12/9/2016

Presented by Ir. Cheng KimHua


Beng(Hon),DHE, FIEM,MISTT , PE
Tunnelcon@gmail.com
+65-94551399, +6011-3995 4759

JKR , SgSTT

cv cheng kim hua


Ir. CHENG KIM HUA graduated BE (Hons) from Monash University, Australia
in 1976 and obtained his post graduate diploma in Hydraulic and Land
Development from Delft International Institute (Holland) in 1982. He served
the Malaysias government from 1976 85, and has been with the Private sector
in Singapore, Malaysia, India, Thailand, and Middle East. Mr. Cheng is a
registered Professional engineer in Singapore and Malaysia. He has been in
the engineering / construction works since 1976. A total of 36 years involving in
the planning, design, and construction supervision and business development
of engineering works including civil and infra and trenchless /Tunnel works/
structures.
He has worked and travelled extensively, and covered countries including
Singapore, Malaysia, Thailand, Vietnam, India and Middle East. Mr. Cheng
served in many professional bodies such as the vice president of the
Institution of Engineers, Malaysia, and Board Member of the Highway
Authority, Malaysia and the Board of Engineers, Malaysia. He has also served
in the continuing Education committee of the PE Board, Singapore and as
Treasurer of Singapore Concrete Institute. He is widely travelled and have
worked in trenchless areas in SE Asia and the Middle East for over 25 years and
is currently project Director with Alliance Water & Environ Sdn. Bhd. He has
also just completed a report as chairman for MITI on the export potential of
tunnel and trenchless industry. Ir. Cheng will cover the Development and
export potential for tunnel Trenchless technology within Malaysian
Companies.

12/9/2016

Presented by Ir. Cheng KimHua


Beng(Hon),DHE, FIEM,MISTT , PE
Tunnelcon@gmail.com
+65-94551399, +6011-3995 4759

JKR , SgSTT

cv cheng kim hua


Ir. CHENG KIM HUA graduated BE (Hons) from Monash University, Australia
in 1976 and obtained his post graduate diploma in Hydraulic and Land
Development from Delft International Institute (Holland) in 1982. He served
the Malaysias government from 1976 85, and has been with the Private sector
in Singapore, Malaysia, India, Thailand, and Middle East. Mr. Cheng is a
registered Professional engineer in Singapore and Malaysia. He has been in
the engineering / construction works since 1976. A total of 36 years involving in
the planning, design, and construction supervision and business development
of engineering works including civil and infra and trenchless /Tunnel works/
structures.
He has worked and travelled extensively, and covered countries including
Singapore, Malaysia, Thailand, Vietnam, India and Middle East. Mr. Cheng
served in many professional bodies such as the vice president of the
Institution of Engineers, Malaysia, and Board Member of the Highway
Authority, Malaysia and the Board of Engineers, Malaysia. He has also served
in the continuing Education committee of the PE Board, Singapore and as
Treasurer of Singapore Concrete Institute. He is widely travelled and have
worked in trenchless areas in SE Asia and the Middle East for over 25 years and
is currently project Director with Alliance Water & Environ Sdn. Bhd. He has
also just completed a report as chairman for MITI on the export potential of
tunnel and trenchless industry. Ir. Cheng will cover the Development and
export potential for tunnel Trenchless technology within Malaysian
Companies.

Session 2 1 Dec 2015-JKR Pipe Jacking


1) Formation Society

2) Contract Documentation
Related specifications ,
3) Problems , issues , practice
4) Miti Study on Export Potential for Tunnel / Pipe Jacking / HDD
Expertise
Cheng Kim Hua
PE, FIEM, M.SgSTT
ciwise1@gmail.com
+6011-3995 4759 / +65 9455 1399

1 Dec JKR Pipe Jacking

36

Session 2- Contract and Standard

1 Dec JKR Pipe Jacking

37

2-1 Contract Documentation

Typical contents
Prequalification's
Tender invitation
Form of tender , earnest money , guarantee
Specifications
Drawings
Standards drawings
Fidic / Conditions of contract etc
1 Dec JKR Pipe Jacking

38

2-01 -1 Dec JKR- Session 2


1) Formation Society

2) Contract Documentation
Related specifications ,
3) Problems , issues , practice
4) Miti Study on Export Potential for Tunnel / Pipe Jacking / HDD
Expertise
Cheng Kim Hua
PE, FIEM, M.SgSTT
ciwise1@gmail.com
+6011-3995 4759 / +65 9455 1399
1 Dec JKR Pipe Jacking

