Professional Documents
Culture Documents
Dalit Pilar NI MARINEL
Dalit Pilar NI MARINEL
ITEM
NO.
DESCRIPTION
(1)
UNIT
MARK-UPS
IN PERCENT
OCM[1]
PROFIT
TOTAL MARK-UP
MOB.\ DEMOB.[2] %
VAT[3]
VALUE
(3)
(4)
(5)
(6)
(7)
(8)
(9)
1.00
Lot
10,204.12
9.00%
8.00%
0.00%
17.00%
803
46.08
cu.m.
16,467.15
9.00%
8.00%
0.00%
17.00%
104
EMBANKMENT
205.16
cu.m.
99,657.25
9.00%
8.00%
0.00%
17.00%
900
REINFORCED CONCRETE
65.40
cu.m.
374,575.41
9.00%
8.00%
0.00%
17.00%
63,677.82
21,912.66
404
8357.91
Kg.
388,062.56
9.00%
8.00%
0.00%
17.00%
65,970.64
22,701.66
414
265.00
Cu.m.
150,897.48
9.00%
8.00%
0.00%
17.00%
25,652.57 P
8,827.50
704
MASONRY WORKS
196.34
Sq.m.
156,897.15
9.00%
8.00%
0.00%
17.00%
26,672.52 P
9,178.48
1002
PLUMBING WORKS
14.00
Lin.m.
57,980.00
9.00%
8.00%
0.00%
17.00%
3,391.83
1102
ELECTRICAL WORKS
58.00
Outlet
113,319.36
9.00%
8.00%
0.00%
17.00%
19,264.29 P
6,629.18
1027
PLASTERING WORKS
719.76
Sq.m.
261,685.60
9.00%
8.00%
0.00%
17.00%
44,486.55
15,308.61
1010
WOODEN DOORS
9.00
Set
58,748.06
9.00%
8.00%
0.00%
17.00%
9,987.17
3,436.76
1009
JALOUSIE WINDOW
12.00
Set
66,399.96
9.00%
8.00%
0.00%
17.00%
11,287.99 P
403
317.98
Sq.m.
335,032.42
9.00%
8.00%
0.00%
17.00%
56,955.51
1014
ROOFING WORKS
317.98
Sq.m.
186,593.24
9.00%
8.00%
0.00%
17.00%
1003
CARPENTRY WORKS
21.28
Sq.m.
32,809.12
9.00%
8.00%
0.00%
17.00%
Spl.1
276.63
Sq.m.
123,585.96
9.00%
8.00%
0.00%
17.00%
1032
PAINTING WORKS
354.78
Sq.m.
75,719.60
9.00%
8.00%
0.00%
17.00%
101
(2)
QUANTITY
ESTIMATED
DIRECT COST
(10)
(11)
1,734.70
2,799.42
963.33
16,941.73 P
5,829.95
9,856.60
596.94
3,884.40
19,599.40
31,720.85
10,915.70
5,577.55
1,919.33
21,009.61 P
7,229.78
12,872.33 P
4,429.60
THREE MILLION EIGHTY-ONE THOUSAND EIGHT HUNDRED FIFTY-NINE PESOS & 08/100
PREPARED/SUBMITTED BY:
FERDINAND A. TADEO
Engineer III
APPROVED:
LORETO B. DACOROON
JONATHAN T. BOBITA
Engineer II
Contract Duration:
TOTAL
INDIRECT
COST
TOTAL COST
(12)
2,331.64
120 cd
UNIT COST
(13)
(14)
12,535.76
12,535.76
12,535.76
12,535.76
3,762.75
20,230.04
439.02
22,771.68
122,429.23
596.75
85,590.48
460,166.17
7,036.18
88,672.30
476,735.19
57.04
34,480.07
185,378.10
699.54
35,851.00
192,748.94
981.71
13,248.43
71,228.50
5,087.75
25,893.47
139,212.76
2,400.22
59,795.16
321,480.80
446.65
446.65
321,480.76
13,423.93
72,171.99
8,019.11
8,019.11
72,171.99
15,172.39
81,572.40
6,797.70
6,797.70
81,572.35
76,554.91 P
411,586.95 P
1,294.38
42,636.55
229,228.60
720.89
7,496.88
40,306.02
1,894.08
28,239.39
151,825.61
548.84
17,301.93
93,022.01
262.20
3,081,859.08
100
LORETO B. DACOROON
CARETAKER
3,081,859.08
0.00
PROJECT TITLE:
LOCATION:
Lot
CD.
