MRP Solution PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 59

Chapter 12 - MRP and ERP

CHAPTER 12
MRP AND ERP
Solutions
1.

a. Each E requires 2 F + 1 G + 1 H.
Each F requires 2 J + 4 D.
Each G requires 2 L + 2 J.
Each H requires 4 A + 2 D.
Total J required = (2 F * 2 J) + (1 G * 2 J) = 4 + 2 = 6.
Total D required = (2 F * 4 D) + (1 H * 2 D) = 8 + 2 = 10.
Total L required = 1 G * 2 L = 2.
Total A required = 1 H * 4 A = 4.
Total required of each:
F = 2, G = 1, H =1.
J = 6, D = 10, L = 2, A = 4.
b. Product structure tree (tree diagram) for stapler:
Stapler

Top Assembly

Cover

Spring

Base Assembly

Slide Assembly

Base

Slide

Strike Pad

Rubber Pad(2)

Spring

12-1
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

2.

Given:
We have the following information:
End Item

B(2)

E(2)

D(3)

F(3)

G(2)

End

LT (wk)

Amount
on hand

10

10

25

12

30

Item

E(2)

H(4)

E(2)

a. If 20 units of the end item are to be assembled, how many additional units of E are
needed?
Step 1:
Determine the gross requirements and the net requirements for the End Item:
Item

Gross Requirements On Hand =

Net Requirements

End Item

20 0 =

20

Step 2:
Determine the gross requirements and the net requirements for B, C, & D.
Multiply the net requirements for the end item by the usage quantities of B, C, & D to
determine the gross requirements for B, C, & D.

Item

Gross Requirements On Hand =

Net Requirements

(20 * 2) = 40 10 =

30

(20 * 1) = 20 10 =

10

(20 * 3) = 60 25 =

35

Step 3:
Determine the gross requirements and net requirements for E.
Multiply the net requirements for B, C, & D by the usage quantities of E to determine gross
requirements for E.
Item

Gross Requirements On Hand =

Net Requirements

[(30 B * 2) + (10 C * 2) + (35 D * 2)] = 150 12 =

138

12-2
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

b. Given:
An order for the end item is to be shipped at the start of week 11. Determine the latest week
that the order could be started.
To solve this, we need to determine the longest sequence through the product structure tree
moving from the end item down to the lowest items. The lead time for each item is indicated
in bold to the left of each item in the product structure tree shown below.
1 wk End Item

2 wk B(2)

1 wk E(2)
1 wk

3 wk C

2 wk F(3) 1 wk G(2)
1 wk

Total LT = 4 wk

3 wk D(3)

1 wk E(2) 2 wk H(4)

1 wk

5 wk

1 wk

5 wk

5 wk

1 wk E(2)
1 wk

6 wk

5 wk

The longest sequence is 6 weeks (End Item D H). 11 6 weeks = start of week 5.
3.

Given:
We have the following information:
Item

End

LT (wk)

Amount
on hand

10

15

20

30

30

Item
End
L
C
K

Direct Components
L(2), C(1), K(3)
B(2), J(3)
G(2), B(2)
H(4), B(2)

Using the information above, we can construct a product structure tree as shown below:
End Item

L(2)

B(2)

J(3)

G(2)

K(3)

B(2)

H(4)

B(2)

12-3
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

a. If 40 units of the end item are to be assembled, how many additional units of B are needed?
Step 1:
Determine the gross requirements and the net requirements for the end item:
Item

Gross Requirements On Hand =

Net Requirements

End Item

40 0 =

40

Step 2:
Determine the gross requirements and the net requirements for L, C, & K.
Multiply the net requirements for the end item by the usage quantities of L, C, & K to
determine the gross requirements for L, C, & K.

Item

Gross Requirements On Hand =

Net Requirements

(40 * 2) = 80 10 =

70

(40 * 1) = 40 15 =

25

(40 * 3) = 120 20 =

100

Step 3:
Determine the gross requirements and net requirements for B.
Multiply the net requirements for L, C, & K by the usage quantities of B to determine gross
requirements for B.
Item

Gross Requirements On Hand =

Net Requirements

[(70 L * 2) + (25 C * 2) + (100 K * 2)] = 390 30 =

360

b. Given:
An order for the end item is to be shipped at the start of week 8. Determine the latest week
that the order could be started.
To solve this, we need to determine the longest sequence through the product structure tree
moving from the end item down to the lowest items. The lead time for each item is indicated
in bold to the left of each item in the product structure tree shown below.
1 wk End Item

2 wk L(2)

2 wk B(2)

Total LT = 5 wk

3 wk C

3 wk J(3)

6 wk

3 wk G(2)

7 wk

3 wk K(3)

2 wk B(2) 2 wk H(4)

6 wk

6 wk

2 wk B(2)

6 wk

The longest sequence is 7 weeks (End Item C G). 8 7 weeks = start of week 1.
12-4
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

4.

Given:
Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case)
of J have been ordered, and one case is scheduled to arrive in week 3, one in week 4, and one in
week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units.
There are 60 units of B and 20 units of J on hand. Lead times are 2 weeks each for E and B, and 1
week for J. The product structure tree is shown below:
E

B(2)

J(4)

J(3)

F(2)

a. Determine a material requirements plan for J. We will need to prepare material plans for E, B,
and J. All given information is highlighted in bold in the tables below.
POH is the projected on hand inventory at the beginning of each period.
All MRP problems below will use the following formula to determine POH:
POH (Current Period) = [POH + Planned-Order Receipts Gross Requirements (Prior
Period)] + Scheduled Receipts (Current Period) or using subscripts, we have the following:
POHt = [POHt-1 + Planned-Order Receiptst-1 Gross Requirementst-1] + Scheduled Receiptst
Net Requirements = Max[(Gross Requirements POH), 0].
Note: This ensures that we have net requirements only when the Gross Requirements > POH.
Master
Schedule for:
E

Week

Quantity

E
LT = 2
Lot size: Lot-for-Lot
Gross requirements

6
80

Beg.
Inv.

6
80

Scheduled receipts
Projected on hand

Net requirements

80

Planned-order receipts

80

Planned-order releases

80

12-5
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

B(2)

LT = 2

Lot size: Multiples of 120

Beg.
Inv.

Gross requirements

20

20

160

Scheduled receipts
Projected on hand

60

60

60

60

60

Net requirements

100

Planned-order receipts

120

Planned-order releases
120
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 80 E * 2 = 160.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [60 + 0 0] + 0 = 60.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [60 + 120 160] + 0 = 20.
J(3) & J(4) LT = 1
Lot size: Multiples of 30
Gross requirements

Beg.
Inv.

2
480

Scheduled receipts
Projected on hand

20

20

20

240
30

30

30

50

80

50

Net requirements

460

160

Planned-order receipts

480

180

50

Planned-order releases
480
180
Notes:
Gross Requirements (week 2) = Planned-Order Releases of 120 B * 4 = 480.
Gross Requirements (week 4) = Planned-Order Releases of 80 E * 3 = 240.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3.
POH3 = [20 + 480 480] + 30 = 50.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4.
POH4 = [50 + 0 0] + 30 = 80.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5.
POH5 = [80 + 180 240] + 30 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6.
POH6 = [50 + 0 0] + 0 = 50.
Planned-Order Receipts (week 2) = 16 * 30 = 480 (must order in cases of 30).
Planned-Order Receipts (week 4) = 6 * 30 = 180 (must order in cases of 30).

12-6
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

b.