39

2-02contract documentations See D05-Folder

1 Dec JKR Pipe Jacking

40

2-1
1 Contract Documentation Specifications see pdf JPP-D14,100 km

1 Dec JKR Pipe Jacking

41

2-2 Specifications -general

SECTION 1 GENERAL REQUIREMENTS


1.1 APPLICATION
1.2 WORKMANSHIP ..
1.3 STANDARDS AND SUPPLEMENTARY
SPECIFICATIONS
1.4 GENERAL SITE PLAN
1.5 CHECKING OF DRAWINGS
1.6 OTHER CONTRACTORS
1.7 SURVEY AND SETTING OUT OF THE WORKS
1.8 COMPLIANCE WITH LAWS AND REGULATION
1.9 SUPERVISION AND INSPECTION
1.10 SUPERINTENDENCE
AND LABOUR COMPETENCY42
1 Dec JKR Pipe Jacking
OL

Drawings-section

1 Dec JKR Pipe Jacking

43

Drawing- completed pipe roof -1

1 Dec JKR Pipe Jacking

44

Drawing- completed pipe roof -2

1 Dec JKR Pipe Jacking

45

Drawing- completed pipe roof -3

1 Dec JKR Pipe Jacking

46

Drawing- completed pipe roof -4

1 Dec JKR Pipe Jacking

47

Drawing- completed pipe roof -5

1 Dec JKR Pipe Jacking

48

Drawing- completed pipe roof -6

1 Dec JKR Pipe Jacking

49

Drawing- completed pipe roof -7

1 Dec JKR Pipe Jacking

50

Drawing- completed pipe roof -8

1 Dec JKR Pipe Jacking

51

Section1 cont.

1.11 MATERIAL IN GENERAL


1.12 TESTING AND REJECTION
1.13 SPOIL TIPS
1.14 PROTECTION OF PROPERTY AND
UTILITIES
1.15 CONTACT OF UTILITY OWNERS
1.16 MAINTENANCE AND REPAIR
1.17 NOTIFICATION TO AGENCIES AND THE
S.O.
1.18 PRIVATE SEWERS AND SANITARY
FACILITIES
1 Dec JKR Pipe Jacking

52

Bill Of Quantity -1

1 Dec JKR Pipe Jacking

53

BQ-2

1 Dec JKR Pipe Jacking

54

BQ-3 Grouting and removal machine

1 Dec JKR Pipe Jacking

55

BQ-4 PIPE MATLS

1 Dec JKR Pipe Jacking

56

BQ-5-Pipe linings

1 Dec JKR Pipe Jacking

57

BQ-6-Protection

1 Dec JKR Pipe Jacking

58

BQ-7-Other expenses-summary

1 Dec JKR Pipe Jacking

59

Section 1 General -2
1.19 WATER SERVICE , 1.20 FIRE HYDRANT
1.21 TEMPORARY MAINTENANCE OR
RELOCATION
1.22 RIGHT OF ACCESSIBILITY
1.23 CHANGES DUE TO EXISTING UTILITY
1.27 TEMPORARY WORKS ,1.28
NOTIFICATION OF PUBLIC
1.29 CONDITIONS AFFECTING WORK
1 Dec JKR Pipe Jacking

60

Section 1 General -3
1.30 EXISTING UTILITIES
1.31 DAMAGE AND INTERFERENCE
1.32 DEMOLITION , 1.35 PROTECTION OF
COMPLETED WORK
1.36 CLEANING UP
1.37 SAFETY AND SECURITY REQUIREMENTS AND
ACCIDENT PREVENTION
1.38 NOISE CONTROL
1.39 POLLUTION CONTR
1 Dec JKR Pipe Jacking

61

1.3 Standard specs


STANDARDS AND SUPPLEMENTARY SPECIFICATIONS
1.3.1 Malaysian, American or British Standards and Codes
of Practice
relevant Malaysian, American or British Standard or
Code of Practice
current on the date fixed for receipt of tenders.
1.3.2 Other Standards
Compliance with other Standards or Codes of Practice
proposed by the Contractor at the
time of tendering provided that these other Standards or
Code of Practice are equivalent
1 Dec JKR Pipe Jacking

62

Section 10 pipe materials


10.1 GENERAL FOR PIPELINE, materials , VCP ,
RCP Jacking pipe
10.5 HIGH DENSITY POLYETHYLENE PIPES
(HDPE) AND FITTINGS, 10.6 GRP 10.7
MATERIAL FOR FORCE MAIN
10.8 DUCTILE IRON PIPE (DI) AND FITTINGS
10.9 CAST IRON PIPES (CI) AND FITTINGS
10.10 MILD STEEL PIPES (MS) AND FITTINGS
10.11 HIGH DENSITY POLYETHYLENE (HDPE)
PIPES & FITTINGS
10.12 SACRIFICIAL LINING
1 Dec JKR Pipe Jacking