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
4
4
4
Rate/Day
250.00
Duration
4
P
P
P
P
Total cost
2,302.44
3,332.00
2,569.68
8,204.12
P
P
P
P
P
P
P
P
P
P
Total cost
2,000.00
2,000.00
10,204.12
1,734.70
11,938.82
596.94
12,535.76
12,535.76
12,535.76
12,535.76
P
P
P
P
P
P
P
P
P
P
P
P
Total cost
1,726.83
1,249.50
13,490.82
16,467.15
16,467.15
2,799.42
19,266.57
963.33
20,229.90
20,229.90
439.02
20,230.04
EQUIPMENT
Equipment
Needed
2
Minor tools
Sub-total
Mark-up
17%
VAT
5%
46.08
3
cu.m.
CD.
LABOR
Manpower
Construction Foreman
Skilled laborer
Laborer
Needed
1
1
14
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
3
3
3
Sub-total
Mark-up
17%
VAT
5%
MATERIALS
Description of Material/s
EarthFill ( Excavated Material )
Gravel bedding
205.16
cu.m.
3.66
7.33
10.99
11.00
CD.
Quantity
174.36
30.80
Unit
cu.m.
cu.m.
Unit Cost
P
1,424.00
Total Cost
P
P
P
43,859.20
43,859.20
P
P
P
Total cost
6,331.71
49,466.34
55,798.05
99,657.25
LABOR
Manpower
Construction Foreman
Laborer
Needed
1
14
P
P
Rate/Day
575.61
321.21
Sub-total
Duration
11.00
11.00
Mark-up
17%
VAT
5%
P
P
P
P
P
P
P
16,941.73
116,598.98
5,829.95
122,428.93
122,428.93
596.75
122,429.23
P
P
P
P
Total Cost
157,669.05
46,992.00
86,528.00
291,189.05
P
P
P
P
Total cost
9,785.37
14,161.00
38,223.99
62,170.36
P
P
P
P
P
P
P
P
P
P
Total cost
21,216.00
21,216.00
374,575.41
63,677.82
438,253.23
21,912.66
460,165.89
460,165.89
7,036.18
460,166.17
36.01
29.39
65.40
cu.m.
7.00
10.00
17.00
CD.
Quantity
595
33
52
Unit
Bags
Cu.m.
Cu.m.
P
P
P
Unit Cost
264.99
1,424.00
1,664.00
LABOR
Manpower
Construction Foreman
Mason
Laborer
Needed
1
2
7
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
17.00
17.00
17.00
Needed
1
Rate/Day
1,248.00
Duration
17
EQUIPMENT
Equipment
1-Bagger conc. Mixer
Sub-total
Mark-up
17%
VAT
5%
8357.91
12
Quantity
535.17
1618.81
2171.64
2287.35
1200.1
544.84
8357.91
8
125
1
Kg.
CD.
Unit
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Pcs.
Kgs.
lot
Unit Cost
P
P
P
P
35.62
450.00
90.00
3,748.25
Total Cost
P
P
P
P
P
297,708.75
3,600.00
11,250.00
3,748.25
316,307.00
LABOR
Manpower
Construction Foreman
Steelman
Laborer
Needed
1
3
12
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
12
12
12
300.00
12
Sub-total
Mark-up
17%
VAT
5%
P
P
P
P
Total cost
6,907.32
14,994.00
46,254.24
68,155.56
P
P
P
P
P
P
P
P
P
P
3,600.00
3,600.00
388,062.56
65,970.64
454,033.20
22,701.66
476,734.86
476,734.86
57.04
476,735.19
P
P
P
P
Total Cost
17,980.00
63,882.00
11,300.00
93,162.00
P
P
P
P
P
P
P
P
P
P
P
P
Total cost
6,907.32
19,992.00
30,836.16
57,735.48
150,897.48
25,652.57
176,550.05
8,827.50
185,377.55
185,377.55
699.54
185,378.10
EQUIPMENT
Equipment
Cut-off machine
265
29.39
Sq.m.
Cu.m.
7.57
4.42
11.99
12
CD.
Quantity
29
2366
113
Unit
Pcs.
Bd.ft.
Kgs.
P
P
P
Unit Cost
620.00
27.00
100.00
LABOR
Manpower
Construction Foreman
Carpenter
Laborer
Needed
1
4
8
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
12
12
12
Sub-total
Mark-up
17%
VAT
5%
196.34
7
Quantity
196.34
2454
Sq.m.
