Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 180

Standard Form Number: SF-INFR-01

Revised on: July 28, 2004

APPROVED BUDGET FOR THE CONTRACT

CONSTRUCTION OF 1 STOREY, 3 CL SCHOOL BLDG.


Dalit Elementary School, Pilar, Abra
Project Name and Location
Stations:
Length:

ITEM
NO.

DESCRIPTION

(1)

UNIT

MARK-UPS
IN PERCENT
OCM[1]

PROFIT

TOTAL MARK-UP
MOB.\ DEMOB.[2] %

VAT[3]

VALUE

(3)

(4)

(5)

(6)

(7)

(8)

(9)

1.00

Lot

10,204.12

9.00%

8.00%

0.00%

17.00%

803

REMOVAL OF STRUCTURES &


OBSTRUCTION
STRUCTURE EXCAVATION

46.08

cu.m.

16,467.15

9.00%

8.00%

0.00%

17.00%

104

EMBANKMENT

205.16

cu.m.

99,657.25

9.00%

8.00%

0.00%

17.00%

900

REINFORCED CONCRETE

65.40

cu.m.

374,575.41

9.00%

8.00%

0.00%

17.00%

63,677.82

21,912.66

404

REINFORCING STEEL BARS

8357.91

Kg.

388,062.56

9.00%

8.00%

0.00%

17.00%

65,970.64

22,701.66

414

FORMS & FALSEWORK

265.00

Cu.m.

150,897.48

9.00%

8.00%

0.00%

17.00%

25,652.57 P

8,827.50

704

MASONRY WORKS

196.34

Sq.m.

156,897.15

9.00%

8.00%

0.00%

17.00%

26,672.52 P

9,178.48

1002

PLUMBING WORKS

14.00

Lin.m.

57,980.00

9.00%

8.00%

0.00%

17.00%

3,391.83

1102

ELECTRICAL WORKS

58.00

Outlet

113,319.36

9.00%

8.00%

0.00%

17.00%

19,264.29 P

6,629.18

1027

PLASTERING WORKS

719.76

Sq.m.

261,685.60

9.00%

8.00%

0.00%

17.00%

44,486.55

15,308.61

1010

WOODEN DOORS

9.00

Set

58,748.06

9.00%

8.00%

0.00%

17.00%

9,987.17

3,436.76

1009

JALOUSIE WINDOW

12.00

Set

66,399.96

9.00%

8.00%

0.00%

17.00%

11,287.99 P

403

METAL STRUCTURES (ROOF FRAMING)

317.98

Sq.m.

335,032.42

9.00%

8.00%

0.00%

17.00%

56,955.51

1014

ROOFING WORKS

317.98

Sq.m.

186,593.24

9.00%

8.00%

0.00%

17.00%

1003

CARPENTRY WORKS

21.28

Sq.m.

32,809.12

9.00%

8.00%

0.00%

17.00%

Spl.1

METAL FURRING CEILING

276.63

Sq.m.

123,585.96

9.00%

8.00%

0.00%

17.00%

1032

PAINTING WORKS

354.78

Sq.m.

75,719.60

9.00%

8.00%

0.00%

17.00%

101

(2)

QUANTITY

ESTIMATED
DIRECT COST

(10)

(11)

1,734.70

2,799.42

963.33

16,941.73 P

5,829.95

9,856.60

596.94

3,884.40

19,599.40

31,720.85

10,915.70

5,577.55

1,919.33

21,009.61 P

7,229.78

12,872.33 P

4,429.60

THREE MILLION EIGHTY-ONE THOUSAND EIGHT HUNDRED FIFTY-NINE PESOS & 08/100
PREPARED/SUBMITTED BY:

FERDINAND A. TADEO

Engineer III

SOCORRO LITO S. BENEDITO


Engineer II

APPROVED:

LORETO B. DACOROON

JONATHAN T. BOBITA
Engineer II

Contract Duration:
TOTAL
INDIRECT
COST

TOTAL COST

(12)

2,331.64

120 cd
UNIT COST

(13)

(14)

12,535.76

12,535.76

12,535.76

12,535.76

3,762.75

20,230.04

439.02

22,771.68

122,429.23

596.75

85,590.48

460,166.17

7,036.18

88,672.30

476,735.19

57.04

34,480.07

185,378.10

699.54

35,851.00

192,748.94

981.71

13,248.43

71,228.50

5,087.75

25,893.47

139,212.76

2,400.22

59,795.16

321,480.80

446.65

446.65

321,480.76

13,423.93

72,171.99

8,019.11

8,019.11

72,171.99

15,172.39

81,572.40

6,797.70

6,797.70

81,572.35

76,554.91 P

411,586.95 P

1,294.38

42,636.55

229,228.60

720.89

7,496.88

40,306.02

1,894.08

28,239.39

151,825.61

548.84

17,301.93

93,022.01

262.20

3,081,859.08

100

LORETO B. DACOROON
CARETAKER

3,081,859.08

0.00

PROJECT TITLE:
LOCATION:

CONSTRUCTION OF 1 STOREY, 3 CL SCHOOL BLDG.


Dalit Elementary School, Pilar, Abra
DETAILED ESTIMATE

101 REMOVAL OF STRUCTURES & OBSTRUCTION


Quantity:
1.00
Duration:
4
LABOR
Manpower
Needed
Construction Foreman
1
Skilled laborer
2
Laborer
2

Lot
CD.

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
4
4
4

Rate/Day
250.00

Duration
4

P
P
P
P

Total cost
2,302.44
3,332.00
2,569.68
8,204.12

P
P
P
P
P
P
P
P
P
P

Total cost
2,000.00
2,000.00
10,204.12
1,734.70
11,938.82
596.94
12,535.76
12,535.76
12,535.76
12,535.76

P
P
P
P
P
P
P
P
P
P
P
P

Total cost
1,726.83
1,249.50
13,490.82
16,467.15
16,467.15
2,799.42
19,266.57
963.33
20,229.90
20,229.90
439.02
20,230.04

EQUIPMENT
Equipment

Needed
2

Minor tools

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost
803 STRUCTURE EXCAVATION
Quantity:
Duration:

46.08
3

cu.m.
CD.