Suppose that in week 4 the quantity of E needed is changed from 80 to 70 units. The
planned-order releases through week 3 have all been executed. How many more Bs and
Js will be on hand in week 6? Note: We are now at the start of week 4.
Step 1:
Before we do the MRP processing, we list what changes have occurred:
1. All Planned-Order Releases in weeks 1 3 have been executed.
B had Planned-Order Releases in week 2 (120) corresponding to Planned-Order
Receipts (120) in week 4. Change the Planned-Order Receipts to Scheduled Receipts
in week 4.
J had Planned-Order Releases in week 1 (480) corresponding to Planned-Order
Receipts (480) in week 2. The Planned-Order Receipts would have been changed to
Scheduled Receipts and received in week 2 (this increases inventory).
J had Planned-Order Releases in week 3 (180) corresponding to Planned-Order
Receipts (180) in week 4. These will show up as Scheduled Receipts in week 4 and
will be added to the original amount of Scheduled Receipts (30) in week 4.
2. Scheduled Receipts for J in week 3 (30) would have been received (this increases
inventory).
3. Gross requirements for all items in weeks 1 3 would have been disbursed (these
transactions decrease inventory).
Step 2:
Determine the ending inventory for each item at the end of week 3. These will become
the beginning inventory balances in week 4.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements
Item E
Ending Inventory

Week 1
0+00=0

Week 2
0+00=0

Week 3
0+00=0

Item B
Ending Inventory

Week 1
60 + 0 0 = 60

Week 2
60 + 0 0 = 60

Week 3
60 + 0 0 = 60

Item J
Ending Inventory

Week 1
20 + 0 0 = 20

Week 2
20 + 480 480 = 20

Week 3
20 + 30 0 = 50

12-7
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Step 3:
Fill in all beginning inventory balances and scheduled receipts, and then change E to 70
units in week 6 of the master schedule. Our MRP tables are shown for weeks 4 6 only.
Master
Schedule for:
E

Week

Quantity

E
LT = 2
Lot size: Lot-for-Lot
Gross requirements

6
70

Beg.
Inv.

6
70

Scheduled receipts
Projected on hand

Net requirements

70

Planned-order receipts

70

Planned-order releases
B(2)

LT = 2

Lot size: Multiples of 120

70
Beg.
Inv.

Gross requirements

140

Scheduled receipts

120

Projected on hand

60

180

40

40

Net requirements
Planned-order receipts
Planned-order releases
Notes:
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled
Receipts4.
POH4 = [60 + 0 0] + 120 = 180.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled
Receipts5.
POH5 = [180 + 0 140] + 0 = 40.

12-8
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

J(4) & J(3) LT = 1


Lot size: Multiples of 30
Gross requirements

Beg.
Inv.

210

Scheduled receipts
Projected on hand

50

210

30

260

80

80

Net requirements
Planned-order receipts
Planned-order releases
Notes:
Scheduled Receipts (week 4) = Original amount of 30 + 180 = 210.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled
Receipts4.
POH4 = [50 + 0 0] + 210 = 260.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled
Receipts5.
POH5 = [260 + 0 210] + 30 = 80.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled
Receipts6.
POH6 = [80 + 0 0] + 0 = 80.
Original on hand amounts (week 6):
B = 20 & J = 50.
Revised on hand amounts (week 6):
B = 40 & J = 80.
There will be an additional 20 units of B & 30 units of J on hand.

12-9
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

5.

a. Given:
120 units of end item Z are needed at the beginning of week 7. On hand balances: Z = 40, A
70, B = 100, and C = 30 units. There is a scheduled receipt of 20 units of C in week 4. Lead
times are 2 weeks for Z and B, and 1 week for other items. Lot-for-lot ordering is used for all
items. The product structure tree is shown below:
Z

A(2)

C(3)

B(4)

D(2)

E(2)

C(2)

Prepare a material requirements plan for component C:


We will need to prepare material plans for Z, A, B, and C.
Master
Schedule for:
Z

Week

Quantity

Z
LT = 2
Lot size: Lot-for-Lot
Gross requirements

7
120

Beg.
Inv.

7
120

Scheduled receipts
Projected on hand

40

40

40

40

40

40

40

40

Net requirements

80

Planned-order receipts

80

Planned-order releases
80
Notes:
POH7 = [POH6 + Planned-Order Receipts6 Gross Requirements6] + Scheduled Receipts7
POH7 = [40 + 0 0] + 0 = 40.
A(2)
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

160

Scheduled receipts
Projected on hand

70

70

70

70

70

70

Net requirements

90

Planned-order receipts

90

Planned-order releases
90
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 Z * 2 = 160.

12-10
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

B(4)
LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

320

Scheduled receipts
Projected on hand

100

100

100

100

100

100

Net requirements

220

Planned-order receipts

220

Planned-order releases
220
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 Z * 4 = 320.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [100 + 220 320] + 0 = 0.
C(3) & C(2) LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

440

270

Scheduled receipts
Projected on hand

20
30

20

Net requirements

410

250

Planned-order receipts

410

250

30

30

30

Planned-order releases
410
250
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 220 B * 2 = 440.
Gross Requirements (week 4) = Planned-Order Releases of 90 A * 3 = 270.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [30 + 410 440] + 20 = 20.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [20 + 250 270] + 0 = 0.

12-11
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

b. Given:
95 units of end item E are needed at the beginning of week 7. On hand balances: E = 5, B =
50, C = 100, and D = 80 units. There is a scheduled receipt of 30 units of C in week 4. Lead
times are 2 weeks for E and C, and 1 week for other items. Assume lot-for-lot ordering except
for D, where multiples of 40 must be used. The product structure tree is shown below:
E

B(3)

D(2)

C(2)

I(2)

S(2)

D(2)

Prepare a material requirements plan for component D:


We will need to prepare material plans for E, B, C, and D.

Master
Schedule for:
E

Week

Quantity

E
LT = 2
Lot size: Lot-for-Lot
Gross requirements

7
95

Beg.
Inv.

7
95

Scheduled receipts
Projected on hand

Net requirements

90

Planned-order receipts

90

Planned-order releases
B(3)
LT = 1
Lot size: Lot-for-Lot
Gross requirements

90
Beg.
Inv.

270

Scheduled receipts
Projected on hand

50

50

50

50

50

50

Net requirements

220

Planned-order receipts

220

Planned-order releases
220
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 90 E * 3 = 270.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 220 270] + 0 = 0.

12-12
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

C(2)
LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

180

Scheduled receipts
Projected on hand

30
100

100

100

100

130

130

Net requirements

50

Planned-order receipts

50

Planned-order releases
50
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 90 E * 2 = 180.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 0 0] + 30 = 130.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [130 + 0 0] + 0 = 130.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [130 + 50 180] + 0 = 0
D(2) & D(2) LT = 1
Lot size: Multiples of 40
Gross requirements

Beg.
Inv.

100

440

80

20

Net requirements

20

420

Planned-order receipts

40

440

20

20

20

Scheduled receipts
Projected on hand

80

80

80

Planned-order releases
40
440
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 50 C * 2 = 100.
Gross Requirements (week 4) = Planned-Order Releases of 220 B * 2 = 440.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [80 + 40 100] + 0 = 20.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [20 + 440 440] + 0 = 20.
Planned-Order Receipts (week 3) = 1 * 40 = 40 (multiples of 40 must be used).
Planned-Order Receipts (week 4) = 11 * 40 = 440 (multiples of 40 must be used).

12-13
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

6.

Given:
The company that makes a table wants to ship 100 units at the beginning of day 4, 150 units at the
beginning of day 5, and 200 units at the beginning of day 7. Receipts of 100 wood sections are
scheduled at the beginning of day 2. On hand balances: Braces = 60 and Legs = 120. Lead times
(in days) for all items are shown in the table below. The product structure tree is shown below
also:
Quantity

Lead Time

1-200

201-550

551-999

Table

Wood Sections(2)

Braces(3)

Legs(4)

Prepare a material requirements plan using lot-for-lot ordering for all items:
Master
Schedule for:
Table

Day

Quantity

Table
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

100

150

100

150

100
100

150

200

150

200

200
6

7
200

Scheduled receipts
Projected on hand

Net requirements
Planned-order receipts

Planned-order releases
100
150
200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 100 100] + 0 = 0.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [0 + 150 150] + 0 = 0.
Planned-Order Releases (days 3, 4, & 6) were back-scheduled 1 day from their Planned-Order
Receipts because all lead times = 1 day for quantities of 1-200.

12-14
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Wood Sections(2)
Lot size: Lot-for-Lot

Beg.
Inv.

200

300

100

Net requirements

100

Planned-order receipts

100

300
300

Gross requirements
Scheduled receipts
Projected on hand

400

100
0

100

400
400

Planned-order releases
400
400
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 2 = 200.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 2 = 300.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 2 = 400.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [100 + 0 0] + 0 = 100.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 100 200] + 0 = 0.
Planned-Order Releases (day 2) = 100 from Planned-Order Receipts of 100 in day 3 (lead time = 1
day for quantities of 1-200) + 300 from Planned-Order Receipts of 300 in day 4 (lead time = 2 days
for quantities of 201-550) = 400.
Planned-Order Releases (day 4) = 400 from Planned-Order Receipts of 400 in day 6 (lead time = 2
days for quantities of 201-550).
Braces(3)
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

300

450

60

240
240

450

600

450

600

600

Scheduled receipts
Projected on hand

60

60

60

Net requirements
Planned-order receipts

Planned-order releases
240
450
600
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 3 = 300.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 3 = 450.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 3 = 600.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [60 + 240 300] + 0 = 0.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 450 450] + 0 = 0.
Planned-Order Releases (day 1) = 240 from Planned-Order Receipts of 240 in day 3 (lead time = 2
days for quantities of 201-550).
Planned-Order Releases (day 2) = 450 from Planned-Order Receipts of 450 in day 4 (lead time = 2
days for quantities of 201-550).
Planned-Order Releases (day 3) = 600 from Planned-Order Receipts of 600 in day 6 (lead time = 3
days for quantities of 551-999).