CD
Unit
Sq.m.
Pcs.
Unit Cost
P
14.00
Total Cost
P
34,356.00
241
13
Bags
Cu.m.
P
P
264.99
1,424.00
Manpower
Construction Foreman
Mason
Laborer
Needed
1
4
7
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
7
7
7
Equipment
1-Bagger conc. Mixer
Needed
1
Rate/Day
1,248.00
Duration
7
Sub-total
Mark-up
17%
VAT
5%
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
63,862.59
18,512.00
116,730.59
Total cost
4,029.27
11,662.00
15,739.29
31,430.56
Total cost
8,736.00
8,736.00
156,897.15
26,672.52
183,569.67
9,178.48
192,748.15
192,748.15
981.71
192,748.94
14.00
4.00
Quantity
Lin.m.
CD.
Unit
Unit Cost
Total Cost
3
3
1
2
2
3
Set
Set
Pcs.
Pcs.
Pcs.
Pcs.
P
P
P
P
P
P
8,000.00
3,000.00
250.00
350.00
385.00
120.00
P
P
P
P
P
P
24,000.00
9,000.00
250.00
700.00
770.00
360.00
12
6
14
6
6
1
3
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
P
P
P
P
P
P
P
330.00
30.00
40.00
35.00
165.00
80.00
30.00
P
P
P
P
P
P
P
3,960.00
180.00
560.00
210.00
990.00
80.00
90.00
7
9
4
Pcs.
Pcs.
Pcs.
P
P
P
580.00
280.00
100.00
P
P
P
4,060.00
2,520.00
400.00
4
3
3
6
4
6
4
4
6
4
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Cans
P
P
P
P
P
P
P
P
P
P
100.00
150.00
150.00
150.00
95.00
45.00
45.00
60.00
120.00
165.00
Manpower
Construction Foreman
Plumber
Helper
Needed
1
1
1
P
P
P
Rate/Day
450.00
300.00
250.00
Duration
4.00
4.00
4.00
Equipment
Pipe threader / cutter
Needed
1
Rate/Day
300.00
Duration
4
Sub-total
Mark-up
17%
VAT
5%
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
400.00
450.00
450.00
900.00
380.00
270.00
180.00
240.00
720.00
660.00
52,780.00
Total cost
1,800.00
1,200.00
1,000.00
4,000.00
Total cost
1,200.00
1,200.00
57,980.00
9,856.60
67,836.60
3,391.83
71,228.43
71,228.43
5,087.75
71,228.50
P
P
P
P
P
Total Cost
15,000.00
21,600.00
2,000.00
500.00
900.00
P
P
P
P
58.00
12.00
Quantity
6
18
8
5
6
Outlet
CD.
Unit
Set
Pcs.
Pcs.
Set
Set
P
P
P
P
P
Unit Cost
2,500.00
1,200.00
250.00
100.00
150.00
12
6
1
1
3
2
32
34
10
5
1
2
1
91
45
1
3
3
4
1
Set
Set
Set
Set
Set
Set
Set
Set
Pcs.
Mtrs.
Rolls
Rolls
Rolls
Pcs
Pcs
Pcs.
Pcs.
Pcs.
Pcs.
Lot
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
150.00
100.00
4,000.00
3,250.00
350.00
350.00
45.00
35.00
40.00
140.00
5,000.00
3,500.00
2,500.00
90.00
30.00
100.00
95.00
50.00
500.00
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
1,800.00
600.00
4,000.00
3,250.00
1,050.00
700.00
1,440.00
1,190.00
400.00
700.00
5,000.00
7,000.00
2,500.00
8,190.00
1,350.00
100.00
285.00
150.00
2,000.00
12,000.00
93,705.00
P
P
P
P
P
P
P
P
P
P
P
P
Total cost
6,907.32
4,998.00
7,709.04
19,614.36
113,319.36
19,264.29
132,583.65
6,629.18
139,212.83
139,212.83
2,400.22
139,212.76
P
P
P
Total Cost
125,870.25
19,936.00
145,806.25
P
P
P
P
Total cost
8,634.15
49,980.00
38,545.20
97,159.35
P
P
P
P
P
P
P
P
P
Total cost
18,720.00
18,720.00
261,685.60
44,486.55
306,172.15
15,308.61
321,480.76
321,480.76
446.65
LABOR
Manpower
Construction Foreman
Electrician
Helper
Needed
1
1
2
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
12
12
12
Sub-total
Mark-up
17%
VAT
5%
220.58
499.18
719.76
15
Sq.m.
