MRP - Tutorial SAP
MRP - Tutorial SAP
MRP - Tutorial SAP
A separate run occurs for the MPS items; they are not included in
the MRP run.
Processing Key
1. Net change (NETCH): In this run, the system considers those
materials in the planning run from their last MRP run which have
undergone some changes pertaining to receipts and issues or any
stock changes.
2. Net Change in Planning Horizon (NETPL): In this run, the system
considers those materials in the planning run from their last MRP
run which have undergone some changes pertaining to receipts
and issues or any stock changes. It considers the requirements in
a pre-defined planning horizon, unlike NETCH key which considers
the total futuristic requirements.
3. Regenerative Planning (NEUPL): It plans all the materials for the
MRP Run irrespective of the changes they undergo. This plan is
not so widely used. It takes a long time to obtain the final result.
2.
Planning Mode
1. Adapt planning data: It only processes the changed data.
2. Re explodes BOM and Routing: Read BOM and routing data again
for the existing orders.
3. Delete and recreate planning data: It completely deletes the
planning data (all receipts) and creates again.
3.
Scheduling
1. Basic Scheduling: MRP calculates only basic dates for the orders
and in house production time for the material master is used.
2. Lead Time Scheduling: The production dates are determined by
the lead time scheduling for planned orders. The routings are
read to schedule and calculate the capacity requirements on work
centers.
Enter your manufacturing Plant for which you want to take MRP
run.
2.
3.
4.
Enter "3" for schedule lines which means MRP will generate
schedule lines for raw materials having scheduling agreement.
5.
Enter "1" in MRP List and system will create MRP list similar to
stock /requirement list for later analysis of previous MRP run.
6.
7.
Enter Scheduling indicator "2" which means MRP will do lead time
scheduling and consider routing times to calculate planned order
dates.
The system asks you nicely to re-check your input parameter because
the MRP run is going to reschedule and overwrite all existing data. Are
you sure??? If so, press enter.
Are you really, really sure that you want to continue??? If so, then again
press enter.
Step 2) System will take some time to calculate the material
requirement.
1.
Input the material code for which you want to run MRP.
Enter your manufacturing Plant code for which you want to take
MRP run.
3.
4.
5.
Enter "3" for schedule lines which means MRP will generate
schedule lines for raw materials having scheduling agreement.
6.
Enter "1" in MRP List and system will create MRP list similar to
stock /requirement list for later analysis of previous MRP run.
7.
8.
Enter Scheduling indicator "2" which means MRP will do lead time
scheduling and consider routing times to calculate planned order
dates.
The system asks you nicely to re-check your input parameter because
the MRP run is going to reschedule and overwrite all existing data. Are
you sure??? If so, press enter.
Are you 100% sure that you really want to continue??? If so, then again
press enter.
Step 2) System will take some time to calculate the material
requirement.
1.
After the calculation is done, a report will appear. Here, you can
see how many materials were planned.
1.
Input the material for which you want to run MPS. Here we have
taken ID "13967476".
2.
Enter your manufacturing Plant "INA2" for which you want to take
MPS run.
3.
4.
5.
Enter "3" for schedule lines which means MPS will generate
schedule lines for raw materials having scheduling agreement.
6.
Enter "1" in MRP List and system will create MRP list similar to
stock /requirement list for later analysis of previous MPS run.
7.
8.
Enter Scheduling indicator "2" which means MRP will do lead time
scheduling and consider routing times to calculate planned order
dates.
Click
to next screen after filling all the fields, the system will show
message
, click again, if everything is O.K.
Step 2) In this step, we are going to generate the interactive planning
data by which simultaneously you can see the planning results.
1.
2.
2.
to go to the
1.
Troubleshooting
There might be the case wherein material master record does not
exist. For this, you need to create the material master for the material
before running MPS/MRP.