LABOR
Manpower
Construction Foreman
Skilled laborer
Laborer

Needed
1
1
14

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
3
3
3

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost
104 EMBANKMENT
Quantity:
Duration:
Placing
Compaction

MATERIALS
Description of Material/s
EarthFill ( Excavated Material )
Gravel bedding

205.16

cu.m.

3.66
7.33
10.99
11.00

CD.

Quantity
174.36
30.80

Unit
cu.m.
cu.m.

Unit Cost
P

1,424.00

Total Cost
P
P
P

43,859.20
43,859.20

P
P
P

Total cost
6,331.71
49,466.34
55,798.05

99,657.25

LABOR
Manpower
Construction Foreman
Laborer

Needed
1
14

P
P

Rate/Day
575.61
321.21

Sub-total

Duration
11.00
11.00

Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

P
P
P
P
P
P
P

16,941.73
116,598.98
5,829.95
122,428.93
122,428.93
596.75
122,429.23

P
P
P
P

Total Cost
157,669.05
46,992.00
86,528.00
291,189.05

P
P
P
P

Total cost
9,785.37
14,161.00
38,223.99
62,170.36

P
P
P
P
P
P
P
P
P
P

Total cost
21,216.00
21,216.00
374,575.41
63,677.82
438,253.23
21,912.66
460,165.89
460,165.89
7,036.18
460,166.17

900 REINFORCED CONCRETE


Quantity:
Slab on Fill,F1 & WF1=
Columns & Beams=
Duration:
Slab on Fill=
Columns & Beams=
MATERIALS
Description of Material/s
40 kg. Portland Cement
Fine aggregates
Coarse aggregates (2" Gravel pea)

36.01
29.39
65.40

cu.m.

7.00
10.00
17.00

CD.

Quantity
595
33
52

Unit
Bags
Cu.m.
Cu.m.

P
P
P

Unit Cost
264.99
1,424.00
1,664.00

LABOR
Manpower
Construction Foreman
Mason
Laborer

Needed
1
2
7

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
17.00
17.00
17.00

Needed
1

Rate/Day
1,248.00

Duration
17

EQUIPMENT
Equipment
1-Bagger conc. Mixer

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost
404 REINFORCING STEEL BARS
Quantity:
Duration:
MATERIALS
Description of Material/s
Column & Wall Footing
Footing Tie Beam
Column, Pc & Stiffener
RG & LRB
SOF, corridor and ramp
Masonry wall
Total
14" cut-off machine blade
#16 G.I. Tie wire
Transhipment

8357.91
12
Quantity
535.17
1618.81
2171.64
2287.35
1200.1
544.84
8357.91
8
125
1

Kg.
CD.
Unit
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Pcs.
Kgs.
lot

Unit Cost

P
P
P
P

35.62
450.00
90.00
3,748.25

Total Cost

P
P
P
P
P

297,708.75
3,600.00
11,250.00
3,748.25
316,307.00

LABOR
Manpower
Construction Foreman
Steelman
Laborer

Needed
1
3
12

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
12
12
12

300.00

12

Sub-total
Mark-up

17%

VAT

5%

P
P
P
P

Total cost
6,907.32
14,994.00
46,254.24
68,155.56

P
P
P
P
P
P
P
P
P
P

3,600.00
3,600.00
388,062.56
65,970.64
454,033.20
22,701.66
476,734.86
476,734.86
57.04
476,735.19

P
P
P
P

Total Cost
17,980.00
63,882.00
11,300.00
93,162.00

P
P
P
P
P
P
P
P
P
P
P
P

Total cost
6,907.32
19,992.00
30,836.16
57,735.48
150,897.48
25,652.57
176,550.05
8,827.50
185,377.55
185,377.55
699.54
185,378.10

EQUIPMENT
Equipment
Cut-off machine

Total Item Cost


Unit Cost
Total Adjusted Cost

414 FORMS & FALSEWORK


Quantity:
Approx. area
Volume of conc. To be formed:
Duration:
Fabrication & Installation
Removal
Say
MATERIALS
Description of Material/s
1/2"thk.Ordinary plywood
Form lumber
Assorted nails

265
29.39

Sq.m.
Cu.m.

7.57
4.42
11.99
12

CD.

Quantity
29
2366
113

Unit
Pcs.
Bd.ft.
Kgs.

P
P
P

Unit Cost
620.00
27.00
100.00

LABOR
Manpower
Construction Foreman
Carpenter
Laborer

Needed
1
4
8

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
12
12
12

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost
704 MASONRY WORKS
Quantity:
Duration:
Description of Material/s
Exterior wall: Class A I:2 Mix
5"thk. CHB

196.34
7
Quantity
196.34
2454

Sq.m.
CD
Unit
Sq.m.
Pcs.

Unit Cost
P

14.00

Total Cost
P

34,356.00

40kg. Portland cement


Sand

241
13

Bags
Cu.m.

P
P

264.99
1,424.00

Manpower
Construction Foreman
Mason
Laborer

Needed
1
4
7

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
7
7
7

Equipment
1-Bagger conc. Mixer

Needed
1

Rate/Day
1,248.00

Duration
7

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

63,862.59
18,512.00
116,730.59
Total cost
4,029.27
11,662.00
15,739.29
31,430.56
Total cost
8,736.00
8,736.00
156,897.15
26,672.52
183,569.67
9,178.48
192,748.15
192,748.15
981.71
192,748.94

1002 PLUMBING WORKS


Quantity:
Duration:
Description of Material/s
A. Fixtures:
Water closet w/ tank
Lavatory
1/2" Hose bibb
1/2"0 Angle valve
1/2"0 Gate valve
4"x4" Floor drain
B. PPR Pipe & Fittings:
1/2"0x4.00m.PPR pipe
1/2"0 Coupling
1/2"0 Elbow
1/2"0 Tee
1/2"0 male / female adaptor
1/2"0 Union patente
1/2"x3" Nipple
C. Sewer & Fittings:
4"0 x 10' PVC pipe
2"0 x 10' PVC pipe
4"0 Elbow 90 deg

14.00
4.00
Quantity

Lin.m.
CD.
Unit

Unit Cost

Total Cost

3
3
1
2
2
3

Set
Set
Pcs.
Pcs.
Pcs.
Pcs.