12-15
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Legs(4)
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

400

600

120

280
280

600

800

600

800

800

Scheduled receipts
Projected on hand

120

120

120

Net requirements
Planned-order receipts

Planned-order releases
880
800
Notes:
Gross Requirements (day 3) = Planned-Order Releases of 100 Tables * 4 = 400.
Gross Requirements (day 4) = Planned-Order Releases of 150 Tables * 4 = 600.
Gross Requirements (day 6) = Planned-Order Releases of 200 Tables * 4 = 800.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [120 + 0 0] + 0 = 120.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [120 + 280 400] + 0 = 0.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [0 + 600 600] + 0 = 0.
Planned-Order Releases (day 1) = 280 from Planned-Order Receipts of 280 in day 3 (lead time = 2
days for quantities of 201-550) + 600 from Planned-Order Receipts of 600 in day 4 (lead time = 3
days for quantities of 551-999) = 880.
Planned-Order Releases (day 3) = 800 from Planned-Order Receipts of 800 in day 6 (lead time = 3
days for quantities of 551-999).

12-16
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

7.

Given:
80 units of end item X are needed at the beginning of week 6, and another 30 units are needed at
the beginning of week 8. D can be ordered only in whole cases (50 units per case). One case of D
(50 units) is received automatically every other week, beginning in week 1. On hand balances: B
= 30 and D = 20 units. Lead times are a function of quantity as shown in the table below. The
product structure tree is shown below also:
Quantity

Lead Time

1-100

1 wk

101-200

2 wk

201-300

3 wk

301+

4 wk
X

B(2)

D(2)

D(3)

F(2)

Prepare a material requirements plan for component D using lot-for-lot ordering for all items
except D. We will need to prepare material plans for X, B, and D.

Master
Schedule for: X

Week

Quantity

X
Lot size: Lot-for-Lot
Gross requirements

80
Beg.
Inv.

8
30

80

8
30

Scheduled receipts
Projected on hand

Net requirements

80

30

Planned-order receipts

80

30

Planned-order releases
80
30
Notes:
Planned-Order Releases (week 5 and week 7) have a lead time of 1 week (lead time = 1 week for
quantities of 1-100).

12-17
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

B(2)
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

160

60

Scheduled receipts
Projected on hand

30

30

30

30

30

30

Net requirements

130

60

Planned-order receipts

130

60

Planned-order releases
130
60
Notes:
Gross Requirements (week 5) = Planned-Order Releases of 80 X * 2 = 160.
Gross Requirements (week 7) = Planned-Order Releases of 30 X * 2 = 60.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [30 +130 160] + 0 = 0.
Planned-Order Releases (week 3) = 130 from Planned-Order Receipts of 130 in week 5 (lead time = 2
weeks for quantities of 101-200).
Planned-Order Releases (week 6) = 60 from Planned-Order Receipts of 60 in week 7 (lead time = 1
week for quantities of 1-100).
D(2) & D(3)
Lot size: Multiples of 50
Gross requirements

Beg.
Inv.

Scheduled receipts
Projected on hand

50
20

70

70

Net requirements

260

240

120

90

50

50

120
140
150

Planned-order receipts

10

50

60

20

50

180
200

100
100

40

10

50

Planned-order releases
150
200
100
50
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 130 B * 2 = 260.
Gross Requirements (week 5) = Planned-Order Releases of 80 X * 3 = 240.
Gross Requirements (week 6) = Planned-Order Releases of 60 B * 2 = 120.
Gross Requirements (week 7) = Planned-Order Releases of 30 X * 3 = 90.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [70 + 0 0] + 50 = 120.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [120 + 150 260] + 0 = 10.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [60 + 200 240] + 0 = 20.
POH7 = [POH6 + Planned-Order Receipts6 Gross Requirements6] + Scheduled Receipts7
POH7 = [20 + 100 120] + 50 = 50.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [50 + 50 90] + 0 = 10.

12-18
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

8.

Given:
Oh No! Inc. sells three models: A, B, and C. Lead times are 1 week for all items except C (2
weeks). On hand balances: B = 10, C = 10, and D = 25 units. Lot-sizing rules are lot-for-lot for all
items except D, which must be ordered in multiples of 100. There is a scheduled receipt of 100
units of D in week 1. The master schedule shows that 40 units of A are needed at the beginning of
week 4, 60 units of B at the beginning of week 5, and 30 units of C at the beginning of week 6.
The product structure tree for each item is shown below:
A

D(2)

D(4)

Prepare a material requirements plan for component D and its parents. We will need to prepare
material plans for A, B, C, and D.
Master
Schedule for: A

Week

Quantity

A
LT = 1
Lot size: Lot-for-Lot
Gross requirements

40
Beg.
Inv.

4
40

Scheduled receipts
Projected on hand

Net requirements

40

Planned-order receipts

40

Planned-order releases
Master
Schedule for: B

40

Week

Quantity

B
LT = 1
Lot size: Lot-for-Lot
Gross requirements

60
Beg.
Inv.

60

Scheduled receipts
Projected on hand

10

10

10

10

10

10

Net requirements

50

Planned-order receipts

50

Planned-order releases

50

12-19
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Master
Schedule for: C

Week

Quantity

C
LT = 2
Lot size: Lot-for-Lot
Gross requirements

6
30

Beg.
Inv.

6
30

Scheduled receipts
Projected on hand

10

10

10

10

10

10

10

Net requirements

20

Planned-order receipts

20

Planned-order releases

D, D(2), & D(4) LT = 1


Lot size: Multiples of 100
Gross requirements

20

Beg.
Inv.

Scheduled receipts
Projected on hand

40

180

125

85

100
25

125

125

Net requirements

95

Planned-order receipts

100

Planned-order releases
100
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 40 A * 1 = 40.
Gross Requirements (week 4) = (Planned-Order Releases of 50 B * 2) + (Planned-Order
Releases of 20 C * 4) = 100 + 80 = 180.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [125 + 0 40] + 0 = 85.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [85 + 100 180] + 0 = 5.
Planned-Order Receipts (week 5) = 1 * 100 = 100 (must order in multiples of 100).

12-20
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

9.

Given:
50 chain saws are needed at the start of week 8. The inventory information (shown in bold) and
the product structure tree are listed below in the problem solution:
a. Product tree structure:
Saw
A(2)

E(3)

C(4)

D(2)

F(3)

E(2)

D(2)

Assembly time chart:

E
F
Saw

D
D
C

E
1

week
Start of week 2

Start of week 8

Master schedule:
Master
Schedule for:
Saw

Week

Quantity

8
50

b. Material requirements plan for E using lot-for-lot ordering for all items. We will need to
prepare material plans for Saw, A, C, and E.
Master
Schedule for:
Saw

Week

Quantity

Saw
LT = 2
Lot size: Lot-for-Lot
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases

8
50

Beg.
Inv.

8
50

15

15

15

15

15

15

15

15

15
35
35

35
12-21

Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

A(2)
LT = 1
Lot size: Lot-for-Lot
Gross requirements
Scheduled receipts
Projected on hand
Net requirements

Beg.
Inv.

70
10

10

10

10

10

Planned-order receipts
Planned-order releases

10

10
60
60

60

Notes:
Gross Requirements (week 6) = Planned-Order Releases of 35 Saws * 2 = 70.
C(4)
LT = 2
Beg.
1
2
3
4
5
6
Lot size: Lot-for-Lot
Inv.
Gross requirements
140
Scheduled receipts
Projected on hand
65
65
65
65
65
65
65
Net requirements
75
Planned-order receipts
75
Planned-order releases
75
Notes:
Gross Requirements (week 6) = Planned-Order Releases of 35 Saws * 4 = 140.
E(3) & E(2) LT = 1
Lot size: Lot-for-Lot
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts

Beg.
Inv.

