Professional Documents
Culture Documents
Design and Construction of A Deep Excavation in Soft Soils Adjacent To The Shanghai Metro Tunnels
Design and Construction of A Deep Excavation in Soft Soils Adjacent To The Shanghai Metro Tunnels
933
Abstract: This paper presents the design and construction of a deep excavation for building foundations in saturated
soil. This deep excavation was of particular interest because it was located above and beside the Shanghai Metro tunnels. The twin Shanghai Metro tunnels had to be in full operation during the deep excavation. Potential large deformation of the twin tunnels was one of the main concerns during the design and construction for the deep excavation. The
paper discusses in detail the criteria and measures for controlling the soil and tunnel deformation. The measures included cast-in-place concrete diaphragm walls with bracing structural members, pumping consolidation, cementsoil
mix pile systems, and rational excavation procedures. A simplified theoretical method was proposed to estimate the increment in undrained shear strength in a soft clay layer due to pumping consolidation. Furthermore, conventional finite
element methods were used to predict the soil vertical and horizontal displacements induced by the excavation. Using
the design and construction methods discussed in the paper, the settlement and horizontal displacement of the tunnels
were successfully controlled within 5.0 mm and 9.0 mm, respectively. The curvature of longitudinal deformation curve
of the tunnels was less than 1/15 000. The horizontal displacement of the braced diaphragm walls was less than 0.12%
of the total excavation depth.
Key words: Metro tunnels, saturated soft soil, deep excavation, design, construction, ground improvement, case studies.
Rsum : Cet article prsente la conception et la construction dune excavation profonde pour la construction de fondations dans des sols saturs mous. Cette fondation profonde tait particulire en ce quelle tait situe au-dessus et
ct des tunnels du mtro de Shanghai. Les tunnels du mtro sont jumels et devaient rester en opration continuelle
durant les travaux pour lexcavation profonde. Une dformation potentiellement importante des tunnels jumels constituait une des principales proccupations lors de la conception et de la construction de lexcavation profonde. Cet article
discute en dtail les critres et des mesures prises pour contrler le sol et la dformation des tunnels. Les mesures
comportaient des parois moules en bton avec des membrures de contreventement, de la consolidation par pompage,
des systmes de pieux mixes de solciment et des procdures rationnelles dexcavation. On a propos une mthode
thorique simplifie pour estimer laccroissement de la rsistance au cisaillement dans la couche dargile molle d la
consolidation par pompage. De plus, on a utilis des mthodes dlments finis conventionnelles pour prdire les dplacements horizontaux et verticaux du sol induits par lexcavation. En utilisant les mthodes de conception et de construction discutes dans cet article, le tassement et le dplacement horizontal des tunnels ont t contrls avec succs
moins de 5,0 mm et 9,0 mm respectivement. La courbure de la courbe de dformation longitudinale des tunnels tait
infrieure 1/15 000. La dformation horizontale de la paroi moule taye tait infrieure 0.12 % de la profondeur
totale de lexcavation.
Mots cls : tunnels de mtro, sol mou satur, excavation profonde, conception, construction, amlioration du terrain,
tudes de cas.
[Traduit par la Rdaction]
Hu et al.
948
1. Introduction
Shanghai is one of the largest and most well-known cities
in China and around the world. Shanghai has a population
exceeding 13 million and a municipal area of about
Received 5 February 2002. Accepted 1 May 2003. Published
on the NRC Research Press Web site at http://cgj.nrc.ca on
17 September 2003.
Z.F. Hu and J. Zhou. Department of Geotechnical
Engineering, Tongji University, Shanghai, 200092,
Peoples Republic of China.
Z.Q. Yue1 and L.G. Tham. Department of Civil
Engineering, The University of Hong Kong, Pokfulam Road,
Hong Kong, Peoples Republic of China.
1
I:\cgj\CGJ40-05\T03-041.vp
September 12, 2003 1:33:21 PM
2. Background
2.1. Shanghai Metro tunnels
Shanghai Metro line 1, as one of the main components of
the municipal transportation network, is located in the down-
doi: 10.1139/T03-041
934
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:17 PM
Hu et al.
935
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:18 PM
936
Fig. 2. Plan of the design and construction for the deep excavation at Shanghai New World Commercial City Complex. All dimensions
in metres.
Fig. 3. Geological cross section II perpendicular to the Metro tunnels. All dimensions in metres.
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:19 PM
Hu et al.
937
Fig. 4. Geological cross section IIII parallel to the Metro tunnels. All depths in metres.
Table 1. Profile and geological description of the soils located along Shanghai Metro line 1.
Period
3
Soil
classification
Layer
No.