P
P
P
P
P
P

8,000.00
3,000.00
250.00
350.00
385.00
120.00

P
P
P
P
P
P

24,000.00
9,000.00
250.00
700.00
770.00
360.00

12
6
14
6
6
1
3

Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.

P
P
P
P
P
P
P

330.00
30.00
40.00
35.00
165.00
80.00
30.00

P
P
P
P
P
P
P

3,960.00
180.00
560.00
210.00
990.00
80.00
90.00

7
9
4

Pcs.
Pcs.
Pcs.

P
P
P

580.00
280.00
100.00

P
P
P

4,060.00
2,520.00
400.00

4"0 Elbow 45 deg


4"0 Sanitary tee
4"0 Wye
2"x4" wye
4"0 Clean-out
2"0 Elbow 90 deg.
2"0 Elbow 45 deg.
2"0 Sanitary tee
2"0 P-trap
Solvent cement sealant 100cc

4
3
3
6
4
6
4
4
6
4

Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Cans

P
P
P
P
P
P
P
P
P
P

100.00
150.00
150.00
150.00
95.00
45.00
45.00
60.00
120.00
165.00

Manpower
Construction Foreman
Plumber
Helper

Needed
1
1
1

P
P
P

Rate/Day
450.00
300.00
250.00

Duration
4.00
4.00
4.00

Equipment
Pipe threader / cutter

Needed
1

Rate/Day
300.00

Duration
4

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

P
P
P
P
P
P
P
P
P
P
P

P
P
P
P
P
P
P
P
P
P

400.00
450.00
450.00
900.00
380.00
270.00
180.00
240.00
720.00
660.00
52,780.00
Total cost
1,800.00
1,200.00
1,000.00
4,000.00
Total cost
1,200.00
1,200.00
57,980.00
9,856.60
67,836.60
3,391.83
71,228.43
71,228.43
5,087.75
71,228.50

P
P
P
P
P

Total Cost
15,000.00
21,600.00
2,000.00
500.00
900.00

P
P
P
P

1102 ELECTRICAL WORKS


Quantity:
Duration:
Description of Material/s
Wall fan
2-36w Fluorescent Lamp w/ box casing
18w Fluorescent Bulb w/ receptacle
1-gang switch w/ plate
2-gang switch w/ plate

58.00
12.00
Quantity
6
18
8
5
6

Outlet
CD.
Unit
Set
Pcs.
Pcs.
Set
Set

P
P
P
P
P

Unit Cost
2,500.00
1,200.00
250.00
100.00
150.00

2-gang Conv. Outlet,Fm. w/ plate


1-gang Conv. Outlet,Fm. w/ plate(wallfan CO)

5 hole Panel Board center main CB


40 amp. Main Ckt. Breaker
20 amp. Ckt. Breaker
15 amp. Ckt. Breaker
Junction box,deep type
Utility box,deep type
Electrical tape (big)
14mm.sq.TW copper wire
5.5mm.sq.THHN copper wire
3.5mm.sq.THHN copper wire
2.0mm.sq.THHN copper wire
20mm PVC conduit Pipe (Orange)
20mm PVC long elbow (Orange)
32mm.0 Entrance cap
32mm.0 RSC elbow
32mm.0 RSC coupling
32mm.0 Rigid steel conduit
Abreco meter connection

12
6
1
1
3
2
32
34
10
5
1
2
1
91
45
1
3
3
4
1

Set
Set
Set
Set
Set
Set
Set
Set
Pcs.
Mtrs.
Rolls
Rolls
Rolls
Pcs
Pcs
Pcs.
Pcs.
Pcs.
Pcs.
Lot

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

150.00
100.00
4,000.00
3,250.00
350.00
350.00
45.00
35.00
40.00
140.00
5,000.00
3,500.00
2,500.00
90.00
30.00
100.00
95.00
50.00
500.00

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

1,800.00
600.00
4,000.00
3,250.00
1,050.00
700.00
1,440.00
1,190.00
400.00
700.00
5,000.00
7,000.00
2,500.00
8,190.00
1,350.00
100.00
285.00
150.00
2,000.00
12,000.00

93,705.00

P
P
P
P
P
P
P
P
P
P
P
P

Total cost
6,907.32
4,998.00
7,709.04
19,614.36
113,319.36
19,264.29
132,583.65
6,629.18
139,212.83
139,212.83
2,400.22
139,212.76

P
P
P

Total Cost
125,870.25
19,936.00
145,806.25

P
P
P
P

Total cost
8,634.15
49,980.00
38,545.20
97,159.35

P
P
P
P
P
P
P
P
P

Total cost
18,720.00
18,720.00
261,685.60
44,486.55
306,172.15
15,308.61
321,480.76
321,480.76
446.65

LABOR
Manpower
Construction Foreman
Electrician
Helper

Needed
1
1
2

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
12
12
12

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost
1027 PLASTERING WORKS
Quantity:
Flooring ( non skid)
Wall
Duration:
MATERIALS
Description of Material/s
40kg. Portland Cement
Fine aggregates

220.58
499.18
719.76
15

Sq.m.
Sq.m.
Sq.m.
CD.

Quantity
475
14

Unit
Bags
Cu.m.

P
P

Unit Cost
264.99
1,424.00

LABOR
Manpower
Construction Foreman
Mason
Laborer

Needed
1
8
8

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
15
15
15

Needed
1

Rate/Day
1,248.00

Duration
15

EQUIPMENT
Equipment
1-Bagger conc. Mixer

Sub-total
Mark-up
Labor Cost
VAT
Total Item Cost
Unit Cost

17%
5%

Total Adjusted Cost

321,480.80

1010 WOODEN DOORS


Quantity:
Duration:
Doors
MATERIALS
Description of Material/s
D1- 0.90x2.40 m.Mahogany Panel door
on 50x150mm.thk Mahogany jamb w/
fixed clear glass transom
D5- 0.70x2.10 m. Hollow core flush type
swing dooron 50x150mm.thk jamb w/
Marine plywd. Facing inside & ordinary
outside
Lockset
3 1/2"x 3 1/2" loose pin hindges

9.00

Set

2.00
2.00

CD.
CD.