63

GRP-Polymer pipe- high standard


demanded -

1 Dec JKR Pipe Jacking

64

Grp information needed

1 Dec JKR Pipe Jacking

65

New Materials- Polymer pipe

1 Dec JKR Pipe Jacking

66

Polymer pipes

1 Dec JKR Pipe Jacking

67

Polymer pipe properties

1 Dec JKR Pipe Jacking

68

Materials section 10 vcp

1 Dec JKR Pipe Jacking

69

Ductile iron pipe

1 Dec JKR Pipe Jacking

70

DI Pipe Jacking China Zhengzhou direct force main replace


traditionally- pipe sleeve n Normal DI
pipe
Largest China made DI Jacking pipe-3.2km done:
Published: 2013-07-29

Recently, China's first ductile iron pipe jacking projectZhengzhou


Wulongkou sewage treatment plant to Xinli plant reclaimed water pipeline

3.2 km pipeline has been completed Xinxing Cathay International Group ,


Xinxing Ductile Iron Pipes Company (000778)s ductile iron pipe jacking
products was first successfully applied
advantages of ductile iron pipe jacking products in construction process,
foreign countries have largely applied the products, but that is the first
time in the China.

The successful development of this new product and technology fills the
blank of domestic ductile iron pipe jacking, which will play a very good
demonstration effect on opening up new areas of Xinxing ductile iron
pipes. At the same time, this construction also provided detailed technical
1 Dec JKR Pipe Jacking
71
data of pipe jacking for several
major water institute in the domestic.

Others Materials
Mild steel
Hdpe Pipe

1 Dec JKR Pipe Jacking

72

Section 11-pipeline installation


SECTION 11-PIPE INSTALLATIONS
11.1 GENERAL FOR PIPELINE INSTALLATION
.,Scope, define,
11.2 INSTALLATION OF PIPES
11.3 SPECIAL LAYING METHODS : JACKING
11.4 VITRIFIED CLAY PIPE (VCP) ..
11.5 REINFORCED CONCRETE PIPE (RCP)...
11.6 PIPES FOR FORCE MAIN
11.8 CUTTING PIPES
11.9 JOINTS AND JOINTING MATERIALS
11.10 CHANGES IN LINE AND GRADE
1 Dec JKR Pipe Jacking

73

Section 1-pieline instln


11.11 STREAM AND RIVER CROSSING
11.15 SEWER LATERALS ....
11.16 MEASUREMENT OF SEWER
INSTALLATION
11.17 TESTING PIPELINES
11.18 CCTV INSPECTION
11.19 SEWER CLEANING
11.20 CLEANLINESS OF PIPELINE
11.21 TEMPORARY SURFACING
11.22 LIABILITY IN PIPE INSTALLATION
11.23 TESTING, ETC., NOT SEPARATELY VALUED
11.24 MAINTENANCE IN PIPE INSTALLATION
WORK
1 Dec JKR Pipe Jacking

74

Pipe line installation

Major areasGeneral installation


Method of pipe laying
For force main
Jointing of pipes
Measurement of sewer
Testing /Cctv
1 Dec JKR Pipe Jacking

75

Pipeline- laying by pipe jakcing for


approval of SO

1 Dec JKR Pipe Jacking

76

Pipe jacking pits( see later , record)

1 Dec JKR Pipe Jacking

77

Testing

Low pressure water test


Cctv

1 Dec JKR Pipe Jacking

78

13.12.4 Cctv-FOR Pipe less than 900


mm
The Contractor shall arrange for closed circuit
television (CCTV) to inspect newly constructed
pipeline less thn900mm in diameter laid by the
jacking method.
The CCTV recording shall be carried out in the
presence of the S.O. or his representative and a
video
tape recording ,a written report shall be submitted to
Any defects detected shall be rectified immediately
and the rectification work shall be confirmed by
CCTV
1 Dec JKR Pipe Jacking
79

CCTV To survey up to 350 m Specialist contractors trained -

1 Dec JKR Pipe Jacking

80

Cctv-cont.-interpret and action taken


To interpret acceptability areas of
contentious Singapore- pre contract and
post installation