Sq.m.
Sq.m.
CD.
Quantity
475
14
Unit
Bags
Cu.m.
P
P
Unit Cost
264.99
1,424.00
LABOR
Manpower
Construction Foreman
Mason
Laborer
Needed
1
8
8
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
15
15
15
Needed
1
Rate/Day
1,248.00
Duration
15
EQUIPMENT
Equipment
1-Bagger conc. Mixer
Sub-total
Mark-up
Labor Cost
VAT
Total Item Cost
Unit Cost
17%
5%
321,480.80
9.00
Set
2.00
2.00
CD.
CD.
Quantity
6
Unit
Set
Unit Cost
6,000.00
Total Cost
36,000.00
Set
3,500.00
10,500.00
9
27
Pcs.
Pcs.
P
P
450.00
90.00
P
P
P
4,050.00
2,430.00
52,980.00
P
P
P
P
P
P
P
P
P
P
P
P
P
Total cost
1,151.22
1,666.00
1,666.00
1,284.84
5,768.06
58,748.06
9,987.17
68,735.23
3,436.76
72,171.99
72,171.99
8,019.11
72,171.99
LABOR
Manpower
Construction Foreman
Carpenter
Mason
Helper
Needed
1
2
2
2
P
P
P
P
Rate/Day
575.61
416.50
416.50
321.21
Duration
2
2
2
2
Sub-total
Mark-up
17%
VAT
5%
12.00
3.00
Set
CD.
Quantity
3.00
Unit
Set
Unit Cost
9,375.00
Total Cost
28,125.00
6.00
Set
5,250.00
31,500.00
3.00
Set
945.00
2,835.00
62,460.00
P
P
P
P
P
Total cost
1,726.83
1,249.50
963.63
3,939.96
66,399.96
LABOR
Manpower
Construction Foreman
Skilled Laborer
Helper
Needed
1
1
1
P
P
P
Rate/Day
575.61
416.50
321.21
Sub-total
Duration
3
3
3
Mark-up
17%
VAT
5%
317.98
Sq.m.
27.00
7.00
34.00
CD.
Quantity
2262.57
3635.56
207.02
65.83
255.81
6426.79
24
1
21
5
Unit
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Pcs.
Lot
Kgs.
Pcs.
P
P
P
P
P
P
P
Unit Cost
P
P
P
P
P
35.62
60.00
3,000.00
100.00
495.00
11,287.99
77,687.95
3,884.40
81,572.35
81,572.35
6,797.70
81,572.40
Total Cost
P
P
P
P
P
P
228,922.26
1,440.00
3,000.00
2,100.00
2,475.00
237,937.26
P
P
P
P
Total cost
19,570.74
14,161.00
32,763.42
66,495.16
P
P
P
P
P
P
P
P
P
P
P
20,400.00
10,200.00
30,600.00
335,032.42
56,955.51
391,987.93
19,599.40
411,587.33
411,587.33
1,294.38
411,586.95
LABOR
Manpower
Construction Foreman
Welder
Helper
Needed
1
1
3
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
34.00
34.00
34.00
1
1
P
P
600.00
300.00
34
34
Sub-total
Mark-up
17%
VAT
5%
EQUIPMENT
Equipment
Welding machine
Cut-off machine
317.98
Sq.m.
7.00
5.00
12.00
CD.
Description of Material/s
Rib-type Roof Ga.24
Ga. 24, 24"x 8' PPGI Ridge roll
12mm x 12"x8' Cement fiber facia bd.
55mm. Tekscrew
5/32" Blind rivets
Touch-up paint
Vulca seal
Quantity
317.98
16
12
3500
4
6
5
Unit
Lin.m.
Pcs.
Pcs.
Pcs.
Boxes
Lit.
Lit.