10

10

10

10

150

180

10
140
140

0
180
180

Planned-order releases
140
180
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 75 C * 2 = 150.
Gross Requirements (week 5) = Planned-Order Releases of 60 A * 3 = 180.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 0 0] + 0 = 10.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [10 + 140 150] + 0 = 0.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [0 + 180 180] + 0 = 0.

12-22
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

10.

Given:
40 units of an industrial robot are needed at the beginning of week 7. Subassembly G must be
ordered in multiples of 80 and all other components are ordered lot-for-lot. The inventory
information (shown in bold) and the product structure tree are listed below in the problem
solution. Prepare the material plan for G. We will need to prepare material plans for Robot, C, &
G.
Robot

C(3)

Master
Schedule for:
Robot

Week

G(2)

Quantity

Robot
LT = 2
Lot size: Lot-for-Lot
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts

40
Beg.
Inv.

7
40

10

10

10

10

10

Planned-order releases
C(3)
LT = 1
Lot size: Lot-for-Lot
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases

10

10

10
30
30

30
Beg.
Inv.

5
90

20

20

20

20

20

20
70
70

70

Notes:
Gross Requirements (week 5) = Planned-Order Releases of 30 Robots * 3 = 90.

12-23
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

G & G(2)
LT = 2
Lot size: Multiples of 80
Gross requirements
Scheduled receipts

Beg.
Inv.

Projected on hand
Net requirements

15

15

15

15

Planned-order receipts

140

30

15
125

35

160

Planned-order releases
160
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 70 C * 2 = 140.
Gross Requirements (week 5) = Planned-Order Releases of 30 Robots * 1 = 30.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [15 + 0 0] + 0 = 15.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [15 + 160 140] + 0 = 35.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [35 + 0 30] + 0 = 5.
11.

a. Given:
Refer back to Solved Problem 3. On hand balances: N = 100 and E = 0. Scheduled receipts: I
= 40 and V = 10 at the beginning of week 3. 120 E are needed at the start of week 5. We have
the product structure tree shown below. Determine material requirements plans for E, I, N,
and V using lot-for-lot ordering as was used in Solved Problem 3:
E

M(3)

R(2)

Master
Schedule for:
E

I(2)

N(4)

Period

Quantity

E
LT = 1
Lot size: Lot-for-Lot
Gross requirements

120
Beg.
Inv.

5
120

Scheduled receipts
Projected on hand

Net requirements

120

Planned-order receipts

120

Planned-order releases

120

12-24
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

I(2)
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

240

Scheduled receipts
Projected on hand

40
0

40

40

Net requirements

200

Planned-order receipts

200

Planned-order releases
200
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 120 E * 2 = 240.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 200 240] + 0 = 0.
N(4)
LT = 2
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

800

Scheduled receipts
Projected on hand

100

100

100

100

Net requirements

700

Planned order receipts

700

Planned order releases


700
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 200 I * 4 = 800.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 700 800] + 0 = 0.
V
LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

200

Scheduled receipts
Projected on hand

10
0

10

Net requirements

190

Planned order receipts

190

Planned order releases


190
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 200 I * 1 = 200.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 10 = 10.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 190 200] + 0 = 0.

12-25
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

b. Given:
Assume that on hand balances and scheduled receipts remain the same as in part a. On hand
balances: N = 100 and E = 0. Scheduled receipts: I = 40 and V = 10 at the beginning of week
3.
New information: 100 E are needed at the start of week 5 and 55 are needed at the start of
week 7. Determine the material requirements plans for E, I, N, and V using lot-for-lot
ordering for E and I, and multiples of these order sizes: N = 800 and V = 200.
E

M(3)

R(2)

Master
Schedule for:
E

I(2)

N(4)

Period

Quantity

E
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.

55
6

100

55

Scheduled receipts
Projected on hand

Net requirements

100

55

Planned-order receipts

100

55

Planned-order releases
I(2)
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.

55
5

200

Scheduled receipts
Projected on hand

110

40
0

40

40

Net requirements

160

110

Planned-order receipts

160

110

Planned-order releases
160
110
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 100 E * 2 = 200.
Gross Requirements (week 6) = Planned-Order Releases of 55 E * 2 = 110.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 160 200] + 0 = 0.

12-26
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

N(4)
LT = 2
Lot size: Multiples of 800
Gross requirements

Beg.
Inv.

640

620

620

620

440

Scheduled receipts
Projected on hand

100

100

100

Net requirements

100

260

540
800

Planned order receipts

260
180
800

Planned order releases


800
800
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 4 = 640.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 4 = 440.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [100 + 800 640] + 0 = 260.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [260 + 800 440] + 0 = 620.
V
LT = 2
Lot size: Multiples of 200
Gross requirements

Beg.
Inv.

160

Scheduled receipts
Projected on hand

140

140

140

110

10
0

Net requirements

10
150
200

Planned order receipts

50

50
60
200

Planned order releases


200
200
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 1 = 160.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 1 = 110.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 10 = 10.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [10 + 200 160] + 0 = 50.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 0 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 200 110] + 0 = 140.

12-27
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

c. Case 1 Given:
Refer back to part b. 1 week has elapsed. It is now the start of week 2. 100 E are needed at
the start of week 9. Assume that all orders were released and received as planned.
Notes:
a. We will drop 1 week (week 1) from the material plans and add 1 week at the end of each
plan.
b. Any Planned-Order Releases from week 1 must now show up as Scheduled Receipts:
Item N: Change Planned-Order Receipts of 800 in week 3 to Scheduled Receipts in week 3.
Item V: Change Planned-Order Receipts of 200 in week 3 to Scheduled Receipts in week 3.
The revised amount of Scheduled Receipts (week 3) = original amount of 10 + 200 = 210.
c. Determine the on hand balances at the start of week 2:
Determine the ending inventory for each item at the end of week 1. These will become the
beginning inventory balances in week 2.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements
Item E
Ending Inventory

Week 1
0+00=0

Item I
Ending Inventory

Week 1
0+00=0

Item N
Ending Inventory

Week 1
100 + 0 0 = 100

Item V
Ending Inventory

Week 1
0+00=0

M(3)

R(2)

I(2)

N(4)

12-28
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

c. continued
Master
Schedule for:
E

Period

Quantity

E
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.

55
6

100

9
100

55

9
100

Scheduled receipts
Projected on hand
Net requirements

100

55

0
100

Planned-order receipts

100

55

100

Planned-order releases
I(2)
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.

55
5

200

Scheduled receipts
Projected on hand

100
7

110

200

40
0

40

40

Net requirements

160

110

200

Planned-order receipts

160

110

200

Planned-order releases
160
110
200
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 100 E * 2 = 200.
Gross Requirements (week 6) = Planned-Order Releases of 55 E * 2 = 110.
Gross Requirements (week 8) = Planned-Order Releases of 100 E * 2 = 200.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [40 + 0 0] + 0 = 40.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [40 + 160 200] + 0 = 0.
POH9 = [POH8 + Planned-Order Receipts8 Gross Requirements8] + Scheduled Receipts9
POH9 = [0 + 200 200] + 0 = 0.

12-29
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

N(4)
LT = 2
Lot size: Multiples of 800
Gross requirements

Beg.
Inv.

640

Scheduled receipts
Projected on hand

440

620

620

800

800
100

100

900

260

Net requirements

260

620

180
800

Planned order receipts

620
180
800

Planned order releases


800
800
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 4 = 640.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 4 = 440.
Gross Requirements (week 7) = Planned-Order Releases of 200 I * 4 = 800.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [100 + 0 0] + 800 = 900.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [900 + 0 640] + 0 = 260.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [260 + 800 440] + 0 = 620.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [620 + 800 800] + 0 = 620.
V
LT = 2
Lot size: Multiples of 200
Gross requirements

Beg.
Inv.

160

Scheduled receipts
Projected on hand

110

140

140

200

210
0

210

Net requirements

50

50
60
200

Planned order receipts

140

140
60
200

Planned order releases


200
200
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 160 I * 1 = 160.
Gross Requirements (week 5) = Planned-Order Releases of 110 I * 1 = 110.
Gross Requirements (week 7) = Planned-Order Releases of 200 I * 1 = 200.
POH3 = [POH2 + Planned-Order Receipts2 Gross Requirements2] + Scheduled Receipts3
POH3 = [0 + 0 0] + 210 = 210.
POH4 = [POH3 + Planned-Order Receipts3 Gross Requirements3] + Scheduled Receipts4
POH4 = [210 + 0 160] + 0 = 50.
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 0 = 50.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [50 + 200 110] + 0 = 140.
POH8 = [POH7 + Planned-Order Receipts7 Gross Requirements7] + Scheduled Receipts8
POH8 = [140 + 200 200] + 0 = 140.