Quantity
6

Unit
Set

Unit Cost
6,000.00

Total Cost
36,000.00

Set

3,500.00

10,500.00

9
27

Pcs.
Pcs.

P
P

450.00
90.00

P
P
P

4,050.00
2,430.00
52,980.00

P
P
P
P
P
P
P
P
P
P
P
P
P

Total cost
1,151.22
1,666.00
1,666.00
1,284.84
5,768.06
58,748.06
9,987.17
68,735.23
3,436.76
72,171.99
72,171.99
8,019.11
72,171.99

LABOR
Manpower
Construction Foreman
Carpenter
Mason
Helper

Needed
1
2
2
2

P
P
P
P

Rate/Day
575.61
416.50
416.50
321.21

Duration
2
2
2
2

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost
1009 JALOUSIE WINDOW
Quantity:
Duration:
MATERIALS
Description of Material/s
W-1. 2.50x1.50 m. Jalousie window w/ clear
glass blades on standard jalouplus casing
& fixed clear glass transom on 50x150mm.
Mahogany jamb complete w/ hardware &
accessories
W-2. 1.40x1.50 m. Jalousie window w/ clear
glass blades on standard jalouplus casing
& fixed clear glass transom on 50x150mm.
Mahogany jamb complete w/ hardware &
accessories
W-3. 0.60x0.63 m. Jalousie window w/ clear
glass blades on standard jalouplus casing
on 50x150mm. Mahogany jamb complete
w/ hardware & accessories

12.00
3.00

Set
CD.

Quantity
3.00

Unit
Set

Unit Cost
9,375.00

Total Cost
28,125.00

6.00

Set

5,250.00

31,500.00

3.00

Set

945.00

2,835.00

62,460.00

P
P
P
P
P

Total cost
1,726.83
1,249.50
963.63
3,939.96
66,399.96

LABOR
Manpower
Construction Foreman
Skilled Laborer
Helper

Needed
1
1
1

P
P
P

Rate/Day
575.61
416.50
321.21
Sub-total

Duration
3
3
3

Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

403 METAL STRUCTURES (ROOF FRAMING)


Quantity:
Duration:
Fabrication of steel trusses
Installation of Purlins & Facia bd.
MATERIALS
Description of Material/s
Steel Trusses
Purlins & Channel beams
Angular base plate
Sag rod
Cross bracing
Total
Turn buckle
Rail guard
Welding rod
Cut-off saw blade

317.98

Sq.m.

27.00
7.00
34.00

CD.

Quantity
2262.57
3635.56
207.02
65.83
255.81
6426.79
24
1
21
5

Unit
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Kgs.
Pcs.
Lot
Kgs.
Pcs.

P
P
P
P
P
P
P

Unit Cost

P
P
P
P
P

35.62
60.00
3,000.00
100.00
495.00

11,287.99
77,687.95
3,884.40
81,572.35
81,572.35
6,797.70
81,572.40

Total Cost

P
P
P
P
P
P

228,922.26
1,440.00
3,000.00
2,100.00
2,475.00
237,937.26

P
P
P
P

Total cost
19,570.74
14,161.00
32,763.42
66,495.16

P
P
P
P
P
P
P
P
P
P
P

20,400.00
10,200.00
30,600.00
335,032.42
56,955.51
391,987.93
19,599.40
411,587.33
411,587.33
1,294.38
411,586.95

LABOR
Manpower
Construction Foreman
Welder
Helper

Needed
1
1
3

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
34.00
34.00
34.00

1
1

P
P

600.00
300.00

34
34

Sub-total
Mark-up

17%

VAT

5%

EQUIPMENT
Equipment
Welding machine
Cut-off machine

Total Item Cost


Unit Cost
Total Adjusted Cost
1014 ROOFING WORKS
Quantity:
Duration:
Intallation of Roofing
Intallation of Gutter/flashing/ridgeroll
MATERIALS

317.98

Sq.m.

7.00
5.00
12.00

CD.

Description of Material/s
Rib-type Roof Ga.24
Ga. 24, 24"x 8' PPGI Ridge roll
12mm x 12"x8' Cement fiber facia bd.
55mm. Tekscrew
5/32" Blind rivets
Touch-up paint
Vulca seal

Quantity
317.98
16
12
3500
4
6
5

Unit
Lin.m.
Pcs.
Pcs.
Pcs.
Boxes
Lit.
Lit.

P
P
P
P
P
P
P

Unit Cost
360.00
440.00
550.00
2.50
800.00
150.00
400.00

P
P
P
P
P
P
P
P

Total Cost
114,472.80
7,040.00
6,600.00
8,750.00
3,200.00
900.00
2,000.00
142,962.80

P
P
P
P

Total cost
6,907.32
9,996.00
23,127.12
40,030.44

P
P
P
P
P
P
P
P
P
P

Total cost
3,600.00
3,600.00
186,593.24
31,720.85
218,314.09
10,915.70
229,229.79
229,229.79
720.89
229,228.60

LABOR
Manpower
Construction Foreman
Latero
Helper

Needed
1
2
6

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
12.00
12.00
12.00

Needed
2

Rate/Day
150.00

Duration
12

EQUIPMENT
Equipment
Elec. Drill

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

1003 CARPENTRY WORKS


Quantity:
Duration:
Description of Material/s
3-1.20x4.80 m. Blackboard
3/4"thk. Plyboard
1/4" thk. Lawanit board
2"x2" Lumber
1"x2" Lumber
10mm. Anchor bolt
2mm x 10mm x 10mm Wire mess
Assorted Nails
Air vent
2mm x 10mm x 10mm Wire mess
1"x3" S4S KD Lumber
1"x1" S4S KD Lumber
Assorted Nails

21.28
4.00
Quantity
17.28
3
12
250
55
24
0.6
10
4.00
4
15
7
2

Manpower
Construction Foreman
Carpenter
Laborer

Needed
1
2
2

Sq.m.
CD.
Unit
Sq.m.
Pc.
Pcs.
Bd.ft.
Bd.ft.
Pcs.
Sq.m.
Kgs.
Sq.m.
Sq.m.
Bd.ft.
Bd.ft.
Kgs.