P
P
P
P
P
P
P
Unit Cost
360.00
440.00
550.00
2.50
800.00
150.00
400.00
P
P
P
P
P
P
P
P
Total Cost
114,472.80
7,040.00
6,600.00
8,750.00
3,200.00
900.00
2,000.00
142,962.80
P
P
P
P
Total cost
6,907.32
9,996.00
23,127.12
40,030.44
P
P
P
P
P
P
P
P
P
P
Total cost
3,600.00
3,600.00
186,593.24
31,720.85
218,314.09
10,915.70
229,229.79
229,229.79
720.89
229,228.60
LABOR
Manpower
Construction Foreman
Latero
Helper
Needed
1
2
6
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
12.00
12.00
12.00
Needed
2
Rate/Day
150.00
Duration
12
EQUIPMENT
Equipment
Elec. Drill
Sub-total
Mark-up
17%
VAT
5%
21.28
4.00
Quantity
17.28
3
12
250
55
24
0.6
10
4.00
4
15
7
2
Manpower
Construction Foreman
Carpenter
Laborer
Needed
1
2
2
Sq.m.
CD.
Unit
Sq.m.
Pc.
Pcs.
Bd.ft.
Bd.ft.
Pcs.
Sq.m.
Kgs.
Sq.m.
Sq.m.
Bd.ft.
Bd.ft.
Kgs.
P
P
P
Unit Cost
Rate/Day
575.61
416.50
321.21
P
P
P
P
P
P
P
1,000.00
700.00
27.00
27.00
50.00
200.00
100.00
P
P
P
P
P
P
P
3,000.00
8,400.00
6,750.00
1,485.00
1,200.00
120.00
1,000.00
P
P
P
P
200.00
75.00
75.00
100.00
P
P
P
P
P
800.00
1,125.00
525.00
200.00
24,605.00
Total cost
2,302.44
3,332.00
2,569.68
8,204.12
32,809.12
5,577.55
38,386.67
1,919.33
40,306.00
40,306.00
1,894.08
40,306.02
Duration
4
4
4
Sub-total
Mark-up
17%
VAT
5%
Total Cost
P
P
P
P
P
P
P
P
P
P
P
P
276.63
8.00
Quantity
93
52
114
469
101
5533
337
5
3
Manpower
Construction Foreman
Carpenter
Laborer
Needed
1
3
6
P
P
P
Rate/Day
575.61
416.50
321.21
Duration
8
8
8
Equipment
Needed
2
Rate/Day
150.00
Duration
8
Elec. Drill
Sq.m.
CD.
Unit
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Box
P
P
P
P
P
P
P
P
P
Unit Cost
80.00
165.00
170.00
15.00
400.00
1.00
2.00
65.00
600.00
Sub-total
Mark-up
17%
VAT
5%
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
Total Cost
7,440.00
8,580.00
19,380.00
7,035.00
40,400.00
5,533.00
674.00
325.00
1,800.00
91,167.00
Total cost
4,604.88
9,996.00
15,418.08
30,018.96
Total cost
2,400.00
2,400.00
123,585.96
21,009.61
144,595.57
7,229.78
151,825.35
151,825.35
548.84
151,825.61
354.78
5.00
Quantity
236.49
9
17
1
12
4
61.34
3
5
4
4
17.28
1
Sq.m.
CD.
Unit
Sq.m.
Gal.
Gal.
Gal.
Kgs
Lit.
Sq.m.
Gal.
Gal.
Gal.
Gal.
Sq.m.
Gal.
Unit Cost
Total Cost
P
P
P
P
P
500.00
520.00
250.00
50.00
123.00
P
P
P
P
P
4,500.00
8,840.00
250.00
600.00
492.00
P
P
P
P
550.00
600.00
520.00
260.00
P
P
P
P
1,650.00
3,000.00
2,080.00
1,040.00
900.00
900.00
Polytuff putty
Paint thinner
Metal:
Red oxide paint
Flatwall enamel
Quick dry enamel
Glazing Putty
Paint thinner
9" Roller brush
Pan
Pallet knives
3" Paint brush
Sand paper
Transhipment
Manpower
Construction Foreman
Painter
Helper
1
1
39.67
1
1
3
2
2
20
6
6
18
200
1
Needed
1
6
6
Gal.
Gal.
Sq.m.
Gal.
Gal.
Gal.
Gal.
Gal.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
lot
P
P
P
Rate/Day
575.61
416.50
321.21
P
P
540.00
260.00
P
P
540.00
260.00
P
P
P
P
P
P
P
P
P
P
P
400.00
550.00
600.00
520.00
260.00
105.00
95.00
50.00
85.00
70.00
3,748.25
P
P
P
P
P
P
P
P
P
P
P
P
400.00
550.00
1,800.00
1,040.00
520.00
2,100.00
570.00
300.00
1,530.00
14,000.00
3,748.25
50,710.25
Total cost
2,878.05
12,495.00
9,636.30
25,009.35
75,719.60
12,872.33
88,591.93
4,429.60
93,021.53
93,021.53
262.20
93,022.01
Duration
5
5
5
Sub-total
Mark-up
17%
VAT
5%
P
P
P
P
P
P
P
P
P
P
P
P
SUMMARY
NO.