1 Dec JKR Pipe Jacking

81

CCTV-Defects

1 Dec JKR Pipe Jacking

82

Cctv mean and tolerance level

1 Dec JKR Pipe Jacking

83

Pipeline-measurement
11.16 MEASUREMENT OF SEWER INSTALLATION
The measurement for payment for sewer installation
shall be in meters and measured along

centerline of the pipe from inner wall of


manholes/structures and all wyes and
specials will
No extras will be allowed for cutting pipes
to waste on account of sewer laterals or for pipe
closures at manholes as detailed on the
drawings.
1 Dec JKR Pipe Jacking

84

Pipe Jacking standard

STANDARD SPECIFICATIONS

SECTION 13 PIPE JACKING -contractor

to

responsible

13.1 GENERAL
underground pipelines from one manhole to
another using trenchless method.
The envisaged construction method involves
jacking a sewer pipe.
This Specification is
intended to be primarily functional in nature
and to define in general terms the work to be
accomplished.
The Contractor shall have full discretion to
select the method of tunnel
construction, subject to review and approval by
1 Dec JKR Pipe Jacking
the S.O.

85

Section 13- Pipe Jacking Docs


Submittal to include description and
drawings, schedules, and other documents
defining Contractors plans and procedures
for tunnelling.
To design and Specification requirements.
Review: -The S.O. will review submitted shop
drawing and data for compliance with the
requirements
All structural designs and other engineered
components shall be signed by the
Contractors Professional Engineer
Tunnelling Work Plan, including shop
drawings, shall address

1 Dec JKR Pipe Jacking

86

Section 13- Pipe Jacking Docs cont. 2


tunnelling
Tunnelling Work Plan, including shop drawings, shall address
1) TBM or shield
2) arrangement drawings and technical specifications
modifications), track record of the proposed type of machine,
qualification and training records for the equipment operator,
and a copy of the manufacturers operation manual.
3) Method of controlling line and grade of tunnelling operation.
4) Method and details of spoil removal including equipment
type and numbers, surface storage, processing and disposal.
5) Ventilation system. ,Lighting layout. , Electrical system
6) Proposed contingency plans for critical phases and areas of
tunnelling.
7) routing techniques to be used for over-excavation including
equipment, pumping and injection procedures, pressure grout
types, and mixtures.
8) Details of the pipe jacking method and operation including
jack set-up for jack thrust1 Dec JKR Pipe Jacking
87

Machine and performance

machine (TBM), provided the Contractor can


demonstrate the Works in accordance a prerequisite
of any method of tunnel construction, which also
provides for man-access to the tunnel excavation
face.
D. Contractor shall be responsible for the final
constructed product, materials, and tools used,
and for furnishing the labour and qualified
superintendents necessary for the method of
tunnel construction. E. The Contractor must
demonstrate that the chosen method will control the
flow of water and prevent loss of soil /face stable
1 Dec JKR Pipe Jacking

88

Typical requirement- specific machine data

1 Dec JKR Pipe Jacking

89

Section 13- Pipe Jacking Docs cont. 2


method

Details of method proposed to cushion and


distribute jacking forces at pipe joints. Plans for
storage and handling of pipe.
Groundwater control methods.
Quality Control Methods: Supervision: Supervisory
control to ensure that work is performed in
accordance with the Drawings, Specifications and
Tunnelling Work Plan. Line and Grade: Procedures
for surveying, controlling and checking line and
grade, including field forms. Tunnelling Observation
and Monitoring: Procedures for preparing and
submitting daily logs 1Operation
Data, and Article
Dec JKR Pipe Jacking
90
Control of Line and Grade.

Section 13- Pipe Jacking Docs cont. 2


method

Products and Materials: A plan for testing


and submittal of test results to demonstrate
compliance ,for testing and acceptance.
Safety: Procedures to meet all applicable
safety requirements of relevant authorities.
Means for emergency evacuation and selfrescue.
Protection of shaft including traffic barriers,
accidental or unauthorized entry, and falling
objects
1 Dec JKR Pipe Jacking

91

Design of jakcing pipes


By manufacturer Soil parameters

1 Dec JKR Pipe Jacking

92

Design

1 Dec JKR Pipe Jacking

93

design

1 Dec JKR Pipe Jacking

94

Soil profile Soil investigation-Every


200 m or so

1 Dec JKR Pipe Jacking

95

General soil map -

1 Dec JKR Pipe Jacking

96

Soil

See various soil reports


MMC- 100 km
D44 etc
Singapore Sembawang
1 Dec JKR Pipe Jacking

97

Typical RC Pipe

1 Dec JKR Pipe Jacking

98

Jacking force
See prof Shou lecture

1 Dec JKR Pipe Jacking

99

Pits or shaft working

1 Dec JKR Pipe Jacking

100

Design shafts code

1 Dec JKR Pipe Jacking

101

Design shafts code cont.