P
P
P

Unit Cost

Rate/Day
575.61
416.50
321.21

P
P
P
P
P
P
P

1,000.00
700.00
27.00
27.00
50.00
200.00
100.00

P
P
P
P
P
P
P

3,000.00
8,400.00
6,750.00
1,485.00
1,200.00
120.00
1,000.00

P
P
P
P

200.00
75.00
75.00
100.00

P
P
P
P
P

800.00
1,125.00
525.00
200.00
24,605.00
Total cost
2,302.44
3,332.00
2,569.68
8,204.12
32,809.12
5,577.55
38,386.67
1,919.33
40,306.00
40,306.00
1,894.08
40,306.02

Duration
4
4
4

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

Total Cost

P
P
P
P
P
P
P
P
P
P
P
P

Spl.1 METAL FURRING CEILING


Quantity:
Duration:
Description of Material/s
Wall angle
Carrying channel
Double furring
W-clip
4.5mmx1.22mx2.44m Fiber cement board
1" Self tapping screw
1/8"x1" Tox with screw
1/8" Drill bit
1/8"x1" Bling rivets

276.63
8.00
Quantity
93
52
114
469
101
5533
337
5
3

Manpower
Construction Foreman
Carpenter
Laborer

Needed
1
3
6

P
P
P

Rate/Day
575.61
416.50
321.21

Duration
8
8
8

Equipment

Needed
2

Rate/Day
150.00

Duration
8

Elec. Drill

Sq.m.
CD.
Unit
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
Box

P
P
P
P
P
P
P
P
P

Unit Cost
80.00
165.00
170.00
15.00
400.00
1.00
2.00
65.00
600.00

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

Total Cost
7,440.00
8,580.00
19,380.00
7,035.00
40,400.00
5,533.00
674.00
325.00
1,800.00
91,167.00
Total cost
4,604.88
9,996.00
15,418.08
30,018.96
Total cost
2,400.00
2,400.00
123,585.96
21,009.61
144,595.57
7,229.78
151,825.35
151,825.35
548.84
151,825.61

1032 PAINTING WORKS


Quantity:
Duration:
Description of Material/s
Masonry wall(interior):
Boysen Flat Latex Paint
Boysen Semi-Gloss Latex Paint
Concrete Neutralizer
Patching compoud
Latex Tinting colors
Wood:
Flatwall enamel
Quick dry enamel
Glazing Putty
Paint thinner
Blackboard:
Blackboard paint

354.78
5.00
Quantity
236.49
9
17
1
12
4
61.34
3
5
4
4
17.28
1

Sq.m.
CD.
Unit
Sq.m.
Gal.
Gal.
Gal.
Kgs
Lit.
Sq.m.
Gal.
Gal.
Gal.
Gal.
Sq.m.
Gal.

Unit Cost

Total Cost

P
P
P
P
P

500.00
520.00
250.00
50.00
123.00

P
P
P
P
P

4,500.00
8,840.00
250.00
600.00
492.00

P
P
P
P

550.00
600.00
520.00
260.00

P
P
P
P

1,650.00
3,000.00
2,080.00
1,040.00

900.00

900.00

Polytuff putty
Paint thinner
Metal:
Red oxide paint
Flatwall enamel
Quick dry enamel
Glazing Putty
Paint thinner
9" Roller brush
Pan
Pallet knives
3" Paint brush
Sand paper
Transhipment
Manpower
Construction Foreman
Painter
Helper

1
1
39.67
1
1
3
2
2
20
6
6
18
200
1
Needed
1
6
6

Gal.
Gal.
Sq.m.
Gal.
Gal.
Gal.
Gal.
Gal.
Pcs.
Pcs.
Pcs.
Pcs.
Pcs.
lot

P
P
P

Rate/Day
575.61
416.50
321.21

P
P

540.00
260.00

P
P

540.00
260.00

P
P
P
P
P
P
P
P
P
P
P

400.00
550.00
600.00
520.00
260.00
105.00
95.00
50.00
85.00
70.00
3,748.25

P
P
P
P
P
P
P
P
P
P
P
P

400.00
550.00
1,800.00
1,040.00
520.00
2,100.00
570.00
300.00
1,530.00
14,000.00
3,748.25
50,710.25
Total cost
2,878.05
12,495.00
9,636.30
25,009.35
75,719.60
12,872.33
88,591.93
4,429.60
93,021.53
93,021.53
262.20
93,022.01

Duration
5
5
5

Sub-total
Mark-up

17%

VAT

5%

Total Item Cost


Unit Cost
Total Adjusted Cost

P
P
P
P
P
P
P
P
P
P
P
P

SUMMARY
NO.

WORK ITEM

DURATION

MATERIALS

LABOR

EQUIPMENT

101REMOVAL OF STRUCTURES & OBSTRUCTION


803 STRUCTURE EXCAVATION
104 EMBANKMENT
900 REINFORCED CONCRETE
404 REINFORCING STEEL BARS
414 FORMS & FALSEWORK
704 MASONRY WORKS
1002 PLUMBING WORKS
1102 ELECTRICAL WORKS
1027 PLASTERING WORKS
1010 WOODEN DOORS
1009 JALOUSIE WINDOW
403 METAL STRUCTURES (ROOF FRAMING)
1014 ROOFING WORKS
1003 CARPENTRY WORKS
Spl.1 METAL FURRING CEILING
1032 PAINTING WORKS

NO.
101
803
104
900
404
414
704
1002
1102
1027
1010
1009
403
1014
1003
Spl.1
1032

4
3.00
11.00
17
12
12
7
4
12
15
2
3
34
12
4
8
5
165

WORK ITEM
QUANTITY
REMOVAL OF STRUCTURES & OBSTRUCT
1.00
STRUCTURE EXCAVATION
46.08
EMBANKMENT
205.16
REINFORCED CONCRETE
65.40
REINFORCING STEEL BARS
8357.91
FORMS & FALSEWORK
265.00
MASONRY WORKS
196.34
PLUMBING WORKS
14.00
ELECTRICAL WORKS
58.00
PLASTERING WORKS
719.76
WOODEN DOORS
9.00
JALOUSIE WINDOW
12.00
METAL STRUCTURES (ROOF FRAMING)
317.98
ROOFING WORKS
317.98
CARPENTRY WORKS
21.28
METAL FURRING CEILING
276.63
PAINTING WORKS
354.78