12-30
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Case 2 Given:
Refer back to the previous update. It is now the start of week 4. Assume that all orders were
released and received as planned in weeks 2 and 3.
Notes:
a. We will drop 2 weeks (weeks 2 & 3) from the material plans and add 2 weeks at the end of
each plan.
b. Any Planned-Order Releases from weeks 2 & 3 must now show up as Scheduled Receipts:
Item I: Change Planned-Order Receipts of 160 in week 4 to Scheduled Receipts in week 4.
Item N: Change Planned-Order Receipts of 800 in week 5 to Scheduled Receipts in week 5.
Item V: Change Planned-Order Receipts of 200 in week 5 to Scheduled Receipts in week 5.
c. Determine the on hand balances at the start of week 4:
Determine the ending inventory for each item at the end of week 3. These will become the
beginning inventory balances in week 4.
Remember: Scheduled receipts increase inventory while gross requirements decrease
inventory.
Ending Inventory = Beginning Inventory + Scheduled Receipts Gross Requirements
Item E
Ending Inventory

Week 2
0+00=0

Item I
Ending Inventory
Item N
Ending Inventory
Item V
Ending Inventory

Week 3
0+00=0

Week 2
0+00=0

Week 3
0 + 40 0 = 40

Week 2
100 + 0 0 = 100

Week 3
100 + 800 640 = 260

Week 2
0+00=0

Week 3
0 + 210 160 = 50

M(3)

R(2)

I(2)

N(4)

12-31
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Master
Schedule for:
E

Period

Quantity

E
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.

55
6

100

10

11

10

11

10

11

100
8

55

9
100

Scheduled receipts
Projected on hand
Net requirements

100

55

0
100

Planned-order receipts

100

55

100

Planned-order releases
I(2)
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.

55
5

200

Scheduled receipts
Projected on hand

100
7

110

8
200

160
40

200

Net requirements

110

200

Planned-order receipts

110

200

Planned-order releases
110
200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [200 + 0 200] + 0 = 0.

12-32
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

N(4)
LT = 2
Lot size: Multiples of 800

Beg.
Inv.

Gross requirements

440

Scheduled receipts

800

Projected on hand

260

260

1060

10

11

620

620

620

620

800
620

620

Net requirements

180

Planned order receipts

800

Planned order releases


800
Notes:
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [1060 + 0 440] + 0 = 620.
V
LT = 2
Lot size: Multiples of 200
Gross requirements

Beg.
Inv.

110

Scheduled receipts
Projected on hand

10

11

140

140

140

140

200

200
50

50

250

140

140

Net requirements

60

Planned order receipts

200

Planned order releases


200
Notes:
POH5 = [POH4 + Planned-Order Receipts4 Gross Requirements4] + Scheduled Receipts5
POH5 = [50 + 0 0] + 200 = 250.
POH6 = [POH5 + Planned-Order Receipts5 Gross Requirements5] + Scheduled Receipts6
POH6 = [250 + 0 110] + 0 = 140.

12-33
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

12.

Given:
200 carts must be ready at the beginning of week 8. The product structure tree, assembly time
chart, and inventory information are shown in the solutions below:
a. Product structure tree:
Golf
Cart

Top

Supports(4)

Base

Cover

Motor

Body

Frame

Controls

Seats(2)

Wheels(4)

Assembly Time Chart


Supports
Top

b.
Cover

Cart
Motor
Frame
Body

Controls

Base

Wheels
Seats

7
week

Start of week 2

Start of week 8

12-34
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

c. Develop a material requirements plan that will provide 200 golf carts by week 8 assuming
lot-for-lot ordering.
Master
Schedule for:
Golf Cart

Week

Quantity

Golf Cart
LT = 1
Lot size: Lot-for-Lot
Gross requirements

8
200

Beg.
Inv.

8
200

Scheduled receipts
Projected on hand

Net requirements

200

Planned-order receipts

200

Planned-order releases
Top
LT = 1
Lot size: Lot-for-Lot
Gross requirements

200
Beg.
Inv.

200

Scheduled receipts
Projected on hand

40

40

40

40

40

40

40

40

Net requirements

160

Planned-order receipts

160

Planned-order releases
160
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.
Supports(4)
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

640

Scheduled receipts
Projected on hand

200

200

200

200

200

200

200

Net requirements

440

Planned-order receipts

440

Planned-order releases
440
Notes: Gross Requirements (week 6) = Planned-Order Releases of 160 Tops * 4 = 640.

12-35
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

12. c. (continued)
Cover
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

160

Scheduled receipts
Projected on hand

Net requirements

160

Planned-order receipts

160

Planned-order releases
160
Notes: Gross Requirements (week 6) = Planned-Order Releases of 160 Tops * 1 = 160.
Base
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

200

Scheduled receipts
Projected on hand

20

20

20

20

20

20

20

20

Net requirements

180

Planned-order receipts

180

Planned-order releases
180
Notes: Gross Requirements (week 7) = Planned-Order Releases of 200 Golf Carts * 1 = 200.
Motor
LT = 2
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

120

120

180

Scheduled receipts
Projected on hand

300

300

300

300

300

300

300

Net requirements
Planned-order receipts
Planned-order releases
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.

12-36
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

12. c. (Continued)
Body
LT = 3
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

180

Scheduled receipts
Projected on hand

50

50

50

50

50

50

50

Net requirements

130

Planned-order receipts

130

Planned-order releases
130
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 1 = 180.
Seats(2)
LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

6
360

Scheduled receipts
Projected on hand

120

120

120

120

120

120

120

Net requirements

240

Planned-order receipts

240

Planned-order releases
240
Notes: Gross Requirements (week 6) = Planned-Order Releases of 180 Bases * 2 = 360.
Frame
LT = 1
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

130

Scheduled receipts
Projected on hand

35

35

35

35

Net requirements

95

Planned-order receipts

95

Planned-order releases
95
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.

12-37
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

12. c. (Continued)
Controls
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

130

Scheduled receipts
Projected on hand

Net requirements

130

Planned-order receipts

130

Planned-order releases
130
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 1 = 130.
Wheel Assemblies(4) LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

520

Scheduled receipts
Projected on hand

240

240

240

240

Net requirements

280

Planned-order receipts

280

Planned-order releases
280
Notes: Gross Requirements (week 3) = Planned-Order Releases of 130 Body * 4 = 520.

12-38
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

13.

Given:
Refer back to Problem 12. The revised plan calls for 100 golf carts to be available at the start of
week 6, 100 at the start of week 8, and 100 at the start of week 9.
a. Develop a master schedule for this revised plan.

Master
Schedule for:
Golf Carts

Week

Quantity

100

100

100

100

100

b. Determine the timing and quantities for orders for tops and bases.
Golf Cart
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

100

Scheduled receipts
Projected on hand

Net requirements

100

100

100

Planned-order receipts

100

100

100

Planned-order releases
Top
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.
Inv.

40

40

100

100

100

100

100

Scheduled receipts
Projected on hand

40

40

40

40

Net requirements

60

100

100

Planned-order receipts

60

100

100

Planned-order releases
Base
LT = 1
Lot size: Lot-for-Lot

60
Beg.
Inv.

Gross requirements

100

100

100

100

100

Scheduled receipts
Projected on hand

20

20

20

20

20

20

Net requirements

80

100

100

Planned-order receipts

80

100

100

Planned-order releases

80

100

100

12-39
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

c. The firms capacity limits the assembly of bases to 50 units per week. Revise the plan, but
still meet delivery dates. Note: We should try to minimize inventory also.
The key will be to move Planned-Order Receipts and Planned-Order Releases earlier in the
plan.
Consider the plan for Bases in b above:
Planned Order-Receipts (week 8) = 100
Planned Order-Receipts (week 7) = 100
Planned Order-Receipts (week 5) = 80
Given the capacity limit of 50 per week, we could divide the Planned-Order Receipts as
follows:
Week 8 (100): Week 7 (50) & Week 8 (50)
Week 7 (100): Week 5 (50) & Week 6 (50)
Week 5 (80): Week 3 (30) & Week 4 (50)
Note: Because some of these Planned-Order Receipts need to be planned earlier than they
should be, the planner will have to lock in the timing and quantity of these Planned-Order
Receipts by designating them as Firm Planned Orders so that the MRP system does not reschedule them automatically.
Master
Schedule for:
Golf Carts

Week

Quantity

Golf Cart
LT = 1
Lot size: Lot-for-Lot
Gross requirements

100
Beg.
Inv.

100

100

100

100

100

Scheduled receipts
Projected on hand

Net requirements

100

100

100

Planned-order receipts

100

100

100

Planned-order releases
Base
LT = 1
Lot size: Lot-for-Lot

100
Beg.
Inv.

Gross requirements

100

100

100

100

100

Scheduled receipts
Projected on hand

20

20

20

20

50

100

50

100

50

30

50

50

50

50

50

50

50

50

50

50

Net requirements
Planned-order receipts
Planned-order releases

30

12-40
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

14.