1 Dec JKR Pipe Jacking

102

Typical shafts caisson

1 Dec JKR Pipe Jacking

103

RC Caisson

1 Dec JKR Pipe Jacking

104

Insitu or sinking
Cast and sink in

1 Dec JKR Pipe Jacking

105

Cast caisson
Obstruction service need protected

1 Dec JKR Pipe Jacking

106

Steel caisson Beach RD Mtd

1 Dec JKR Pipe Jacking

107

3.2 Steel Caisson

1 Dec JKR Pipe Jacking

108

Caisson steel Beach Rd

1 Dec JKR Pipe Jacking

109

30 m shaft caisson

1 Dec JKR Pipe Jacking

110

1 Dec JKR Pipe Jacking

111

Caisson problems
Services some times in way need
protect or use other method
Need jet grouting ( clay in Beach
Road )
Can some times do as sink in
caisson
1 Dec JKR Pipe Jacking

112

Rock define as 100 MPA or more

Rock 13.12 EXCAVATION AND JACKING OF PIPE


Rock in Pipe Jacking
A. Rocks shall be as defined in Section for Earthworks.
B. Excavation in solid rock in pipe jacking shall mean
excavation in rock found in ledges or
masses in its original position that have Unconfined
Compressive Strength (qu,UCS) not less
than 100 MPa.
C. The Contractor to notify the Engineer as soon as he
encounters rock or hard material s.
D Engineer to assess the Contractor claim on rock in the pipe
jacking, the Contractor is to establish the actual subsurface
conditions encountered along the sewer alignment at the
grade of the pipes to be jacked to determine the extent of
rock at no additional cost to the Employer.
E. Geotechnical information
shall be obtained from
1 Dec JKR Pipe Jacking
113
undisturbed samples taken by boring or
additional test pits planned to be excavated along the

Sheet pile shaft -1

1 Dec JKR Pipe Jacking

114

Sheet pile -2

1 Dec JKR Pipe Jacking

115

1 Dec JKR Pipe Jacking

116

Typical sheet pile cal

1 Dec JKR Pipe Jacking

117

Thrust wall

1 Dec JKR Pipe Jacking

118

13-12-4 Grouting
Where chemical stabilization of soil is used, a
chemical grout shall be pressure injected into
the soil over and ahead of the pipe jacking to
stabilize the soil. The chemical grout used
shall have a demonstrated history of
success for stabilizing soils similar to that
through which the pipe is to be jacked.

1 Dec JKR Pipe Jacking

119

13.14 jacking operating data


1. Location of TBM face or shield by
station and progress during shift .
2. Hours worked per shift.
3. Completed field forms -line and
grade, with achieved tolerance relative
to design alignment. Copies of steering
control data will generally acceptable.
4. Thrusting pressures and rate of
thrusting
1 Dec JKR Pipe Jacking

120

Jacking data
5. Maximum pipe jacking pressures per shove
and rams used.
6. Location, elevation and brief soil
7. Groundwater control operations and piezo
metric levels.
8. Observation of lost ground or movement
and settlement of existing structure.
9. Indications of damaged pipe joint or pipe.
10. Any unusual conditions or event.
11. Operation shutdown periods or other
interruptions in the work and reason.
1 Dec JKR Pipe Jacking

121

13-14 Line and grade


check control each week or for each
75 m

Each day ( 24 hours to submit) records


When out to correct and / or work stopped
Line and Grade; The pipes shall be jacked into place
true to line and level. The maximum tolerance
allowable in the displacement of the centerline of the
jacked pipe from the design centerline

is 75 mm in the horizontal plane


and 25 mm in the vertical plane but there
shall be no
backfill at any point.
1 Dec JKR Pipe Jacking

122

13-21 Long distance curve jakcing


Accuracy of jakcing ( workmanship ) more so
important fro this case
Always avoid sudden changes in direction and
in point loading the outer edges of the pipe ,
tightness of the drive is to be maintained.
Changes in direction cause more resistance to
the movement of the machine and all the
following pipes that in turn require greater
hydraulic forces to overcome the increased
friction.
1 Dec JKR Pipe Jacking

123

Long/curve jakcing
long distance or curved pipe jacking in the
supply of the guidance information to the
machine operator.
This is the positioning of the laser reference in a
stable position once the machine has
advanced to a point where the laser beam can
no longer activate the Target from the start
shaft.
At this point the laser reference most be
positioned within the moving pipe. As soon as
the laser reference is no longer in a stable
position it is necessary to accommodate this
fact. Use gyro
1 Dec JKR Pipe Jacking