Agg.tax P

1,400.00

8,204.12
16,467.15
55,798.05
62,170.36
68,155.56
57,735.48
31,430.56
4,000.00
19,614.36
97,159.35
5,768.06
3,939.96
66,495.16
40,030.44
8,204.12
30,018.96
25,009.35

2,000.00

P
P

21,216.00
3,600.00

P 93,162.00
P 116,730.59
P 52,780.00
P 93,705.00
P 145,806.25
P 52,980.00
P 62,460.00
P 237,937.26
P 142,962.80
P 24,605.00
P 91,167.00
P 50,710.25

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

P
P

8,736.00
1,200.00

18,720.00

P
P

30,600.00
3,600.00

2,400.00

1,816,361.40

600,201.04

92,072.00

1.67

1,816,363.08

P 43,859.20
P 291,189.05
P

316,307.00

UNIT
Lot
cu.m.
cu.m.
cu.m.
Kg.
Cu.m.
Sq.m.
Lin.m.
Outlet
Sq.m.
Set
Set
Sq.m.
Sq.m.
Sq.m.
Sq.m.
Sq.m.

UNIT COST ADJ.COST/ITEM


P 12,535.76 P
12,535.76
P
439.02 P
20,230.04
P
596.75 P 122,429.23
P
7,036.18 P 460,166.17
P
57.04 P 476,735.19
P
699.54 P 185,378.10
P
981.71 P 192,748.94
P
5,087.75 P
71,228.50
P
2,400.22 P 139,212.76
P
446.65 P 321,480.80
P
8,019.11 P
72,171.99
P
6,797.70 P
81,572.40
P
1,294.38 P 411,586.95
P
720.89 P 229,228.60
P
1,894.08 P
40,306.02
P
548.84 P 151,825.61
P
262.20 P
93,022.01
P 3,081,859.08

9.72

ramp
wf

0.91
0.4

6
9.3333333333
11
24.3333333333

18.3333333333

10

9.6666666667
6

50.4
50.4

0.0957177093
1.4955892083

3
3

37.8
37.8

0.10%
1.50%

3
2.3333333333
11
4.5833333333

1,335,258.44

1,541,451.93

1,680,664.69

2,002,145.50

21,192.00

#REF!

2,016,677.13

71,381.18

#REF!

455.00
693.00

295.75
346.50

325.33
381.15

318.50
485.10

878.00

439.00

482.90

614.60

42,888.84

2,796,705.44

182.00

P
P
P
P
P
P
P
P
P

2.97
5.32
2.43
0.59
2.74
0.05
0.82
55.33
92.21

#REF!

236.49
222.99
35.74

(0.01)

(0.00)

MARK-UP

VAT

COST/ITEM

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

1,734.70 P
2,799.42 P
16,941.73 P
63,677.82 P
65,970.64 P
25,652.57 P
26,672.52 P
9,856.60 P
19,264.29 P
44,486.55 P
9,987.17 P
11,287.99 P
56,955.51 P
31,720.85 P
5,577.55 P
21,009.61 P
12,872.33 P
426,467.85 P
P

596.94 P
963.33 P
5,829.95 P
21,912.66 P
22,701.66 P
8,827.50 P
9,178.48 P
3,391.83 P
6,629.18 P
15,308.61 P
3,436.76 P
3,884.40 P
19,599.40 P
10,915.70 P
1,919.33 P
7,229.78 P
4,429.60 P
146,755.11 P
573,222.96 P

12,535.76
20,229.90
122,428.93
460,165.89
476,734.86
185,377.55
192,748.15
71,228.43
139,212.83
321,480.76
72,171.99
81,572.35
411,587.33
229,229.79
40,306.00
151,825.35
93,021.53
3,081,857.40
3,081,859.08

P
12,535.76
P
20,229.90
P
122,428.93
P
460,165.89
P
476,734.86
P
185,377.55
P
192,748.15
P
71,228.43
P
139,212.83
P
321,480.76
P
72,171.99
P
81,572.35
P
411,587.33
P
229,229.79
P
40,306.00
P
151,825.35
P
93,021.53
P 3,081,857.40
P 3,081,857.40

P
P

(3,911.48)
(25,009.35)

575191.69
-21097.87

J.COST/ITEM
P
12,535.76
P
20,230.04
P
122,429.23
P
460,166.17
P
476,735.19
P
185,378.10
P
192,748.94
P
71,228.50
P
139,212.76
P
321,480.80
P
72,171.99
P
81,572.40
P
411,586.95
P
229,228.60
P
40,306.02
P
151,825.61
P
93,023.32
P 3,081,860.39

(1.67)

I. CONSTRUCTION OF STEEL STAIR

B. LABOR
Manpower
Construction Foreman
Welder

NO.
1
1

P
P

Rate/Day
300.00
280.00

Duration
#REF!
#REF!

Mark-up
Total Item Cost
Unit Cost
Total Adjusted Cost

10%

I. CONSTRUCTION OF STEEL STAIR & FLATFORM

Total cost
#REF!
#REF!

B. LABOR
Manpower
Construction Foreman

NO.
1

Rate/Day
300.00

Labor Cost

Duration
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

Materials+Labor
Mark-up
Total Item Cost
Unit Cost

10%

Total cost
#REF!

