ADES ENGINEERING PTE LTD

PROJECT: PROPOSED EXTENSION, ADDITIONS AND ALTERATION OF EXTG 7 - STOREY NURSING HOME TO BECOME 8-STOREY
NURSING HOME WITH SUPERVISORY HEALTH CARE FACILITIES ON LOT 01402A PT 02390W PT MK21 AT NO.70 BUANGKOK VIEW
(HOUGANG PLANNING AREA)

Progress Claim No. 18 Dated: 23/01/2017

SCHEDULE OF BREAKDOWN PRICES

S/N Description Contract Work Done This Claim Remarks


$ % $

1 Design, supply and installation of Sanitary/Sewer System including


producing of post construction CCTV and report with all piping Pre&Post survey done by
$2,800.00 0% $0.00
connection to new Inspection Chamber and from last IC to public HKC.
sewer.
2 Design and construct new Inspection Chamber with all pipes New ICs fully completed with
$18,100.00 100% $18,100.00
connection covers.
3 Design, supply and install new sewerage waste and vent stacks
1)ZONE-1 STACK PIPES
with connection to inspection chamber including vent pipes to roof.
CONNECT TO LEVEL-2 IC-
01.
2)ZONE-2 STACK PIPES
CONNECT TO NEW IC-02
$13,400.00 90% $12,060.00 3)ZONE-03 STACK PIPE
AND GI PIPE CONNECT TO
EXISTING IC AND VENT
PIPE COMPLETED UNTIL
ROOF PHASE-2
WORK WILL CONTINUE.
4 Supply and installation of all piping connections from fittings to
1)ZONE-1 &2 LEVEL-2 TO
floor wastes/floor traps and water closets to main stack
LEVEL-8 SANITARY
SERVICES COMPLETED.
2)ZONE-3 LEVEL-1 TO
$140,000.00 90% $126,000.00
LEVEL-6 SANITARY
SERVICES COMPLETED
PHASE-2 WORK WILL
CONTINUE.
5 Design, supply and installation of potable water supply pipes after
the Main meter to all fittings in 1)WATER MAIN FROM
the building including supply and installation of BULK METER TO LEVEL-5
transfer tanks with pumps to top up the storage tanks at the lower COMPLETED. 2)ZONE-
roof including down feed water supply with booster pumps 1 LEVEL-2 TO LEVEL-8
installation. PLUMBING SERVICES
COMPLETED.
3)ZONE-3 LEVEL-1 TO
LEVEL-5 PLUMBING
SERVICES COMPLETED
$330,300.00 90% $297,270.00
4)Transfer water tank and
pumps installation completed
with all necessary piping
works. 5) Zone-2 Level 1 to
Level 3 Plumbing work
completed. 6) Water
Sampling Test Done
(Attached) PHASE-2
WORK WILL CONTINUE.

6 Supply and installation of additional dry riser


BY OTHERS BY OTHERS
system with provision of standby hoses where necessary.
7 Supply, installation and testing of Fire Hosereel including the
Hosereel tank and pump set, all piping, hoses, nozzles, painting BY OTHERS BY OTHERS
and valves etc.
8 Supply, installation and testing of Hot Water Claim for Hot Water
Piping including all supports, brackets and all Pipework serving the toilets
piping connection etc. (Note: Onclude also the main water supplies $72,000.00 100% $72,000.00 under Phase 1
to the Solar Water System for the Specialist to continues from
here)

Page 1 of 2
9 Supply and installation of short length of gas pipe for the 3 Nos. of Claim under Optional Item
EXCLUDED EXCLUDED
Dryers in the Laundry extension. (a)
10 Other items and works not included in the above list (Please state):

Work done on site for item 1


(a) Site Co-Ordination $79,500.00 91% $72,444.82 to item 8 /Contract Sum of
these items.
(b) Shop Drawing (Hard copy)
$5,000.00 100% $5,000.00 All Shop Drawings Approved
(c) As-built drawings and O&M Manual $500.00 100% $500.00
(d) Fire Hydrant System
Installation ,Testing and
$6,600.00 100% $6,600.00
Commissioning Completed

TOTAL FOR PLUMBING, AND SANITARY SERVICES TO BE


$668,200.00 $609,974.82
CARRIED TO FINAL M & E SUMMARY
LESS: AGREED DISCOUNT -$66,820.00 -$60,997.48

TOTAL AMOUNT $601,380.00 $548,977.34

ADD: OPTIONAL ITEMS

Supply and Installation of Gas Pipe for 3 nos. Dryers in the Claim for authority
a) $6,500.00 15% $975.00
Laundry extension. submission.

(Claim base on NSC Solar


b) Profit & Attendant for Co-ordination of Solar Water Heater System $2,880.00 100% $2,880.00
Subcon Claim Percentage)

(Claim base on NSC Solar


Provision Sum for Solar Water System $72,000.00 100% $12,240.00 Subcon Amount, refer
attached)

TOTAL AMOUNT WITH OPTIONS BEFORE GST = $682,760.00 $565,072.34