124

Long curve jakcing


4. Control surveys shall be taken in static
situations. This absolute measurement shall
be applied to the guidance of the machine in
the dynamic situation where the hydraulic
forces
used and varying geological conditions cause
short-term anomalies in the position of the
elements of the pipeline and components
within it.
1 Dec JKR Pipe Jacking

125

Jacking force in sand- PhD

1 Dec JKR Pipe Jacking

126

PhD -Jacking force


Sarawak Swinburne

1 Dec JKR Pipe Jacking

127

Problems- Machine stuck


Soil harder or un-stable compared to envisaged
Choice of wrong machine( lack of fund , try luck
, unforeseen)
Litigations- rock too high winning by in
contractor recently but hard to win
Tunnel project more Monet more
Insufficient data
Contractor all take responsibility
1 Dec JKR Pipe Jacking

128

Problem of design against

No intermediate jacking station


Insufficient preparation
Skills
Expertise
Consultancy advice not sought prior
Fire fighting
Safety
Quality( 75 mm and 25 mm - )
CCTV see more problems
1 Dec JKR Pipe Jacking

129

Typical failures In projects-cannot


move

1 Dec JKR Pipe Jacking

130

Rescue shaft-Bell caisson( reduce


traffic disruption)

1 Dec JKR Pipe Jacking

131

Base failure

1 Dec JKR Pipe Jacking

132

Tilting of existing canal walls

1 Dec JKR Pipe Jacking

133

Instrumentation
To record movements
Set alert and work suspension level
For tunnel continuous monitoring

1 Dec JKR Pipe Jacking

134

Pipe Roof - Monitoring


Bouna Vista Pipe Roof
Construction Impact assessment :

1 Dec JKR Pipe Jacking

135

Ground movement

1 Dec JKR Pipe Jacking

136

1 Dec JKR Pipe Jacking

137

1 Dec JKR Pipe Jacking

138

1 Dec JKR Pipe Jacking

139

Loss to annular Spec


Due to steering

1 Dec JKR Pipe Jacking

140

1 Dec JKR Pipe Jacking

141

Impact

Mitigation measurement

1 Dec JKR Pipe Jacking

142

1 Dec JKR Pipe Jacking

143

Scheme

1 Dec JKR Pipe Jacking

144

Project layout sensitive services t

1 Dec JKR Pipe Jacking

145

1 Dec JKR Pipe Jacking

146

1 Dec JKR Pipe Jacking

147

1 Dec JKR Pipe Jacking

148

1 Dec JKR Pipe Jacking

149

1 Dec JKR Pipe Jacking

150

1 Dec JKR Pipe Jacking

151

Box jacking

1 Dec JKR Pipe Jacking

152

SG Monitoring Sewer Jacking

1 Dec JKR Pipe Jacking

153

1 Dec JKR Pipe Jacking

154

Inclinometer

1 Dec JKR Pipe Jacking

155

Ground Water level -within alert level

1 Dec JKR Pipe Jacking

156

Tilt meter

1 Dec JKR Pipe Jacking

157

Settlement marker

1 Dec JKR Pipe Jacking

158

Risk management

1 Dec JKR Pipe Jacking

159

1 Dec JKR Pipe Jacking

160

1 Dec JKR Pipe Jacking

161

1 Dec JKR Pipe Jacking

162

1 Dec JKR Pipe Jacking

163

Design to reduce risk

1 Dec JKR Pipe Jacking

164

Beware of challenging ground

1 Dec JKR Pipe Jacking

165

1 Dec JKR Pipe Jacking

166

Trial holes

1 Dec JKR Pipe Jacking

167

Investigation method

1 Dec JKR Pipe Jacking

168

Planning stage need identify risks

1 Dec JKR Pipe Jacking

169

Points in contract management fro


success in Trenchless

1 Dec JKR Pipe Jacking

170

1 Dec JKR Pipe Jacking

171

1 Dec JKR Pipe Jacking

172

1 Dec JKR Pipe Jacking

173

1 Dec JKR Pipe Jacking

174

1 Dec JKR Pipe Jacking

175

1 Dec JKR Pipe Jacking

176

1 Dec JKR Pipe Jacking

177

1 Dec JKR Pipe Jacking

178

MITIGATE Areas Singapore/USA

1 Dec JKR Pipe Jacking

179

1 Dec JKR Pipe Jacking

180

1 Dec JKR Pipe Jacking

181

2-B1- JKR Specs

JKR Sabah specs


on Pipe Jacking
1 Dec JKR Pipe Jacking

182

2-B2-JKR Specs-P Jacking


Pl see JKR Relevant specs D06-JKR-Specs Pipe Jacking , pipe works, Manhole
See D07- Comments on Pipe Jacking
Compared with MMC ( 100 km and IWK )
See D08 -IWK Civil and .. Sewerage specs

