Professional Documents
Culture Documents
1609-C01-Cheng Kim Hua Workshop Mat-All
1609-C01-Cheng Kim Hua Workshop Mat-All
JKR , SgSTT
12/9/2016
JKR , SgSTT
2) Contract Documentation
Related specifications ,
3) Problems , issues , practice
4) Miti Study on Export Potential for Tunnel / Pipe Jacking / HDD
Expertise
Cheng Kim Hua
PE, FIEM, M.SgSTT
ciwise1@gmail.com
+6011-3995 4759 / +65 9455 1399
36
37
Typical contents
Prequalification's
Tender invitation
Form of tender , earnest money , guarantee
Specifications
Drawings
Standards drawings
Fidic / Conditions of contract etc
1 Dec JKR Pipe Jacking
38
2) Contract Documentation
Related specifications ,
3) Problems , issues , practice
4) Miti Study on Export Potential for Tunnel / Pipe Jacking / HDD
Expertise
Cheng Kim Hua
PE, FIEM, M.SgSTT
ciwise1@gmail.com
+6011-3995 4759 / +65 9455 1399
1 Dec JKR Pipe Jacking
39
40
2-1
1 Contract Documentation Specifications see pdf JPP-D14,100 km
41
Drawings-section
43
44
45
46
47
48
49
50
51
Section1 cont.
52
Bill Of Quantity -1
53
BQ-2
54
55
56
BQ-5-Pipe linings
57
BQ-6-Protection
58
BQ-7-Other expenses-summary
59
Section 1 General -2
1.19 WATER SERVICE , 1.20 FIRE HYDRANT
1.21 TEMPORARY MAINTENANCE OR
RELOCATION
1.22 RIGHT OF ACCESSIBILITY
1.23 CHANGES DUE TO EXISTING UTILITY
1.27 TEMPORARY WORKS ,1.28
NOTIFICATION OF PUBLIC
1.29 CONDITIONS AFFECTING WORK
1 Dec JKR Pipe Jacking
60
Section 1 General -3
1.30 EXISTING UTILITIES
1.31 DAMAGE AND INTERFERENCE
1.32 DEMOLITION , 1.35 PROTECTION OF
COMPLETED WORK
1.36 CLEANING UP
1.37 SAFETY AND SECURITY REQUIREMENTS AND
ACCIDENT PREVENTION
1.38 NOISE CONTROL
1.39 POLLUTION CONTR
1 Dec JKR Pipe Jacking
61
62
63
64
65
66
Polymer pipes
67
68
69
70
The successful development of this new product and technology fills the
blank of domestic ductile iron pipe jacking, which will play a very good
demonstration effect on opening up new areas of Xinxing ductile iron
pipes. At the same time, this construction also provided detailed technical
1 Dec JKR Pipe Jacking
71
data of pipe jacking for several
major water institute in the domestic.
Others Materials
Mild steel
Hdpe Pipe
72
73
74
75
76
77
Testing
78
80
81
CCTV-Defects
82
83
Pipeline-measurement
11.16 MEASUREMENT OF SEWER INSTALLATION
The measurement for payment for sewer installation
shall be in meters and measured along
84
STANDARD SPECIFICATIONS
to
responsible
13.1 GENERAL
underground pipelines from one manhole to
another using trenchless method.
The envisaged construction method involves
jacking a sewer pipe.
This Specification is
intended to be primarily functional in nature
and to define in general terms the work to be
accomplished.
The Contractor shall have full discretion to
select the method of tunnel
construction, subject to review and approval by
1 Dec JKR Pipe Jacking
the S.O.
85
86
88
89
91
92
Design
93
design
94
95
96
Soil
97
Typical RC Pipe
98
Jacking force
See prof Shou lecture
99
100
101
102
103
RC Caisson
104
Insitu or sinking
Cast and sink in
105
Cast caisson
Obstruction service need protected
106
107
108
109
30 m shaft caisson
110
111
Caisson problems
Services some times in way need
protect or use other method
Need jet grouting ( clay in Beach
Road )
Can some times do as sink in
caisson
1 Dec JKR Pipe Jacking
112
114
Sheet pile -2
115
116
117
Thrust wall
118
13-12-4 Grouting
Where chemical stabilization of soil is used, a
chemical grout shall be pressure injected into
the soil over and ahead of the pipe jacking to
stabilize the soil. The chemical grout used
shall have a demonstrated history of
success for stabilizing soils similar to that
through which the pipe is to be jacked.