Given:
a. Draw a product structure tree (tree diagram) for the scissors. Lead times are 1 day for each
component and final scissor assembly, but 2 days for the plastic grips. 600 scissors are
needed on Day 6. On hand inventory: Straight blades = 200, bent blades = 350, and top blade
assembly = 40.
Scissors

Bottom Blade Assembly

Straight Blade

Screw

Top Blade Assembly

Straight Plastic Grip

Bent Blade

Bent Plastic Grip

b. Material plans:
Master
Schedule for:
Scissors

Week

Beg.
Inv.

Quantity

Scissors
LT = 1
Lot size: Lot-for-Lot
Gross requirements

600
Beg.
Inv.

6
600

Scheduled receipts
Projected on hand

Net requirements

600

Planned-order receipts

600

Planned-order releases

Bottom Blade Assembly


LT = 1
Lot size: Lot-for-Lot
Gross requirements

600

Beg.
Inv.

5
600

Scheduled receipts
Projected on hand

Net requirements

600

Planned-order receipts

600

Planned-order releases

600

Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.


12-41
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Top Blade Assembly


LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

600

Scheduled receipts
Projected on hand

40

40

40

40

40

40

Net requirements

560

Planned-order receipts

560

Planned-order releases

560

Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.


Screw
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

600

Scheduled receipts
Projected on hand

Net requirements

600

Planned-order receipts

600

Planned-order releases
600
Notes: Gross Requirements (week 5) = Planned-Order Releases of 600 Scissors * 1 = 600.
Straight Blade LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

600

Scheduled receipts
Projected on hand

200

200

200

200

200

Net requirements

400

Planned-order receipts

400

Planned-order releases

400

Notes: Gross Requirements (week 4) = Planned-Order Releases of 600 Bottom Blade Assembly * 1 =
600.

12-42
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Straight Plastic Grip


LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

600

Scheduled receipts
Projected on hand

Net requirements

600

Planned-order receipts

600

Planned-order releases

600

Notes: Gross Requirements (week 4) = Planned-Order Releases of 600 Bottom Blade Assembly * 1 =
600.
Bent Blade
LT = 1
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

560

Scheduled receipts
Projected on hand

350

350

350

350

350

Net requirements

210

Planned-order receipts

210

Planned-order releases

210

Notes: Gross Requirements (week 4) = Planned-Order Releases of 560 Top Blade Assembly * 1 = 560.
Bent Plastic Grip LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

560

Scheduled receipts
Projected on hand

Net requirements

560

Planned-order receipts

560

Planned-order releases
560
Notes: Gross Requirements (week 4) = Planned-Order Releases of 560 Top Blade Assembly * 1 = 560.

12-43
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

15.

Given:
A company has the following demand for its products, labor and machine standards, and available
capacities:
Week number
Material (tons)

1
40

2
80

Production standard
(hours per ton)
Weekly production
capacity (hours)

3
60

4
70

Labor
4

Machine
3

300

200

a. Determine capacity utilization for labor and machine for each of the four weeks:
Capacity Requirements (Load) =
Units * Standard Labor and/or Machine Requirements per Unit

Week number
Material (tons)
Labor standard
Labor
requirements
(load)
Machine standard
Machine
requirements
(load)

Week number
Labor
requirements
Labor capacity
Labor
utilization
Machine
requirements
Machine capacity
Machine
utilization

Labor and Machine Capacity Requirements (Load)


1
2
3
40
80
60
4
4
4

4
70
4

40 * 4 = 160

80 * 4 = 320

60 * 4 = 240

70 * 4 = 280

40 * 3 = 120

80 * 3 = 240

60 * 3 = 180

70 * 3 = 210

Capacity Utilization (round % to two decimals)


1
2
3
160
320
240

4
280

300
160/300 * 100 =
53.33%
120

300
320/300 * 100 =
106.67%
240

300
240/300 * 100 =
80.00%
180

300
280/300 * 100 =
93.33%
210

200
120/200 * 100 =
60.00%

200
240/200 * 100 =
120.00%

200
180/200 * 100 =
90.00%

200
210/200 * 100 =
105.00%

b. Capacity utilization exceeds 100% for both labor and machine in week 2, and for machine in
week 4.
Production could be shifted to earlier or later weeks in which capacity is underutilized.
Shifting to an earlier week would result in added carrying costs; shifting to later weeks would
mean backorder costs.
Another option could be to work overtime. Labor cost would increase due to overtime
premium, a probable decrease in productivity, and a possible increase in accidents.
12-44
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

16.

Given:
A company produces 2 products that go through a 3-day sequence of fabrication, assembly, and
packaging. Each step requires 1 day for a lot to be processed and moved to the next department.
Processing requirements for the departments (hours per unit) are:

Product
A
B

FABRICATION
Labor
Machine
2
1
1
1

ASSEMBLY
Labor
Machine
1.5
1
1
1

PACKAGING
Labor
Machine
1
.5
1.5
.5

Department capacities are all 700 hours of labor and 500 hours of machine time, except Friday,
when capacities are 200 hours for both labor and machine time. The following production
schedule is for next week:
Product
A
B

Mon
200
300

Tue
400
200

Wed
100
200

Thu
300
200

Fri
100
200

a. Determine the labor and machine capacity requirements for each product and the total load at
each department for each day.
For example, the 200 units of Product A & 300 units of Product B will be processed at
Fabrication on Monday, Assembly on Tuesday, and Packaging on Wednesday.
Monday Fabrication Labor Load = (200 A * 2 = 400) + (300 B * 1 = 300) = 700.
Monday Fabrication Machine Load = (200 A * 1 = 200) + (300 B * 1 = 300) = 500.
Tuesday Assembly Labor Load = (200 A * 1.5 = 300) + (300 B * 1 = 300) = 600.
Tuesday Assembly Machine Load = (200 A * 1 = 200) + (300 B * 1 = 300) = 500.
Wednesday Packaging Labor Load = (200 A * 1 = 200) + (300 B * 1.5 = 450) = 650.
Wednesday Packaging Machine Load = (200 A * .5 = 100) + (300 B * .5 = 150) = 250.

12-45
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Day Product

Fabrication
Labor
Machine

Assembly
Labor
Machine

Packaging
Labor
Machine

Mon

A
B
Load
Capacity

400
300
700
700

200
300
500
500

Tue

A
B
Load
Capacity

800
200
1000
700

400
200
600
500

300
300
600
700

200
300
500
500

Wed

A
B
Load
Capacity

200
200
400
700

100
200
300
500

600
200
800
700

400
200
600
500

200
450
650
700

100
150
250
500

Thu

A
B
Load
Capacity

600
200
800
700

300
200
500
500

150
200
350
700

100
200
300
500

400
300
700
700

200
100
300
500

Fri

A
B
Load
Capacity

200
200
400
200

100
200
300
200

450
200
650
200

300
200
500
200

100
300
400
200

50
100
150
200

b. Evaluate the loading for the first 3 days of the week:


