Professional Documents
Culture Documents
The Decision Making Process
The Decision Making Process
The Decision Making Process
Critical Chain Project Management was developed by Dr Eli Goldratt and was first
introduced to the market in his Theory of Constraints book Critical Chain in 1997. It
was developed in response to many projects being dogged by poor performance
manifested in longer than expected durations, frequently missed deadlines, increased
costs in excess of budget, and substantially less deliverables than originally promised.
1.Not starting the task until the last moment (Student Syndrome)
Planning
Critical Chain - the Critical Chain is defined as the longest chain [not path] of dependent
tasks. In this case, dependent refers to resources and resource contention across
tasks/projects as well as the sequence and logical dependencies of the tasks themselves.
This differs from the Critical Path Method.
Estimations To reduce the behaviours and time wasting associated with having too
much embedded safety, Critical Chain Project Management recommends that task
estimates are cut to half the length of a normal duration.
Safety Critical Chain Project Management uses safety Buffers to manage the impact of
variation and uncertainty around projects. The safety at a task level is aggregated and
moved to strategic points in the project flow. There are three types of buffer/strategic
points necessary to ensure the project has sufficient safety:
Project Buffer A project buffer is inserted at the end of the project network
between the last task and the completion date. Any delays on the longest chain
of dependant tasks will consume some of the buffer but will leave the completion
date unchanged and so protect the project. The project buffer is typically
recommended to be half the size of the safety time taken out, resulting in a
project that is planned to be 75% of a traditional project network.
Feeding Buffers delays on paths of tasks feeding into the longest chain can
impact the project by delaying a subsequent task on the Critical Chain. To protect
against this, feeding buffers are inserted between the last task on a feeding path
and the Critical Chain. The feeding buffer is typically recommended to be half the
size of the safety time taken out of the feeding path.
Resource Buffers Resource buffers can be set alongside of the Critical Chain
to ensure that the appropriate people and skills are available to work on the
Critical Chain tasks as soon as needed.
Execution
Priorities - All resources on a project are given clear and aligned priorities relating to the
health of the Critical Chain relative to its associated buffer and hence the project as a
whole. A resource with more than one task open should normally be assigned to
complete any task jeopardising any projects Critical Chain before completing any feeding
path task.
Review
Buffer Management the amount each buffer is consumed relative to project progress
tells us how badly the delays are effecting our committed delivery date. If the variation
throughout the project is uniform then the project should consume its project buffer at
the same rate tasks are completed. The result is a project completed with the buffer
fully consumed on the day it was estimated and committed. Project Managers determine
the corrective actions necessary to recover buffer time at points in the project where
the buffer consumption is occurring faster than the project is progressing.
Remaining duration tasks are monitored on their remaining duration, not their
percentage complete. Resources report upon tasks in progress based on the number of
days they estimate until the task will be complete. If the remaining duration stays static
or increases, then Project Managers and Resource Managers watching the buffers know
exactly where a blockage or potential delay is occurring and can take decisive action
quickly to recover.
The Decision Making Process
Project Management thrives on the rationality of decisions and here is where it is
important for the Project manager to have a process which enables him and his team
decide rationally about different aspects of the project.
Facts
If you want to make a decision, the basic requirement for the same is gathering
relevant information. Appropriate use of this information will be helpful in deciding
about ways to reach to the goal or an objective.
Values
Decisions are primarily based on situations. An action to a particular situation is
determined by values.
Means
It is the way you reach your objective based on already devised values and
significances
Ends
These are the intermediate goals which add up to a final objective. Here, you can
see that decision making is an iterative process.
In simple words, there are four steps in the process of decision making pertaining to
the above points
Find, analyse all the alternatives and select the best of them
Here are some of the most commonly used decision making models in Project
Management
Pareto Principle
This is also called as 80-20 rule wherein you prioritize your problems and then find
out solutions. In order to understand the concept, this 80-20 rule can be described as
an example of problems in organization created by people. We can say that the 80%
of the problems are created by 20% of the people in any organization.
Let us say you have a BPO and 5 of the problems in your organization are due to
lack of promptness, 3 problems are due to poor linguistic ability and 2 problems are
due to poor organization skills. So you can say that major problem here is caused by
the lack of training and development because if you impart training to your
employees automatically promptness and linguistics will be taken care.
There are many more decision making models and those can be effectively used in
professional as well as personal life. These tools are sometimes regarded highly in
the sphere of project management as their capacity of backing up decisions taken by
project manager is enormous. A good project manager can understand the need of
these effective tools which can be used all through the life cycle of project
management.