1 Dec JKR Pipe Jacking

183

2-B3- General Specs - Comments

1 Dec JKR Pipe Jacking

184

2B4-MATERIALS

1 Dec JKR Pipe Jacking

185

2B-5- Pipe Jacking operations

1 Dec JKR Pipe Jacking

186

2b-6-Jacking contd

1 Dec JKR Pipe Jacking

187

2-B7- CEMENT GROUTING

1 Dec JKR Pipe Jacking

188

2B-8-Settlement / lighting

1 Dec JKR Pipe Jacking

189

2B-9-Compressed Air

1 Dec JKR Pipe Jacking

190

1 Dec JKR Pipe Jacking

191

1 Dec JKR Pipe Jacking

192

1 of 41. JKR Specs on Pipe Jacking etc

1 of 41.

2 of 41. JKR Specs on Pipe Jacking etc

2 of 41.

3 of 41. JKR Specs on Pipe Jacking etc

3 of 41.

4 of 41. JKR Specs on Pipe Jacking etc

4 of 41.

5 of 41. JKR Specs on Pipe Jacking etc

5 of 41.

6 of 41. JKR Specs on Pipe Jacking etc

6 of 41.

7 of 41. JKR Specs on Pipe Jacking etc

7 of 41.

8 of 41. JKR Specs on Pipe Jacking etc

8 of 41.

9 of 41. JKR Specs on Pipe Jacking etc

9 of 41.

10 of 41. JKR Specs on Pipe Jacking etc

10 of 41.

11 of 41. JKR Specs on Pipe Jacking etc

11 of 41.

12 of 41. JKR Specs on Pipe Jacking etc

12 of 41.

13 of 41. JKR Specs on Pipe Jacking etc

13 of 41.

14 of 41. JKR Specs on Pipe Jacking etc

14 of 41.

15 of 41. JKR Specs on Pipe Jacking etc

15 of 41.

16 of 41. JKR Specs on Pipe Jacking etc

16 of 41.

17 of 41. JKR Specs on Pipe Jacking etc

17 of 41.

18 of 41. JKR Specs on Pipe Jacking etc

18 of 41.

19 of 41. JKR Specs on Pipe Jacking etc

19 of 41.

20 of 41. JKR Specs on Pipe Jacking etc

20 of 41.

21 of 41. JKR Specs on Pipe Jacking etc

21 of 41.

22 of 41. JKR Specs on Pipe Jacking etc

22 of 41.

23 of 41. JKR Specs on Pipe Jacking etc

23 of 41.

24 of 41. JKR Specs on Pipe Jacking etc

24 of 41.

25 of 41. JKR Specs on Pipe Jacking etc

25 of 41.

26 of 41. JKR Specs on Pipe Jacking etc

26 of 41.

27 of 41. JKR Specs on Pipe Jacking etc

27 of 41.

28 of 41. JKR Specs on Pipe Jacking etc

28 of 41.

29 of 41. JKR Specs on Pipe Jacking etc

29 of 41.

30 of 41. JKR Specs on Pipe Jacking etc

30 of 41.

31 of 41. JKR Specs on Pipe Jacking etc

31 of 41.

32 of 41. JKR Specs on Pipe Jacking etc

32 of 41.

33 of 41. JKR Specs on Pipe Jacking etc

33 of 41.

34 of 41. JKR Specs on Pipe Jacking etc

34 of 41.

35 of 41. JKR Specs on Pipe Jacking etc

35 of 41.

36 of 41. JKR Specs on Pipe Jacking etc

36 of 41.

37 of 41. JKR Specs on Pipe Jacking etc

37 of 41.

38 of 41. JKR Specs on Pipe Jacking etc

38 of 41.

39 of 41. JKR Specs on Pipe Jacking etc

39 of 41.

40 of 41. JKR Specs on Pipe Jacking etc

40 of 41.

41 of 41. JKR Specs on Pipe Jacking etc

41 of 41.

