-Destructive
Examination Method Application and
Evaluation of Results

See Remarks

See Remarks

W1/RH1

W1/R1

3.13

Weekly reporting of the following:


a) Production Weld Status,
b) Welder & Project Repair Rate
c) Welder's Repair Assessment &
Tracer Welds

SAIC-W-2016

SAIC-W-2016
SATR-W-2013
SATR-W-2018
SATR-W-2019

H1

R1

3.14

Post Weld Heat Treatment Inspection

SAIC-W-2004

SAIC-W-2004
SATR-W-2005

H1

W1& R1

Refer to Note 1 of the General Notes for S.Aramco


Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.

3.15

Verification of Hardness Testing


Application and Results

SAIC-W-2014

SAIC-W-2014
SATR-W-2012

H1

W1 & R1

Refer to Note 1 of the General Notes for S.Aramco


Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.

Page 3 of 4

S. Aramco reviews on weekly basis.

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)


APPROVED DATE

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


WELDING OF ON-PLOT PIPING

SATIP-W-011-01

PROJECT TITLE:

ITEM
NO.

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

PROJECT PHASE

TASK / ACTIVITY

CHECKLIST
and/or
TEST RECORD

QUALITY
RECORD

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

3.16

Positive Material Identification (PMI) of


Deposited Weld for alloyed materials
within the scope of SAES-A-206.

SAIC-L-2010

SAIC-L-2010
SATR-A-2012
SATR-A-2013

H1

W\1 & R1

3.17

Weld Modification or Re-Work After Weld


Acceptance

SAIC-W-2036

SAIC-W-2036

H1

H1

SATR-W-2008

H1

R1

4.0

DISCIPLINE:

REMARKS

Refer to Note 1 of the General Notes for S.Aramco


Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.

PRE-COMMISSIONING
Final Welding Inspection &
Documentation (Welding Summary
Report / Record & Weld Map)

4.1

Refer to Note 1 of the General Notes for S.Aramco


Inspection responsibility, afterwhich pre-arranged or
random Review shall be agreed upon.

GENERAL NOTES
1

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
of Saudi Aramco participation based upon the Contractors performance.

Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
is not present.

Hold:

If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

LEGEND
W1

100% Witness Inspection/Test

H2

Sample Hold Point for QC Inspection or Test

RH1

100% Review and Approval of Documents

W2

Sample Witness Inspection/Test

R1

100% Review of Documents

RH2

Sample Review and Approval of Documents

H1

100% Hold Point for QC Inspection or Test

R2

Sample Review of Documents

Page 4 of 4

Surveillance

You might also like