WORK ITEM
DURATION
MATERIALS
LABOR
EQUIPMENT
NO.
101
803
104
900
404
414
704
1002
1102
1027
1010
1009
403
1014
1003
Spl.1
1032
4
3.00
11.00
17
12
12
7
4
12
15
2
3
34
12
4
8
5
165
WORK ITEM
QUANTITY
REMOVAL OF STRUCTURES & OBSTRUCT
1.00
STRUCTURE EXCAVATION
46.08
EMBANKMENT
205.16
REINFORCED CONCRETE
65.40
REINFORCING STEEL BARS
8357.91
FORMS & FALSEWORK
265.00
MASONRY WORKS
196.34
PLUMBING WORKS
14.00
ELECTRICAL WORKS
58.00
PLASTERING WORKS
719.76
WOODEN DOORS
9.00
JALOUSIE WINDOW
12.00
METAL STRUCTURES (ROOF FRAMING)
317.98
ROOFING WORKS
317.98
CARPENTRY WORKS
21.28
METAL FURRING CEILING
276.63
PAINTING WORKS
354.78
Agg.tax P
1,400.00
8,204.12
16,467.15
55,798.05
62,170.36
68,155.56
57,735.48
31,430.56
4,000.00
19,614.36
97,159.35
5,768.06
3,939.96
66,495.16
40,030.44
8,204.12
30,018.96
25,009.35
2,000.00
P
P
21,216.00
3,600.00
P 93,162.00
P 116,730.59
P 52,780.00
P 93,705.00
P 145,806.25
P 52,980.00
P 62,460.00
P 237,937.26
P 142,962.80
P 24,605.00
P 91,167.00
P 50,710.25
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
8,736.00
1,200.00
18,720.00
P
P
30,600.00
3,600.00
2,400.00
1,816,361.40
600,201.04
92,072.00
1.67
1,816,363.08
P 43,859.20
P 291,189.05
P
316,307.00
UNIT
Lot
cu.m.
cu.m.
cu.m.
Kg.
Cu.m.
Sq.m.
Lin.m.
Outlet
Sq.m.
Set
Set
Sq.m.
Sq.m.
Sq.m.
Sq.m.
Sq.m.
9.72
ramp
wf
0.91
0.4
6
9.3333333333
11
24.3333333333
18.3333333333
10
9.6666666667
6
50.4
50.4
0.0957177093
1.4955892083
3
3
37.8
37.8
0.10%
1.50%
3
2.3333333333
11
4.5833333333
1,335,258.44
1,541,451.93
1,680,664.69
2,002,145.50
21,192.00
#REF!
2,016,677.13
71,381.18
#REF!
455.00
693.00
295.75
346.50
325.33
381.15
318.50
485.10
878.00
439.00
482.90
614.60
42,888.84
2,796,705.44
182.00
P
P
P
P
P
P
P
P
P
2.97
5.32
2.43
0.59
2.74
0.05
0.82
55.33
92.21
#REF!
236.49
222.99
35.74
(0.01)
(0.00)
MARK-UP
VAT
COST/ITEM
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
1,734.70 P
2,799.42 P
16,941.73 P
63,677.82 P
65,970.64 P
25,652.57 P
26,672.52 P
9,856.60 P
19,264.29 P
44,486.55 P
9,987.17 P
11,287.99 P
56,955.51 P
31,720.85 P
5,577.55 P
21,009.61 P
12,872.33 P
426,467.85 P
P
596.94 P
963.33 P
5,829.95 P
21,912.66 P
22,701.66 P
8,827.50 P
9,178.48 P
3,391.83 P
6,629.18 P
15,308.61 P
3,436.76 P
3,884.40 P
19,599.40 P
10,915.70 P
1,919.33 P
7,229.78 P
4,429.60 P
146,755.11 P
573,222.96 P
12,535.76
20,229.90
122,428.93
460,165.89
476,734.86
185,377.55
192,748.15
71,228.43
139,212.83
321,480.76
72,171.99
81,572.35
411,587.33
229,229.79
40,306.00
151,825.35
93,021.53
3,081,857.40
3,081,859.08
P
12,535.76
P
20,229.90
P
122,428.93
P
460,165.89
P
476,734.86
P
185,377.55
P
192,748.15
P
71,228.43
P
139,212.83
P
321,480.76
P
72,171.99
P
81,572.35
P
411,587.33
P
229,229.79
P
40,306.00
P
151,825.35
P
93,021.53
P 3,081,857.40
P 3,081,857.40
P
P
(3,911.48)
(25,009.35)
575191.69
-21097.87
J.COST/ITEM
P
12,535.76
P
20,230.04
P
122,429.23
P
460,166.17
P
476,735.19
P
185,378.10
P
192,748.94
P
71,228.50
P
139,212.76
P
321,480.80
P
72,171.99
P
81,572.40
P
411,586.95
P
229,228.60
P
40,306.02
P
151,825.61
P
93,023.32
P 3,081,860.39
(1.67)
B. LABOR
Manpower
Construction Foreman
Welder
NO.