Pipe Jacking Specs

S
S 14.1
S 14.2.1
S 14.2.2

S 14.2.3
S 14.2.4

Page 1 of 3

JKR section 14-Pipe Jacking


title
note
additional
General
where specified works by pipe
jakcing
Plan to be submitted to Engineer to include all method
can refer to other references
for approval prior
statement , plants ,
workability , risk assessment
etc
contractor to check soil
to carry out additional soil
test
soil instable and high water
suggest all by earth
For safety and worker welfare
table .maintain face and prevent pressure or slurry unless
loss of ground. No manual jacking otherwise
or semi mechanical for dia
smaller than 1.2 m

S 14.2.5

submit method proposed . And


manufacturer , crew , experience

submit equipment maker


at tender -

SG -KL MMC , has a list of


equipment and also list of
parameters fro machines .Client
consultant to evaluate and
enquire suitability

S 14.2.6

to monitor settlement

inclinometer , near shafts


settllement markers at 2m
interval along road .Allow
alert and suspend level

see s 14.5 Movement of


structures to be 50 m m at
head, and max 100 mm at
surface after .

S 14.2.7

inspect location and conditions

vcp

vcp can crack easily , SG m=now


have alternative . For 450 and
above still use RCP

S 14.2
S 14.2.1

S 14.2.2

Materials
Pipes to be vcp or rcp .

S 14.2.4

All 900 mm and larger to have 2


grout holes each pipe
vcp pipe to 600 mm ( and jacking
force )
RCP to design for 1.5 or 1 H

S 14.2.5

Submit full details of pipe's

S 14.2.6
S 14.2.7

pipes to be mature
steel collars- BS 4360 Grade 43

S 14.2.8
S 14.2.9

shield to fit to 1st pipe


use jacking ring

S 14.2.3

S 14.3
S 14.3.1

to include Calculation of
force and others
usually 28 days

Jacking operations
contractor filly responsible for
materials, equipment ,and
facilities for jacking

1511-Section 2 - JKR specs

Now may have to be stainless


steel
to spread load - also packer ???

Mean all contractor own design(


sg need QP ./PE Contractor
design)

Pipe Jacking Specs

Page 2 of 3

S 14.3.2

prior work submit to SO detail


schedule of jacking operations
and must have proven
procedures as submitted

S 14.3.3

compressed air to comply Cl


14.07
where chemical stabilization is
used , pressure grout the
chemical
where mechanical shield used
,proof it is used in similar soil

S 14.3.4

S 14.3.5

need design

experience to be verified

S 14.3.6

after start jakcing work


continuously 24 hours

in SG , KL some laces dont allow


such 24 hours- may be day or
night or steel plate over shaftneed to review this

S 14.3.7

jack true to line and grade . Max


is 50 mm horizontal and 20 mm
vertical
prevent relative movement
between pipes
thrust block etc may be needed pits to equip with rail etc

to stringent should be internal


50 mm . Not back flow

contractor to deisgn jacking and


receving pits-- full proposal to
submit
Contractor to monitor progress
.Daily record to be maintained
and provide to Engineer

to be endorsed by PE

S 14.3.8
S 14.3.9

S 14.3.10

S 14.3.11

complete tunnels to be
watertight . To carry any remedial
works
S 14.3.13
arrange closed CCTV For pipes
smaller than 900 mm .Cleaning
prior to Cctv
S 14.4
cement grouting
S 14.4.1
prevent voids outside of pipe , fill
eth grout when happen
S 14.4.2
immediate as jacking complete
pressure grout jacked section

record form to design and


submit . Some machine have
automatic recording- not
necessary

S 14.3.12

S 14.4.3
S 14.4.4
S 14.4.5
S 14.4.6

grout system to main free from


dust ,.
mixing and placing of grout- type
approved - continuous flow
after grout, maintain pressure by
cocks and wait for set
For PVC/HDPE ensure watertight
prior to welding

1511-Section 2 - JKR specs

Cctv - mmc specs have details

Pipe Jacking Specs


S 14.5
S 14.5.1

S 14.5.2

S 14.6

S 14.7
S 14.7.1
S 14.7.2

S 14.7.3
S 14.7.4

Page 3 of 3
Limit of settlement
front face max 50 mm, and max
allowed after void grouted is 100
mm
crossing road , include in method
to ensure all settlement are
arrested
lighting and electrical work
engage likened electrical workers
compressed air and locks
maintain pressure to supply air
demand
equipment incl compressors, air
receivers , piping's etc .Separate
locks for materials and personnel
, FOR long tunnel- electrically
operated
airlocks to operational within and
outside
if pressure exceed 1 Bar , all
safeguards to be taken include
medical locks and physicians

1511-Section 2 - JKR specs

monitoring procedure - how long


after works ?
Risk and hazard plus
contingencies measures

1 -1511-RA Slurry Jacking works

2 -1511-RA Slurry Jacking works

3 -1511-RA Slurry Jacking works