#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

Republic of the Philippines


Department of Public Works and Highways
Cordillera Administrative Region
OFFICE OF THE DISTRICT ENGINEER
Bangued, Abra
DATE:
Region:
District:
Name of Project:
Location:
Appopriation:

N/A
N/A

CONSTRUCTION OF 1 STOREY, 3 CL SCHOOL BLDG. Type of Structure:


Dalit Elementary School, Pilar, Abra No. of Spans:
P
3,102,592.44 No. of Storeys:

Source of Funds:
Limits:
Length:

No. of Classrooms/Beds:
Type of Structure:
No.of Days to Complete:

Classification:
Starting Date:

Type of Superstructure:
Mode of Implementation:

NO.
101
803
104
900
404
414
704
1002
1102
1027
1010
1009
403
1014
1003
Spl.1
1032

NO.
101
803
104
900
404
414
704
1002
1102
1027
1010
1009
403
1014
1003
Spl.1
1032

1
2
3
4
5
6
7
8
9

1-Jul-15

PROGAM OF WORK
CAR
Roadbed Width:
Abra Engineering District Pavement Width:

Upon Approval

ITEM/S OF WORK TO BE DONE

PERCENT

LABOR:
MATERIALS:
EQUIPMENT EXPENSES:
INDIRECT COST (VAT):
SOIL EXPLORATION:
ENG'G.,ADMIN.OVERHEAD:
CONST. CONTINGENCIES:
AGGREGATE TAX:
ROAD RIGHT OF WAY:

BREAKDOWN OF ESTIMATED EXPENDITURES


PERCENT
P
600,201.04
19.35
P
1,816,363.08
58.54
P
92,072.00
2.97
P
573,222.96
18.48
P
P
P

15,512.96
460.40
1,400.00

0.50
0.01
0.05

120
By Contract
EQUIPMENT
NEEDED

DESCRIPTION

REMOVAL OF STRUCTURES & OBSTRUCTIO


0.41
Minor tools
STRUCTURE EXCAVATION
0.66
1-Bagger conc. Mixer
EMBANKMENT
3.97
Cut-off machine
REINFORCED CONCRETE
14.93
Pipe threader / cutter
REINFORCING STEEL BARS
15.47
Welding machine
FORMS & FALSEWORK
6.02
Elec. Drill
MASONRY WORKS
6.25
PLUMBING WORKS
2.31
ELECTRICAL WORKS
4.52
PLASTERING WORKS
10.43
WOODEN DOORS
2.34
JALOUSIE WINDOW
2.65
METAL STRUCTURES (ROOF FRAMING)
13.36
ROOFING WORKS
7.44
CARPENTRY WORKS
1.31
METAL FURRING CEILING
4.93
PAINTING WORKS
3.02
Total:
100.00
ESTIMATED COST OF PREPARED WORK
ITEM/S OF WORK TO BE DONE
UNIT
QUANTITY
1.00
REMOVAL OF STRUCTURES & OBSTRUCTIO
Lot
46.08
STRUCTURE EXCAVATION
cu.m.
205.16
EMBANKMENT
cu.m.
65.40
REINFORCED CONCRETE
cu.m.
8357.91
REINFORCING STEEL BARS
Kg.
265.00
FORMS & FALSEWORK
Cu.m.
196.34
MASONRY WORKS
Sq.m.
14.00
PLUMBING WORKS
Lin.m.
58.00
ELECTRICAL WORKS
Outlet
719.76
PLASTERING WORKS
Sq.m.
9.00
WOODEN DOORS
Set
12.00
JALOUSIE WINDOW
Set
317.98
METAL STRUCTURES (ROOF FRAMING)
Sq.m.
317.98
ROOFING WORKS
Sq.m.
21.28
CARPENTRY WORKS
Sq.m.
276.63
METAL FURRING CEILING
Sq.m.
354.78
PAINTING WORKS
Sq.m.

AVAILABLE

2
2
1
1
1
2

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

UNIT COST
12,535.76
439.02
596.75
7,036.18
57.04
699.54
981.71
5,087.75
2,400.22
446.65
8,019.11
6,797.70
1,294.38
720.89
1,894.08
548.84
262.20

TOTAL PROJECT
COST(DIRECT &
INDIRECTCOST):
ENG'G.,ADMIN.
OVERHEAD:
CONST. CONT.:
AGGREGATE TAX:
ROAD RIGHT OF WAY:
SURVEY PLAN &

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

TOTAL COST
12,535.76
20,230.04
122,429.23
460,166.17
476,735.19
185,378.10
192,748.94
71,228.50
139,212.76
321,480.80
72,171.99
81,572.40
411,586.95
229,228.60
40,306.02
151,825.61
93,022.01
3,081,859.08

3,081,859.08

P
P
P
P

15,512.96
460.40
1,400.00
-

10
11
12

SURVEY PLAN & PREPARATION:


PUBLICATION FEE:
BILLBOARD:

PREPARED BY:
JUAN ANTONIO E. FLORENTINO
ARCHITECT II
APPROVED:

3,360.00

3,102,592.44
CHECKED BY:

PUBLICATION FEE:
SOIL EXPLORATION:
BILLBOARD:

0.11
0.00
100.00

P
P
P

3,360.00
-

3,102,592.44

SUBMITTED BY:

EMMANUEL T. COLLADO
ENGINEER II

CHONA LUISA A. RAMOS


CHIEF, Planning & Design Section

CONCURRED BY:
LORETO B. DACOROON

RONALD B. CASTILLO, CESO VI

CARETAKER

SCHOOL DIVISION SUPERINTENDENT

P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P

12,535.76
20,230.04
122,429.23
460,166.17
476,735.19
185,378.10
192,748.94
71,228.50
139,212.76
321,480.80
72,171.99
81,572.40
411,586.95
229,228.60
40,306.02
151,825.61
93,023.32
3,081,860.39

(0.00)

3,102,592.44
P

0.00

VAT
#REF!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
P
P
P

3,083,259.08
-

P
P
P
P

#REF!

I. HAULING COST OF FINE/COARSE AGGREGATES


HAULING DISTANCE =
50

KMS.
1 DUMPTRUCK WITH A CAPACITY OF 4 CU.M.
LOADING TIME =
5
UNLOADING TIME =
1
SLACK TIME =
6
12

LOADED TRIP =

50

KMS. X
20

60
KPH

MINS/HR

150

UNLOADED TRIP =

50

KMS. X
25

60
KPH

MINS/HR

120

TOTAL TIME =
NO OF HRS./TRIP =

282
60

282
=

4.7

MINS./HR.

Equipment Rental:
1- Dumptruck 6-8 tons, 4 cu.m.