Thickness
(m)
Artificial fill
1-1
0.52.0
Creek fill
1-2
1.03.0
Silty clay
2-1
1.53.5
Sandy silt
2-2
2.010.0
1.58.0
4.013.0
Clay
5-1
7.020.0
Silty clay
5-2
3.020.0
Silty clay
2.04.5
Silty sand
7-1
5.010.0
the east and west excavation sites were arranged in the same
axis lines. Thus, the members constitute a stable bracing
system as shown in Fig. 2.
In addition, a reinforced concrete lock beam was poured
along the top of the whole diaphragm walls. As a result, the
overall stiffness of the bracing structural system for the east
and west excavations was enhanced. Consequently, both the
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:20 PM
938
Table 2. Geotechnical properties and parameters of the foundation soils at the Shanghai New World Commercial City Complex.
Layer
No.
Soil classification
2
3
4
5-1
5-2
6
7-1
Silty
Very
Very
Clay
Silty
Silty
Silty
clay
soft silty clay
soft clay
clay
clay
sand
Thickness (m)
Layer bottom
depth (m)
Liquid limit,
LL (%)
Plastic
limit, PL
(%)
1.102.15
4.705.80
7.208.40
9.5010.90
11.0013.20
2.403.50
8.3510.20
3.03.8
8.59.2
16.016.9
25.527.4
38.038.8
40.941.8
49.752.0
38.4
39.0
46.8
39.7
33.6
30.9
22.2
25.1
27.0
24.1
20.2
19.1
Coefficient
of earth
pressure at
rest, K0
Water
content,
w (%)
0.49
0.52
34.0
43.4
48.6
36.6
33.3
22.6
27.6
Note: c and were obtained from the consolidated quick direct shear test.
Table 3. Results of in situ vane shear tests for the undrained shear strength, Su, of soft soil layer 4 before
and after pumping.
Soil classification
Value
Minimum
Maximum
Mean
19
29
22
27
35
30
42
21
36
Fig. 5. Cross section of the design and construction for the deep excavation at Shanghai New World Commercial City Complex. All
dimensions in metres.
the support of the bracing structural system described previously showed that the horizontal maximum displacement of
the diaphragm walls would be about 28.5 mm, and the maximum settlement of the ground adjoining the walls would be
about 23.1 mm. Such limited displacements and settlement
would not severely affect the foundation excavation and
building structure construction safety and the environment
around the building. These displacements would affect some
special areas closely adjacent to the operating Metro tunnels,
however. This issue had to be resolved for the safe operation
of the Metro tunnels.
The bracing structural system has adequate strength, stiffness, and stability. Its vertical stiffness coefficient EI/h4
was estimated at about 6.17 or 11.44 MPa, where E
(= 21 700 MPa) and I (= 1.0 0.83 / 12 = 0.0427 m4) are the
elastic modulus and the moment of inertia of the cross section of the diaphragm walls, respectively; and h (= 3.5 or
3.0 m) is the vertical spacing of the bracing members. In
Shanghai, a bracing structural system for excavation pits can
be considered structurally stable if its vertical stiffness coefficient EI/h4 is greater than 2.0 MPa. Thus the bracing structural system was considered structurally stable.
2003 NRC Canada
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:21 PM
Hu et al.
939
Unit weight,
(kN/m3)
Void
ratio, e
Modulus of
deformation,
Es (MPa)
18.8
17.6
17.2
18.2
18.3
22.0
18.9
0.95
1.22
1.37
1.05
0.98
0.67
0.81
4.58
2.93
2.45
4.37
5.81
8.60
14.47
Cohesion,
c (kPa)
Angle of
internal
friction, ()
Horizontal
permeability
coefficient, Kh
(cm/s)
Vertical
permeability
coefficient, Kv
(cm/s)
14.5
7.0
7.5
13.0
10.0
36.5
5.0
11.5
14.0
9.5
11.0
17.0
15.5
23.0
7.66105
1.27105
1.19106
3.17105
1.41206
1.13107
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:21 PM
940
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:22 PM
Hu et al.
941
Fig. 7. Plan of cementsoil mixed piles for strengthening the foundation pit. All dimensions in millimetres.
Fig. 8. Plan of the construction sequence for the east portion of the deep excavation at Shanghai New World Commercial City Complex. All dimensions in metres.
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:23 PM
942
Fig. 9. Profile of the construction sequence for the east portion of the deep excavation at Shanghai New World Commercial City Complex. All dimensions in metres.
Fig.v 10. Sketch showing the relation between the seepage velocity V = (Vx + Vy v+ Vz ) in an anisotropic soil and the water head
gradient vector J.
Ki =
2(KhJh) 2 + (KvJv) 2
2KhJh2 + KvJv2
Li =
2Kh2
Kv2
Ut = 1
2Ki Es
8
exp
t
2
2
4Li w
9 2Ki Es
8
exp
t
2
9
4L2i w
2003 NRC Canada
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:23 PM
Hu et al.