119
120
Jacking data
5. Maximum pipe jacking pressures per shove
and rams used.
6. Location, elevation and brief soil
7. Groundwater control operations and piezo
metric levels.
8. Observation of lost ground or movement
and settlement of existing structure.
9. Indications of damaged pipe joint or pipe.
10. Any unusual conditions or event.
11. Operation shutdown periods or other
interruptions in the work and reason.
1 Dec JKR Pipe Jacking
121
122
123
Long/curve jakcing
long distance or curved pipe jacking in the
supply of the guidance information to the
machine operator.
This is the positioning of the laser reference in a
stable position once the machine has
advanced to a point where the laser beam can
no longer activate the Target from the start
shaft.
At this point the laser reference most be
positioned within the moving pipe. As soon as
the laser reference is no longer in a stable
position it is necessary to accommodate this
fact. Use gyro
1 Dec JKR Pipe Jacking
124
125
126
127
128
129
130
131
Base failure
132
133
Instrumentation
To record movements
Set alert and work suspension level
For tunnel continuous monitoring
134
135
Ground movement
136
137
138
139
140
141
Impact
Mitigation measurement
142
143
Scheme
144
145
146
147
148
149
150
151
Box jacking
152
153
154
Inclinometer
155
156
Tilt meter
157
Settlement marker
158
Risk management
159
160
161
162
163
164
165
166
Trial holes
167
Investigation method
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
2B4-MATERIALS
185
186
2b-6-Jacking contd
187
188
2B-8-Settlement / lighting
189
2B-9-Compressed Air
190
191
192
1 of 41.
2 of 41.
3 of 41.
4 of 41.
5 of 41.
6 of 41.
7 of 41.
8 of 41.
9 of 41.
10 of 41.
11 of 41.
12 of 41.
13 of 41.
14 of 41.
15 of 41.
16 of 41.
17 of 41.
18 of 41.
19 of 41.
20 of 41.
21 of 41.
22 of 41.
23 of 41.
24 of 41.
25 of 41.
26 of 41.
27 of 41.
28 of 41.
29 of 41.
30 of 41.
31 of 41.
32 of 41.
33 of 41.
34 of 41.
35 of 41.
36 of 41.
37 of 41.
38 of 41.
39 of 41.
40 of 41.
41 of 41.
S
S 14.1
S 14.2.1
S 14.2.2
S 14.2.3
S 14.2.4
Page 1 of 3
S 14.2.5
S 14.2.6
to monitor settlement
S 14.2.7
vcp
S 14.2
S 14.2.1
S 14.2.2
Materials
Pipes to be vcp or rcp .
S 14.2.4
S 14.2.5
S 14.2.6
S 14.2.7
pipes to be mature
steel collars- BS 4360 Grade 43
S 14.2.8
S 14.2.9
S 14.2.3
S 14.3
S 14.3.1
to include Calculation of
force and others
usually 28 days
Jacking operations
contractor filly responsible for
materials, equipment ,and
facilities for jacking
Page 2 of 3
S 14.3.2
S 14.3.3
S 14.3.4
S 14.3.5
need design
experience to be verified
S 14.3.6
S 14.3.7
to be endorsed by PE
S 14.3.8
S 14.3.9
S 14.3.10
S 14.3.11
complete tunnels to be
watertight . To carry any remedial
works
S 14.3.13
arrange closed CCTV For pipes
smaller than 900 mm .Cleaning
prior to Cctv
S 14.4
cement grouting
S 14.4.1
prevent voids outside of pipe , fill
eth grout when happen
S 14.4.2
immediate as jacking complete
pressure grout jacked section
S 14.3.12
S 14.4.3
S 14.4.4
S 14.4.5
S 14.4.6
S 14.5.2
S 14.6
S 14.7
S 14.7.1
S 14.7.2
S 14.7.3
S 14.7.4
Page 3 of 3
Limit of settlement
front face max 50 mm, and max
allowed after void grouted is 100
mm
crossing road , include in method
to ensure all settlement are
arrested
lighting and electrical work
engage likened electrical workers
compressed air and locks
maintain pressure to supply air
demand
equipment incl compressors, air
receivers , piping's etc .Separate
locks for materials and personnel
, FOR long tunnel- electrically
operated
airlocks to operational within and
outside
if pressure exceed 1 Bar , all
safeguards to be taken include
medical locks and physicians