Podium Slab - Inspection Workflow

Sequence of Work
Podium Slab

Lean Concrete
- Installation of Formwork

Inspection Flow
- Survey Data shall be taken for Record

Verification
Documents

A-Beam Support/Formwork (pre-concreting)

- Inspection by ARUP prior to Concreting


work

- WIR Form, PreConcreting Checklist

- Installation Rebar (Pre-Concreting Work)

- Inspection by ARUP prior to Concreting


work

- WIR Form, PreConcreting Checklist

- Final Inspection Before Concrete

- Inspection by RSP (to Attach Inspection


Record Approval by KTA & ARUP)

GE1-4

- Survey Data

- WIR form, Pre- Inspection by RSP prior to reinforcement Concreting Checklist


installation, As-built soffit slab level to be
provided during the inspection

- Inspection by KTA for MEP Opening,


conduits and fittings

GE1-3

Date of Inspection

- WIR Form, Preconcreting Checklist

- WIR Form, PreConcreting Checklist

- Concreting Work (During Concrete Pour)

- Inspection by ARUP

- WIR, Concreting
Checklist

- Post Concreting Work Inspection - Curing,


Slab/Surface Finishing

- Inspection by ARUP & RSP

- WIR Form, postConcreting Checklist

16/5/2016

24/5/2016

20/5/2016

28/5/2016

20/5/2016

28/5/2016

23/5/2016

30/5/2016

23/5/2016

30/5/2016