Earthwork Design Report
Earthwork Design Report
1.0
INTRODUCTION
Project Location
The proposed site is located along the main road between Kaki Bukit and
Padang Besar in Perlis as indicated in the Key Plan in Figure 1 and
Location Plan in Figure 2.
10-270-GLK/EW/001
Project Description
The existing SMK Raja Puan Muda Tengku Fauziah has the following
facilities:
(a)
8 blocks of classroom building
(b)
1 canteen
(c)
2 prayer halls (surau)
(d)
1 dining hall
(e)
1 MPV building
(f)
1 block of agricultural building (bangunan pertanian)
(g)
2 blocks of student hostel
(h)
3 blocks of teacher quarters
(i)
1 football field
(j)
1 volleyball court
(k)
Several stores, garages and parking facilities
KPM plans to demolish some existing features occupying the
development site such as the volleyball and tennis courts and some
structures to make way for some new buildings. This is to increase the
capacity of the school to accommodate increasing number of students.
Some of the new facilities to be built are:
(a)
1 new administration office building
(b)
1 new library building
(c)
1 new workshop building
(d)
1 new academic block
1.3
Site Photographs
2
10-270-GLK/EW/001
During a site visit on 05 May 2010, some site photographs were taken
and shown as below:
10-270-GLK/EW/001
10-270-GLK/EW/001
10-270-GLK/EW/001
2.0
SCOPE OF WORK
(b)
3.0
EARTHWORK DESIGN
3.1
Reference
Design Criteria
The proposed new platform levels for buildings shall be above the
flood level for the development area as obtained from JPS.
(b)
The proposed new platform levels shall take into consideration the
existing surrounding platform levels.
(c)
(d)
The cut and fill quantity calculation shall allow a 10% factor for
swelling and shrinkage of earth.
10-270-GLK/EW/001
(g)
(i)
3.3
(h)
Proposed
Earth Platform
Level
(m RL)
Proposed
Finished Level
(m RL)
General
49.5
49.5
Building
49.5
49.7
49.0 48.3
49.5 48.8
Road
The cut and fill earth volume is calculated using a computer software
called Terramodel (Version 10.41). The earth volumes can be calculated
using average end area method or the higher accuracy surface to surface
method.
A 10% swelling and shrinkage factor is applied in the calculation. The
detail earthwork volume report is attached in Appendix B together with
the proposed platform layout for analysis and a 3D visualisation. The
results summarised below:
Total Fill Quantity (m3)
Total Cut Quantity (m3)
Balance Fill to be imported (m3)
3.4
3,880
992
2,888
10-270-GLK/EW/001
www.infobanjir.water.gov.my
The data is assembled and the 75th percentile is calculated using
Microsoft Excel equation function and presented in Appendix C. The
dimensions of the sediment trap can be summarised in the table below:
Top of water level dimension
(width x length)
Base of pond dimension
(width x length)
Settling Zone Depth (m)
Storage Zone Depth (m)
Total depth with freeboard
Outlet pipe sizing
Emergency spillway sizing
17 m x 36m
14m x 33 m
0.6 m
0.3 m
1.4 m
Nil
2.5 m x 0.3m
Among the other erosion and sediment control measures proposed for
this development are:
(a)
(b)
(c)
(d)
(e)
4.0
CONCLUSION
10-270-GLK/EW/001
The earth platform levels for general, building and road area have been
designed mostly to match the adjoining existing roads and platforms. Unless
the flood level is specifically imposed by JPS, the existing main road level is
taken as above the flood level. However, for safe design a confirmation by JPS is
necessary.
The earth cut and fill quantity is calculated with a balance fill of about 2,888 m 3.
Also proposed are sediment traps, wash through, temporary earth drains, earth
bunds, check dam and turfing as measures to check on the soil erosion as a
result of exposing bare earth during earthwork construction. The design of the
sediment trap is in reference to the provision in MASMA.