Monday:
Fabrication: Load = capacity for both labor and machine.
Tuesday:
Fabrication: Labor load is over capacity by 300 hours. Machine load is over capacity by 100
hours.
Assembly: Labor load is under capacity by 100 hours. Machine load = capacity.
Wednesday:
Fabrication: Labor load is under capacity by 300 hours. Machine load is under capacity by
200 hours.
Assembly: Labor load is over capacity by 100 hours. Machine load is over capacity by 100
hours.
Packaging: Labor load is under capacity by 50 hours. Machine load is under capacity by 250
hours.
The schedule does not appear to be feasible. Fabrication is overloaded for labor and machine
on Tuesday and underloaded for labor and machine on Wednesday. In addition, Assembly is
overloaded for labor and machine on Wednesday.
One solution could be to shift some of the 400 A & 200 B scheduled in Fabrication on
Tuesday to Wednesday. For example, we could shift 150 A in Fabrication from Tuesday to
12-46
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Wednesday. We now would schedule 250 A on Tuesday (400-150) and 250 A on Wednesday
(100+150). The new load values are highlighted in bold in the table below:

Day Product

Fabrication
Labor
Machine

Assembly
Labor
Machine

Packaging
Labor
Machine

Mon

A
B
Load
Capacity

400
300
700
700

200
300
500
500

Tue

A
B
Load
Capacity

500
200
700
700

250
200
450
500

300
300
600
700

200
300
500
500

Wed

A
B
Load
Capacity

500
200
700
700

250
200
450
500

375
200
575
700

250
200
450
500

200
450
650
700

100
150
250
500

Thu

A
B
Load
Capacity

600
200
800
700

300
200
500
500

375
200
575
700

250
200
450
500

250
300
550
700

125
100
225
500

Fri

A
B
Load
Capacity

200
200
400
200

100
200
300
200

450
200
650
200

300
200
500
200

250
300
550
200

125
100
225
200

12-47
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

17.

Given:
The MRP departments computer died just as it spit out the following information: Planned-Order
Releases for Item J27 = 640 units in week 2. We have the following product structure tree and
inventory information shown below:
565

X43

Y36(2)

J27(4)

N78

X43

Part Number
565
X43

On Hand
0
60

N78
Y36
J27

0
200
0

Lot Size
Lot-for-lot
Multiples
of 120
Lot-for-lot
Lot-for-lot
Lot-for-lot

Lead Time
1 week
1 week
2 weeks
1 week
2 weeks

Step 1:
Look at which items are linked together by the Planned-Order Releases for J27: J27, Y36, and
565.
Step 2:
Work from the bottom to the top of the product structure tree. Start with J27 to determine its
Planned-Order Receipts, Net Requirements, and Gross Requirements.
a. We know that J27 has a Planned-Order Release = 640 in week 2.
The lead time for J27 = 2 weeks. This means that the Planned-Order Receipts = 640 in week
4 (2 weeks later).
The lot size for J27 = lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 4 = 640.
The on hand balance for J27 = 0. This means that the Gross Requirements in week 4 = Net
Requirements + On Hand = 640 + 0 = 640.
b. If the Gross Requirements for J27 = 640 in week 4, then the Planned-Order Releases for Y36
= 160 (640 / 4) in week 4.
The lead time for Y36 = 1 week. This means that the Planned-Order Receipts = 160 in week
5 (1 week later).
The lot size for Y36 is lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 5 = 160.
The on hand balance for Y36 = 200. This means that the Gross Requirements in week 5 = Net
Requirements + On Hand = 160 + 200 = 360.

12-48
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

c. If the Gross Requirements for Y36 = 360 in week 5, the Planned-Order Releases for 565 =
180 (360 / 2) in week 5.
The lead time for 565 = 1 week. This means that the Planned-Order Receipts = 180 in week 6
(1 week later).
The lot size for 565 is lot-for-lot. This means that the Net Requirements = Planned-Order
Receipts in week 6 = 180.
The on hand balance for 565 = 0. This means that the Gross Requirements in week 6 = Net
Requirements + On Hand = 180 + 0 = 180.
Conclusion: There should be a quantity of 180 listed in week 6 of the master schedule for
Item 565.
Below are the MRP tables verifying the proof discussed above:
Master
Schedule for:
565

Week

Quantity

565
LT = 1
Lot size: Lot-for-Lot

6
180

Beg.
Inv.

Gross requirements

6
180

Scheduled receipts
Projected on hand

Net requirements

180

Planned-order receipts

180

Planned-order releases
Y36(2)
LT = 1
Lot size: Lot-for-Lot

180
Beg.
Inv.

Gross requirements

5
360

Scheduled receipts
Projected on hand

200

200

200

200

200

200

Net requirements

160

Planned-order receipts

160

Planned-order releases
J27(4)
LT = 2
Lot size: Lot-for-Lot
Gross requirements

160
Beg.
Inv.

4
640

Scheduled receipts
Projected on hand

Net requirements

640

Planned-order receipts

640

Planned-order releases

640

12-49
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

18.

Given:
Develop a material requirements plan for component H. Use lot-for-lot ordering for all items.
Lead times for the end item and each component (except B) = 1 week. The lead time for B = 3
weeks. On hand balances: B = 15 & E = 130. Scheduled Receipts for H = 50 in week 2. 60 units
of A are needed at the start of week 8. We have the following product structure tree:
A

B(2)

D(2)

E(2)

D(2)

H(3)

E(4)

H(3)

We will need material plans for A, B, C, E, & H.


Master

Week

Schedule
for: A

Quantity

LT = 1

Lot size: Lot-for-Lot

8
60

Beg.
Inv.

Gross requirements

8
60

Scheduled receipts
Projected on hand

Net requirements

60

Planned-order receipts

60

Planned-order releases

60

12-50
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

B(2)

LT = 3

Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

120

Scheduled receipts
Projected on hand

15

15

15

15

15

15

15

15

Net requirements

105

Planned-order receipts

105

Planned-order releases
C

LT = 1

Lot size: Lot-for-Lot

105

Beg.
Inv.

Gross requirements

60

Scheduled receipts
Projected on hand

Net requirements

60

Planned-order receipts

60

Planned-order releases
E(2) & E(4)

LT = 1

Lot size: Lot-for-Lot

60

Beg.
Inv.

Gross requirements

210

240

Scheduled receipts
Projected on hand

130

130

130

130

130

Net requirements

80

240

Planned-order receipts

80

240

Planned-order releases
80
240
Notes:
Gross Requirements (week 4) = Planned-Order Releases of 105 B * 2 = 210.
Gross Requirements (week 6) = Planned-Order Releases of 60 C * 4 = 240.

12-51
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

H(3)

LT = 1

Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

240

Scheduled receipts
Projected on hand

720

50
0

50

50

Net requirements

190

720

Planned-order receipts

190

720

Planned-order releases
190
720
Notes:
Gross Requirements (week 3) = Planned-Order Releases of 80 E * 3 = 240.
Gross Requirements (week 5) = Planned-Order Releases of 240 E * 3 = 720.

Case: Promotional Novelties


Given:
Promotional Novelties has received an order for 20,000 toy Tractor-Trailers to be ready at the beginning
of week 8. The company can complete final assembly of the Tractor-Trailers at a rate of 10,000 a week.
Tractors and Trailers are purchased and have a lead time = 3 weeks. The company has sufficient supply of
Brackets on hand. Assembly time = 1 week for Tractors, Trailers, and Wheel Assembly. However, the
Wheel Department can assemble a maximum of 100,000 Wheels a week. The manager plans to use the
Wheel Department to full capacity, starting in week 2 of the schedule, and order additional Wheels from a
supplier as needed. Wheels are ordered in sets (multiples) of 6,400, and the lead time from the supplier =
2 to 3 weeks. All items use lot-for-lot ordering except for the purchased Wheels (lot size = multiples of
6,400).
Comments on the product structure tree shown in the text:
The Wheel Assembly of the Tractor differs from the Wheel Assembly of the Trailer.
The Body of the Tractor differs from the Body of the Trailer.
The Tractor and the Trailer use the same Wheel.
We will develop material plans for Tractor-Trailer, Tractor, Trailer, Tractor Wheel Assembly, Trailer
Wheel Assembly, & Wheels.
If the order of 20,000 tractor-trailers is due at the start of week 8 and final assembly is limited to 10,000
per week, then we must list 10,000 in week 7 and 10,000 in week 8 of the master schedule.

12-52
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Master

Week

Schedule

Quantity

10,000

10,000

10,000

10,000

Net requirements

10,000

10,000

Planned-order receipts

10,000

10,000

Tractor-Trailer
LT = 1
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements
Scheduled receipts
Projected on hand

Planned-order releases

10,000

10,000

10,000

10,000

Net requirements

10,000

10,000

Planned-order receipts

10,000

10,000

Tractor

LT = 1

Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

Scheduled receipts
Projected on hand

Planned-order releases

10,000

10,000

10,000

10,000

Net requirements

10,000

10,000

Planned-order receipts

10,000

10,000

Trailer

LT = 1

Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

Scheduled receipts
Projected on hand

Planned-order releases

10,000

10,000

12-53
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Tractor Wheel
Assembly
LT = 1

Beg.
Inv.