1
1
P
P
Rate/Day
300.00
280.00
Duration
#REF!
#REF!
Mark-up
Total Item Cost
Unit Cost
Total Adjusted Cost
10%
Total cost
#REF!
#REF!
B. LABOR
Manpower
Construction Foreman
NO.
1
Rate/Day
300.00
Labor Cost
Duration
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Materials+Labor
Mark-up
Total Item Cost
Unit Cost
10%
Total cost
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
N/A
N/A
Source of Funds:
Limits:
Length:
No. of Classrooms/Beds:
Type of Structure:
No.of Days to Complete:
Classification:
Starting Date:
Type of Superstructure:
Mode of Implementation:
NO.
101
803
104
900
404
414
704
1002
1102
1027
1010
1009
403
1014
1003
Spl.1
1032
NO.
101
803
104
900
404
414
704
1002
1102
1027
1010
1009
403
1014
1003
Spl.1
1032
1
2
3
4
5
6
7
8
9
1-Jul-15
PROGAM OF WORK
CAR
Roadbed Width:
Abra Engineering District Pavement Width:
Upon Approval
PERCENT
LABOR:
MATERIALS:
EQUIPMENT EXPENSES:
INDIRECT COST (VAT):
SOIL EXPLORATION:
ENG'G.,ADMIN.OVERHEAD:
CONST. CONTINGENCIES:
AGGREGATE TAX:
ROAD RIGHT OF WAY:
15,512.96
460.40
1,400.00
0.50
0.01
0.05
120
By Contract
EQUIPMENT
NEEDED
DESCRIPTION
AVAILABLE
2
2
1
1
1
2
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
UNIT COST
12,535.76
439.02
596.75
7,036.18
57.04
699.54
981.71
5,087.75
2,400.22
446.65
8,019.11
6,797.70
1,294.38
720.89
1,894.08
548.84
262.20
TOTAL PROJECT
COST(DIRECT &
INDIRECTCOST):
ENG'G.,ADMIN.
OVERHEAD:
CONST. CONT.:
AGGREGATE TAX:
ROAD RIGHT OF WAY:
SURVEY PLAN &
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
TOTAL COST
12,535.76
20,230.04
122,429.23
460,166.17
476,735.19
185,378.10
192,748.94
71,228.50
139,212.76
321,480.80
72,171.99
81,572.40
411,586.95
229,228.60
40,306.02
151,825.61
93,022.01
3,081,859.08
3,081,859.08
P
P
P
P
15,512.96
460.40
1,400.00
-
10
11
12
PREPARED BY:
JUAN ANTONIO E. FLORENTINO
ARCHITECT II
APPROVED:
3,360.00
3,102,592.44
CHECKED BY:
PUBLICATION FEE:
SOIL EXPLORATION:
BILLBOARD:
0.11
0.00
100.00
P
P
P
3,360.00
-
3,102,592.44
SUBMITTED BY:
EMMANUEL T. COLLADO
ENGINEER II
CONCURRED BY:
LORETO B. DACOROON
CARETAKER
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
12,535.76
20,230.04
122,429.23
460,166.17
476,735.19
185,378.10
192,748.94
71,228.50
139,212.76
321,480.80
72,171.99
81,572.40
411,586.95
229,228.60
40,306.02
151,825.61
93,023.32
3,081,860.39
(0.00)
3,102,592.44
P
0.00
VAT
#REF!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
P
P
P
3,083,259.08
-
P
P
P
P
#REF!
