EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW

OPERATION PROCEDURE FOR STRAND JACK


Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

REVISION HISTORICAL SHEET

Revision Date Description


0 28/11/2014 Issued for Information

Page 2 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 3 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 4 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 5 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 6 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 7 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 8 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 9 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 10 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 11 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 12 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 13 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

Page 14 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation


EPCC TOTAL PROYEK PANAS BUMI KAMOJANG 1x35 MW
OPERATION PROCEDURE FOR STRAND JACK
Job No : Document No : Rev : Date : Prepared Checked Approved
13-1106 KMJ5-C-0-D0-CP-AA0-037R 0 28/11/14 ES DDS BD

10

11

Page 15 of 15

Consortium of PT. REKAYASA INDUSTRI Sumitomo Corporation