10,000

10,000

Net requirements

10,000

10,000

Planned-order receipts

10,000

10,000

Lot size: Lot-for-Lot

Gross requirements

Scheduled receipts
Projected on hand

Planned-order releases

10,000

10,000

10,000

10,000

Net requirements

10,000

10,000

Planned-order receipts

10,000

10,000

Trailer Wheel
Assembly
LT = 1
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements
Scheduled receipts
Projected on hand

Planned-order releases

10,000

10,000

12-54
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Wheels (6) & (12)


LT = 1
Lot size: Lot-for-Lot

Beg.
Inv.

Gross requirements

180,000

180,000

100,000

20,000

80,000

160,000

4,000

4,000

4,000

Scheduled receipts
Projected on hand

Net requirements
Planned-order receipts
Planned-order releases

100,000
64,000*

100,000

100,000

100,000

100,000

100,000
64,000*

Notes:
Gross Requirements (week 4) = Planned-Order Releases of (10,000 Tractor Wheel Assembly * 6) +
(10,000 Trailer Wheel Assembly * 12) = 60,000 + 120,000 = 180,000.
Gross Requirements (week 5) = Planned-Order Releases of (10,000 Tractor Wheel Assembly * 6) +
(10,000 Trailer Wheel Assembly * 12) = 60,000 + 120,000 = 180,000.
The Planned-Order Receipts in weeks 3, 4, & 5 would be entered as Firm Planned Orders locked in by the
MRP planner so that the MRP system does not re-schedule these amounts automatically.
Planned-Order Releases (week 2) = [Planned-Order Receipts (week 3) of 100,000] + [Planned-Order
Receipts (week 5) of 64,000] = 100,000 + 64,000 = 164,000.
1.

The company will need a total of 360,000 Wheels. It will be able to produce only 300,000 during
weeks 2, 3, & 4. The company will need to order at least 60,000 Wheels as indicated with the * in
week 2. The company actually would have to purchase 10 sets of 6,400 Wheels per set = 64,000.

2.

The company will need the Wheels in week 5. If lead time will be 2-3 weeks, then assume that it
will be 3 weeks, and order the Wheels from the supplier in week 2.

12-55
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Case: DMD Enterprises


Given:
Marty wants to assemble 15 Arrows and 10 Darts each week to have them ready at the start of weeks 4
through 8. The product structure trees are given in the text along with inventory information on lead
times, on hand amounts, and lot sizing rules. Scheduled Receipts: Arrows = 20 in week 1 & W = 18 in
week 1. Darts = 20 in week 2 & F = 15 in week 2. Develop the material plans for all items.
Master
Schedule for:
Arrows

Week

Master
Schedule for:
Darts

Week

15

15

15

15

15

10

10

10

10

10

15

15

15

15

15

25

10

Net requirements

15

15

15

Planned-order receipts

15

15

15

Quantity
1

Quantity

Arrows
LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

Scheduled receipts
Projected on hand

20
5

25

25

25

15

15

15

10

10

10

10

10

22

12

Net requirements

10

10

Planned-order receipts

10

10

Planned-order releases
Darts
LT = 2
Lot size: Lot-for-Lot
Gross requirements

Beg.
Inv.

Scheduled receipts
Projected on hand

20
2

22

22

10

10

15

15

15

10

20

Net requirements

15

Planned-order receipts

25

25

Planned-order releases
X
LT = 1
Lot size: Multiples of 25
Gross requirements

Beg.
Inv.

Scheduled receipts
Projected on hand

25

Planned-order releases

25

12-56
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Case: DMD Enterprises (continued)


M
LT = 1
Lot size: Lot-for-lot
Gross requirements

Beg.
Inv.

15

15

15

Net requirements

15

15

15

Planned-order receipts

15

15

15

15

15

15

16

20

20

Net requirements

13

20

20

Planned-order receipts

13

20

20

Scheduled receipts
Projected on hand

Planned-order releases
K(2)
LT = 1
Lot size: Lot-for-lot

Beg.
Inv.

Gross requirements
Scheduled receipts
Projected on hand

Planned-order releases

13
20
20
Gross Requirements (week 4) = Planned-Order Releases of 8 Darts * 2 = 16.
Gross Requirements (week 5) = Planned-Order Releases of 10 Darts * 2 = 20.
Gross Requirements (week 6) = Planned-Order Releases of 10 Darts * 2 = 20.
F&F
LT = 1
Lot size: Multiples of 30
Gross requirements

Beg.
Inv.

25

33

10

10

25

27

17

Net requirements

33

Planned-order receipts

60

Scheduled receipts
Projected on hand

15
10

10

25

Planned-order releases

60

Notes:
Gross Requirements (week 3) = Planned-Order Releases of 25 X * 1 = 25.
Gross Requirements (week 4) = Planned-Order Releases of (8 Darts * 1) + (25 X * 1) = 8 + 25 = 33.
Gross Requirements (week 5) = Planned-Order Releases of 10 Darts * 1 = 10.
Gross Requirements (week 6) = Planned-Order Releases of 10 Darts * 1 = 10.

12-57
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

W & W(2) LT* = 2 or 3


Lot size: Multiples of 12
Gross requirements
Scheduled receipts
Projected on hand

Beg.
Inv.

31

55

55

15

18
20

11

Net requirements

11

49

Planned-order receipts

12

54
60

60

12

Planned-order releases

20

72

20

60

12

Notes:
Gross Requirements (week 3) = Planned-Order Releases of (5 Arrows *1) + (13 K * 2) = 5 + 26 =
31.
Gross Requirements (week 4) = Planned-Order Releases of (15 Arrows * 1) + (20 K * 2) = 15 + 40
= 55.
Gross Requirements (week 5) = Planned-Order Releases of (15 Arrows * 1) + (20 K * 2) = 15 + 40
= 55.
Gross Requirements (week 6) = Planned-Order Releases of 15 Arrows * 1 = 15.
*Lead time = 2 weeks for orders < 36 & 3 weeks for orders 36.
Planned-Order Releases (week 1) = [Planned-Order Receipts (week 3) = 12] + [Planned-Order
Receipts (week 4) = 60] = 72.
Q
LT = 1
Lot size: Multiples of 30
Gross requirements

Beg.
Inv.

13

20

20

15

12

Net requirements

18

Planned-order receipts

30

30

Scheduled receipts
Projected on hand

15

15

15

22

22

22

Planned-order releases

30
30
Gross Requirements (week 3) = Planned-Order Releases of 13 K * 1 = 13.
Gross Requirements (week 4) = Planned-Order Releases of 20 K * 1 = 20.
Gross Requirements (week 5) = Planned-Order Releases of 20 K * 1 = 20.

12-58
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

Chapter 12 - MRP and ERP

Operations Tour: Stickley Furniture


1.

Batch processing is used with typical lot sizes of 25 to 60 pieces of different types of furniture,
such as tables, chairs, desks, dressers, etc. Repetitive processing is used at sawing, drilling,
finishing, etc. Job shop processing is used for expensive one-of-a-kind special orders that may be
received.

2.

Each job is accompanied by a set of bar codes that identifies the job and the operation. As each
operation is completed, the operator removes a bar code sticker and delivers it to the scheduling
office, where it is scanned into a computer, thereby enabling production control to keep track of
progress on a job, and to know its location in the shop.

3.

The information needed to plan, schedule, and process the order for 40 mission oak dining room
sets includes:
a. Number of finished units presently in inventory
b. Type of wood
c. Type of furniture
d. Style of furniture
e. Number of finished products needed
f.

List of component parts for each finished product

g. Operations required for each component part


h. Inventory for each component part
i.

Sequence of operations for each component

j.

Sequence of operations for each finished product

k. Orders already in progress or scheduled to precede this order


l.

Unutilized equipment and labor

m. Processing times for each component and total processing time for the finished product
4.

One benefit would be the stability and improved morale brought about by maintaining a constant
size workforce. A problem could be the buildup of inventories during certain quarters of the year.

5.

Because there is a dependent demand situation for all of the components that go into the finished
products, the installation of an MRP system might be of great help to this company in meeting its
delivery dates and in keeping inventory costs down.

12-59
Copyright 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.

You might also like