K0
Su = wHw(1 K0)
Ut
2 K0
943
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:24 PM
944
Materials
Reinforced concrete for tunnels
Diaphragm walls
Cementsoil mixed piles
Bearing piles of building
Strengthened soil body
Layer 2 silty clay
Layer 3 very soft silty clay
Layer 4 very soft silty clay
Layer 5-1 clay
Layer 5-2 silty clay
Layer 6 silty clay
Layer 7 silty sand
Unit weight,
(kN/m3)
Cohesion,
c (kPa)
Angle of internal
friction, ()
25.0
25.0
18.5
24.0
17.8
250
30
Modulus of
deformation
(MPa)
Poissons
ratio
21 700
21 700
500
15 000
100
5.0
5.0
3.0
5.0
4.0
8.0
27.5
0.20
0.20
0.28
0.20
0.30
0.42
0.40
0.40
0.40
0.40
0.40
0.40
Note: For unit weight, cohesion, and angle of internal friction values for layers 27. see Table 2.
Fig. 11. Predicted contours of the horizontal displacement (mm) distribution for the soil and tunnels due to the deep excavation at the
east portion.
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:25 PM
Hu et al.
945
Fig. 12. Predicted contours of the vertical displacement (mm) distribution for the soil and tunnels due to the deep excavation at the
east portion.
Fig. 13. Predicted contours of the horizontal displacement (mm) distribution for the soil and tunnels due to the deep excavation at the
east and west portions.
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:26 PM
946
Fig. 14. Predicted contours of the vertical displacement (mm) distribution for the soil and tunnels due to the deep excavation at the
east and west portions.
8. Conclusions
In this paper we have presented the design and construction of the deep excavation of a commercial building closely
above and beside the Shanghai Metro tunnels. From the
studies, we make the following conclusions:
(1) For deep excavations in saturated soft soils and closely
adjacent to the twin Metro tunnels, it is very important
to adopt deformation control based design and construction measures.
(2) For the deep excavation discussed in this paper, the
combined design and construction measures have successfully resulted in maintaining the measured deformations within the criteria that were required to control
deformation of the operating Metro tunnels. These measures include the diaphragm walls with bracing members, pumping consolidation for saturated soft clay soils
below the excavation, cementsoil mix piles behind the
diaphragm walls and around the twin tunnels, and rational excavation procedures for reduction of immediate
soil deformation.
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:27 PM
Hu et al.
Fig. 15. Comparison of the predicted and measured horizontal
displacements of the diaphragm wall with depth.
947
Fig. 16. Variation of the measured horizontal displacement of the
north bound tunnel along its longitudinal direction.
References
deep excavation in soft soils surrounding the Metro tunnels, which were in full operation during the excavation.
It was also critical to select correct values for the mechanical parameters in the theoretical predictions. Good
knowledge and experience of the local soft soil conditions and properties were assets in the selection of the
parameter values for prediction.
(6) The soft clay layer 4 shows high cross-anisotropy in soil
permeability. Such cross-anisotropy was examined and
taken into account in the analysis of the undrained shear
strength increment due to dumping consolidation. It
would be useful and interesting to further examine the
cross-anisotropy in the soil shear strength and modulus
and its effect on the soil deformation due to deep excavation, although such an effect might not be important.
(7) Lastly, it is noted that the deep excavation and other
building construction activities have been completed for
more than 3 years and both the commercial buildings
and the Metro tunnels continue to function well.
Acknowledgements
The authors would like to thank the Research Grants
Council of the Hong Kong SAR Government for financial
support and the Editor, Professor A.J. Valsangkar, Associate
Editor, and two peer reviewers for their valuable comments
and suggestions, which have enhanced the paper presentation.
Ki =
Kx2Jx2 + K 2y J 2y + Kv2Jv2
Kx Jx2 + K y J 2y + KvJv2
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:28 PM
948
v
head gradient vector J. Equation [A1] can be reduced as follows:
[A2]
Ki =
2(KhJh) 2 + (KvJv) 2
2KhJh2 + KvJv2
K H
Vi = Ki Ji = i
Li
Vi =
As a result, we have the following equation for the drainage path length:
[A5]
We further assume Vi =
+ Vy2
+ Vv2
Vi =
2Vh2 + Vv2
[A7]
Vi = Jh
Kv2(Jv
J h)
Li =
Li =
2K E 1
9 2Ki Es
8
t
exp 2 i s t + exp
2
4Li w 9
4L2i w
[A14] K1 =
[A11] Ut = 1
9 2
2 1
T + exp
T + ...
exp
4
4 9
K0
2 K0
K0
[A18] Su = wHw(1 K0)
U
2 K0
K0
[A19] Su = wHw(1 K0)
Ut
2 K0
I:\cgj\CGJ40-05\T03-041.vp
September 10, 2003 3:03:28 PM