KMS.
1 DUMPTRUCK WITH A CAPACITY OF 4 CU.M.
LOADING TIME =
5
UNLOADING TIME =
1
SLACK TIME =
6
12
LOADED TRIP =
50
KMS. X
20
60
KPH
MINS/HR
150
UNLOADED TRIP =
50
KMS. X
25
60
KPH
MINS/HR
120
TOTAL TIME =
NO OF HRS./TRIP =
282
60
282
=
4.7
MINS./HR.
Equipment Rental:
1- Dumptruck 6-8 tons, 4 cu.m.
P 807.00 /hour
P 6,456.00 /day
P 6,456.00
X
6
4.7
HRS.
P 5,057.20
SAY
P 5,057.00 =
4
SAY
/cu.m.
(processed material)
(processed material)
P 1,424.00
say
1,424.00
P 1,424.00
say
1,424.00
say
1,664.00
/cu.m.
(processed material)
P 1,264.25 /CU.M.
P 1,264.00 /CU.M.
P 5,057.00
97.35 /CU.M.
40
KMS.
USING 1 PAYLOADER
1 DUMPTRUCK WITH A CAPACITY OF 4 CU.M.
LOADED TRIP =
LOADED TRIP =
40
40
KMS. X
15
KMS. X
20
LOADING TIME =
MINS.
UNLOADING TIME =
SLACK TIME =
1
2
8
MINS.
MINS.
MINS.
60
MINS/H =
160
MINS
60
MINS/H =
120
MINS
288
MINS
KPH
KPH
TOTAL TIME =
NO OF HRS./TRIP =
288
60 MINS./HR.
X
8
4.8
HRS.
4.8 HOURS
3,403.20
69.25
3,472.45
TOTAL =
UNIT COST =
P 3,472.45
4
97.35
=
SAY
P
P
965.46 /CU.M.
965.00 /CU.M.
#REF!
PAINTING ( 2-Coats )
Wall Area:
Ceiling Area:
80
Total Area:
80
Duration:
A. MATERIALS
Description of Material/s Quantity
Boysen Flat Latex
Paint Thinner
10
Concrete Neutraliz
Sand paper
28
3
0.5
Material cost
B. LABOR
Manpower
NO.
Construction Fore
Painter
Laborer
3
Labor Cost
PAINTING
#REF!
PAINTING
MINS
MINS
HOURS
P 807.00 /hour
P 6,456.00 /day
Manpower:
6-Laborers @ P 25.00/man hr.
Loading Time:
Unloading Time:
Slack Time:
Total
Travel Velocity:
Loaded:
Unloaded:
Distance:
Loaded:
35.00
=
105.00
Unloaded:
35.00
84.00
Total=
P 150.00 /hour
P 1,200.00 /day
20.00
20.00
6.00
46.00
minutes
minutes
minutes
minutes
15.00
20.00
35.00
km. X
20.00
minutes
Kph
Kph
Km.
60.00
Kph
km. X
60.00
25.00 Kph
minutes
Min./hour
Min./hour
235.00 minutes
3.92 hours
P 150.00 /hour x
P 807.00 /hour x
4
6000
1687.5
500
cu.m.
Kgs.
Bd.ft
Pcs./trip
bags/trip
Pick-up at Site
P 240.00 P 264.99
Pick-up at Site
P 35.00 P 35.62
Pick-up at Site
P 36.00 P 38.22
4" Chb
Pick-up at Site
P 9.00 P 16.50
5" Chb
Pick-up at Site
3.92
3.92
Total
=
=
=
P
587.50
P 3,160.75
P 3,748.25
P 11.00
Cu.m.
18.50
Sq.m.
Sq.m.
Sq.m.
C.D.
Unit
Gal.
Gal.
Gal.
Gal.
Total Cost
Pcs.
#REF!
Lit.
#REF!
Lit.
#REF!
Trip
#REF!
Material cost
#REF!
VAT
#REF!
Mark-up
#REF!
#REF!
#REF!
Rate/Day
#REF!
P277.30
#REF!
P209.90
#REF!
P194.70
Labor Cost Total cost
VAT
#REF!
Mark-up
#REF!
#REF!
#REF!
Unit Cost
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
MARK-UP
#REF!
#REF!
#REF!
#REF!
#REF!
P
#REF!
#REF!
#REF!
#REF!
80.00
#REF!
per trip