P 807.00 /hour
P 6,456.00 /day

TOTAL COST PER TRIP =

P 6,456.00

X
6

4.7
HRS.

P 5,057.20
SAY

HAULING COST PER CU.M. =

FOR FINE AGGREGATES:


Pick-up price=
P 160.00
Hauling cost=
P 1,264.00

P 5,057.00 =
4
SAY

/cu.m.

(processed material)

FOR COARSE AGGREGATES:


Pick-up price=
P 160.00
/cu.m.
Hauling cost=
P 1,264.00

(processed material)

P 1,424.00

say

1,424.00

P 1,424.00

say

1,424.00

FOR Gravel pea:


Pick-up price=
P 400.00
Hauling cost=
P 1,264.00
P 1,664.00

say

1,664.00

/cu.m.

(processed material)

P 1,264.25 /CU.M.
P 1,264.00 /CU.M.

P 5,057.00

II. PRODUCTION COST OF BOULDERS


PICKING & STOCK PILING FROM RIVER BED
LABOR CAPACITY=
2
CU.M./DAY
EMPLOYING 7 LABORERS=
14
CU.M./DAY
LABOR RATE ( P 194.70 X 7)= P 1,362.90 / DAY
PRODUCTION COST OF BOULDERS

PRODUCTION COST = P 1,362.90


14
= P

II. HAULING COST OF BOULDERS


HAULING DISTANCE =

97.35 /CU.M.

40

KMS.
USING 1 PAYLOADER
1 DUMPTRUCK WITH A CAPACITY OF 4 CU.M.

LOADED TRIP =

LOADED TRIP =

40

40

KMS. X
15

KMS. X
20

LOADING TIME =

MINS.

UNLOADING TIME =
SLACK TIME =

1
2
8

MINS.
MINS.
MINS.

60

MINS/H =

160

MINS

60

MINS/H =

120

MINS

288

MINS

KPH

KPH
TOTAL TIME =

NO OF HRS./TRIP =

288
60 MINS./HR.

COST OF 1 DUMPTRUCK = P 5,672.00

X
8

4.8
HRS.

COST OF 1 PAYLOADER = P 6,648.00


X
8 (60 MINS./HR)

4.8 HOURS

3,403.20

69.25

3,472.45

TOTAL =

UNIT COST =

P 3,472.45
4

97.35

=
SAY

P
P

965.46 /CU.M.
965.00 /CU.M.

Quantity of conc.to be formed:

#REF!

PAINTING ( 2-Coats )
Wall Area:

Ceiling Area:

80

Total Area:

80

Duration:

A. MATERIALS
Description of Material/s Quantity
Boysen Flat Latex

Boysen Quick Dry

Paint Thinner

10

Concrete Neutraliz

Sand paper

28

Concrete Putty fille

Wood Paste fillers


Transhipment

3
0.5
Material cost

B. LABOR
Manpower

NO.

Construction Fore

Painter

Laborer

3
Labor Cost

Total Item Cost


Unit Cost

Total Adjusted Cost

PAINTING

#REF!

PAINTING

II. HAULING COST OF BUILDING MATERIALS


Equipment Rental:
1- Dumptruck 6-8 tons, 4 cu.m.
MINS.
MINS.
MINS.
MINS.
MINS

MINS

MINS
HOURS

P 807.00 /hour
P 6,456.00 /day

Manpower:
6-Laborers @ P 25.00/man hr.

Loading Time:
Unloading Time:
Slack Time:
Total
Travel Velocity:
Loaded:
Unloaded:
Distance:
Loaded:
35.00
=

105.00

Unloaded:

35.00

84.00

Total=

P 150.00 /hour
P 1,200.00 /day
20.00
20.00
6.00
46.00

minutes
minutes
minutes
minutes

15.00
20.00
35.00
km. X
20.00
minutes

Kph
Kph
Km.
60.00
Kph

km. X
60.00
25.00 Kph
minutes

Min./hour

Min./hour

235.00 minutes
3.92 hours

Hauling Cost of Building Materials:


Equipment Rental:
6-Laborers @ P 25.00/man hr.
1-Dumptruck (5.00 cu.m.)
Capacity of 1-unit Dumptruck=
6.0 Tons=
5 Cu.yard=
4"CHB

P 150.00 /hour x
P 807.00 /hour x
4
6000
1687.5
500

Hauling Cost of 40 kg.Portland cement:


6000
kgs./ 40 kgs.per bag =
150
= P
P

3,748.25 per trip


150 bags/trip
24.99
24.99 /bag

cu.m.
Kgs.
Bd.ft
Pcs./trip

bags/trip

Pick-up at Site
P 240.00 P 264.99

Hauling Cost per kilograms:


= P 3,748.25 per trip
6000 Kgs.
P
0.62 /Kgs.
0.62

Pick-up at Site
P 35.00 P 35.62

Hauling Cost per Bd.Ft.:


= P 3,748.25 per trip
1687.5 Bd.ft
P
2.22 /Bd.Ft.
2.22

Pick-up at Site
P 36.00 P 38.22

Hauling Cost per CHB.:


= P 3,748.25 per trip
500 Pcs./trip
P
7.50 /Pcs.
7.50

4" Chb
Pick-up at Site
P 9.00 P 16.50
5" Chb
Pick-up at Site

3.92
3.92
Total

=
=
=

P
587.50
P 3,160.75
P 3,748.25

P 11.00

Cu.m.

18.50

Sq.m.
Sq.m.
Sq.m.
C.D.
Unit
Gal.
Gal.
Gal.
Gal.

Total Cost

Pcs.

#REF!

Lit.

#REF!

Lit.

#REF!

Trip

#REF!

Material cost

#REF!

VAT

#REF!

Mark-up

#REF!
#REF!
#REF!

Rate/Day

#REF!

P277.30

#REF!

P209.90

#REF!

P194.70
Labor Cost Total cost
VAT

#REF!

Mark-up

#REF!
#REF!

Total Item Cost

#REF!

Unit Cost

#REF!

Total Adjusted Cost

#REF!
#REF!
#REF!
#REF!
#REF!

MARK-UP
#REF!
#REF!
#REF!
#REF!
#REF!

P
#REF!

#REF!
#REF!
#REF!

80.00

#REF!

per trip

You might also like